A Competitive Genetic Algorithm For Resource-Constrained Project Scheduling

This document describes a genetic algorithm approach for solving the resource-constrained project scheduling problem (RCPSP). It proposes a new genetic algorithm that uses a permutation-based encoding where individuals represent activity sequences. It compares this approach to two other genetic algorithms from literature that use priority value-based and priority rule-based encodings. The results of computational experiments on standard test instances show that the proposed permutation-based genetic algorithm performs better than the other two approaches and yields better results than some heuristic methods from literature.

Uploaded by

rorrito33
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
92 views

A Competitive Genetic Algorithm For Resource-Constrained Project Scheduling

This document describes a genetic algorithm approach for solving the resource-constrained project scheduling problem (RCPSP). It proposes a new genetic algorithm that uses a permutation-based encoding where individuals represent activity sequences. It compares this approach to two other genetic algorithms from literature that use priority value-based and priority rule-based encodings. The results of computational experiments on standard test instances show that the proposed permutation-based genetic algorithm performs better than the other two approaches and yields better results than some heuristic methods from literature.

Uploaded by

rorrito33
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

Published in Naval Research Logistics 45:733-750 (1998).

c Wiley & Sons,


doi:10.1002/(SICI)1520-6750(199810)45:7<733::AID-NAV5>3.0.CO;2-C

A Competitive Genetic Algorithm for


Resource-Constrained Project Scheduling

Sönke Hartmann∗

Christian-Albrechts-Universität zu Kiel, Lehrstuhl für Produktion und Logistik, D-24098


Kiel, Germany. E-mail: [email protected]

supported by the Studienstiftung des deutschen Volkes

Abstract. In this paper we consider the resource-constrained project scheduling problem


(RCPSP) with makespan minimization as objective. We propose a new genetic algorithm ap-
proach to solve this problem. Subsequently, we compare it to two genetic algorithm concepts
from the literature. While our approach makes use of a permutation based genetic encoding
that contains problem-specific knowledge, the other two procedures employ a priority value
based and a priority rule based representation, respectively. Then we present the results of
our thorough computational study for which standard sets of project instances have been
used. The outcome reveals that our procedure is the most promising genetic algorithm to
solve the RCPSP. Finally, we show that our genetic algorithm yields better results than
several heuristic procedures presented in the literature.
Keywords. Project Management and Scheduling, Resource-Constraints, Genetic Algo-
rithms, Computational Results.

1 Introduction
Within the classical resource-constrained project scheduling problem (RCPSP), the activities of a
project have to be scheduled such that the makespan of the project is minimized. This problem
arises within project management software as well as within systems for production planning and
scheduling. The currently most powerful exact procedures have been presented by Brucker et
al. [3], Demeulemeester and Herroelen [6, 7], Mingozzi et al. [24], and Sprecher [32]. However, they
are unable to find optimal schedules for highly resource-constrained projects with 60 activities
or more. Hence, in practice heuristic algorithms to generate near-optimal schedules for larger
projects are of special interest. Recently, an evaluation study (see Kolisch and Hempel [18] and
Kolisch [14]) showed that commercial software packages for project management generate schedules
with an average deviation of 4.3% to 9.8% from the optimal solution for projects with up to 30
activities. These rather disappointing results indicate the need for (fast) heuristics to obtain better
near-optimal schedules which should be implemented in software packages.
Recently proposed heuristic algorithms for the RCPSP include the following: Bell and Han
[2] present a two-phase algorithm based on the concept of disjunctive arcs. Sampson and Weiss
[31] introduce a local search approach in which a schedule is encoded by a shift vector. Özdamar
and Ulusoy [26] propose the so-called local constraint based analysis (LCBA), which is extended
to an iterative algorithm in Özdamar and Ulusoy [28]. Kolisch [15] develops three new priority
rules for the parallel scheduling scheme and tests them in a single-pass environment. Kolisch [16]
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 2

compares some good priority rules within both the serial and the parallel scheduling scheme and
reports experiences with sampling procedures. Kolisch and Drexl [17] introduce a so-called adaptive
search procedure which applies a scheduling scheme and priority rules after analyzing the project
instance at hand. Baar et al. [1] develop two tabu search approaches. Lee and Kim [21] compare
a genetic algorithm (GA), a simulated annealing heuristic, and a tabu search method. Cho and
Kim [4] improve the simulated annealing procedure of Lee and Kim [21]. Leon and Ramamoorthy
[22] suggest a GA and two local search procedures which are based on the so-called problem space
based representation. Kohlmorgen et al. [13] summarize their experiences with an implementation
of a GA for the RCPSP on parallel processors.
The purpose of this paper is to introduce a new GA approach for solving the RCPSP and to
compare it to two existing GA concepts for this problem class. The three procedures are based
on different genetic encodings and encoding-specific genetic operators. We proceed as follows:
Section 2 provides a description of the RCPSP. Section 3 introduces the new GA which makes use
of a permutation based representation. Sections 4 and 5 summarize two GA approaches from the
literature which employ a priority value and a priority rule based encoding, respectively. Section
6 gives the results of our in-depth computational experiments. Finally, Section 7 states some
conclusions.

2 Problem Description
We consider a project which consists of J activities (jobs) labeled j = 1, . . . , J. Due to technological
requirements, there are precedence relations between some of the jobs. These precedence relations
are given by sets of immediate predecessors Pj indicating that an activity j may not be started
before all of its predecessors are completed. Analogously, Sj is the set of the immediate successors
of activity j. The transitive closure of the precedence relations is given by sets of (not necessarily
immediate) successors S j . The precedence relations can be represented by an activity-on-node
network which is assumed to be acyclic. We consider additional activities j = 0 representing the
single source and j = J + 1 representing the single sink activity of the network.
With the exception of the (dummy) source and (dummy) sink activity, each activity requires
certain amounts of (renewable) resources to be performed. The set of resources is referred to as K.
For each resource k ∈ K the per-period-availability is constant and given by Rk . The processing
time (duration) of an activity j is denoted as pj , its request for resource k is given by rjk . Once
started, an activity may not be interrupted. W.l.o.g., we assume that the dummy source and the
dummy sink activity have a duration of zero periods and no request for any resource.
The parameters are assumed to be nonnegative and integer valued. The objective is to deter-
mine a schedule with minimal makespan such that both the precedence and resource constraints
are fulfilled. Mathematical programming formulations of the RCPSP have been given by e.g. De-
meulemeester and Herroelen [6, 7], Mingozzi et al. [24], and Sprecher [32].

