All Presentations For Website
All Presentations For Website
– Solar panels
– Inverter
e8/PPA
e8 Grid Connected
/ PPA DSM
2-6, 20091-5, 2010
Palau - November
Misconception about Grid Connected PV
building first then the surplus goes to the grid. All the
solar power goes into the grid and all the building
Republic
annual accounting.
– Solar tends to be seasonal so some months there
may be a surplus sent into the grid from solar and
some months there will be more used from the grid
Grid Connected
retail charge.
If payment is zero, that encourages users to
Republic
Wp of capacity
Fiji
(currently ~US$2/Wp
When new, may be a
better performer than
crystalline panels in the
Grid Connected
the tropics
e8/PPA
e8
2-6, 20091-5, 2010
Panel Connections for Grid-Connected Solar
Palau - November
• Panel interconnections
IslandsofNovember
environment
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010
Palau - November
Individual connectors
Fiji Workshop Solar PV Workshop
Melting of connector
in service in Fiji
Grid Connected
caused by resistance
heating due to salt
/ PPA DSM
corrosion
e8/PPA
e8
e8/PPA
e8 Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Palau - November
IslandsofNovember 2-6, 20091-5, 2010
Panel
junction box
connections
using standard
2-6, 20091-5, 2010
Palau - November
Panel Mounting
• Roof mount
– Lowest cost
IslandsofNovember
– No land needed
– Fastest installation
Republic
• Ground mount
– Expensive
– Need significant land area
– Very flexible for array arrangement and
Grid Connected
orientation
– Easy to access for testing and maintenance
/ PPA DSM
equator.
Fiji
temperatures
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010
Palau - November
Inverter
Frequency variations
Fiji
Voltage variations
Excessive rate of frequency variation
Workshop Solar PV Workshop
multi-phase configurations
– Often installed with many paralleled inverter units
in a rack or on a wall for larger systems
Workshop Solar PV Workshop
• Rack of paralleled
inverters for larger
Workshop Solar PV Workshop
scale PV Grid
Connection
Grid Connected
/ PPA DSM
e8/PPA
Photo by SMA
Bank of 100 kW inverters
2-6, 20091-5, 2010
Republic
Fiji Palau - November
IslandsofNovember
Workshop Solar PV Workshop
Grid Connected
3 Phase Multiple Inverter Installation
transformer.
Republic
Fiji
DC disconnect switch
Fiji
inverter
Fiji
is not a problem)
Should be cleaned during installation or at
commissioning because manufacturing
Workshop Solar PV Workshop
problem exists
e8/PPA
e8
2-6, 20091-5, 2010
Palau - November
Solar Panels
2-6, 20091-5, 2010
Palau - November Photovoltaics
• In the tropics, solar cells are 50C to over 60C. Higher cell temperatures
Fiji
• Panels rarely face directly toward the sun, surface reflections increase
Workshop Solar PV Workshop
• There is often a mismatch between the load and the panel resulting in a
few percent reduction from the rated value.
e8/PPA
e8 Grid Connected
/ PPA DSM
2-6, 20091-5, 2010
Panel Types
Palau - November
This is the oldest design and provides the highest light to electricity
conversion efficiency. Round cells are made initially but they may be
cut square. Panel made up of many cells connected in series. Very
Republic
reliable.
Fiji
Excellent reliability.
Cells
Polycrystalline
volts. The area of the cell determines the Amperes it can produce with
modern cells providing 5-8A under full sun conditions.
Workshop Solar PV Workshop
• Cells are embedded in a clear plastic material between the top layer
Grid Connected
and the bottom layer. This is called the encapsulant and serves to help
waterproof the panel and to reduce internal reflections that would lower
/ PPA DSM
panel efficiency.
e8/PPA
e8
e8/PPA
e8 Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Palau - November
IslandsofNovember 2-6, 20091-5, 2010
cross section
Typical solar PV
panel construction
e8/PPA
e8 Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Palau - November
IslandsofNovember 2-6, 20091-5, 2010
Terminology
2-6, 20091-5, 2010
Recommended Specifications
Palau - November
• Panels
IslandsofNovember
inverter
Fiji
temperature goes up
Fiji
connection will work well only if the panels have the same ampere rating.
e8/PPA
e8
2-6, 20091-5, 2010
Palau - November Ampere Rating of Panels
over 1000 V
/ PPA DSM
e8/PPA
e8
e8/PPA
e8 Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Palau - November
IslandsofNovember 2-6, 20091-5, 2010
The shaded cell acts as a resistor and absorbs power from the string
e8/PPA
e8
2-6, 20091-5, 2010
Seasonal Changes and Shade
Fiji Palau - November
IslandsofNovember
Republic Workshop Solar PV Workshop
Grid Connected
panel output can fall as much as 20% over the Wp rating just due to
temperature
• Monocrystalline and polycrystalline panels lose much more power with
increased temperature than thin film panels
Workshop Solar PV Workshop
• NEVER mount solar panels flush on any surface, if at all possible provide 150
mm (6 inches) or more of ventilation space underneath panels, especially on
metal roofs and never less than 60 mm (2.5 inches)
e8/PPA
e8 Grid Connected
/ PPA DSM
e8/PPA
e8 Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Palau - November
IslandsofNovember 2-6, 20091-5, 2010
Temperature Effects – Crystalline Cells
e8/PPA
e8 Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Palau - November
IslandsofNovember 2-6, 20091-5, 2010
Spacing Under Panels for Ventilation
• Type = Monocrystalline
IslandsofNovember
• Wp = 170 Watts
Republic
Fiji
• Voc = 43.3V
• Isc = 5.0 A
Workshop Solar PV Workshop
• Vmpp = 36.1V
Grid Connected
• Impp = 4.7 A
/ PPA DSM
91.7mV/°F)
e8
Grid-Connected Solar PV – Inverters
and Strings
Dr. Herbert A. Wade
power for input to the grid when the main grid supply is
off
Republic
– Effective loading
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010
Palau - November
Common in Europe
– One inverter fails and only a part of the output is lost
– Spare parts are not expensive and are easily stocked for
Workshop Solar PV Workshop
quick replacement
– Maintenance does not require special skills or training
for the specific type of inverter being used
– Slightly higher overall cost than a single large inverter
Grid Connected
but the life cycle cost is lower for the Pacific Islands due
to the cost of repair and shipping for single large
inverters
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010 Typical Inverter
SMA Sunny Boy 3300
Fiji Palau - November
IslandsofNovember
Republic Workshop Solar PV Workshop
Grid Connected
Utilities that follow specific (Australia, NZ, USA) power standards must be sure
to require the installation of inverters that follow those same power standards.
/ PPA DSM
some may have peculiarities that keep them from fitting the standards exactly.
e8
e8/PPA
e8 Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Palau - November
IslandsofNovember 2-6, 20091-5, 2010
Sample Inverter Specification Sheet
2-6, 20091-5, 2010
Primary Specifications
Palau - November
• Output Power
Republic
– Transformer included
Fiji
AC power
requires it
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010
Transformerless Inverters
Palau - November
Must be grounded
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010
Palau - November
Inputs from the PV Array
the string
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010
Arcing
Palau - November
is broken
motion)
– Fan operation
– Time and date of last restart
/ PPA DSM
before sunrise)
– If actual data are not available assume 19°C
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010
Palau - November
when the cells are coldest (for the sample panels that
is 43.3V
Republic
Voc
Isc
Vpmax = Vmpp
Ipmax = Impp
Workshop Solar PV Workshop
input
whole number)
e8/PPA
e8
2-6, 20091-5, 2010
Minimum Panels in a String
Palau - November
can be made
Fiji
loops
CORRECT
Republic
Fiji
INCORRECT
Workshop Solar PV Workshop
Grid Connected
/ PPA DSM
requirements:
– A DC disconnect for each string
Republic
range
e8/PPA
e8 Grid Connected
/ PPA DSM
2-6, 20091-5, 2010
Sample Basic Residential System
Palau - November
IslandsofNovember
• 10 panels
• SMA Sunny Boy 3300 inverter
Republic
• Watts = 1700 Wp
Fiji
http://eosweb.larc.nasa.gov/cgi-
bin/sse/grid.cgi?email=
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010
Input estimation
Republic
Fiji Palau - November
IslandsofNovember
Workshop Solar PV Workshop
The width of the rectangle = “peak sun hours” or the hours that
the sun would have to shine at 1000 W/m2 to provide the same
energy as it actually did over the day. That will be the same number
/ PPA DSM
rating times “peak sun hours at 1000 W/m2 gives the output from
IslandsofNovember
would be:
Fiji
the actual output will be about 170 x 5.1 x .73 = 633 Wh/day
e8/PPA
e8
2-6, 20091-5, 2010
Adjustment for System Losses
Palau - November
about 10° and the site being within 10° of the equator.
For sites with a latitude higher than 10° the tilt should
Republic
the equator
/ PPA DSM
e8/PPA
e8
2-6, 20091-5, 2010
Shading
Palau - November
temperature measurement
/ PPA Grid
e8/PPA
e8
21-26, 2010
The Building at 0845 on a Clear Day
Republic
Fiji ofNovember
Islands 2-6, 2009
Fiji – November
Workshop Solar PV Workshop
DSMConnected
The roof peak runs NW-SE and the slope is about 15°. Wood truss
/ PPA Grid
east.
e8
21-26, 2010
Choice of Roof side
2-6, 2009
• The maximum sun over the year falls on a south facing roof. The
Fiji – November
temperature is lowest.
– Morning will be when the panel temperature is lowest so
Islands
– The most energy will fall over the year on the SW roof
because of the sun being lower in the south sky during the
dry season when there is high sun input
Workshop Solar PV Workshop
east roof was made partly because the output reducing effect of
high afternoon temperature will be high in this environment and
partly because of the shading that may be introduced by the light
/ PPA Grid
Possible shading.
/ PPA Grid
e8/PPA
e8
21-26, 2010
Laying out the Inverter Installation
2-6, 2009
place on the rails. In this case, two rows of five was the
ofNovember
• Teamwork
On the Roof Mounting Panels
e8/PPA
e8 / PPA Grid
DSMConnected
Workshop Solar PV Workshop Republic
Fiji Islands Fiji – November
ofNovember 21-26, 2010
2-6, 2009
Clamping Panels to Rails
e8/PPA
e8 / PPA Grid
DSMConnected
Workshop Solar PV Workshop Republic
Fiji Islands Fiji – November
ofNovember 21-26, 2010
2-6, 2009
Wiring the String to the Inverter
• Mounting the junction boxes (for + and − to DC disconnect)
e8/PPA
e8 / PPA Grid
DSMConnected
Workshop Solar PV Workshop Republic
Fiji Islands Fiji – November
ofNovember 21-26, 2010
2-6, 2009
Why not crimp on connectors?
21-26, 2010
Wiring the String to the Inverter
2-6, 2009
the box. The − wire goes through the + box just to enter
Republic
touches the roof. Run the ground wire through the main
conduit along with the string connection wires.
Fiji Islands
Republic
e8/PPA
e8 Workshop Solar PV Workshop
DSMConnected
/ PPA Grid
e8/PPA
e8 / PPA Grid
DSMConnected
Workshop Solar PV Workshop Republic
Fiji Islands Fiji – November
ofNovember 21-26, 2010
2-6, 2009
Finished on the Roof
e8/PPA
e8 / PPA Grid
DSMConnected
Workshop Solar PV Workshop Republic
Fiji Islands Fiji – November
ofNovember 21-26, 2010
2-6, 2009
Wire AC and DC disconnects and Ground
21-26, 2010
Connect the Final Panel Connection
2-6, 2009
Source Energy
Hydro 2 TW (1012)
176PW = 176 Х1015
Fiji
Reach
to the earth (peta Watt)
Tidal force 3 TW
defined as 100%
Geothermal 32 TW
Workshop Solar PV Workshop
Wind 3.7 PW
The earth
e8e8/PPA
2
22-26, 2010
Introduction – About Q2.
2-6, 2009
Gobi desert
Fiji
Total of land
surface
3
22-26, 2010
Introduction – About Q2.
2-6, 2009
25%
Fiji
20
Workshop Solar PV Workshop
10
6%
0
1950 1960 1970 1980 1990 2000
Grid Connected
the almost limitless energy of the sun for the uses of civilization”.
4
22-26, 2010
Introduction
2-6, 2009
PV is installed rapidly!
