Ch09 v2020 Print Version
Ch09 v2020 Print Version
•Public Sector:
•Ownership – by citizens- the public
•Public Sector Projects:
•Provide needed services to the public an “no profit”
9.1 Types of Projects
•Hospitals
•Parks and recreation facilities
•Highways, Dams, Bridges
•Courts, schools, prisons
•Public Housing
•Many other types
9.1 Characteristics - compared
Characteristic Public Sector Private Sector
Size of Investment Larger Some Large; medium to
small
Life Estimates Quite Long 30 – 50 years Shorter:
2-25 years
Annual Cash Flow No Profit: costs and benefits Revenues – profit cost
estimates estimates
Funding Taxes, fees, bonds, Pvt. funds Sale of new stock, bonds,
loans, Ret. earnings
Interest Rate Tends to be lower Higher: At market cost
9. 1 Evaluation Process
•The viewpoint finally adopted will:
•Determine the estimates of..
•Costs
•Benefits
•Disbenefits
•Thus, the viewpoint must be established before the economic evaluation
Section 9. 2
B/C Analysis – Single Project
• Historical Point
• B/C analysis philosophy was instituted and promoted by the Flood Control
Act of 1936
• Introduced to promote a sense of objectivity in an analysis
9.2 B/C Formulations
PW (benefits )
B/C
PW (cos ts )
AW (benefits )
AW (cos ts )
FW ( benefits )
FW (cos ts )
9. 2 Notes regarding signs
•By convention:
•Revenues are assigned (+) signs
•Costs are assigned (+) signs
•Salvage values are subtracted from costs
•Disbenefits are treated more than one way
9. 2 Handling Disbenefits
9. 2 Decision Rule
9. 2 Benefit-Cost Difference
1. Using either PW or AW determine the total equivalent cost for all options.
If unequal lives, apply AW
2. Create the rankings based upon lowest to highest total cost of the
alternatives
3. Determine the total equivalent net benefits for each alternative
4. The lowest cost option is the first Defender and the next higher cost
alternative is the first challenger
Compute the B/C ratio on the increment
If B/C < 0, eliminate the Challenger else eliminate the Defender.
Current winner becomes new Defender
5. Compare the new defender to the next higher cost challenger and repeat
the analysis.
6. Continue through the alternative until there are no more challengers.
7. The last “champion” is the winner
Non Profit Organization
EUAW :
Benefit : $ 500,000 per year
Investment : 1,500,000 (A/P, 6%,10) = $ 203,805
O&M cost : $ 50,000 per year
Disbenefit : $ 200,000 per year
A. Conventional B/C Analysis :
B/C = (500,000-200,000)/(203,805+50,000)
If the roads are assumed to last 30 years with no salvage value, which route
should accepted on the basis of a benefit/cost analysis using an interest rate
of 5% per year?
Solutions
Cost
EUAW (N) = 10,000,000 (A/P,5%,30) + 35,000 = 685,500
EUAW (S) = 15,000,000 ( A/P,5%,30) + 55,000 = 1,030,750
C = EUAW(S) – EUAW(N) = 345,250 per year
Benefit
• B = $ 450,000-$ 200,000
B/C Ratio
250,000/345,250 = 0.724
Select N
Mutually Exclusive
Alternatives , 30 years, i%
C A B D
Building Cost 190,000 200,000 275,000 350,000
Cash Flow 19,500 22,000 35,000 42,000
PW of CF 183,826 207,394 329,945 395,934
Overall B/C 0.97 1.03 1.2 1.13
Project Compared B to A D to B
Increment Benefit 122,551 65,989
Increment Cost 75,000 75,000
Increment B/C 1,64 0.88
Project Selected B B