3 Permutation based Genetic Algorithm


3.1 Basic Scheme
Introduced by Holland [12], genetic algorithms (GAs) serve as a heuristic meta strategy to solve
hard optimization problems. For an introduction into GAs, we refer to Goldberg [9]. In this section
we propose a new GA approach for the RCPSP.
The GA starts by computing an initial population, i.e. the first generation. We assume that the
initial population contains P OP individuals where P OP is an even integer. After computing the
fitness values of the individuals, the population is randomly partitioned into pairs of individuals.
To each resulting pair of (parent) individuals, we apply the crossover operator to produce two new
(children) individuals. Subsequently, we apply the mutation operator to the genotypes of the newly
produced children. After determining the fitness of each child individual, we add the children to
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 3

3/2 2/4 1/3 K = {1}; R1 = 4


1 - 3 - 5
 @
0/0 @ 0/0
@
0 R 7
@
@ 
@ 4/3 2/4 4/2 pj /rj1
@R 2
@ - 4 - 6 j

Figure 1: Project instance

R1
6
4
3 1
2 4 3
2 5
1 6
-
1 2 3 4 5 6 7 8 9 10 11 12 13 t

Figure 2: Example schedule

the current population, leading to a population size of 2 · P OP . Finally, applying the selection
operator to reduce the population to its former size, we obtain the next generation. The algorithm
stops if a prespecified number of generations which is denoted as GEN or a given time limit is
reached. Clearly, at most P OP · GEN different individuals (and related schedules) are calculated.

3.2 Individuals and fitness


In the first GA variant to be examined, an individual I is given by an activity sequence

I = (j1I , . . . , jJI ).

This job sequence is assumed to be a precedence feasible permutation of the set of activities, that
is, we have {j1I , . . . , jJI } = {1, . . . , J} and PjiI ⊆ {0, j1I , . . . , ji−1
I
} for i = 1, . . . , J.
Each genotype is related to a uniquely determined schedule (phenotype) which is computed
using the following serial scheduling scheme: First, the dummy source activity is started at time
0. Then we schedule the activities in the order that is prescribed by the sequence (j1I , . . . , jJI ).
Thereby, each activity is assigned the earliest feasible start time. Note that the result is an active
schedule, cf. Kolisch [16]. That is, no activity can be left shifted without violating the constraints
(for a formal definition of active schedules cf. Sprecher et al. [33]). The fitness of an individual I
is given by the makespan of the related schedule. Consider the project instance shown in Figure
1. Applying the serial scheduling procedure described above to example individual

I = (2, 4, 6, 1, 3, 5)

leads to the schedule given in Figure 2. The fitness of this individual is 13.
The initial population is computed as follows: Starting with the empty job sequence, we obtain
a precedence feasible job sequence by repeatedly applying the following step: The next activity in
the job sequence is randomly taken from the set of those currently unselected activities all non-
dummy predecessors of which have already been selected for the job sequence. In addition to this
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 4

random algorithm, we have tested another variant which determines the initial population with a
sampling procedure as described by Kolisch [16]. More precisely, we employ a good priority rule,
in our case the latest finish time rule (LFT), to derive probabilities which are used to select the
next activity for the job sequence.
Notice that, while each individual is related to a unique schedule, a schedule can be related to
more than one individual. In other words, there is some redundancy in the search space as dis-
tinct elements of the search space (i.e. genotypes) may be related to the same schedule. Consider
again the project instance of Figure 1 and the above example individual I. Obviously, exchang-
ing activities 1 and 6 in this job sequence, we obtain a different precedence feasible genotype,
i. e. (2, 4, 1, 6, 3, 5). However, both genotypes are related to the same schedule, i.e. the schedule
displayed in Figure 2.

3.3 Crossover
We consider three different crossover variants for the permutation based encoding. They are similar
to the general crossover technique described by Reeves [30] for permutation based genotypes, with
the difference that our encoding takes precedence relations into account.
The first crossover operator is called one-point crossover. We consider two individuals se-
lected for crossover, a mother M and a father F . Then we draw a random integer q with 1 ≤ q < J.
Now two new individuals, a daughter D and a son S, are produced from the parents. We first
consider D which is defined as follows: In the job sequence of D, the positions i = 1, . . . , q are
taken from the mother, that is,
jiD := jiM .
The job sequence of positions i = q + 1, . . . , J in D is taken from the father. However, the jobs
that have already been taken from the mother may not be considered again. We obtain

jiD := jkF where k is the lowest index such that jkF ∈


/ {j1D , . . . , ji−1
D
}.

As a result, the relative positions in the parents’ job sequences are preserved. This way, the
parents contribute to the child’s fitness. For illustration, we consider again Figure 1 and, given
q = 3, the individuals

M = (1, 3, 2, 5, 4, 6), F = (2, 4, 6, 1, 3, 5), D = (1, 3, 2, 4, 6, 5).

While the above definition obviously ensures that each activity appears exactly once in the
resulting job sequence, the following theorem shows that also the precedence assumption is fulfilled.

Theorem 1 If applied to precedence feasible parent individuals, the one-point crossover operator
for the permutation based genetic encoding results in a precedence feasible offspring genotype.