Fiji - November
IslandsofNovember
16000
14000
Fiji
12000
10000
FIT (Feed-In-Tariff) started in
Workshop Solar PV Workshop
8000 Germany.
6000
4000
2000
Grid Connected
0
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
/ PPA DSM
Year
e8e8/PPA
5
22-26, 2010
Introduction – What is FIT (Feed-In-Tariff)
2-6, 2009
power rate.
Fiji
40 36.0
▪But electric power company’s
32.8 29.8
27.1
24.7 burden becomes large, and
20 usual electric power rate is
/ PPA DSM
increasing.
e8e8/PPA
0
2004 2006 2008 2010 2012 2014 2016
6
22-26, 2010
Introduction – FIT in Japan
2-6, 2009
Japanese Feed-In-Tariff
Fiji - November
IslandsofNovember
Japan Germany
(since 2009) (since 2004)
Republic
purchase
10 years 20 years
period
Fiji
keeps down tariff of PV than Germany because this system makes electricity
e8e8/PPA
lower tax
8
22-26, 2010
Introduction Features of PV system
2-6, 2009
Fiji - November
Advantage Disadvantage
IslandsofNovember
present situation
4.Possible mass production 4. DC output (can be advantage
because of modular structure in some case)
5.Free and easy design from
Grid Connected
9
22-26, 2010
Type of power system
2-6, 2009
PV
Install a renewable energy system
PV PV in each household separately
This system is applied mainly for a
Republic
10
22-26, 2010
Off Grid: Solar Home System (SHS)
2-6, 2009
Fiji - November
No Title Sub-title Main Grid Supplied Gen Size Genset Other Battery Note
IslandsofNovember
grid Households
Battery
Fiji
charge
station
PV hybrid Off AC 10 - 500kW Optional Wind Optional New
systems (a few biomass components
within hours micro-hydro
mini-grid per day) etc.
Workshop Solar PV Workshop
etc.
hours
per day)
/ PPA DSM
e8e8/PPA
11
e8e8/PPA Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Fiji - November
IslandsofNovember 22-26, 2010
2-6, 2009
PV
Modules
Calculators
<Example>
DC
Solar Direct System
Load
Fans
(car accessory)
Off Grid: Solar Home System (SHS)
Water pump
12
22-26, 2010
Off Grid: Solar Home System (SHS)
2-6, 2009
PV Charge
Battery Load
Modules Controller DC
Republic
Fiji
<Example>
Message Board Outdoor Light
/ PPA DSM
e8e8/PPA Workshop Solar PV Workshop
Grid Connected
13
22-26, 2010
Off Grid: Solar Home System (SHS)
2-6, 2009
If any
IslandsofNovember
PV Charge
Battery Load
Modules Controller DC
Republic
Solar array AC
/ PPA DSM
e8e8/PPA Workshop Solar PV Workshop
Grid Connected
14
22-26, 2010
Off Grid: Solar Home System (SHS)
2-6, 2009
15
22-26, 2010
Off Grid: Solar Home System (SHS)
2-6, 2009
Quiz
Fiji - November
IslandsofNovember
16
22-26, 2010
Off Grid: Solar Home System (SHS)
2-6, 2009
nomad.
Workshop Solar PV Workshop
17
22-26, 2010
Off Grid: Solar Home System (SHS)
2-6, 2009
<Example> PV on a camel
IslandsofNovember
Republic
solar panel
Fiji Workshop Solar PV Workshop
Grid Connected
18
22-26, 2010
Off Grid: DC and AC supply system
2-6, 2009
Fiji - November
No Title Sub-t.itle Main Grid Supplied Gen Size Genset Other Battery Note
IslandsofNovember
grid Households
Battery
Fiji
charge
station
PV hybrid Off AC 10 - 500kW Optional Wind Optional New
systems (a few biomass components
within hours micro-hydro
mini-grid per day) etc.
Workshop Solar PV Workshop
etc.
hours
per day)
/ PPA DSM
e8e8/PPA
19
22-26, 2010
DC and AC supply system (PV system)
2-6, 2009
Fiji - November
50 – 70 W
IslandsofNovember
1 to 50 kW
Stationary PV system
20
22-26, 2010
Feature of DC and AC supply system
2-6, 2009
Fiji - November
IslandsofNovember
components
AC Connection of • Free selection of energy • Necessity of Inverters
sources and sources (standard grid
loads via AC components)
distribution • Long distances between
Grid Connected
line components
• Simple extendibility, future-
proof
/ PPA DSM
e8e8/PPA
21
22-26, 2010
Off Grid: PV mini grid
2-6, 2009
Fiji - November
No Title Sub-t.itle Main Grid Supplied Gen Size Genset Other Battery Note
IslandsofNovember
grid Households
Battery
Fiji
charge
station
PV hybrid Off AC 10 - 500kW Optional Wind Optional New
systems (a few biomass components
within hours micro-hydro
mini-grid per day) etc.
Workshop Solar PV Workshop
etc.
hours
per day)
/ PPA DSM
e8e8/PPA
22
22-26, 2010 Off Grid: PV mini grid:
System configuration
2-6, 2009
Fiji - November
IslandsofNovember
PV panel (≅ 50 kWp)
Republic
Fiji
Isolated, AC supply,
no genset
Grid Connected
through a grid
23
22-26, 2010
DC → AC
IslandsofNovember
Peripheral equipments
PV array Junction box Power Conditioner
Republic
AC
DC
Fiji
grid
DC/DC chopper
PV mounting Insulation transformer
Workshop Solar PV Workshop
Protection system
structure Wh meter
For buying
For selling
For wiring
Maintenance clerk Battery It’s important for
Grid Connected
24
22-26, 2010
• Junction box
IslandsofNovember
– Lightning protection/Arrester
Lightning protection
Fiji
– Terminal block
– Box Reverse flow protection
PV array Junction box
Workshop Solar PV Workshop
• Distribution board P1 P
N1 To
• Wh meter From N
inverter
• Battery PV Main CB
P2
array N2
Grid Connected
Pn
/ PPA DSM
Nn
e8e8/PPA
25
22-26, 2010
DC Solar panel
AC
Republic
Selling
Fiji
Buying inverter
Workshop Solar PV Workshop
Junction
Wh meter
box
Distribution
Grid Connected
board
/ PPA DSM
e8e8/PPA
26
e8e8/PPA Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Fiji - November
IslandsofNovember 22-26, 2010
2-6, 2009
0.5
0
1.5
1
2
1
3 5 7 9 11 13 15 17 19 21 23
0
50
3kW PV output and household demand (in Japan)
100
150
Source: METI
27
22-26, 2010
Off Grid: PV mini grid: Examples
Republic
Fiji 2-6, 2009
Fiji - November
IslandsofNovember
Workshop Solar PV Workshop
Source: GTZ-ZSW
Battery Sealed (AGM) lead acid battery, cells 2 V/1300 Ah, 3 parallel strings with
Fiji
AC 2 isolated and not grounded single phase grids supply different parts of
Distribution the township. The single households have electronic energy Meters
Households All electrified households have electric light (fluorescent lamps (9W) or
incandescent lamps (40W)), 90 % of the households have colour TV +
satellite receiver + DVD player, and chest freezer to store meat, more
Grid Connected
and more households have electric heating blankets and pillows, some
have washing machines (for external hot water supply)
/ PPA DSM
Source: GTZ-ZSW
e8e8/PPA
29
22-26, 2010
16kW 24kW
Fiji - November
40kW
18module (85W)
×26 strings
858kWh 2 isolated and not grounded single phase grids supply different parts of the
3 parallel strings township.
with 110 cells. <Household>
All electrified households have electric light (fluorescent lamps (9W) or
/ PPA DSM
receiver + DVD player, and chest freezer to store meat, more and more
households have electric heating blankets and pillows, some have washing
machines (for external hot water supply) 30
e8e8/PPA Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Fiji - November
IslandsofNovember 22-26, 2010
2-6, 2009
31
22-26, 2010
Nighttime Pleasant!
Workshop Solar PV Workshop
Grid Connected
Source: NEDO
32
e8e8/PPA Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Fiji - November
IslandsofNovember 22-26, 2010
2-6, 2009
Battery-Charging Station
Source: NEDO
33
22-26, 2010
2-6, 2009
Design procedure
• Significance
Fiji - November
• Concept
IslandsofNovember
• Feasibility study
– Generation
Republic
– Distribution
– Demand forecast and dispatching
Fiji
– Environmental assessment
– Economical evaluation
• Design
Workshop Solar PV Workshop
– System configuration
– Design
– Regulation
– Specification of components
Grid Connected
– How to select
– Installation
/ PPA DSM
• O&M
e8e8/PPA
34
22-26, 2010
Planning & design
2-6, 2009
Concept design of the system Demand characteristics, energy cost, electricity tariff
Investigation of target site REN main unit, inverter, grid connection, battery, env.
measure
Republic
Generation cost,
Workshop Solar PV Workshop
Analyze cost/benefit
Grid Connected
Implementation
35
22-26, 2010
Check list on planning (1)
2-6, 2009
– For what?
IslandsofNovember
– Where?
Is existing facility or not? Exact location.
Fiji
– What load?
Characteristics and size of load. Enough space
for installed equipment?
Workshop Solar PV Workshop
– Which system?
Isolated or grid-connected? With battery or not?
– When and how much?
Construction schedule and cost. Can it be
Grid Connected
available?
/ PPA DSM
e8e8/PPA
36
22-26, 2010
Check list on planning (2)
2-6, 2009
• Project team
Fiji - November
37
22-26, 2010
Check list on planning (3)
2-6, 2009
• Site survey
Fiji - November
– Ambient environment
IslandsofNovember
Effect of fallen leaves and sand dust, snow cover (depth and
frequency)
Fiji
38
22-26, 2010
Check list on planning (4)
2-6, 2009
• Preliminary consultation
Fiji - November
• Concept check
Workshop Solar PV Workshop
39
22-26, 2010
Check list on design (5)
2-6, 2009
– Firm policy? – For what? Where? How big? How is the system?
When? How much?
IslandsofNovember
– Subsidy
– Application for local authority
• Design check
/ PPA DSM
Cover glass
Fiji
Electrode
Bird
Falling dung
leaf
Workshop Solar PV Workshop
PV cell
HOT SPOT!
e8e8/PPA
41
22-26, 2010
Key issue ; Ambient environment
2-6, 2009
Stone
throwing Falling nuts
Republic
Fiji
Sand breeze
Workshop Solar PV Workshop
Example of countermeasure
Sand scratch
(like frosted grass)
Grid Connected
/ PPA DSM
Sand-break forest
e8e8/PPA
42
22-26, 2010
Key issue ; Ambient environment
2-6, 2009
SOx Contamination
Electrically
Sea breeze grounding
Workshop Solar PV Workshop
43
22-26, 2010
Key issue ; Ambient environment
2-6, 2009
Lightning rod
Strong enough
for stormy wind
Workshop Solar PV Workshop
Heat up
Enough ventilation
for cooling
Grid Connected
/ PPA DSM
44
22-26, 2010
Key issue ; Ambient environment
2-6, 2009
0
-1 Slide is starting when
-2 thickness of snow cover
-3
/ PPA DSM
is over 20 – 30 cm.
-4 Rain
e8e8/PPA
Days
10 20 30
45
22-26, 2010
Key issue ; Installed site
2-6, 2009
decrease of PV.
