Plumbing Commissioning
Plumbing Commissioning
Chapter 1
Project: _____________________________________________ Address: ________________________________
Owner: _____________________________________________ Email/Phone: _____________________________
Owner’s Project Manager: ______________________________ Email/Phone: _____________________________
Cx Provider: _________________________________________ Email/Phone: _____________________________
Date Initiated: ______________________ Date Revised: ______________________
System Integrated System
Chapter 2
Commissioning
Commissioning Commissioning
Item Equipment/System Complete—
Required— Required—
Date
Y/N Y/N
1. Water distribution systems (potable and
nonpotable) plumbing fixtures and fittings
Chapter 3
2. Pumping and piping systems (water)
3. Water treatment devices and equipment
4. Water efficiency of plumbing fixtures
5. Nonpotable plumbing systems
6. Water storage tanks
Chapter 4
7. Backflow prevention assemblies
8. Swimming pool and decorative fountain
circulating systems
9. Water heating and recirculation
10. Solar hot-water heating
Chapter 5
11. Drainage, waste, and vent piping systems
(gravity and pressure)
Appendix B
Appendix B
The approval section that follows can be used if applicable to the planning process. Approval can be granted by the
Owner/representative, Design Team, or CxP depending on the Owner’s requirements.
I have reviewed the required items and plans and verified that they meet the project requirements:
Appendix B