Proof. Let the genotypes of the parents M and F fulfill the precedence assumption. We assume
that the child individual D produced by the crossover operator is not precedence feasible. That
is, there are two activities jiD and jkD with 1 ≤ i < k ≤ J and jkD ∈ PjiD . Three cases can be
distinguished:
Case 1: We have i, k ≤ q. Then activity jiD is before activity jkD in the job sequence of M , a
contradiction to the precedence feasibility of M .
Case 2: We have i, k > q. As the relative positions are maintained by the crossover operator,
activity jiD is before activity jkD in the job sequence of F , contradicting the precedence feasibility
of F .
Case 3: We have i ≤ q and k > q. Then activity jiD is before activity jkD in the job sequence
of M , again a contradiction to the precedence feasibility of M . 

The son S of the individuals M and F is computed similarly. However, the positions 1, . . . , q
of the son’s job sequence are taken from the father and the remaining positions are determined by
the mother. Obviously, Theorem 1 holds for both offspring individuals D and S.
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 5

The second crossover operator is an extension of the one-point variant, called two-point
crossover. Here, we draw two random integers q1 and q2 with 1 ≤ q1 < q2 ≤ J. Now the
daughter individual D is determined by taking the job sequence of the positions i = 1, . . . , q1 from
the mother, that is,
jiD := jiM .
The positions i = q1 + 1, . . . , q2 are derived from the father:

jiD := jkF where k is the lowest index such that jkF ∈


/ {j1D , . . . , ji−1
D
}.

The remaining positions i = q2 + 1, . . . , J are again taken from the mother, that is,

jiD := jkM where k is the lowest index such that jkM ∈


/ {j1D , . . . , ji−1
D
}.

Considering again Figure 1 and the above example parents M and F , we obtain for q1 = 1 and
q2 = 3 daughter
D = (1, 2, 4, 3, 5, 6).
The son individual is computed analogously, taking the first and third part from the father and
the second one from the mother. Obviously, Theorem 1 can easily be extended to the two-point
crossover. Observe also that fixing q2 = J leads to the one-point variant which therefore is a special
case of the two-point crossover.
The third crossover type is called uniform crossover. Here, the daughter D is determined as
follows: We draw a sequence of random numbers pi ∈ {0, 1}, i = 1, . . . , J. Then we successively
fill positions i = 1, . . . , J in D. If we have pi = 1, we take that activity from the mother’s job
sequence which has the lowest index among the currently unselected activities, that is,

jiD := jkM where k is the lowest index such that jkM ∈


/ {j1D , . . . , ji−1
D
}.

Otherwise, if pi = 0, the activity is analogously derived from the father’s job sequence:

jiD := jkF where k is the lowest index such that jkF ∈


/ {j1D , . . . , ji−1
D
}.

For the above example individuals M and F and random number sequence 0, 1, 1, 0, 1, 1, we
obtain daughter
D = (2, 1, 3, 4, 5, 6).
The son S is computed using an analogous procedure which takes the i-th job from the father if
p1 = 1 and from the mother otherwise. Note that the uniform crossover generalizes the two-point
variant: Fixing pi = 1 for i ∈ {1, . . . , q1 , q2 + 1, . . . , J} and pi = 0 for i ∈ {q1 + 1, . . . , q2 } leads to
the definition of the daughter in the two-point crossover. With arguments similar to those used in
the proof of Theorem 1, one can show that also the uniform crossover produces precedence feasible
offspring.

3.4 Mutation
Given a permutation based individual I, the mutation operator modifies the related job sequence
as follows: For all positions i = 1, . . . , J − 1, activities jiI and ji+1
I
are exchanged with a probability
of pmutation , if the result is a job sequence which fulfills the precedence assumption.
The mutation operator may create job sequences (i.e. gene combinations) that could not have
been produced by the crossover operator. However, it should be noted that performing a mutation
on an individual does not necessarily change the related schedule. This is due to the redundancy
in the genetic representation: For example, interchanging two activities in the job sequence which
have the same start time changes the individual, but not the related schedule.
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 6

3.5 Selection
We consider four alternative selection operators which follow a survival-of-the-fittest strategy as
similarly described by e.g. Michalewicz [23]. The first one is a simple ranking method: We keep
the P OP best individuals and remove the remaining ones from the population (ties are broken
arbitrarily).
The second variant, the proportional selection, can be viewed as a randomized version of
the previously described ranking technique. Let f (I) be the fitness of an individual I, and let P
denote the current population, that is, a list containing the individuals. Note that we use a list of
individuals instead of a set because we explicitly allow two (or more) distinct individuals with the
same genotype in a population. We restore the original population size by successively removing
individuals from the population until P OP individuals are left, using the following probability:
Denoting with fbest = min{f (I) | I ∈ P} the best fitness in the current population, the probability
to die for an individual I is given by

(f (I) − fbest + 1)2


pdeath (I) = P 0 2
.
I 0 ∈P (f (I ) − fbest + 1)

Next, we consider two versions of the tournament technique. In the 2-tournament selection,
two different randomly chosen individuals I1 and I2 compete for (temporary) survival. If individual
I1 is not better than individual I2 , i.e. f (I1 ) ≥ f (I2 ), then it dies and is removed from the
population (again, ties are broken arbitrarily). This process is repeated until P OP individuals are
left. Recall that a lower fitness value implies a better quality of the individual.
Finally, the 3-tournament selection extends the previously described method by randomly
selecting three individuals I1 , I2 , and I3 . If we have f (I1 ) ≥ f (I2 ) and f (I1 ) ≥ f (I3 ), individual
I1 is removed from the population. Again, this step is repeated until P OP individuals are left.

4 Priority Value based Genetic Algorithm


This section is devoted to a GA which makes use of a priority value based encoding as similarly used
by Lee and Kim [21] within their GA for the RCPSP. We employ the priority value representation
into the basic GA scheme that was used for the permutation based GA. This allows us to obtain
comparable results when evaluating the GA approaches. We also make use of the selection operator
variants here that have been defined for the permutation based GA as they are not encoding specific.
In the following, the priority value based representation and the related crossover and mutation
operators are discussed.

4.1 Individuals and fitness


In this GA approach, an individual I is represented by a sequence of priority values

I = (pv1I , . . . , pvJI ).