Build
Grid Connected
ing Mountain
4
<Typical type of Japanese roof>
Fiji
south
north
3
east west east
Workshop Solar PV Workshop
2 west
north south
1
(ventilation = 30 degree)
Grid Connected
0
20 40 60 80
/ PPA DSM
Ventilation (degree)
e8e8/PPA
47
22-26, 2010
Key issues; Design of operation pattern
2-6, 2009
Generation curve
Workshop Solar PV Workshop
AM PM
/ PPA DSM
48
22-26, 2010
Key issues: operation & maintenance
2-6, 2009
Load curve
Workshop Solar PV Workshop
Inverter
facility
AM PM PCS
Battery
Supply from battery
e8e8/PPA
49
22-26, 2010
EL Х D Х R
PAS =
(HA / GS) Х K
Republic
Fiji
Bracket
50
22-26, 2010
PAS =
Considering (HA / GS) Х K Loss, etc
margin, loss
Republic
(kWh) (kWh)
On site Wee hours Daytime Nighttime
EL condition HA ХGS/HA AM PM
condition
back up
= EL / (GS / HA)
e8e8/PPA
generator
51
22-26, 2010
Calculate from
Fiji - November
Exercise1
electric energy
IslandsofNovember
EL Х D Х R
PAS = = kW
(HA / GS) Х K
Republic
Fiji
K = 0.7 (typical)
e8e8/PPA
52
22-26, 2010
square measure
IslandsofNovember
EP = HA Х K ХPAS
Republic
Cell
Backside film Cell Filling
Bracket
/ PPA DSM
e8e8/PPA
53
22-26, 2010
▪ residence
IslandsofNovember
54
22-26, 2010
solar radiation
Calculation Example
Fiji - November
[kWh / m2 ▪ day]
▪ roof top mount 1 3.67
Republic
north 2 3.73
Fiji
3 4.14
4 4.12
south In Japan 5 4.39
Workshop Solar PV Workshop
9 3.39
10 3.32
/ PPA DSM
11 3.10
e8e8/PPA
12 3.29
55
22-26, 2010
Calculation Example
Fiji - November
Please modify
IslandsofNovember
= 102W Х 6 = 612W
(3) Output voltage of one string
= 34V Х 6 = 204V
Workshop Solar PV Workshop
(4) The number of strings, which can be installed on the roof top
= 4 strings (refer to previous slide)
(5) electricity output of this solar power system (in standard condition)
= 612W Х 4 = 2448W → about 2.4kW (PAS)
Grid Connected
▪ Condo
IslandsofNovember
57
22-26, 2010
solar radiation
Exercise 2
Fiji - November
[kWh / m2 ▪ day]
▪ roof top mount 1 3.67
Republic
2 3.73
north
Fiji
3 4.14
4 4.12
5 4.39
Workshop Solar PV Workshop
south 6 3.77
7 3.74
--- 8 4.22
Grid Connected
--- 9 3.39
10 3.32
---
/ PPA DSM
11 3.10
e8e8/PPA
12 3.29
58
22-26, 2010
Exercise 2
Fiji - November
IslandsofNovember
= W
(3) Output voltage of one string
= V
Workshop Solar PV Workshop
=
e8e8/PPA
59
22-26, 2010
PCS
• Procedure
– Decide purpose of battery system
Workshop Solar PV Workshop
60
22-26, 2010
Battery discharge
DOD ( Depth of Discharge) = Х100
Nominal battery capacity
Republic
Example of DOD
Workshop Solar PV Workshop
Cycle life is
decreasing with
increase of DOD.
Grid Connected
/ PPA DSM
e8e8/PPA
61
22-26, 2010
Accident prevention
IslandsofNovember
PCS Grid
Republic
Day time
Night time
Battery
Workshop Solar PV Workshop
PCS Grid
outage
Grid Connected
Types of battery
2-6, 2009
PCS Grid
Republic
Electricity flow
Fiji
Peak time
Off peak time
Battery
Workshop Solar PV Workshop
DC Load
Electricity flow
/ PPA DSM
Day time
Battery
e8e8/PPA
Night time
63
22-26, 2010
■Discharge current Id ;
IslandsofNovember
Calculation Example
Fiji - November
IslandsofNovember
Load for
Vd = 2V Ef = 90%
Accident prevention
PCS Grid
outage
Grid Connected
Vi = 250V P = 3kW
Should discharge
Charger
for 12 hours (T)
/ PPA DSM
1.8V
e8e8/PPA
Battery 5℃
65
22-26, 2010
Calculation Example
Fiji - November
1.5-9.5h
25 11.50 10.00 9.40 8.90
10h 5(outside) 12.70 10.50 10.00 9.70
-5(inside) 14.00 12.00 11.00 10.60
Grid Connected
/ PPA DSM
e8e8/PPA
66
22-26, 2010
Calculation Example
Fiji - November
3000W = 13.2A
IslandsofNovember
(1)Discharge current Id =
0.9 Х(250V + 2V)
(2)Required number of battery connected in series N
Republic
250V + 2V
= = 140
Fiji
1.8V
(3)Convertion time of capacity K
Workshop Solar PV Workshop
K = 10.50 + 12 – 10 = 12.50
Grid Connected
(4)Battery capacity C
12.50h Х13.2A
/ PPA DSM
= = 206Ah
0.8
e8e8/PPA
67
22-26, 2010
Exercise 3
Fiji - November
IslandsofNovember
PCS Grid
Grid Connected
Vd = 2V
Battery
22-26, 2010
Exercise 3
Fiji - November
1-1.5h
Fiji
70
22-26, 2010
Exercise 3
Fiji - November
IslandsofNovember
(1)Discharge current Id = A
=
Fiji
K=
(4)Battery capacity C
= Ah
Grid Connected
/ PPA DSM
e8e8/PPA
71
22-26, 2010
■Battery capacity C ;
Workshop Solar PV Workshop
72
22-26, 2010
Exercise 4
Fiji - November
▪ N ; Number of battery = 48
Fiji
10days
▪ DOD ; Depth Of Discharge = 65%
Stand alone
Workshop Solar PV Workshop
2.4kWh
Vd = 2V DC Load
48cells
2V Should discharge for maximum
/ PPA DSM
DOD 65%
duration without sunshine (Df)
Battery
e8e8/PPA
73
e8e8/PPA Grid Connected
/ PPA DSM Workshop Solar PV Workshop Republic
Fiji Fiji - November
IslandsofNovember 22-26, 2010
2-6, 2009
=
Exercise 4
(2)Battery capacity C
Ah
(1)Discharge current Id =
A
Key issues: Battery capacity
74
Mini grid
(PV hybrid systems within mini grid)
No Title Sub-t.itle Main Grid Supplied Gen Size Genset Other Battery Note
connection power (approx.) RNE system
(1) SHS DC SHS Off DC < 1kW No No Yes
AC SHS Off AC < 1kW No No Yes
(2) Mini grid PV Mini Off AC 1 - 50kW No No Yes 50 to 600
grid Households
Battery
charge
station
PV hybrid Off AC 10 - 500kW Optional Wind Optional New
systems (a few biomass components
within hours micro-hydro
mini-grid per day) etc.
e8/PPA Grid Connected Solar PV Workshop
1
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
System configuration
Wind
PV panel
Biomass
Micro
-hydro
e8/PPA Grid Connected Solar PV Workshop
Inverter
Genset
runs for only a few
PCS hours per day For a village
(10 – 500kW)
Battery
Delivers the power to the
Isolated, low voltage households and common
AC distribution systems equipments through a grid
2
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Examples (1)
e8/PPA Grid Connected Solar PV Workshop
3
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Examples (1)
Power center 100kW
Diesel generator #1 - #3
PC SL1
Generation
28,477kWh
Charging
5,796kWh Generation 19,009kWh
Battery #1
PC SL2
Generation
28,850kWh
Charging Total power supply
4,318kWh 95,299kWh
Battery #2
Hospital 40kW
PC SL3
Generation
7,274kWh
e8/PPA Grid Connected Solar PV Workshop
School 40kW
4
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Examples (1)
Source: NEDO
5
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Examples (2)
e8/PPA Grid Connected Solar PV Workshop
Source: NEDO
Upper dam
PV array (100kW)
Dummy load governor
Upper
reservoir
e8/PPA Grid Connected Solar PV Workshop
Spillway
Source: NEDO
7
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Examples (2)
Pattern 1 Operation pattern
Pump up at daytime, generation by mini-hydro Pattern 2
at nighttime Pattern 1 + generation by river-in-flow
Pattern 3 Pattern 4
e8/PPA Grid Connected Solar PV Workshop
Pattern 2 + pump up at light load hours in night Load dispatching by PV and mini-hydro
Source: NEDO
8
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Planning & design (1)
• Measures
– Measures at each REN
– Hybrid with other power source
– Use of battery system
– Use of dummy load
9
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Planning & design (2)
• How to have power source for base load
– Requirement
Reliability
Power controllability
Low generation cost
• Can REN be a base power source?
– Micro-hydro: Possible, if stable flow exists.
e8/PPA Grid Connected Solar PV Workshop
10
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Planning & design (3)
• Combination of various REN
Micro-hydro
(storage pond)
e8/PPA Grid Connected Solar PV Workshop
Wind
PV
Biomass
11
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Planning & design of micro-hydro
– Civil
– Electrical
12
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Planning & design of wind power
• Concept design
– Site selection
– Investigate information of wind condition
– Investigate surrounding natural and social condition
• Basic design
– Detail survey of wind condition
– Wind measurement (point, method)
– Analysis of measured data
e8/PPA Grid Connected Solar PV Workshop
– Simulation
– Evaluation Finalize point and capacity
– Environmental assessment
– Land and soil survey
13
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Planning & design of biomass energy
• Concept design
– Identify biomass resource
Cost
Supply stability
– How to collect biomass?
In-house, collection, delivered
– Investigation of plant size
Amount of biomass resource, area, demand
e8/PPA Grid Connected Solar PV Workshop
14
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Operation & maintenance
• Load forecasting is most important. Daytime: Battery charge by REN source
• Aim to full utilize PV power. Nighttime: Battery discharge for load
• Reserve battery energy for Investigate charge/discharge time
emergency case. Calculate required battery capacity
• Adjust charge/discharge energy in
accordance with varying load.
e8/PPA Grid Connected Solar PV Workshop
Source: NEDO
15
Normal grid
(Examples of grid connected system)
No Title Sub-t.itle Main Grid Supplied Gen Size Genset Other Battery Note
connection power (approx.) RNE system
(1) SHS DC SHS Off DC < 1kW No No Yes
AC SHS Off AC < 1kW No No Yes
(2) Mini grid PV Mini Off AC 1 - 50kW No No Yes 50 to 600
grid Households
Battery
charge
station
PV hybrid Off AC 10 - 500kW Optional Wind Optional New
systems (a few biomass components
within hours micro-hydro
mini-grid per day) etc.
e8/PPA Grid Connected Solar PV Workshop
1
Republic of Fiji - November 22-26, 2010
Grid connected: Large PV system:
System configuration
PV panel
Inverter
e8/PPA Grid Connected Solar PV Workshop
PCS
Optional
For a for village
(> 40kW)
Grid Battery
Grid-connected Delivers the power to the
24 hours power supply households and common
by existing generators Optional battery
equipments through a grid
2
Republic of Fiji - November 22-26, 2010 Grid connected: Large PV system:
Type of grid connection
Source: NEDO
3
Republic of Fiji - November 22-26, 2010 Grid connected: Large PV system:
Examples (1)
Source: KEPCO
e8/PPA Grid Connected Solar PV Workshop
4
Republic of Fiji - November 22-26, 2010 Grid connected: Large PV system:
Examples (2)
e8/PPA Grid Connected Solar PV Workshop
Source: NEDO
6
e8/PPA Grid Connected Solar PV Workshop Republic of Fiji - November 22-26, 2010
Examples (3)
Grid connected: Large PV system:
Source: NEDO
7
Republic of Fiji - November 22-26, 2010 Grid connected: Large PV system:
Examples (4)
e8/PPA Grid Connected Solar PV Workshop
Source: NEDO
8
Republic of Fiji - November 22-26, 2010 Grid connected: Large PV system:
Examples (4)
PV
Source: NEDO
9
Republic of Fiji - November 22-26, 2010 Other various applications of PV
( On the factory roof )
e8/PPA Grid Connected Solar PV Workshop
Capacity:820kW Capacity:50kW
Capacity:260kW
10
Republic of Fiji - November 22-26, 2010 Other various applications of PV
( On the wall surface )
e8/PPA Grid Connected Solar PV Workshop
Capacity:66kW Capacity:4kW
Capacity:15kW
11
Technical requirements
for grid interconnection
1
Republic of Fiji - November 22-26, 2010
Hard to
Grid
keep
system
voltage
e8/PPA Grid Connected Solar PV Workshop
Distributed
generation
× Disconnected
from grid
Distribution ↓
G
substation Hard to keep
system
frequency
Feeder
2
Republic of Fiji - November 22-26, 2010
Pmax
G L
L = G
High
performance
generator Restricted operating rates
Low
e8/PPA Grid Connected Solar PV Workshop
performance
G generator
Low performance
Grid generator
G Pmax
High performance
High generator
performance
generator lower generation cost as a total
3
Republic of Fiji - November 22-26, 2010
The Merit of Grid interconnection (3)
Improve reliability and flexibility in case of
generator’s fault or maintenance check
G L G L
Blackout or
e8/PPA Grid Connected Solar PV Workshop
L L
4
Republic of Fiji - November 22-26, 2010 Considerable points
in case of grid interconnection
Power Grid
Load Load Generator
5
Republic of Fiji - November 22-26, 2010 Considerable points
in case of grid interconnection (detail)
Secure supply ・Dispersed generator’s fault should not effect the
reliability reliability of power grid
・Prevent expansion of fault (by exceeding short
circuit capacity, by malfunction of distribution over
current protection relay, etc)
・Relay protection coordination is important
Maintain power quality ・Possibility of harmful effect to other customers via
grid
・Reduce voltage fluctuation of distribution line by
e8/PPA Grid Connected Solar PV Workshop
Conflict of request
Effect to operation,
<Request from administration, <Request from
generator installer maintenance of power system
side> Power system, etc operator>
e8/PPA Grid Connected Solar PV Workshop
(in principle)
1. Electric system
2. Power factor
3. Measures for voltage fluctuations
4. Measures for power quality
e8/PPA Grid Connected Solar PV Workshop
10
Republic of Fiji - November 22-26, 2010 TR for interconnection
1.Electric system
1. Electric system
Should not to hinder the use of electricity or
electric facilities for others.
