454a-Software Project Management PDF
454a-Software Project Management PDF
1. A unique, planned, scheduled activity with one or more objectives referred as___
A. Project
B. Job
C. Process
D. Task
ANSWER: A
6. Projects may be distinguished by whether their aim is to produce a ________ or meet certain _______.
A. product, objective
B. product, tasks
C. tasks, objective
D. tasks and null objects
ANSWER: A
7. The first stage of the software project is a ________which results in a recommended course of action.
A. system driven project
B. software driven project
C. hardware driven project
D. objectives driven project
ANSWER: D
9. In case of product-driven projects, the objectives of the project are defined in terms of ___________.
A. functional requirements only
B. resource and non-functional requirements
C. functional and quality requirements
D. resource requirements only
ANSWER: C
10. ________ defines what the end product of the project is to do.
A. product perspective.
B. Non-functional requirements.
C. Quality requirements.
D. Functional requirements.
ANSWER: D
11. ________ is a system analysis and design method designed primarily to provide functional requirements.
A. SSTD.
B. SADT.
C. SGTH.
D. STDH.
ANSWER: B
13. _______ is record of how much the organization is willing to spend to the system
A. Resource requirements.
B. Functional requirements.
C. Security requirements.
D. Non-functional requirements.
ANSWER: A
14. Projects are by definition __________ and therefore more uncertain than normal undertakings.
A. routine
B. non-routine
C. specific
D. controllable
ANSWER: B
18. The organization as part of its monitoring and control policy may have a ________ programme in place which dictates that certain statistics have to be collected at
various stages of a project.
A. measurement.
B. system.
C. software.
D. testing.
ANSWER: A
19. The products handed over to the clients at the end of projects are called as __________.
A. software
B. application program
C. deliverables
D. intermediate products
ANSWER: C
22. The relationship between program design and program specification can be portrayed in _________.
A. PFD.
B. DFD.
C. PDF.
D. DDF.
ANSWER: A
23. Which one of the following is NOT an agile method?
A. SCRUM
B. Extreme Programming (XP)
C. DSDM
D. Waterfall
ANSWER: D
24. Same generic fragment relates to more than _________ instance of the particular type of the product.
A. one.
B. two.
C. three
D. four
ANSWER: A
27. In order to carry out a successful strategic assessment of a potential project there should be strategic plan clearly defining the organization's _________.
A. objectives.
B. rules.
C. conditions.
D. ideas.
ANSWER: A
28. The standard way of evaluating the economic benefits of any projects is to carry out a ________ analysis.
A. price-benefit.
B. cost-benefit.
C. cash flow.
D. fund flow.
ANSWER: B
29. The costs that include the salaries and other employment costs of the staff involved in the development project and all associated costs are____________.
A. operational cost.
B. development cost.
C. setup cost
D. direct cost.
ANSWER: B
30. Long term or benefits that are considered very difficult to quantify is called _______.
A. direct benefits.
B. assessable benefits.
C. indirect benefits.
D. intangible benefits.
ANSWER: D
31. _________ will indicate when expenditure and income will take place.
A. Cash flow forecast.
B. Cost analysis.
C. Fund flow.
D. Technical forecast.
ANSWER: A
32. _________ is the time taken to break even or pay back the initial investment.
A. Back period.
B. Payback period.
C. Cash back period.
D. Rate of Return.
ANSWER: B
42. ________prototypes are used and discarded when the true development of the operational system is commenced.
A. Evolutionary.
B. Throw away.
C. Operational.
D. Real.
ANSWER: B
43. ______ is as when copies of input screens are shown to the users on a workstation, but the screens cannot actually be used.
A. Simulation.
B. Annealing.
C. Mock-ups.
D. RAD system.
ANSWER: C
45. The scope of the deliverables for an increment is rigidly constrained by an agreed deadline called as ____________.
A. sand boxing.
B. time boxing.
C. time delaying.
D. local delaying.
ANSWER: B
46. ______ would mean the change can be implemented without software development.