For each priority value of activity j = 1, . . . , J, we have pvjI ∈ [0, 1]. This encoding equals the one
employed by Lee and Kim [21]. In contrast to their approach which employs a parallel scheduling
scheme to derive the schedule related to an individual, however, we employ a serial scheme similar
to that used for the permutation based encoding. We do so because it has been shown by Kolisch
[16] that a serial scheme yields better results when a large number of schedules is computed for
one project instance. This is due to the fact that using the parallel scheme, one might exclude all
optimal solutions from the search space while the search space of the serial scheme always contains
an optimal schedule.
Hence, given an individual I, the related schedule is computed as follows: After starting the
dummy source activity at time 0, we determine the set EJ of the eligible activities, that is, those
activities the predecessors of which are already scheduled. Then we schedule the eligible activity
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 7

j with the highest priority value pvjI = max {pviI | i ∈ EJ} as early as possible such that neither
the precedence nor the resource constraints are violated. Repeatedly scheduling an unscheduled
activity, we obtain a feasible active schedule. Again, the fitness of an individual is defined as the
makespan of the related schedule. Consider again the instance of Figure 1. Example individual
I = (0.58, 0.64, 0.31, 0.87, 0.09, 0.34)
is related to the schedule of Figure 2.
Each individual I of the initial population is determined by randomly drawing a priority value
pvjI ∈ [0, 1] with a uniform distribution for each activity j = 1, . . . , J.
As was the case for the permutation based encoding, there is some redundancy in the search
space also for the priority value based representation. We consider again the above example indi-
vidual I. Clearly, setting for example pv2I = 0.93 instead of 0.64, we obtain a different individual.
However, both individuals are related to the same schedule, namely the one of Figure 2.

4.2 Crossover
This encoding allows us to employ standard crossover operators. Again, we consider two indi-
viduals selected for crossover, a mother M and a father F , from which two offspring individuals
are computed. In the following, we only define the daughter D. As for the permutation based
representation, the son S is computed analogously to the daughter’s definition.
For the one-point crossover, we draw a random integer q with 1 ≤ q < J. The first q
positions of daughter individual D are taken from the mother while the remaining ones are defined
by the father, that is, for each i = 1, . . . , J we have
pviM , if i ∈ {1, . . . , q}

D
pvi =
pviF , if i ∈ {q + 1, . . . , J}.
Using again Figure 1 and q = 3, this definition is illustrated by
M = (0.58, 0.64, 0.31, 0.87, 0.09, 0.34),
F = (0.12, 0.43, 0.99, 0.65, 0.19, 0.22),
D = (0.58, 0.64, 0.31, 0.65, 0.19, 0.22).
Similarly to the permutation based encoding, we have considered the two-point crossover
in addition to the one-point variant defined above. We draw two random integers q1 and q2 with
1 ≤ q1 < q2 ≤ J and obtain for each i = 1, . . . , J
 pviM , if i ∈ {1, . . . , q1 }

D
pvi = pv F , if i ∈ {q1 + 1, . . . , q2 }
 iM
pvi , if i ∈ {q2 + 1, . . . , J}.
Finally, for the uniform crossover, we draw a sequence of random numbers pi ∈ {0, 1},
i = 1, . . . , J. Then we set for each i = 1, . . . , J
pviM , if pi = 1

D
pvi =
pviF , otherwise.

4.3 Mutation
The mutation for the priority value based encoding is defined as follows: Given an individual I,
we modify the related priority value sequence as follows: For all positions i = 1, . . . , J, a new
priority value pviI ∈ [0, 1] is drawn with a probability of pmutation . Clearly, the result is always
a feasible priority value sequence. Obviously, the mutation operator may create priority values
(i.e. genes) that did not occur in the population before. Again, however, performing a mutation
on an individual does not necessarily change the related schedule due to the redundancy discussed
above.
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 8

5 Priority Rule based Genetic Algorithm


In this section, we describe a GA based on a priority rule representation. This representation type
has been developed by Dorndorf and Pesch [8] for the job shop scheduling problem. Özdamar [25]
employed it for the multi-mode extension of the RCPSP. Like the priority value based one, also
this GA employs the basic scheme and the selection operator variants that have been used for the
permutation based GA. Next, the priority rule encoding and the related crossover and mutation
operators are provided.

5.1 Individuals and fitness


In this GA variant, an individual I is given by a sequence of priority rules

I = (pr1I , . . . , prJI )

where we have for each position i = 1, . . . , J

priI ∈ {LFT, LST, MTS, MSLK, WRUP, GRPW}.

Each of these six priority rules has been suggested in the literature and shown to produce good
schedules for the RCPSP, we refer to the study recently performed by Kolisch [16]. Table 1 contains
a brief mathematical definition for each priority rule. Here, LF Tj denotes the latest finish time
of activity j. It can be determined using traditional backward recursion from an upper bound on
the project’s makespan. Finally, with fj we denote the earliest precedence and resource feasible
finish time of activity j in the current partial schedule. Within the WRUP rule which has been
developed by Ulusoy and Özdamar [34], we have employed the weights that performed best in their
study.
Whereas Özdamar [25] employs a parallel scheme to transform an individual into a schedule,
we use a serial scheme for the same reason as the one given in the previous section. We proceed
as follows: First, we start the dummy source activity at time 0. Then, we compute the set of the
eligible activities and use priority rule pr1I to select the eligible activity with the highest priority.
The selected activity is started at the earliest precedence and resource feasible time. After updating
the eligible set, the second activity to be scheduled is selected using priority rule pr2I . Repeatedly
scheduling an unscheduled activity, we obtain a feasible active schedule. Thereby, the i-th decision
which activity to schedule next is made using the i-th priority rule in the sequence. In other words,
the i-th activity to be scheduled is selected using rule priI . The fitness of an individual is again
given by the makespan of the related schedule. Considering the project instance of Figure 1, the
schedule related to the example individual

I = (LST, GRPW, MTS, LST, MSLK, LFT)

is again the one of Figure 2.