- Electric system of generation facilities is to be the alternating-current (AC)
three-phase and three-wire system
- voltage and frequency are the same as those of the interconnected power
systems
<Exception>
e8/PPA Grid Connected Solar PV Workshop
Mr. C Mr. A
Mr. B
12
Republic of Fiji - November 22-26, 2010 TR for interconnection
1.Electric system - Unbalance
Mr. C Mr. A
Mr. B
Voltage
3wire 2wire 2wire
of power system
High voltage
3phase < 6kVA < 6kVA < 2kVA
3wire
200V same
1phase electric system < 6kVA < 2kVA
3wire
14
Republic of Fiji - November 22-26, 2010 TR for interconnection
1.Electric system – About PV capacity
Characteristics (V-I) of PV module
Output power is small
Current Current is large, but voltage is small.
Isc Optimum operating point
short-circuit
Output power become maximum.
current
Pm ; Maximum power
Pm = Ipm Х Vpm
Ipm
Output power is small
e8/PPA Grid Connected Solar PV Workshop
Optimum
Operating Voltage is large,
current but current is small.
Voltage
0 Voc
Vpm open
Optimum operating voltage voltage
Pm
Vpm
e8/PPA Grid Connected Solar PV Workshop
maximum
output Optimum operating voltage
power
Voltage
0 Voc
open
voltage
PV module has optimum operating voltage. If you don’t control PV
voltage, PV system efficiency becomes very low.
16
Republic of Fiji - November 22-26, 2010 TR for interconnection
1.Electric system – About PV capacity
Exercise 1
current (A)
PV 4 <Point B>
optimum
<Point A> operating point
3
2.5
Battery 2
e8/PPA Grid Connected Solar PV Workshop
(6V)
1
0
56 10 15 18 20 25
voltage (V)
■Numerical value is just for exercise. It is different from actual equipment’s.
17
Republic of Fiji - November 22-26, 2010 TR for interconnection
1.Electric system – About PV capacity
Exercise 1
(1) PA (output power at point A) = W
(2) PB (output power at point B) = W
output power at some point
(3)PV efficiency = Х 100
Maximum output power
= %
e8/PPA Grid Connected Solar PV Workshop
18
Republic of Fiji - November 22-26, 2010 TR for interconnection
1.Electric system – PV control
Exercise 2
current (A)
PV 4 <Point B>
optimum
<Point A> operating point
Ipm
Vpm
3
Voltage 2.5
converter 2
e8/PPA Grid Connected Solar PV Workshop
6V I
1
Battery
(6V)
0
56 10 15 18 20 25
voltage (V)
■Numerical value is just for exercise. It is different from actual equipment’s.
19
Republic of Fiji - November 22-26, 2010 TR for interconnection
1.Electric system – PV control
Exercise 2
(1) Vpm (optimum voltage) = V
(2) Ipm (optimum current) = A
(3) Pm (optimum output power) = W
(4) I (battery input current) = A
e8/PPA Grid Connected Solar PV Workshop
20
Republic of Fiji - November 22-26, 2010 TR for interconnection
1.Electric system – MPPT control
DC/DC
converter
Inverter Grid
boost
Vin chopper Vout Iout
input Output Output
voltage control voltage current
PV output controller
MPPT
(Maximum Power Point Tracker) Please modify
e8/PPA Grid Connected Solar PV Workshop
Control On,Off
Booster chopper characteristics
IGBT
Vout Vout = { 1/ (1 – α) } Vin
Vin
α(duty ratio) = Ton / (Ton + Toff)
Boost chopper
21
Republic of Fiji - November 22-26, 2010 TR for interconnection
1.Electric system – MPPT control
What is MPPT control (Maximum Power Point Tracker)
Pm ΔP / ΔV > 0
ΔP / ΔV < 0
maximum then return
output ΔP / ΔV < 0
power ΔP / ΔV > 0
e8/PPA Grid Connected Solar PV Workshop
Go ahead!
0 Voltage
Vpm
ΔP / ΔV < 0 Optimum operating voltage
then return
22
Republic of Fiji - November 22-26, 2010 TR for interconnection
2.Power factor
2. Power factor
Necessary to control reactive power so as to maintain
the appropriate system voltage.
- the power factor of generation facilities should be 0.85 or more at the
receiving point.
- It should not be a leading power factor when viewed from the power
systems to prevent the voltage from increasing (or a lagging power
factor when viewed from generation facilities).
e8/PPA Grid Connected Solar PV Workshop
<Exception>
a. It is unavoidable for preventing voltage increase. (In this case,
the power factor at the receiving point can be controlled up to 0.8.)
b. An inverter with small output is used or the power factor at the
receiving point is deemed appropriate. (In this case, the power
factor of generation facilities is over 0.85 when controlling reactive
power and is over 0.95 when not controlling it.)
23
Republic of Fiji - November 22-26, 2010 TR for interconnection
2.Power factor is ---
receiving point
V(V)
Load impedance
load
r + jX (Ω)
I (A)
P(W) + jQ (Var)
Apparent Power
S(kVA) Impedance
I Z(Ω) Reactance
Reactive
Current jX(Ω)
power
Capacitance
θ V θ Q(Var) θ -jX(Ω)
Voltage Active power resistance
P(W) r(Ω)
24
Republic of Fiji - November 22-26, 2010 TR for interconnection
2.Power factor – cos θ > 0.85
receiving point
V(V)
Load impedance
load
r + jX (Ω)
I (A)
P(W) + jQ (Var)
θ P
I; current
R1 + jX1
Not change
P’
Active power decrease R2 + jX2
Transmission loss = (R1+R2) I2
25
Republic of Fiji - November 22-26, 2010 TR for interconnection
2.Power factor – lead? delay?
2. Power factor
- It should not be a leading power factor when viewed from the power
systems to prevent the voltage from increasing (or a lagging power
factor when viewed from generation facilities).
lag -jQ lead
Viewed from generator Viewed from the power systems
P + jQ
Qg
e8/PPA Grid Connected Solar PV Workshop
Pl G L
-P Pg
Pg + jQg P
Pg + jQg Pl + jQl
Ql
Pl + jQl
lead lag
Viewed from generator jQ Viewed from the power systems
G L
output : 500kW output : 250kW
-P P
power factor 0.80 power factor 0.90
(lead viewed from (lag viewed from
e8/PPA Grid Connected Solar PV Workshop
G L
output : 500kW output : 250kW
-P P
power factor 0.95 power factor 0.90
(lag viewed from (lag viewed from
e8/PPA Grid Connected Solar PV Workshop
lag (viewed from power systems) lead (viewed from power systems)
lead lead
Vs Vs X·Ir
Ir
X·Ir r·Ir
Vr Vr
Ir lag lag
r·Ir Ferranti effect
Vs > Vr Vr > Vs
29
Republic of Fiji - November 22-26, 2010 TR for interconnection
2.Power factor - PV
Power factor of PV is almost 100%!
DC/DC
converter
Inverter Grid
IGBT
ON / OFF
IGBT
ON / OFF
of power control
AQR
PV voltage is APR (Auto P Regulator) ACR PWM
controlled to AQR (Auto Q Regulator) (Auto Current (Pulse Width
optimum voltage Regulator) Modulation)
30
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
3. Measures for voltage fluctuations
31
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
■ In the case of using synchronous generators
- Generator with damping winding (including a synchronous generator
without damping winding that has the hunting-prevention effect
equivalent to or more than that of the damping winding type).
- Automatic synchronism detection devices need to be installed.
■ In the case of using induction generators
If the system voltage may deviate from the proper value (within 10% of
the normal value) due to the voltage dip while being paralleled in.
- Current limiting reactors need to be installed.
e8/PPA Grid Connected Solar PV Workshop
32
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
■ In the case of using inverters
▪ Self-commutated inverters
- With automatically synchronizing function.
▪ Line-commutated
When system voltage deviates from the proper value (within 10% of the
normal value) due to voltage dip while being paralleled in.
- current limiting reactors or similar devices need to be installed.
- If such measures are still ineffective self-commutated power inverters
will be required.
■ When generator output or voltage fluctuations caused by frequent
e8/PPA Grid Connected Solar PV Workshop
parallel in/out will bring about voltage flicker and other problems.
- measures are taken to control voltage fluctuations or reduce the
frequency of parallel in/out.
33
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
<Guideline>
- Appropriate voltage value 101±6V, 202±20V
34
Republic of Fiji - November 22-26, 2010
G L G L
Disconne Load Deviation Disconne Load Deviation Load
ction increase in voltage ction increase in voltage shedding
Voltage Voltage
Deviation Deviation
35
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
3. Measures for voltage fluctuations
<Measure for voltage fluctuation>
■In the case that customer makes inverse power flow
- Automatic voltage control
In the case of low voltage
Yes
Voltage detection
Yes
No Restrained value Leading reactive
e8/PPA Grid Connected Solar PV Workshop
36
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
3. Measures for voltage fluctuations
<Measure for voltage fluctuation>
■In the case that customer makes inverse power flow
- Automatic voltage control
Voltage detection In case of high voltage
No No Controlling In normal
Voltage > upper limit
(Active power, reactive power, SC) condition
Yes
Inverse power flow No
Zone of guide
e8/PPA Grid Connected Solar PV Workshop
37
Republic of Fiji - November 22-26, 2010
G G
Deviation
Vs Vs
Vr > Vr’ Ir Vr’ r▪Ir
Ir Vr X▪Ir X▪Ir
r▪Ir
Lagging Q increasing (from power system)
Leading Q increasing (from generator)
38
Republic of Fiji - November 22-26, 2010
Grid
High
voltage
Distribution Low
substation voltage
Feeder
e8/PPA Grid Connected Solar PV Workshop
Control Voltage
voltage at
each bank
Proper Light load
voltage
Heavy load
39
Republic of Fiji - November 22-26, 2010
Maintain feeder voltage (2) tap-changer
Voltage control of feeder by electric power company
Primary Secondary
Distribution side side
substation High
voltage
Low
voltage
e8/PPA Grid Connected Solar PV Workshop
Voltage
Raise voltage by
Proper switching tap-changer
voltage
Low
SVR voltage
(Step
voltage
e8/PPA Grid Connected Solar PV Workshop
Regulator)
Voltage
41
Republic of Fiji - November 22-26, 2010
Maintain feeder voltage (4) reverse flow
Voltage control of feeder by electric power company
Distribution
substation High Reverse power flow
voltage
Low
voltage
e8/PPA Grid Connected Solar PV Workshop
Dispersed
Generation
Voltage
Light load
Proper
voltage Heavy load
Deviation from
proper voltage
Low
voltage
Can control
voltage by
e8/PPA Grid Connected Solar PV Workshop
monitoring
reverse flow
from dispersed Dispersed
generation, Generation
but…
Voltage
Light load
Heavy load
Proper
voltage
Disconnection
Distribution substation
High voltage
Low
voltage
e8/PPA Grid Connected Solar PV Workshop
Dispersed
Voltage Generation
Deviation from
proper voltage
Proper Light load
voltage
Heavy load
45
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
Voltage drop of high voltage line to pole transfer (△V)
△V = √3Х (Ip Х r + Iq Х x)
Ip : active current (A)
Iq : reactive current (A)
r + jx : line impedance (Ω)
Ip = 81 Х 0.9 = 73(A)
Iq = 81 Х √(1-0.92) = 35(A)
r + jx = 0.228 + j0.395(Ω)
△V = √3 Х (73 Х 0.228 + 35 Х 0.395) = 53(V)
Voltage (point B) V = 6,600 - 53 = 6,547(V)
Voltage (point C) V = 6,547 Х (105 / 6600) = 104.2(V)
46
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
Exercise 5 Please modify
substation for high voltage distribution line (6.6kV)
distribution copper 80mm2 3.0km
Point A
copper 80mm2 1.0km
transformer Point B
47
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
Voltage drop of high voltage line to pole transfer (△V)
△V = √3Х (Ip Х r + Iq Х x)
Ip : active current (A)
Iq : reactive current (A)
r + jx : line impedance (Ω)
48
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
■ In the case of using inverters, induction generators
If the system voltage may deviate from the proper value (within 10% of
the normal value) due to the voltage dip while being paralleled in.