A. One cost.
B. Total cost.
C. Zero cost.
D. No cost.
ANSWER: C
47. SSADM means ___________.
A. Straight Systems Analysis Design Method.
B. Structured Systems Analysis Design Method.
C. Software Systems Analysis Design Method.
D. Solutions Systems Analysis Design Method.
ANSWER: B
54. The statement "If a system does not have to reliable, it can meet any other objective" is from __________.
A. Brooks Law.
B. Peters Law.
C. Parkinson's first Law.
D. Weinberg's Zeroth Law.
ANSWER: D
63. ________ the degree to which there is a large dispersed team as opposed to there being a small tightly knit team.
A. Small cohesion.
B. Team cohesion.
C. Process maturity.
D. Team maturity.
ANSWER: B
69. The activities have zero duration but are assumed to start at the same time as the first and the end at the same time as the last one is called__________.
A. hijacked activity.
B. heuristic activity.
C. hammocked activity.
D. hole activity.
ANSWER: C
70. ____ is carried out to calculate the earliest dates on which each activity may be started and completed.
A. Backward pass.
B. Forward pass.
C. No pass.
D. Increasing pass.
ANSWER: B
71. The time by which an activity may be delayed without affecting any subsequent activity is called _________.
A. action float.
B. terminal float.
C. free float
D. null float
ANSWER: C
72. The objective of ________ is to avoid or minimize the adverse effects of unforeseen events is called
A. risk management.
B. risk maintenance.
C. risk taking.
D. risky job.
ANSWER: A
73. A _________ is an event that might occur and if it occurs, create a problem for the successful completion of the project.
A. planning.
B. hazard.
C. safety.
D. start.
ANSWER: B
78. The shortest time in which we could expect to complete the activity, barring outright miracles called ________.
A. Optimistic Time
B. Pessimistic Time
C. Most Likely Time
D. Shortest Time
ANSWER: A
79. PERT combines three estimates of time and obtains a single expected duration is ____________.
A. te
B. tp
C. tm
D. ts
ANSWER: A
80. _________ is proportional to the difference between the optimistic and pessimistic estimates.
A. Activity Regression
B. Activity mean
C. Activity Standard Deviation
D. Activity Variance
ANSWER: C
81. The________ value in PERT is calculated for each node that has a target date.
A. x value.
B. y value.
C. t value.
D. z value.
ANSWER: D
84. A ________ is any item or person required for the execution of the project.
A. risk.
B. allocation.
C. activity.
D. resource.
ANSWER: D
85. According to Bob Hughes and Mike Cotterell, resources fall into _______ categories.
A. five.
B. four.
C. seven.
D. two.
ANSWER: C
87. "Each activity has been scheduled to start at its earliest start date" is called as_________.
A. likelihood.
B. activity schedule.
C. probability.
D. planning.
ANSWER: A
88. In _________ activities are allocated resources in ascending order of total float.
A. total free priority.
B. total float priority.
C. technical float priority.
D. top float priority
ANSWER: B
89. ______ is the selection of individuals in which the final shape of the project team is taken into account
A. Independent building.
B. Construction building.
C. Team building.
D. Recruitment.
ANSWER: B
90. To know whether a particular individual is available when required is known as _____.
A. reliability.
B. consistency.
C. availability.
D. portability.
ANSWER: C
92. _________ represents expenditure that an organization incurs, which cannot be directly related.
A. Under head
B. Over head.
C. Top head.
D. Miscellaneous expenses
ANSWER: B
96. _______ is an activity bar chart indicating scheduled activity dates and durations frequently augmented with activity floats. .
A. Bar chart.
B. Ball chart.
C. Slip Chart.
D. Gantt chart
ANSWER: D
97. Gantt charts, Slip chars and Ball charts are under ___________ process.
A. monitoring.
B. verification.
C. control.
D. visualization.
ANSWER: D
98. _______ is the method of recording and displaying the way in which targets have changed throughout the duration of the project.
A. Gantt chart.
B. Bar chart.
C. Timeline.
D. Schedule.
ANSWER: C
99. The total value credited to a project at any point is known as _______.
A. earned value.
B. moral value.
C. money value.
D. recurred value
ANSWER: A
100. The priorities we might apply in deciding levels in monitoring is called as ______.
A. deciding monitoring.
B. monitoring.
C. tracking.
D. prioritized monitoring.
ANSWER: D
101. Risk management will occur in the step ____________ of step wise planning.
A. 7
B. 8
C. 6
D. 4
ANSWER: C
102. __________ relates to the physical resources used when the software is executed.