Priority rule formula


LFT latest finish time min LF Tj
LST latest start time min LF Tj − pj
MTS most total successors max |S j |
MSLK minimum slack min LF Tj − fj
P
WRUP weighted resource utilization and precedence max 0.7 |Sj | + 0.3 k∈K rjk /Rk
P
GRPW greatest rank positional weight max pj + i∈Sj pi

Table 1: Good priority rules


A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 9

Each individual I of the initial generation is determined by randomly selecting one of the six
priority rules for priI , i = 1, . . . , J.
Like the two previously described genetic representations, also the priority rule based encoding
contains some redundancy. Consider again example individual I given above. Replacing the first
priority rule in the sequence (LFT) with e.g. the GRPW rule, we obtain a different genotype which
is, however, also related to the schedule of Figure 2.
While the search spaces for the other two encodings always contain an optimal solution, this is
not the case for the priority rule based representation. For the sake of shortness, we do not give a
detailed counterexample, mentioning only that in some cases none of the employed priority rules
may select an activity that must be scheduled next in order to obtain an optimal schedule from the
current partial schedule. This drawback could be overcome by adding a priority rule which allows
any eligible activity to be selected, namely the random rule (RAND). However, we did not employ
the RAND priority rule because it seems to be incompatible with the GA paradigm: Obviously,
selecting an activity with the RAND rule may contribute to the fitness if, by chance, this activity
continues the current partial schedule in an advantageous way. However, the RAND rule itself
does not contain specific information that is worth to be inherited.

5.2 Crossover
We can employ standard crossover operators similar to those used for the priority value encoding.
The definitions of the one-point, two-point, and uniform crossover for the priority rule represen-
tation are obtained from replacing pviI by priI in the respective definitions for the priority value
encoding.

5.3 Mutation
For the priority rule based encoding, the mutation operator is defined as follows: For each position
i = 1, . . . , J of an individual I, a new priority rule

priI ∈ {LFT, LST, MTS, MSLK, WRUP, GRPW}

is randomly drawn with a probability of pmutation . Again, due to the redundancy described above,
performing a mutation on a genotype does not necessarily change the related schedule.

6 Computational Results
6.1 Experimental Design
In this section we present the results of the computational studies concerning the genetic algorithms
introduced in the previous sections. The experiments have been performed on a Pentium-based
IBM-compatible personal computer with 133 MHz clock-pulse and 32 MB RAM. For our study,
we have implemented four procedures: the three GAs described in the previous sections and, as
a benchmark, the priority rule based sampling approach of Kolisch [16]. These procedures have
been coded in ANSI C, compiled with the GNU C compiler, and tested under Linux.
Two different standard sets of benchmark instances from the literature have been used. For
configuration and analysis of the GA approaches (in Subsections 6.2, 6.3, and 6.4), we used a set of
test problems constructed by the project generator ProGen developed by Kolisch et al. [20]. These
instances are available in the project scheduling problem library PSPLIB from the University of
Kiel. For detailed information the reader is referred to Kolisch and Sprecher [19]. In our study,
we have used the ProGen problem instances with 30 and 60 non-dummy activities. We have
4 renewable resources. For each problem size, a set consists of 480 instances which have been
systematically generated by varying three parameters: network complexity, resource factor, and
resource strength. The network complexity reflects the average number of immediate successors
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 10

of an activity. The resource factor is a measure of the average number of resources requested per
job. The resource strength describes the scarceness of the resource capacities. These parameters
are known to have a big impact on the hardness of a project instance, cf. Kolisch et al. [20].
The set with 30 non-dummy activities currently is the hardest standard set of RCPSP-instances
for which all optimal solutions are known, cf. Demeulemeester and Herroelen [7]. In what follows
we report the average percentage deviation from the optimal makespan. However, for some of the
instances with 60 activities, only heuristic solutions are known. In these cases, we give the average
percentage deviation from the best lower and upper bounds as reported in the library PSPLIB
at the time this research was performed. The lower bounds were computed by Baar et al. [1]
and Heilmann and Schwindt [11]. The upper bounds were obtained by Kolisch and Drexl [17],
Kohlmorgen et al. [13], and Baar et al. [1].
Finally, for comparing our GA approach with other procedures presented in the literature
(in Subsection 6.5), we use the set of project instances assembled by Patterson [29]. We do
so because the Patterson instance set has been used to evaluate heuristics in several studies, see
[2, 4, 21, 22, 27, 28, 31]. The Patterson set contains 110 instances with up to 51 activities and up to 3
resources. For all of these test problems, the optimal solutions are known, see e.g. Demeulemeester
and Herroelen [6].

6.2 Configuration of the Genetic Algorithms


Crucial for the success of a GA is an appropriate choice of good genetic operators and adequate
parameter settings, usually on the basis of computational experiments. We report the outcome of
our study to determine the best GA configuration only for the suggested permutation based GA
approach of Section 3 and for the ProGen instance set with 30 non-dummy activities, because the
results for the other GAs and the other instance sets are similar. For each instance, 1,000 schedules
were computed.
Table 2 reports the average and the maximal deviation from the optimum, the percentage of
instances for which an optimal solution was found, and the computation time in seconds for different
combinations of alternative genetic operators. We have tested all possible GA configurations
that arise from combining three mutation probability levels, the three crossover variants, and
the four selection variants. A mutation probability of 0.05, the two-point crossover strategy, and
the ranking method for selection perform best (for the sake of shortness, Table 2 contains only
those configurations that vary this best one in only one point). The two-point crossover operator
appears to be capable of inheriting building blocks that contributed to the parents’ fitness (for
much larger projects, even more than two cuts may probably be advisable). In contrast, the
uniform crossover operator (which yields good results for problems with a different structure such
as e.g. the multidimensional knapsack problem, cf. Chu and Beasley [5]) does not seem to be well
suited for sequencing problems. A randomized selection strategy seems to be advantageous only if
a much larger number of individuals is considered.
Table 3 shows that a population size of 40 and 25 generations is the best parameter relationship
when calculating 1,000 individuals (i.e. schedules). Finally, Table 4 shows that it pays to use a
sampling method instead of a pure random procedure to determine the initial population.
In the further computational studies, the three GAs make use of the best configuration deter-
mined here. That is, they apply a mutation probability of 0.05, a two-point crossover, the ranking
selection, and the relationship of population size and number of generations given above. Recall,
however, that the sampling procedure to determine the initial population is only employed in our
permutation based GA. The other two approaches make use of a pure random procedure.