0 Just example of
actual measurement
Voltage dip (%)
50 Bed side
Magnetic Monitor
switch No Effect
Effected
by voltage dip
100
0.01 0.05 0.1 0.5 1 2 3
Voltage dip duration (S)
49
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
How to deal with voltage dip in power system (Grid Side)
time
stop Conventional type
When voltage dip occurs, this types
of PCS stop output by gate block for
PCS output 5 – 10S.
FRT (Fault Ride Through)
When voltage dip occurs, FRT
continues operation, and recover
output as soon as power system gate block
voltage recovers. 5S – 10S
time
50
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
■ When generator output or voltage fluctuations caused by frequent
parallel in/out will bring about voltage flicker and other problems.
51
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
■ When generator output or voltage fluctuations caused by frequent
parallel in/out will bring about voltage flicker and other problems.
52
Republic of Fiji - November 22-26, 2010 TR for interconnection
3. Measures for voltage fluctuations
Guideline of ΔV10
ΔV10 = √{ (ΔV10_1)2 + - - - + (ΔV10_n)2 } < 0.45 (V)
( ΔV10_1, - - - , ΔV10_n ; Customer connected with same power system)
53
Republic of Fiji - November 22-26, 2010 TR for interconnection
4. Measures for power quality
4. Measures for power quality
Need to take measures to prevent deviation from
the standard power quality
4-1 Harmonic suppression measure
An inflow of harmonic current into power systems may cause a
harmonic strain on the voltage waveform of power systems, damaging
electric facilities as a result.
<Measures for harmonic current>
■End-use customers
e8/PPA Grid Connected Solar PV Workshop
54
Republic of Fiji - November 22-26, 2010 TR for interconnection
4. Measures for power quality
4. Measures for power quality
(1) Calculation of inflow harmonic current
- When there is a facility reducing an inflow harmonic current on the site
of a specified end-use customer, its effect can be considered.
(2) Upper limit of inflow of harmonic current
- The permissible upper limit of an inflow harmonic current from a
specified end-use customer into power systems is obtained by
multiplying the permissible upper limit per 1kW of contract power
(refer to following table) by the contract power of the specified end-use
e8/PPA Grid Connected Solar PV Workshop
over
Order 5th 7th 11th 13th 17th 19th 23rd
23rd
Current
3.5 2.5 1.6 1.3 1.0 0.9 0.76 0.70
(mA/kW)
55
Republic of Fiji - November 22-26, 2010 TR for interconnection
4. Measures for power quality
(3) Measures to control inflow harmonic current
Inflow harmonic current > The upper limit of the inflow harmonic current
→Appropriate measures need to be taken to keep the inflow
harmonic current below its upper limit.
56
Republic of Fiji - November 22-26, 2010 TR for interconnection
4. Measures for power quality
4-1 Harmonic suppression measure
An inflow of harmonic current into power systems may cause a
harmonic strain on the voltage waveform of power systems, damaging
electric facilities as a result.
Time
<Examples of harmonic source>
Representative example is equipment using transistor, diode.
- OA ▪ Appliance ▪ ▪ ▪ TV, PC, printer
- Air-conditioner ▪ ▪ ▪ Inverter air-conditioner
- Lighting equipment ▪ ▪ ▪ fluorescent lamp, sodium (Na) lamp, mercury (Hg) lamp
- Inverter ▪ ▪ ▪ elevator, fan, pomp, inverter for generator
- Uninterruptible power source ▪ ▪ ▪ UPS
57
Republic of Fiji - November 22-26, 2010 TR for interconnection
4. Measures for power quality
<Examples of harmful effect due to harmonic>
58
Republic of Fiji - November 22-26, 2010 TR for interconnection
4. Measures for power quality
(3) Measures to control inflow harmonic current
Inflow harmonic current > The upper limit of the inflow harmonic current
→Appropriate measures need to be taken to keep the inflow
harmonic current below its upper limit.
■AC, DC reactor make harmonic current decrease.
Advantageous effect DC > AC
voltage
Source
side current
AC reactor
e8/PPA Grid Connected Solar PV Workshop
Without reactor
Inverter DC reactor
Load
side
With AC reactor
59
Republic of Fiji - November 22-26, 2010 TR for interconnection
4. Measures for power quality
What is PWM control?
DC/DC
converter
Inverter Grid
IGBT
ON / OFF
IGBT
ON / OFF
of power control
AQR
PV voltage is APR (Auto P Regulator) ACR PWM
controlled to AQR (Auto Q Regulator) (Auto Current (Pulse Width
optimum voltage Regulator) Modulation)
60
Republic of Fiji - November 22-26, 2010 TR for interconnection
4. Measures for power quality
Basic operation of inverter
IGBT IGBT
Q1 Q3
DC
input output
IGBT IGBT
Q2 Q4
e8/PPA Grid Connected Solar PV Workshop
output voltage
1 2 3 4
input voltage
Q1 ON ON OFF OFF
DC 1 AC 1 Q2 OFF OFF ON ON
2 4 time
time 3 Q3 OFF ON ON OFF
Q4 ON OFF OFF ON
61
Republic of Fiji - November 22-26, 2010 TR for interconnection
4. Measures for power quality
PWM control enable to decrease harmonic current !
PMW control pulse width by changing of
PWM output voltage IGBT’s switching timing.
wide time
narrow pulse width
e8/PPA Grid Connected Solar PV Workshop
time
<Measures>
■ Short-circuit capacity > Circuit breaking capability of the other
circuit breakers
e8/PPA Grid Connected Solar PV Workshop
63
Republic of Fiji - November 22-26, 2010 TR for interconnection
5. Countermeasures for short-circuit current
What is % impedance?
Reference capacity (Pb), voltage (Vb), current (Ib), impedance (Zb)
are defined as 100% ▪ ▪ ▪ ▪ ▪ ■b means base in ().
Actual impedance
■%Z = Reference impedance Х100
<Example>
e8/PPA Grid Connected Solar PV Workshop
64
Republic of Fiji - November 22-26, 2010 TR for interconnection
5. Countermeasures for short-circuit current
How to convert % impedance at different capacity?
■%Z is proportional is to reference capacity
Ex.) Pb = 10MVA, %Z = 5%
%Z = 100% → Ps = reference capacity = 10MVA
%Z = 5% → Ps = 10MVA Х 100% / 5% = 200MVA
Is = 200MVA / (√3 Х77kV) = 1500A
65
Republic of Fiji - November 22-26, 2010 TR for interconnection
5. Countermeasures for short-circuit current
Calculation Example
Point ① Circuit breaker
20MVA
rating breaking current = 12.5kA
%Z2 =7.5%
(10MVA base)
L
interconnected
Back Z
e8/PPA Grid Connected Solar PV Workshop
%Z1 = 2.5% L G
2,000kVA
(10MVA base)
G %Z3 =15% 1,000kW 500kVA
substation (mechanically base) power factor %Z5 =15%
= lag 0.9 (mechanically base)
installation personnel of
6.6kV generation facility
66
Republic of Fiji - November 22-26, 2010 TR for interconnection
5. Countermeasures for short-circuit current
■%Z is proportional is to reference capacity
%Z’3at 10MVA = 15% Х 10000kVA / 2000kVA = 75%
before interconnected
Z1 2.5%
Z’3 75% Synthetic impedance %Z
Z2 7.5%
Point①
e8/PPA Grid Connected Solar PV Workshop
1
%Z = = 8.8%
1 1
+
2.5 + 7.5 75
■Short-circuit capacity is inversely proportional to %Z
Ps = 10MVA Х 100 / 8.8 = 114(MVA)
■Is = Ps / (√3 Х Vb)
Is = 114MVA / (√3 Х 6.6kV) = 10.0 kA < 12.5kV (rating breaking current)
It has no problem about short-circuit capacity. (before interconnection)
67
Republic of Fiji - November 22-26, 2010 TR for interconnection
5. Countermeasures for short-circuit current
Exercise 6
Point ① Circuit breaker
rating breaking current = 12.5kA
20MVA
Transmission line
%Z2 =7.5%
%Z4 =16.3% (10MVA base)
(10MVA base)
L
Back Z
e8/PPA Grid Connected Solar PV Workshop
%Z1 = 2.5% L G
2,000kVA
(10MVA base)
G %Z3 =15% 1,000kW 500kVA
substation (mechanically base) power factor %Z5 =15%
= lag 0.9 (mechanically base)
installation personnel of
6.6kV generation facility
68
Republic of Fiji - November 22-26, 2010 TR for interconnection
5. Countermeasures for short-circuit current
Exercise 6
(1)%Z’3 at 10MVA = %
(2)%Z’5 at 10MVA = %
(3)Drawing 10MVA based impedance map
e8/PPA Grid Connected Solar PV Workshop
71
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
■Protection relay for ground fault of power system
<Exception>
- The output of the generation facilities with an inverter interconnecting
with a low voltage line within a site is far smaller than the site load, and
islanding can be detected, stopped and disconnected quickly by a
device with islanding detection function.
■Protection relay for prevention of islanding
a. In the case that there is reverse power flow
- Over/under frequency relay
- Transfer tripping protection or a device with islanding detection
e8/PPA Grid Connected Solar PV Workshop
<Exception>
- If a reverse power relay can detect and protect in case of
interconnection with a line for exclusive use, an under-frequency
relay can be omitted.
- If the output capacity of generation facilities with an inverter
interconnecting with a low voltage line within a site is far smaller than
the site load and islanding can be detected, stopped and
disconnected quickly by a device with islanding detection function, a
reverse power relay can be omitted.
73
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
It is necessary for distributed generation to be disconnected in
concert with the fault detection of system.
Another customer is adversely
affected by failure of generator
Another disconnection .
Distribution substation - unexpected voltage
customer
- unexpected frequency,
High voltage etc
feeder
Transformer
e8/PPA Grid Connected Solar PV Workshop
CB Grounding Generator
CB tripped
(Opened) Without disconnection of
distributed generation, ground
fault continues even after CB
tripping at substation.
(Threat of equipment damage
and electric shock)
74
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
Necessary protection relay for each fault or generation defect
(Low voltage)
AC generator
synchronous induction inverter
generator generator
reverse
No Yes
power flow
generator
OVR▪UVR
defect
e8/PPA Grid Connected Solar PV Workshop
DSR/OCR
short-circuit UVR
/UVR
RPR + UFR OFR + UFR
UPR + UFR
islanding / islanding Islanding detection system
UPR + UFR
detection system (active + passive)
(active + passive)
Intersystem Islanding detection system
fault (passive)
75
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
Necessary protection relay for PV Please modify
(Low voltage) Power system
inverter Trip signal
reverse Relay
No Yes input ZCT
power flow OCGR
fault at OCR CT
customer OCR ▪ OCGR Load
side
generator PCS
e8/PPA Grid Connected Solar PV Workshop
OVR▪UVR VT
defect
Relay input
short-circuit UVR
RPR + UFR OFR + UFR Trip signal CT
islanding Islanding detection system
Relay input
(active + passive)
Output
Intersystem Relays
controller
Gate INV
Islanding detection system
, ground
(passive) PV
fault
Gate block signal
76
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
OVR, UVR for generator’s defect
Symbol Name operation
Over Voltage If an abnormal increase / decrease occurs in
OVR Relay voltage generated by the PV system, the
over / under voltage relay detects the
Under Voltage abnormal voltage, then separates the PV
UVR Relay system from the grid after a predetermined
period of time.
voltage (V)
e8/PPA Grid Connected Solar PV Workshop
Typical
Typical
OVR act relay Detection
timer
115% level
generator operate
100% normally
Avoiding
80% sensitive OVR 115% 1S
relay action
UVR act
UVR 80% 1S
1S Time (S)
77
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
UVR for short-circuit fault
Symbol Name operation
As a countermeasure against short-
Under Voltage
UVR Relay
circuit in transmission line, UVR can be
shared among transmission line.
