PMP Comparisons: The Most Important, By: Dr. Ahmed Alsenosy
PMP Comparisons: The Most Important, By: Dr. Ahmed Alsenosy
Comparisons
The most important, By: Dr. Ahmed
Alsenosy
Contract Charter
A legally binding agreement between the Buyer and the It is usually prepared internally within the Performing
Seller. Organization.
It is a mutually agreed document between the Buyer and It is issued by the Project Sponsor to the Project Manager.
the Seller. Sponsor gives the commitment to provide funds and
resources while PM gives the commitment to complete the
project.
It is a legally binding agreement. Usually it is not a legally binding document.
It can be signed either for a project or for operational work. It is prepared for a project only.
Projects that are done internally without any third party As a good practice, a charter should always be prepared.
direction, support, or governance do not need a contract.
Contract VS Charter
All copyrights are reserved to Ahmed Alsenosy |
www.linkedin.com/in/Alsenosy
Team charter Charter
The team charter is a document that establishes the team It is usually prepared internally within the Performing
values, agreements, and operating guidelines for the team. Organization.
The team charter works best when the team develops it. It is issued by the Project Sponsor to the Project Manager.
All project team members share responsibility for ensuring Sponsor gives the commitment to provide funds and
the rules documented in the team charter are followed. resources while PM gives the commitment to complete the
project.
The team charter can be reviewed and updated periodically Usually it is not a legally binding document.
to ensure a continued understanding of the team ground
rules and to orient and integrate new team members.
It is prepared for a project or many projects It is prepared for a project only.
As a good practice, a team charter should always be As a good practice, a charter should always be prepared.
prepared.
Contains: Sources of overall project risk, indicating which are the most
List of identified risks. important drivers of overall project risk exposure;
Potential risk owners. and
List of potential risk responses. Summary information on identified individual project risks,
a short risk title, risk category, current risk status, one or such as number of identified threats and opportunities,
more causes, one or more effects on objectives, risk distribution of risks across risk categories, metrics and trends,
triggers etc.
Testing is an organized and constructed investigation conducted to An inspection is the examination of a work product to determine if it
provide objective information about the quality of the product or conforms to documented standards. The results
service under test in accordance with the project requirements. of inspections generally include measurements and may be conducted at
any level.
The intent of testing is to find errors, defects, bugs, or other The results of a single activity can be inspected, or the final product of the
nonconformance problems in the product or service. project can be inspected. Inspections may be called reviews, peer reviews,
- HVAC systems audits, or walkthroughs. In some application areas, these terms have
- Elevators narrow and specific meanings. Inspections also are used to verify defect
- Data base integration repairs.
- BMS - Concrete inspection
- Plastering inspection
- Painting inspection
Testing is an organized and constructed investigation conducted to An inspection is the examination of a work product to determine if it
provide objective information about the quality of the product or conforms to documented standards. The results
service under test in accordance with the project requirements. of inspections generally include measurements and may be conducted at
any level.
The intent of testing is to find errors, defects, bugs, or other The results of a single activity can be inspected, or the final product of the
nonconformance problems in the product or service. project can be inspected. Inspections may be called reviews, peer reviews,
- HVAC systems audits, or walkthroughs. In some application areas, these terms have
- Elevators narrow and specific meanings. Inspections also are used to verify defect
- Data base integration repairs.
- BMS - Concrete inspection
- Plastering inspection
- Painting inspection
The intent of testing is to find errors, defects, bugs, or The results of a single activity can be inspected, or the final
other nonconformance problems in the product or product of the project can be inspected. Inspections may be
service. called reviews, peer reviews, audits, or walkthroughs. In some
- HVAC systems application areas, these terms have narrow and specific
- Elevators meanings. Inspections also are used to verify defect repairs.
- Data base integration - Concrete inspection
- BMS - Plastering inspection
- Painting inspection
Example: Example:
If you have completed 1000 m3 excavation for previous If the assigned resource is capable of installing 25 meters of
project in 10 days and your current project have 2000 cable per hour, the duration required to
m3 then your current project excavation will take 20 install 1,000 meters is 40 hours (1,000 meters divided by 25
days meters per hour).
timing At the end of each phase or the project Throughout the project life cycle from start to end
How Establish a good Scope management plan and collect clear Finding & eliminating sources of quality problems
,complete and census requirements (functional or non functional through tools & equipment so that customer's
) and put suitable traceability matrix requirements are continually met.
Who implement Project manager, client or consultative body Quality control team
Example provide the performance report to my sponsor for his approval check the data and figures within my performance
As part of my project management report to ensure they are correct
requirements, I need to produce a
weekly project performance report.
Output (major) Formal acceptance Tally sheet, check sheet, inspection sheet
All copyrights are reserved to Ahmed Alsenosy |
www.linkedin.com/in/Alsenosy
Manage Quality vs Quality Control
item Manage Quality Quality Control
Definition QA is a set of activities for ensuring quality in the processes by which QC is a set of activities for ensuring quality in
products are developed as well as continues improvements. products. The activities focus on identifying defects
in the actual products produced.
Focus on QA aims to prevent defects with a focus on the process used to make the QC aims to identify (and correct) defects in the
product. It is a proactive quality process. finished product. Quality control, therefore, is a
reactive process.
How Establish a good quality management system and the assessment of its Finding & eliminating sources of quality problems
adequacy. Periodic conformance audits of the operations of the system. through tools & equipment so that customer's
requirements are continually met.
Responsibility Everyone on the team involved in developing the product is responsible for Quality control is usually the responsibility of a
quality assurance. specific team that tests the product for defects.
Statistical Techniques Statistical Tools & Techniques can be applied in both QA & QC. When they When statistical tools & techniques are applied to
are applied to processes (process inputs & operational parameters), they finished products (process outputs), they are called
are called Statistical Process Control (SPC); & it becomes the part of QA. as Statistical Quality Control (SQC) & comes under
QC.
Process group Execution All copyrights are reserved to Ahmed Alsenosy | Control
www.linkedin.com/in/Alsenosy
QUALITATIVE vs QUANTITATIVE
QUALITATIVE RISK ANALYSIS QUANTITATIVE RISK ANALYSIS
A qualitative risk analysis prioritizes the identified A quantitative risk analysis is a further analysis of the
project risks using a pre-defined rating scale highest priority risks during a which a numerical or
quantitative rating is assigned in order to develop a
probabilistic analysis of the project.
risk-level project-level
subjective evaluation of probability and impact probabilistic estimates of time and cost
You spend time and money in advance for the given risk You do not spend time or money in advance, but you keep
condition them ready, and invest them when needed
We are expected to mitigate the risks which are outside the By identifying the contingency plan, we do not change the
risk threshold. By applying a mitigation plan, we reduce the probability or impact of the current risk, but we plan to control
probability of impact of the identified risk. the impact as risk event looks like occurring.
This works as the first level of defense for the high exposure This works as a fallback plan for the high exposure risks.
risks
EEFs VS OPAs
Funding Limit reconciliation VS Funding Req.
• An information management system provides a set of standard tools for the project
manager to capture, store, and distribute information to stakeholders about the project’s
costs, schedule progress, and performance. Some software packages allow the project
manager to consolidate reports from several systems and facilitate report distribution to
the project stakeholders.