6.3 Comparison of the Genetic Algorithms


In this subsection, we present the experimental results obtained from the comparison of the pro-
posed GA of Section 3 with the GA approaches described in Sections 4 and 5.
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 11

pmutation crossover selection average dev. max. dev. optimal CPU-sec


0.01 two-point ranking 0.64% 9.7% 77.5% 0.54
0.05 two-point ranking 0.54% 7.9% 81.5% 0.54
0.10 two-point ranking 0.56% 8.6% 80.4% 0.55
0.05 one-point ranking 0.65% 9.7% 77.5% 0.54
0.05 two-point ranking 0.54% 7.9% 81.5% 0.54
0.05 uniform ranking 0.66% 8.6% 79.6% 0.76
0.05 two-point ranking 0.54% 7.9% 81.5% 0.54
0.05 two-point proportional 0.62% 7.7% 78.5% 0.60
0.05 two-point 2-tournament 0.63% 9.3% 79.0% 0.54
0.05 two-point 3-tournament 0.59% 7.3% 80.9% 0.54

Table 2: Alternative genetic operators — permutation based GA, 1,000 schedules, J = 30

P OP GEN average dev. max. dev. optimal CPU-sec


50 20 0.56% 11.1% 80.8% 0.54
40 25 0.54% 7.9% 81.5% 0.54
20 50 0.79% 9.2% 76.5% 0.54

Table 3: Impact of population size — permutation based GA, 1,000 schedules, J = 30

The first numerical results to be presented are obtained from the ProGen project instance set
with 30 activities where 1,000 individuals (i.e. schedules) are computed for each instance. Table
5 gives the average and the maximal deviation from the optimum, the percentage of instances for
which an optimal solution was found, and the computation time in seconds. The permutation based
encoding yields better results than the priority value based representation while both outperform
the priority rule encoding.
Table 5 also shows that the permutation based GA results in the lowest computation times.
This is because we have to determine eligible activities and apply priority rules only for the first
generation, when computing the schedule related to permutation based individuals. Clearly, when
using a heuristic procedure in practice, it is important to obtain good schedules within a reasonable
amount of CPU time. Therefore we have additionally tested the three GA variants with time limits
instead of fixing the number of schedules to be computed. As a further benchmark, we use a good
sampling procedure known from the literature (cf. Kolisch [16]) which is based on the randomized
LFT priority rule.
Table 6 displays the average deviations from the optimum obtained for the instances with
J = 30 from four different time limits. The permutation based GA performs best for all time
limits while the priority rule based GA yields the worst results. Note especially that the deviation
of the permutation based GA is two times lower than that of the priority rule based GA for a time
limit of 0.5 seconds while it is more than four times lower for 4 seconds. That is, the proposed GA is

Initial population average dev. max. dev. optimal CPU-sec


random sampling (LFT) 0.54% 7.9% 81.5% 0.54
random 0.99% 10.5% 70.8% 0.52

Table 4: Impact of initial population — permutation based GA, 1,000 schedules, J = 30


A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 12

GA average dev. max. dev. optimal CPU-sec


permutation 0.54% 7.9% 81.5% 0.54
priority value 1.03% 10.8% 70.6% 0.64
priority rule 1.38% 17.7% 70.6% 0.91

Table 5: Comparison of genetic algorithms — 1,000 schedules, J = 30

Algorithm type 0.5 sec 1.0 sec 2.0 sec 4.0 sec
GA permutation 0.71% 0.45% 0.37% 0.24%
GA priority value 1.16% 0.88% 0.69% 0.54%
GA priority rule 1.51% 1.33% 1.21% 1.13%
sampling LFT 1.00% 0.77% 0.66% 0.55%

Table 6: Average deviations w.r.t. time limit — J = 30

not only the best for small time limits, its superiority also further increases when the computation
time is increased.
Next, we have performed the same experiment on the set of instances with 60 activities. As
for some instances optimal solutions are currently unknown, we measure the deviations from the
best known lower and upper bound here. The results can be found in Tables 7 and 8, respectively.
Again, the permutation based GA performs best for all time limits. In contrast to the instances
with J = 30, however, here the priority rule based GA outperforms the priority value GA and
the sampling approach. This observation can be explained as follows: Selecting J = 60 instead
of J = 30 results in a much larger search space. Within the same time limit, only a much
smaller portion of the search space can be examined. Therefore, the strategy to combine several
good priority rules corresponds to examining only potentially promising regions of the search space.
However, the restriction to the regions identified by the priority rules is disadvantageous for smaller
projects and/or higher computation times (or, of course, faster computers).
We remark here that most of the best known upper bounds for the hard instances were computed
by Kohlmorgen et al. [13] with their parallel GA approach. Using a massively parallel computer
with 16k processing units, they had 16,384 individuals per generation, while our GA could not
evaluate more than 4,000 individuals altogether within 4 seconds when applied to the instances
with 60 activities. Thus, it is not surprising that the best known upper bounds are on the average
0.59% better than our results (cf. Table 8). Nevertheless, it should be mentioned that the schedules
for 3 of the 480 instances with 60 activities found by our GA (with a time limit of 4 seconds) were
better than those reported in the library PSPLIB at the time this research was performed.
The results can be summarized as follows: The permutation based GA outperforms the other
two GA approaches. Considering again Subsection 6.2, we observe that the choice of an appropriate
representation is far more important than other configuration decisions such as crossover and

Algorithm type 0.5 sec 1.0 sec 2.0 sec 4.0 sec
GA permutation 5.30% 4.73% 4.37% 4.16%
GA priority value 7.60% 6.60% 6.17% 5.70%
GA priority rule 5.92% 5.50% 5.18% 4.96%
sampling LFT 6.08% 5.77% 5.63% 5.39%

Table 7: Average deviations from best lower bound w.r.t. time limit — J = 60
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 13

Algorithm type 0.5 sec 1.0 sec 2.0 sec 4.0 sec
GA permutation 1.42% 1.10% 0.79% 0.59%
GA priority value 3.61% 2.88% 2.24% 1.79%
GA priority rule 2.07% 1.80% 1.52% 1.34%
sampling LFT 2.27% 1.99% 1.82% 1.62%

Table 8: Average deviations from best upper bound w.r.t. time limit — J = 60

Encoding GA random
permutation 0.54% 0.82%
priority value 1.03% 1.69%
priority rule 1.38% 1.41%

Table 9: Impact of genetic operators — 1,000 schedules, J = 30

selection type or mutation rate.