R-SΦ short-circuit fault
R-phase A-phase In kansai, we call
S-phase B-phase each phase
T-phase C-phase described as this.
e8/PPA Grid Connected Solar PV Workshop
substation
PV, Load R-phase and S-phase
at come closer due to short-
R
fault circuit fault
before
fault UVR detect voltage
decrease between
T S phases, and act.
78
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
Should prevent islanding
Substation
e8/PPA Grid Connected Solar PV Workshop
②
③
CB tripped
79
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
Example of islanding
Ex. 1
Load Load
Islanding
Load Load
(1)Trandformer ‘s
relay act and CB trip
Load (2) PV is still running
e8/PPA Grid Connected Solar PV Workshop
Ex. 2
Load Load
Load Load
(1)Transmissionn Islanding
line’s relay act and
CB trip Load (2) PV is still running
80
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
Necessary protection relay for PV (Low voltage)
inverter
reverse
No Yes
power flow
fault at
customer OCR – H ▪ OCGR
Only islanding protection
side relay is different under
generator condition whether
e8/PPA Grid Connected Solar PV Workshop
OVR▪UVR
defect reverse power flow exist
short-circuit UVR or not.
RPR + UFR OFR + UFR
islanding Islanding detection system
(active + passive)
Intersystem Islanding detection system
fault (passive)
81
Republic of Fiji - November 22-26, 2010
General idea of Reverse power flow
There is no Reverse power flow There is Reverse power flow
Distribution line Distribution line
Please modify
Please modify
Frequency (Hz)
e8/PPA Grid Connected Solar PV Workshop
Typical
Typical
OFR act relay Detection
timer
102% level
generator operate
100% normally 102%
Avoiding
97% sensitive OFR 51Hz / 1S
relay action 61.2Hz
UFR act 97%
UFR 48.5Hz / 1S
58.2Hz
1S Time (S)
83
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
OFR, UFR for islanding detection with reverse power flow
Power balance
Frequency
Active power Reactive power
Lagging
Rising
(viewed form power system)
e8/PPA Grid Connected Solar PV Workshop
Generation = Load
Leading
Declining
(viewed form power system)
84
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
RPR, UFR for islanding detection without reverse power flow
Symbol Name Function
Prevention of reverse power flow
RPR Reverse Power Relay
Generation > customer’s own load
Abnormal under-frequency
UFR Under-Frequency Relay
Generation < Load
RPR detect direction
substation substation of power flow. RPR
CB tripped
e8/PPA Grid Connected Solar PV Workshop
Power flow at receiving point is from Load may shut down due to power
substation to customer in normal oscillation or voltage fluctuation
condition. (without reverse power flow)
85
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
Characteristic of RPR
relay Typical Detection level Typical timer
About 5% of rated output
RPR 0.5S
capacity of inverter
Normal condition
Current (without reverse flow)
at receiving point
e8/PPA Grid Connected Solar PV Workshop
Abnormal condition
Reference
(with reverse flow)
Voltage vector
Voltage
Detection level at receiving point
RPR
Act
86
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
Types of islanding detection system
Add disturbance signal from generator to grid
continuously
Active On power outage, detect increased response to
disturbance signal
detection
Secure detection, but need several seconds
balance
Possible instant detection
Passive But used as backup of active detection for grid
detection connected generator in high voltage, because of
little change in case that there is large rotating
generator in the same power system
Frequency (Hz)
Time-frequency rate
detection method
output
Δf = 0.2Hz
e8/PPA Grid Connected Solar PV Workshop
Islanding
Time
When frequency Time
Positive feedback
detect gets out of dead zone,
ΔF ΔP increase
islanding
Voltage frequency Voltage frequency
ΔF ΔF
OCGR
Detect fault Detection level Avoiding act
current determined by sensitive
fault current relay action
There is no fault
Short-circuit fault OCGR
In customer side
/ Ground fault OCR
% Z 0 ( Z 2 + %Z 3 ' ) 7×
( 0.5 + 100)
%Z = + %Z1 = = 7.04%
%Z 0 + %Z 2 + %Z 3 '
e8/PPA Grid Connected Solar PV Workshop
7 + 0.5 + 100
■Short-circuit capacity is inversely proportional to %Z
Ps = 10MVA Х 100 / 7.04 = 142.05(MVA)
■Is = Ps / (√3 Х Vb)
Is = 142.05MVA / (√3 Х 6.6kV) = 12426A > 1440A (OCR-H)
→ Feeder A’s OCR-H act. Expected action!
%Z 0 7
I2 = %Z + %Z + %Z ' Х Is = Х 12426 = 809A > 720A (OCR-H)
0 2 3 7 + 0.5 + 100
→ Feeder B’s OCR-H act. That’s too bad!→Some countermeasure is needed!
94
Republic of Fiji - November 22-26, 2010 TR for interconnection
6. Protective relay system
Exercise 7 (Countermeasure against previous calculation case)
I1 Is
A Feeder
OFR X X X
UFR X X X X X X
RPR X X X
isolating Transfer
trip
Islanding X X X
detection
System
97
Republic of Fiji - November 22-26, 2010
Protective Relay (Example of PV system)
OVGR for ground fault in power system
Symbol Name
In the case of a transmission line
fault, the PV system might leak such
Ground Fault Over a low current that OCGR cannot
OVGR Voltage Relay operate. In contrast, OVGR can detect
ground fault voltage. It detects zero-
phase voltage.
e8/PPA Grid Connected Solar PV Workshop
98
Republic of Fiji - November 22-26, 2010 TR for interconnection
7. Neutral point grounding system
7. Neutral point grounding system
99
Republic of Fiji - November 22-26, 2010 TR for interconnection
7. Neutral point grounding system
7. Neutral point grounding system Please add
Example of grounding system designated by power company.
(Example of Kansai)
Voltage Neutral point grounding Features
system In the case of ground fault
Insulated ▪Voltage of sound phase become √3
neutral
6.6kV times larger than usual.
point to
earth ▪Fault current is extremely small.
e8/PPA Grid Connected Solar PV Workshop
Neutral
▪Voltage of sound phase stay about
275kV point
solidly the same.
500kV grounding ▪Fault current is very large.
100
Republic of Fiji - November 22-26, 2010 TR for interconnection
8. Automatic load shedding device
8. Automatic load shedding device
101
Republic of Fiji - November 22-26, 2010 TR for interconnection
9. Device to confirm no-voltage on distribution line
9. Device to confirm no-voltage on distribution line
Prevent faults at the time of automatic reclosing.
A device designed to confirm no voltage on distribution lines is installed at
the outlet of distribution lines from a substation for distribution.
<Exception>
- The installer of the generation facility does not require automatic
reclosing because of connection to a line for exclusive use.
e8/PPA Grid Connected Solar PV Workshop
102
Republic of Fiji - November 22-26, 2010 TR for interconnection
9. Device to confirm no-voltage on distribution line
c. A device with islanding detection function (only active type) and a
reverse power relay whose setting value is less than the minimum
load of distribution lines while the generators are in operation and
each of them disconnects power systems using different circuit
breakers, are installed.
103
Republic of Fiji - November 22-26, 2010 TR for interconnection
9. Device to confirm no-voltage on distribution line
9. Device to confirm no-voltage on distribution line
Prevent faults at the time of automatic reclosing.
generator My electrical
Shock facility was
power Another BROKEN!!
source customer
off → in
Protection If voltage or phase of dispersed generator is
relay closing different from one of power source, electrical shock
automatic signal occurs. To prevent such situation, a device
reclosing
e8/PPA Grid Connected Solar PV Workshop
<Exception>
- A system that allows direct communication with engineers not
passing through the exchange of one who operates generation
facilities is introduced and it is permanently installed at the place of
maintenance /supervision of generation facilities;
- A system capable of interrupting even while the number is
engaged (for example, the so-called catch-phone system) is introduced.
- A system that allows communication even in case of outage.
105
Republic of Fiji - November 22-26, 2010 TR for interconnection
11. Prevention of reverse power flow through main transformer
11. Prevention of reverse power flow through main transformer
Prevent power flow from a high voltage side to a special high
voltage side through a main transformer for distribution.
(hereinafter referred to as “a reverse power flow through a main
transformer”)
A reverse power flow through a main transformer may cause some
problems in voltage management and protection coordination of
distribution systems.
e8/PPA Grid Connected Solar PV Workshop
<Measurement>
- If it is deemed that a reverse power flow through a main transformer is
likely to occur, measures to control generators and similar actions will be
taken.
106
Republic of Fiji - November 22-26, 2010 TR for interconnection
11. Prevention of reverse power flow through main transformer
11. Prevention of reverse power flow through main transformer
A reverse power flow through a main transformer may cause some
problems in voltage management and protection coordination of
distribution systems.
substation
Generation < load Generation > load
Voltage of feeder decline. Voltage of feeder rises.
e8/PPA Grid Connected Solar PV Workshop
Load L L L L
generator
Load
It is difficult to control
voltage of feeder!!
107
e8/PPA Grid Connected Solar PV Workshop Republic of Fiji - November 22-26, 2010
Other issue
108
Republic of Fiji - November 22-26, 2010 Electric power generated at a power station is
dispatched to consumers through substations
[Flow of electricity]
TL UHV S/S
Power Station TL
transmission S/S
Transmission TL TL
TL
e8/PPA Grid Connected Solar PV Workshop
Consumers
Residential house Store Small plant
109
Republic of Fiji - November 22-26, 2010 Electric power is dispatched not to be
detrimental to quality (frequency, voltage, reliability)
110
Republic of Fiji - November 22-26, 2010 To keep the frequency constant, the amount of
electric power supply and demand must be the same.
Frequency control
The balance of supply and demand is
important to keep the frequency constant.
60 HZ
e8/PPA Grid Connected Solar PV Workshop
Demand Supply
( consuming) (generating)
If the amount of supply and demand are not the same, it is impossible to keep the
frequency constant. As a result, factory products and home electric appliances are
adversely affected. 111
Republic of Fiji - November 22-26, 2010
Advanced demand forecasting technology and following
control technology of generators are required to
respond to short-time and long-time demand fluctuation
Power demand
Close up
(KW)
揚水発電
0 3 6 9 12 15 18 21 24
(time) <long-time fluctuation>
Forecasting demand and having
enough reserve margin to respond
to forecasted fluctuation
112
Republic of Fiji - November 22-26, 2010 Challenges for introducing photovoltaic generator are
“surplus”, “fluctuation” and ”reverse power flow”
・power depends on weather
・introducing too much PV
causes surplus power flow
PV
Surplus ・power control is difficult
100
日高エネルギーパーク 晴
晴時々曇 ・introducing too much PV
雨
80
causes surplus power flow
・power control is difficult
出力(%)
60
Fluctu-
40
ation
e8/PPA Grid Connected Solar PV Workshop
20
0
0 2 4 6 8 10 12 14 16 18 20 22
時刻
113
Republic of Fiji - November 22-26, 2010 An imbalance between supply and demand results from
surplus power of PV and this interferes power supply
Heavy load
season
PV PV
In case
PV is introduced Surplus power
e8/PPA Grid Connected Solar PV Workshop
on a large scale
PV PV
115
Republic of Fiji - November 22-26, 2010 Reverse power flow of PV causes voltage increase
of distribution line and generating power of PV is suppressed
Appropriate
voltage range
Voltage goes over
reverse power
no reverse power
116
PV Hybrid system
(Various type of power source)
system
112
160
Fuel consumption ratio (%)
100
120
56
100
39
80
25 50 75 100 110
Output (%)
2
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
Features
• Environmental friendliness
• Clean energy contributing global
warming
• Short construction time and easy
maintenance
• Regional vitalization
e8/PPA Grid Connected Solar PV Workshop
3
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
4
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
Generated power
Generator output P (kW) ;
head Gravity constant g = 9.8
P = potential energy of water
tank
Хefficiency
= mgh▪ η
Head H (m) = Q ▪103(kg) ▪g ▪H(m)▪η
Flow ( water 1m3 = 1000kg)
Q (m3 / S)
e8/PPA Grid Connected Solar PV Workshop
Generator
5
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
How to utilize water
This type of generation
Run-off plant don’t have
balancing reservoir, so
generation energy
depends on weather.
generation
Reservoir plant
This type of generation
(Big) plant have balancing
reservoir, so generation
Pondage energy can be controlled
e8/PPA Grid Connected Solar PV Workshop
generator
Dam type
Water intake
e8/PPA Grid Connected Solar PV Workshop
pipeline
generator
8
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
Example of direct installation
Gate
Generator
Water
channel
Generator
house
9
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
Other example
• Egasaki control room, Water works dept of Kawasaki city
• Water source: Piping for city water
• Utilization of head at water piping Purification
plant Generator
Head
• Max available head: 36.09m
• Horizontal propeller hydraulic turbine (2 sets)
Distribution
• Water flow: 0.6m3/s reservoir
• Output: 170kW(max), 90kW(normal) Water flow Existing
pressure
e8/PPA Grid Connected Solar PV Workshop
10
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
Type Feature Flow
control
Horizontal Wide range in head and Yes
Francis flow
turbine Installed widely from
small to large scale
Controlled flow by guide-
vane, but expensive
Source: NEDO
11
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
Type Feature Flow
control
All-in-one Generation by reverse No
submerged rotation of submerged
turbine with pump with generator
generator Low cost, low efficiency
Need Access to machine
by taking out from water
Cross-flow For middle/small scale Yes
water With guide vane
turbine Low efficiency
e8/PPA Grid Connected Solar PV Workshop
Source: NEDO
13
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Features
▪Clean energy
–No carbon dioxide emission
▪Domestic energy resource
▪Renewable energy
▪Most economical among new energy
resources
▪Stable generation cost
e8/PPA Grid Connected Solar PV Workshop
14
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
140000
120000
100000
Increase rapidly
Capacity
80000
60000
e8/PPA Grid Connected Solar PV Workshop
40000
20000
0
1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
Year
15
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Windmill
16
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Best wind velocity ratio vary according to windmill type.