A. Functionality.
B. Maintainability.
C. Reliability.
D. Efficiency.
ANSWER: D
104. A _________ is a container-like element for organizing other elements into groups.
A. classes.
B. adornments.
C. packages.
D. activities.
ANSWER: C
109. An ______ is a named property of a class that describes the object being modeled.
A. method.
B. constant.
C. message.
D. attribute.
ANSWER: B
111. _______ is a description of a set of objects that share the same attributes,operations, relationships, and semantics.
A. Object.
B. Class.
C. Process.
D. Instance
ANSWER: B
112. _______ will divide the domain of the task hierarchy in activity diagrams.
A. Swim lane.
B. Activity.
C. Interface.
D. Split.
ANSWER: A
113. _______ is the task/process which describes the way in which the actor interact the system.
A. Class.
B. Flow.
C. Object.
D. Use case.
ANSWER: D
115. A metric used to measure the characteristic of documentation and code called as
A. Process metric
B. Product Metric
C. Test metrics
D. None of the above
ANSWER: B
118. Software testing which is done without planning and Documentation is known as
A. adHoc Testing
B. Unit Testing
C. Regression testing
D. Functional testing.
ANSWER: A
119. This type of testing method attempts to find incorrect or missing functions, errors in data structures or external database access, interface errors, Performance errors
and initialization and Termination errors. It is called as
A. White Box Testing
B. Grey Box Testing
C. Black Box Testing
D. Open Box Testing
ANSWER: C
120. Retesting of a single program or component after a change has been made?
A. Full Regression Testing
B. Unit Regression
C. Regional Regression
D. Retesting
ANSWER: B
121. Defects are less costly if detected in which of the following phases
A. Coding
B. Design
C. Requirements Gathering
D. Implementation
ANSWER: C
133. You are told to prepare a report on the most commonly occurring product defects. You review the software defect reports, which categories the defects of coding
errors, requirement errors, documentation errors, etc. The best tool to report this information is
A. A histogram
B. A pareto diagram
C. A cause and effect diagram
D. A scatter plot
ANSWER: A
134. A statistical technique to assess, monitor and maintain the stability of a process is
A. Pareto chart
B. Control chart
C. Run chart
D. Histogram
ANSWER: B
136. If the measurement taken by the two people are same refers to the terms as
A. Reliability
B. Validity
C. Calibration
D. Ease of use and simplicity
ANSWER: A
139. You are performing a test to see that it complies with the user requirement that a certain field be populated by using a drop down box containing a list of values.
What kind of testing are you doing?
A. White box testing
B. Black box testing
C. Load testing
D. Regression testing
ANSWER: B
141. The approach/document used to make sure all the requirements are covered when writing test cases
A. Test Matrix
B. Checklist
C. Test bed
D. Traceablity Matrix
ANSWER: D
142. Executing the same test case by giving the number of inputs on same build called as
A. Regression Testing
B. ReTesting
C. Ad hoc Testing
D. Sanity Testing
ANSWER: B
143. To check whether we are developing the right product according to the customer requirements are not. It is a static process
A. Validation
B. Verification
C. Quality Assurance
D. Quality Control
ANSWER: B
144. To check whether we have developed the product according to the customer requirements r not. It is a Dynamic process.
A. Validation
B. Verification
C. Quality Assurance
D. Quality Control
ANSWER: A
146. A Non-Functional Software testing done to check if the user interface is easy to use and understand
A. Usability Testing
B. Security Testing
C. Unit testing
D. Block Box Testing
ANSWER: A
147. It measures the quality of processes used to create a quality product. It is a system of management activities, It is a preventive process, It applies for entire life cycle
& Deals with Process.
A. Validation
B. Verification
C. Quality Assurance
D. Quality Control
ANSWER: C
150. Name the events that will be analyzed, Count the named incidents, Rank the count by frequency using a bar chart & Validate reasonableness of the analysis is called
as
A. Pareto Analysis
B. Cause and Effect Diagram
C. SWOT Analysis
D. Pie Charts
ANSWER: A
Staff Name
Sujatha S .