6.4 Impact of Genetic Operators


In what follows, we examine the question whether the three representations are well suited for
application in genetic algorithms. In other words, we want to know if they benefit from the
application of genetic operators. Thus, for each encoding, we compare the related GA which
computes 1,000 schedules by applying the genetic operators on 40 individuals over 25 generations
with what we will call a “random procedure”. For each encoding, this random procedure generates
1,000 schedules independently, that is, without applying the genetic operators. Note that it can
be viewed as a GA with a population size of 1,000 and only one generation (i.e. the initial one).
For the three encodings, the average deviations from the optimal solutions for both the “real”
GAs and the random procedures are listed in Table 9. We observe that the GAs clearly outperform
the corresponding random procedures if the permutation and priority value encodings are consid-
ered. However, for the priority rule encoding, there are only slight differences between randomly
generating 1,000 priority rule sequences (and thus schedules) on the one hand and randomly gen-
erating only 40 and applying the genetic operators over 25 generations on the other hand. Hence
we can deduce that the priority rule encoding does not exploit the potential of the GA paradigm
when applied to solve the RCPSP. In contrast, the other two representations are well suited for
application in a GA.
Recall that the initial population of the permutation based GA is computed using a sampling
method. That is, the random procedure for the permutation encoding listed in Table 9 is in fact
a sampling algorithm. Table 9 shows that it is better to determine only 40 schedules using the
sampling procedure and then apply the genetic operators over 25 generations, than to compute all
1,000 schedules with the sampling method.

6.5 Comparison with other heuristics


Finally, we have compared our permutation based GA to further heuristics suggested in the liter-
ature. The results are shown in Table 10. Recall, the priority value and the priority rule based
GAs can be viewed as modified versions of the GAs proposed by Lee and Kim [21] and Özdamar
[25], respectively. In addition to the priority rule based sampling algorithm of Kolisch [16], we
have considered the simulated annealing (SA) procedures of Cho and Kim [4] and Lee and Kim
[21], the local search approach of Sampson and Weiss [31], and the disjunctive arc based two-phase
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 14

Algorithm Reference average dev. optimal CPU-sec


GA (permutation) — 0.00% 100.0% 5.0a
GA (priority value) — 0.25% 88.4% 5.0a
GA (priority rule) — 0.78% 74.6% 5.0a
sampling (LFT) Kolisch [16] 0.05% 96.4% 5.0a
SA Cho, Kim [4] 0.14% 93.6% 18.4b
SA Lee, Kim [21] 0.57% 82.7% 17.0b
local search Sampson, Weiss [31] 1.98% 55.5% 10.2b
two-phase Bell, Han [2] 2.60% 44.5% 28.4c
GA (problem space) Leon, Ramamoorthy [22] 0.74% 75.5% 7.5d
LCBA Özdamar, Ulusoy [28] 1.14% 63.6% 0–25e
a
maximal CPU-time on a Pentium 133 MHz
b
average CPU-time on a Pentium 60 MHz
c
average CPU-time on a Macintosh plus
d
average CPU-time on an IBM RS 6000
e
CPU-time range on an IBM PC 486

Table 10: Comparison of heuristics — Patterson instance set

procedure of Bell and Han [2] as further benchmarks. The results for the latter four heuristics
are given as reported in [4]. Furthermore, the local constraint based analysis (LCBA) method
of Özdamar and Ulusoy [26] has been included in its iterative variant, see Özdamar and Ulusoy
[28]. The results cited here are taken from the study performed by Özdamar and Ulusoy [27, 28].
Finally, we have considered the results obtained by Leon and Ramamoorthy [22] for their GA.
Their approach is based on the so-called problem space based representation which, similarly to
the priority value representation, encodes a solution using an array of real numbers.
Taking the different computers and computation times into account, we can state that the
permutation based GA is the most promising among the these heuristics for the RCPSP. Observe
that our GA solves all Patterson instances to optimality within a time limit of 5 seconds. Finally,
the results show that the success of a GA mainly depends on the underlying representation.

7 Conclusions
We have proposed a genetic algorithm (GA) for solving the classical resource-constrained project
scheduling problem (RCPSP). The representation is based on a precedence feasible permutation
of the set of the activities. The genotypes are transformed into schedules using a serial scheduling
scheme. Among several alternative genetic operators for the permutation encoding, we chose a
ranking selection strategy, a mutation probability of 0.05, and a two-point crossover operator which
preserves precedence feasibility. The initial population was determined with a randomized priority
rule method. In order to evaluate our approach, we have compared it to two GA concepts from
the literature which make use of a priority value and a priority rule representation, respectively.
As further benchmarks, seven other heuristics known from the literature were considered. Our in-
depth computational study revealed that our GA outperformed the other GAs as well as the other
approaches. This outcome suggests to apply our GA to real-world project scheduling problems. In
fact, we have obtained promising results for a medical research project documented in [10].
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 15