→Should select appropriate windmill type in consideration of wind velocity.
Bets’ theoretical limitation
Output coefficient (indicating efficiency)
0.6
Propeller type
0.5 2blades
0.4
e8/PPA Grid Connected Solar PV Workshop
Propeller type
0.3 3blades
Major type.
0.2 Netherlands This type is
Darrieus
type type suitable for large
0.1 wind power
generator
0 5 10
Savonius Wind velocity ratio (wing velocity / wind velocity)
type
17
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Generator, etc are set in this chassis.
Nacelle
Stopping the rotor. (ex. wind velocity is over limitation)
Break system anemovane
Measuring wind
wind power direction and velocity
Speed-up
Rotor Hub generator
gear electric power
Control Center
Rotor revolution : low Supervised
Generator revolution :high control Monitoring (P,Q,rotation - -)
Speed-up gear converts Start, Stop operation
rotation. Electric
Grid
Ex.) gear ratio = 100 converter hard ground ; concrete
Foundation soft ground ; pile + concrete
18
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Quiz
(power)
Wind power electricity output P ∝ V
V ; wind velocity (m / S)
e8/PPA Grid Connected Solar PV Workshop
19
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Answer
3
Wind power electricity output P ∝ V
V ; wind velocity (m / S)
Wind power electricity energy is
air’s energy of highly effected by wind condition!
V
motion
= ½ m V2
Mass of air m
e8/PPA Grid Connected Solar PV Workshop
20
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Output (kW) Please modify
1250
1000
750
500
250
0 10 20 30 Wind velocity
(m/S)
e8/PPA Grid Connected Solar PV Workshop
Keep blade angle against wind constant. Make blade parallel against wind
→ Rotor is stopped by break system
pitch control yaw control
strong wind
parallel
blade
blade nacelle
21
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Electric converter
3 phase AC
(power freq.)
B power
inrush output
Speed-up
gear
Induction
generator
type factor
Rotor current fluctuation
(fixed speed) control
Please (A) AC link (Induction generator)
modify Almost
3 phase AC
(control
3 phase AC
(power freq.)
A A Small
A freq.) Zero
Converter Inverter
e8/PPA Grid Connected Solar PV Workshop
3 phase AC
(power freq.)
Rotor
Speed-up
gear
Induction
generator B Soft start N/A Large
(variable speed)
3 phase AC DC 3 phase AC
(control (power freq.)
freq.) Almost
C
C A Small
Zero
Synchronou Converter Inverter
Rotor s
generator
(variable speed)
(C) DC link (Synchronous generator)
Source: NEDO 22
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Features
• Stock-able fuel
• Clean energy
– Carbon neutral
– Low NOX and SOX emission
– Carbon dioxide absorption via
tree planting
e8/PPA Grid Connected Solar PV Workshop
23
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Biomass resource emit CO2 during burning,
Carbon but it absorbed CO2, when it was plant.
Neutral → CO2 don’t increase over this cycle.
e8/PPA Grid Connected Solar PV Workshop
Biomass resources
CO2
combustion
CO2 CO2
24
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Dry type
Resource
Woody material
▪Remaining materials at forest, thinned wood, unused tree
▪Remaining material of lumbering
Agriculture, Livestock industry, Fishery
▪Rice straw, rice husk, straw, corn
e8/PPA Grid Connected Solar PV Workshop
Biomass processing
25
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Wet type
Resource
Food industry
▪Bagasse
▪Waste from food processing, Kitchen waste, Waste cooking oil
Agriculture, Livestock industry, Fishery
▪Bagasse, livestock dung
e8/PPA Grid Connected Solar PV Workshop
Livefood
▪ Sewage sludge, sludge from night soil purification
Biomass processing
26
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Others
Resource
Paper factory
▪Used paper
▪Sludge from paper production, black liquor
Agriculture, Livestock industry, Fishery
▪Sugar, starch, palm oil , rape oil
e8/PPA Grid Connected Solar PV Workshop
Livefood
▪Industrial edible oil
Please modify
Biomass processing
27
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Silo
Wood tip
e8/PPA Grid Connected Solar PV Workshop
Boiler
generate
Source: NEDO
Burn wood tip
28
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Yagi bio ecology center
29
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Yagi bio ecology center Fermenters make
digestive gas
Digestive gas
gas
Fremen-
ter Digestion Digestion Liquid
bath tank fertilizer
Cow dung, pig
dung, straw, Bean curd
sawdust refuse
Gas
holder Surplus Hydro
extractor Dehydrated cake
gas
combustio
Receiving Raw
tank water combustion
n
e8/PPA Grid Connected Solar PV Workshop
tank Compost
Gas Hot Waste water
holder Hot
water
biomass boiler
water treatment
(Existing)
resources Desulfe (backup)
Source: NEDO
30
e8/PPA Grid Connected Solar PV Workshop Republic of Fiji - November 22-26, 2010
Annex
Annex
31
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
• Possible application
32
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
• Possible application
Target flow Target site Characteristics
Flow Head/Pressure Others
Agricultural Main line Large difference Hard to obtain Depends on height
water Channel in flow between large head by of end-point
Water pipe line irrigation season low-gradient
and non-irrigation
season
Sub line Difference in flow Necessity of dust
e8/PPA Grid Connected Solar PV Workshop
33
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Micro-hydro
• Possible application
Industrial Discharge
effluent channel of constant flow water level Emergency
and stop by facility
sewage trouble
In-house Supply and Stable Utilization of Necessity of
supply and drain water Various flow regulated and consideration
drain water channel quantity depends surplus water about
system on production pressure harmlessness
process Easily obtainable against primary
head or pressure water use
34
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Biomass resources
Unutilized Woody material Remaining materials at forest land, thinned wood, unused tree
resource
Remaining material of lumbering, scrap wood from construction,
others
Paper Used paper, sludge from paper production, black liquor
Agricultural Rice straw, rice husk, straw, bagasse, others
residue
Night soil, dung Cow dung, pig dung, chicken dung, others
and sludge
e8/PPA Grid Connected Solar PV Workshop
35
Republic of Fiji - November 22-26, 2010
Off Grid: PV hybrid systems within mini-grid:
Other power source: Biomass energy
Biomass processing
Carbonization
Esterification
Biochemical Methane fermentation Wet process
conversion
Dry process
Two-stage fermentation
Ethanol fermentation
36
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Propeller
Down wind
Sail wing
Horizontal Propeller Sail wing
axis Lift type
Holland type
Multi-bladed
Holland type Multi-bladed
Windmill
Darrieus Vertical axis
Lift type
e8/PPA Grid Connected Solar PV Workshop
Straight wing
Puddle
Drag type
Cross-flow Sabonius type Puddle
S-shaped rotor
Source: NEDO
37
Republic of Fiji - November 22-26, 2010
Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Type Feature
Horizontal axis Simple structure
High efficiency
Easy to scale-up
Good for generation
Need yaw control for up-wind type
Heavy load exists in nacelle.
Vertical Not depend on wind direction
axis Heavy load exists on ground.
Easy manufacturing of blade compared to propeller
Hard to control rotation speed
Need large torque in start-up
Lower efficiency rather than horizontal axis type
e8/PPA Grid Connected Solar PV Workshop
Large footprint
Lift Good for generation by higher peripheral velocity than wind
type speed
Less blades has higher peripheral velocity
Source: NEDO
38
Republic of Fiji - November 22-26, 2010 Off Grid: PV hybrid systems within mini-grid:
Other power source: Wind power
Blade
Anemovane
Nacelle
Hub
Generator
Console
Drive train axis Report
Rotor axis
Brake system Monitoring system
Speed-up
gear
Yaw drive unit
e8/PPA Grid Connected Solar PV Workshop
Distribution line
Tower Protection
Display system
Power conversion system board Transf
ormer
Communication line
Controller
Source: NEDO
39
Guidline of construction and mantenance
7 - Economical Effects
1
Republic of Fiji - November 22-26, 2010
1.System Construction Design
System Architectural
Laws and regulations
work
Support
Grid- Piping and Piping and Waterproof Foundatio
Structur
Connection wiring sizes wiring routes construction
Earthing Maintenance
n work
e
constru
e8/PPA Grid Connected Solar PV Workshop
-Voltage - Voltage drops - Scaffolding - Lead-in - Existing earthing - Safety - Wind pressure ction
- Wind pressure
- Use of existing cables type regulations calculation calculation
-Protection
routes - Equipment - Waterproof - Electromagnetic
Coordination sheds roofs and interference
rooftops
2
Republic of Fiji - November 22-26, 2010
2. 1 Design and Construction Flow
- Installation Areas
On ground or roof
- Foundation work (rooftop) - Visual Inspection
Length, width and azimuth
Cracks, damage of devices
-Roof type
Deck roofs or sloping roofs - Insulation Resistance test
Roofing materials, Waterproof - Carrying in Cable insulation resistance
types
- Obstacles
- Open-Circuit voltage test
Poles, buildings, antennas, Voltage measurement of
mountains, trees - PV module Support each series of PV modules
(and other obstacles that cast Structure Earthing - Setting of Power
shadows on PV Arrays.)
Conditioner protective relays
e8/PPA Grid Connected Solar PV Workshop
- Piping Routes
Existing piping routes and wiring Setting based on
diagrams - PV modules Installation discussion with the electric
- Equipments Installation locations
power company
Switchboards, control boards,
Power Conditioners, - Adjustment of measuring
instrumentation and display - Electrical piping and instruments
- Routes for Carrying in wiring Deviation from Power
Crane or Wrecker installation
location and temporary placement Conditioner indicating
space values
- Diagram - Devices Installation - Adjustment of indication
Skeleton diagram from electric
power company lead-in cable to Discrepancy between
interconnection point measurements and
- Contract with electric power company - Electric connection work indications
Price of buying and selling power
3
Republic of Fiji - November 22-26, 2010
2. 2 Site investigation Guideline (1)
4
Republic of Fiji - November 22-26, 2010
2. 2 Site investigation Guideline (2)
the electric
power company Staff verifies voltage fluctuations
and frequency variations.
5
Republic of Fiji - November 22-26, 2010
2. 3 Design Guideline (1)
6
Republic of Fiji - November 22-26, 2010
2. 3 Design Guideline (2)
PV module characteristics
Deck roof-
mounted type
Sloping roof-
Design based on mounting
mounted type
method and structural
Wall-mounted
strength
type
7
Republic of Fiji - November 22-26, 2010
2. 3 Design Guideline (3)
8
Republic of Fiji - November 22-26, 2010
2. 4 Example systems
Selling
PV Power electricity Electric
power
modules conditioner company
Buying electricity
e8/PPA Grid Connected Solar PV Workshop
Charge
Storage and Offices
batteries discharge and/or
controller Display system
factories
Applicable to disaster prevention (system
includes storage batteries.)