References [15] R. Kolisch. Efficient priority rules for the resource-


constrained project scheduling problem. Journal of
[1] T. Baar, P. Brucker, and S. Knust. Tabu-search Operations Management, 14:179–192, 1996.
algorithms and lower bounds for the resource-
constrained project scheduling problem. In S. Voss, [16] R. Kolisch. Serial and parallel resource-constrained
S. Martello, I. Osman, and C. Roucairol, edi- project scheduling methods revisited: Theory and
tors, Meta-heuristics: Advances and trends in lo- computation. European Journal of Operational Re-
cal search paradigms for optimization, pages 1–8. search, 90:320–333, 1996.
Kluwer Academic Publishers, 1998.
[17] R. Kolisch and A. Drexl. Adaptive search for solving
[2] C. E. Bell and J. Han. A new heuristic solution hard project scheduling problems. Naval Research
method in resource-constrained project scheduling. Logistics, 43:23–40, 1996.
Naval Research Logistics, 38:315–331, 1991.
[18] R. Kolisch and K. Hempel. Experimentelle Eval-
[3] P. Brucker, S. Knust, A. Schoo, and O. Thiele. uation der Kapazitätsplanung von Projektmanage-
A branch-and-bound algorithm for the resource- mentsoftware. Zeitschrift für betriebswirtschaftliche
constrained project scheduling problem. Euro- Forschung, 48:999–1018, 1996.
pean Journal of Operational Research, 107:272–288,
1998. [19] R. Kolisch and A. Sprecher. PSPLIB – a project
scheduling problem library. European Journal of
[4] J. H. Cho and Y. D. Kim. A simulated annealing Operational Research, 96:205–216, 1996.
algorithm for resource-constrained project schedul-
ing problems. Journal of the Operational Research [20] R. Kolisch, A. Sprecher, and A. Drexl. Characteri-
Society, 48:736–744, 1997. zation and generation of a general class of resource-
constrained project scheduling problems. Manage-
[5] P. C. Chu and J. E. Beasley. A genetic algorithm for ment Science, 41:1693–1703, 1995.
the multidimensional knapsack problem. Technical
report, The Management School, Imperial College, [21] J.-K. Lee and Y.-D. Kim. Search heuristics for
London, England, 1997. resource-constrained project scheduling. Journal of
the Operational Research Society, 47:678–689, 1996.
[6] E. L. Demeulemeester and W. S. Herroelen.
A branch-and-bound procedure for the multiple [22] V. J. Leon and B. Ramamoorthy. Strength and
resource-constrained project scheduling problem. adaptability of problem-space based neighborhoods
Management Science, 38:1803–1818, 1992. for resource-constrained scheduling. OR Spektrum,
17:173–182, 1995.
[7] E. L. Demeulemeester and W. S. Herroelen. New
benchmark results for the resource-constrained [23] Z. Michalewicz. Heuristic methods for evolution-
project scheduling problem. Management Science, ary computation techniques. Journal of Heuristics,
43:1485–1492, 1997. 1:177–206, 1995.
[8] U. Dorndorf and E. Pesch. Evolution based learning [24] A. Mingozzi, V. Maniezzo, S. Ricciardelli, and
in a job shop scheduling environment. Computers L. Bianco. An exact algorithm for the resource-
& Operations Research, 22:25–40, 1995. constrained project scheduling problem based on a
[9] D. E. Goldberg. Genetic algorithms in search, op- new mathematical formulation. Management Sci-
timization, and machine learning. Addison-Wesley, ence, 44:714–729, 1998.
Reading, Massachusetts, 1989.
[25] L. Özdamar. A genetic algorithm approach to a
[10] S. Hartmann. Scheduling medical research experi- general category project scheduling problem. IEEE
ments — An application of project scheduling meth- Transactions on Systems, Man, and Cybernetics,
ods. Manuskripte aus den Instituten für Betrieb- Part C: Applications and Reviews, 29:44–59, 1999.
swirtschaftslehre 452, Universität Kiel, Germany,
[26] L. Özdamar and G. Ulusoy. A local constraint based
1997.
analysis approach to project scheduling under gen-
[11] R. Heilmann and C. Schwindt. Lower bounds for eral resource constraints. European Journal of Op-
RCPSP/max. Technical Report WIOR-511, Uni- erational Research, 79:287–298, 1994.
versität Karlsruhe, Germany, 1997.
[27] L. Özdamar and G. Ulusoy. A survey on the
[12] H. J. Holland. Adaptation in natural and artificial resource-constrained project scheduling problem.
systems. University of Michigan Press, Ann Arbor, IIE Transactions, 27:574–586, 1995.
1975.
[28] L. Özdamar and G. Ulusoy. An iterative local
[13] U. Kohlmorgen, H. Schmeck, and K. Haase. Experi- constraint based analysis for solving the resource-
ences with fine-grained parallel genetic algorithms. constrained project scheduling problem. Journal of
Annals of Operations Research, 90:203–319, 1999. Operations Management, 14:193–208, 1996.

[14] R. Kolisch. Resource allocation capabilities of com- [29] J. H. Patterson. A comparison of exact ap-
mercial project management systems — Resource proaches for solving the multiple constrained re-
management boosts up the German stock exchange. source, project scheduling problem. Management
Interfaces. Forthcoming. Science, 30:854–867, 1984.
A Competitive Genetic Algorithm for Resource-Constrained Project Scheduling 16

[30] C. R. Reeves. Genetic algorithms and combinatorial Instituten für Betriebswirtschaftslehre 425, Univer-
optimization. In V. J. Rayward-Smith, editor, Ap- sität Kiel, Germany, 1996.
plications of modern heuristic methods, pages 111–
125. Alfred Waller Ltd., Henley-on-Thames, 1995. [33] A. Sprecher, R. Kolisch, and A. Drexl. Semi-active,
active and non-delay schedules for the resource-
[31] S. E. Sampson and E. N. Weiss. Local search constrained project scheduling problem. European
techniques for the generalized resource-constrained Journal of Operational Research, 80:94–102, 1995.
project scheduling problem. Naval Research Logis-
tics, 40:665–675, 1993. [34] G. Ulusoy and L. Özdamar. Heuristic performance
and network/resource characteristics in resource-
[32] A. Sprecher. Solving the RCPSP efficiently at mod- constrained project scheduling. Journal of the Op-
est memory requirements. Manuskripte aus den erational Research Society, 40:1145–1152, 1989.