9
Republic of Fiji - November 22-26, 2010
2. 5 System type (1)
10
Republic of Fiji - November 22-26, 2010
2. 5 System type (2)
Storage
Street lights, radio equipment
Stand-Alone DC batteries are
Limited Loads power sources, traffic lights
system used.
Storage
batteries are not DC pumps, battery chargers, fans,
used.
Storage
batteries are Lighting systems
AC used.
Storage
batteries are not AC pumps
used.
e8/PPA Grid Connected Solar PV Workshop
Storage
Electrification in low-population
General Loads DC batteries are
villages
used.
Storage
batteries are not No examples
used.
12
Republic of Fiji - November 22-26, 2010
2. 6 Power conditioner selection (2)
Power Conditioner installation space
<Operating conditions> Ambient temperature : -5 ºC to + 40 ºC (normal operation, standby)
Relative humidity : 30% to 90%
Installation site : Indoor
Outdoor (enabled by accommodating in a cubicle.)
To provide spaces for inspection and heat dissipation, it is necessary to place the inverter off the walls and the
top as shown below.
It is possible to change side walls to parallel boards.
<Example>
Distance to top: 500 mm or more
e8/PPA Grid Connected Solar PV Workshop
[Side View]
Dimensions differ depending on the power conditioner manufacturer.
<Reference> Specifications of indoor inverters of 10 kW to 30 kW (900 W x 1875 H x 700 D)
Weight: 230 kg (10 kW)
290 kg (20 kW)
370 kg (30 kW)
* The above example is a power conditioner of the standard system (of interconnection type).
It is recommended that the power conditioner should be placed outdoors or in an electric-generation room
because of the harmonic noise level.
13
e8/PPA Grid Connected Solar PV Workshop Republic of Fiji - November 22-26, 2010
2. 7 Equipment type
Republic of Fiji - November 22-26, 2010
3. Construction Management Points (1)
Site investigation Roof-mounted Confirm that a lift to the roof is provided.
Determine whether or not the provision of
Installation
Wall-mounted scaffolding and a man lift truck is
site necessary.
confirmation
Recognize the work space for
Ground-mounted construction equipment (s).
15
Republic of Fiji - November 22-26, 2010
3. Construction Management Points (2)
Getting there Determine whether or not the
Temporary Provide an on-site
provision of scaffolding and worker
office office.
lift truck is necessary.
Temporary Provide a materials
Provide a yard close to the site.
yard yard.
PV module Fixture
Support Mount fixture. Mount fixtures to marking.
mounting
Structure Support Assemble the
Installation With stainless bolts, mount the
Structure Support
Support Structure to fixture.
Assembling Structure
PV modules
Installation Mounting PV Carefully handle the PV module,
PV module
modules to the and mount it to the fixture
Installation
Support Structure without damage.
17
Republic of Fiji - November 22-26, 2010
3. Construction Management Points (4)
Electrical Wiring between Wiring of connector Confirm that the circuit and system are
each PV cables between each constructed according to the drawings.
Piping and modules modules
Wiring work Connection Wiring of connectors Confirm the polarity and system of the
between each between each modules cable connectors, and connect them.
PV modules Confirm that the cable plug is securely
connected.
After the connection between modules,
cover terminals with insulation tape to
prevent short-circuits.
Equipment Installation Power Install according to the drawing.
installation Conditioner and Install so that devices cannot cast
Interconnection board shadows on each other.
e8/PPA Grid Connected Solar PV Workshop
18
Republic of Fiji - November 22-26, 2010
3. Construction Management Points (5)
Breaker, OVGR Outage With electroscope, confirm an outage.
Outage work and extension
(altering switchboards)
Circuit breaker Earth units.
and OVGR Earth all devices.
extension
ZPD and OVGR are ZPD and OVGR are mounted in place.
mounted.
Visual Visual Inspection of Confirm that devices are free from cracks.
Inspection Equipments
Inspection
e8/PPA Grid Connected Solar PV Workshop
Trial operation Power Power Conditioner Confirm the setting by the electric
and adjustment Conditioner setting power company.
setting and
operating test
Operate in accordance with the
inverter operating procedure.
Adjustment Adjustment of Adjust according to measuring
and measuring guidelines.
confirmation instruments
of measuring Confirmation of The measurements are compared
instruments measuring with the indication of the inverter.
instruments
e8/PPA Grid Connected Solar PV Workshop
Interconnection
Delivery
20
Republic of Fiji - November 22-26, 2010
4. Pricing Guidelines(1)
21
Republic of Fiji - November 22-26, 2010
4. Pricing Guidelines(2)
22
Republic of Fiji - November 22-26, 2010
5. Self Inspection Items
23
Republic of Fiji - November 22-26, 2010 5.1 Visual inspection and verification test of
structure and quantity (1)
・Check against
manufacturer’s inspection
Output
records when omitting the
field output tests.
24
Republic of Fiji - November 22-26, 2010 5.1 Visual inspection and verification test of
structure and quantity (2)
and fixtures.
Installation
Bolt tightening is appropriately
Visual inspection
conducted.
No loosening is
There is no loosening in the connections
confirmed by touching
between photovoltaic modules.
and visually.
Exposed cables behind the photovoltaic
Visual inspection
Wiring module are wired in order.
Visual inspection
Means of
Item Inspection details Result
inspection
There is neither peeling of surface coating
Appearance Visual inspection
nor deformation.
There is no loosening in screws, bolts and
Installation Visual inspection
fixtures.
P/N(+/-) are correctly connected at the Visual inspection,
e8/PPA Grid Connected Solar PV Workshop
26
Republic of Fiji - November 22-26, 2010 5.1 Visual inspection and verification test of
structure and quantity (4)
(3)-2 Power Conditioner
Performance test
Item Inspection details Performance Result Remarks
Matching Check to the
Model/type Acceptable
Specification document
Protective Check factory inspection
relay test records on behalf of the relay Check to factory inspection records.
(at factory) test in field.
Detection
MCCB(ELCB) is turned off and
e8/PPA Grid Connected Solar PV Workshop
of
operation is shutdown in an Acceptable
Islanding
instance.
operation
The time to
20 seconds restoration
The power conditioner
standby after shall be
automatically starts 20 seconds 20[s] Acceptable
after power restarted consistent
after power restoration.
restoration with Tech.
Spec.
27
Republic of Fiji - November 22-26, 2010 5.1 Visual inspection and verification test of
structure and quantity (5)
(4)Display System
Visual Inspection
Item Inspection details Means of inspection Result
Appearance There is neither peeling of surface coating nor deformation. Visual inspection
Installation There is no loosening in screws, bolts and fixtures. Visual inspection
Nameplate There is no defect to or peeling of nameplate. Visual inspection
Visual inspection,
AC200V control power cables are correctly wired.
Multi Meter
Low voltage cables are correctly wired and there is Visual inspection,
Wiring conduction. Multi Meter
e8/PPA Grid Connected Solar PV Workshop
*Input signals from the secondary cable in the transformer inside the interconnection switchboard to verify the
indicated values on the LED screen.
*Visually check the numerical values indicated by power conditioner panel LCD or data collection system monitor
to verify there is no error in the generated electricity of photovoltaic module and Power Conditioner output.
28
Republic of Fiji - November 22-26, 2010 5.1 Visual inspection and verification test of
structure and quantity (6)
Visual inspection,
P/N(+/-) are correctly connected at the MCCB output.
Multi Meter
Wiring
Earth conductors are connected. Visual inspection
Cables are wired in order. Visual inspection
The panel internal is clean. Visual inspection
29
Republic of Fiji - November 22-26, 2010 5.1 Visual inspection and verification test of
structure and quantity (7)
30
Republic of Fiji - November 22-26, 2010 5.1 Visual inspection and verification test of
structure and quantity (8)
31
Republic of Fiji - November 22-26, 2010 5.2 Equipment installation and
wiring/connection inspection (1)
(1), (2) Insulation resistance measurement of cable between junction box and inverter panel
Insulation resistance measurement of cable between inverter and interconnection switchboard
Insulation resistance measurement of cables between interconnection switchboard, MCB and
existing transformers
[Test procedure]
Measure the insulation resistance of (+,-) polarities and (R,S,T) phases of each cable to ensure that
there is no insulation failure.
Measure the insulation resistance between each cable and the ground (according to code).
e8/PPA Grid Connected Solar PV Workshop
[Acceptance criteria]
600V<Circuit voltage : 0.4MΩ or higher with 1000V insulation resistance tester.
300V<Circuit voltage≦600V: 0.4MΩ or higher with 500V insulation resistance tester.
150V<Circuit voltage≦300V: 0.2MΩ or higher with 500V insulation resistance tester.
Circuit voltage≦150V : 0.1MΩ or higher with 500V insulation resistance tester.
32
Republic of Fiji - November 22-26, 2010 5.2 Equipment installation and
wiring/connection inspection (2)
Measurement of cable insulation resistance
Item Insulation resistance (M ) Cable type Result
Power Conditioner-1~
Interconnection switchboard
>300V
R(red) 100MΩ or higher
e8/PPA Grid Connected Solar PV Workshop
Interconnection switchboard~MCB
MCB~Existing transformer-9
>300V
R(red) 100MΩ or higher
[Acceptance criteria]
Open-circuit voltage≧300V: Acceptable if measurement using 1000V megger shows 0.4MΩ or higher .
[Test procedure]
・Measure the open-circuit voltage of one each string of PV module array to confirm the polarity of
each circuit.
・ Measure the open-circuit voltage of one each string of PV module array to check if the number of
modules in series is correct or not.
<If the measured voltage is out of the acceptance criteria, the modules in series might be
incorrectly connected.>
35
Republic of Fiji - November 22-26, 2010 5.4 Open-circuit voltage test/ground
resistance test – example (2)
(2)DC Open-circuit voltage of cables between photovoltaic modules
[Test conditions]
Tests shall be conducted during daytime hours on a sunny day.
(Solar radiation shall be 0.1kW/m2 or higher.)
[Acceptance criteria]
Measure the open-circuit voltage of one each string of module array to confirm that it meets the
following criteria.
e8/PPA Grid Connected Solar PV Workshop
36
Republic of Fiji - November 22-26, 2010 5.4 Open-circuit voltage test/ground
resistance test – example (3)
(3) Earth resistance measurement
[Test procedure]
Measure the earth resistance.
[Acceptance criteria]
Earth resistance of 100 or less is acceptable.
e8/PPA Grid Connected Solar PV Workshop
Ground resistance
37
Republic of Fiji - November 22-26, 2010
6.1 Some tips for system design (1)
• Surrounding environment and anticipated damage
Sand breeze
Sand scratch
(like frosted grass)
Sea breeze
Contamination
Electrically grounding
Animal bait
38
Republic of Fiji - November 22-26, 2010
6.1 Some tips for system design (2)
• Surrounding environment and anticipated damage
Rain
Lightning
Lightning rod
Strong enough
for stormy wind
Heat up
e8/PPA Grid Connected Solar PV Workshop
Enough ventilation
for cooling
40
Republic of Fiji - November 22-26, 2010 6.2 Maintenance Plan for Photovoltaic
Power Generation System (2)
Monthly Inspection
42
Republic of Fiji - November 22-26, 2010 6.2 Maintenance Plan for Photovoltaic
Power Generation System (4) Regular Inspection
Item Content of Check Measuring Check
・Check of PCS
The numerical value that LCD of each
PCS shows being about the same.
Display System
・Check of Monitoring System
The power generation change according
to Irradiance.
43
Republic of Fiji - November 22-26, 2010 7.1 Economical Effects
1. Conditions
System capacity 100 kW * Total capacity of PV array
44
Republic of Fiji - November 22-26, 2010 7.2 Example Preliminary Calculations of
Economical Effects
2. Preliminary calculations of investment effects
(1) Installation expenses 70,000 thousand yen
(2) General management expenses 7,000 thousand yen (1) × 10%
(3) Total investment amount 77,000 thousand yen (1) + (2)
business use
Electric power capacity under * 20% of the installation capacity of 100 kW is expected.
(8) contract of an expected 20 kW
reduction in demand
Energy saving effect (reduction thousand (7) × (8) ×12
(9) 406
in demand) yen/yr months
thousand
(10) Introduction effects 1,696 (6) + (9)
yen/yr
Expected payback period 45.4 yr (3) ÷ (10)