M.SL-Power-System-Operation-and-Control - PEC PDF
M.SL-Power-System-Operation-and-Control - PEC PDF
VANIYAMBADI– 635751
A Course Material
on
Power System Operation and Control
By
M.SELVAPERUMAL
Associate Professor
Electrical and Electronics Engineering Department
Quality Certificate
Year/Sem:IV/VII
Name:M.Selvaperumal
Designation: ASP
UNIT I INTRODUCTION
9
An overview of power system operation and control – system load variation – load
characteristics – load curves and load-duration curve – load factor – diversity factor –
Importance of load forecasting and quadratic and exponential curve fitting techniques of
forecasting – plant level and system level
controls .
UNIT II REAL POWER – FREQUENCY CONTROL
9
Basics of speed governing mechanism and modeling – speed-load characteristics –
load sharing between two synchronous machines in parallel – control area concept –
LFC control of a single-area system – static and dynamic analysis of uncontrolled and
controlled cases – two-area system–modeling – static analysis of uncontrolled case –
tie line with frequency bias control – state variable model – integration of economic
dispatch control with LFC.
REFERENCES:
1. Nagrath I.J. and Kothari D.P., ‘Modern Power System Analysis’, Tata McGraw-Hill,
Fourth Edition, 2011.
2. Kundur P., ‘Power System Stability and Control, Tata McGraw Hill Education Pvt.
Ltd., New Delhi, 10th reprint, 2010.
3. Hadi Saadat, ‘Power System Analysis’, Tata McGraw Hill Education Pvt. Ltd., New
Delhi, 21st reprint, 2010.
4. N.V.Ramana, “Power System Operation and Control,” Pearson, 2011.
5. C.A.Gross, “Power System Analysis,” Wiley India, 2011.
CONTENTS
1 Unit – I 6
2 Unit – II 23
3 Unit – III 51
4 Unit – IV 80
5 Unit – V 105
Unit – I
INTRODUCTION
Part – A
The curve drawn between the variations of load on the power station with
reference to time is known as load curve. There are three types,
Daily avg demand = (no of units generated per day)/ (24 hours)
Yearly avg demand = (no of units generated in a year)/ (no of hours in a year)
This is the ratio of actual energy produced to the maximum possible energy
that could have been produced during a given period.
Capacity factor= (actual energy produced)/ (maximum energy that have been
produced)
It is the ratio of units generated to the product of plant capacity and the
number
When the load elements of a load curve are arranged in the order of
descending
Unit – I
INTRODUCTION
Part – B
1 INTRODUCTION
1.Draw the Load Curve and Load Duration Curve.Explain The Importance of these
curves in connection with economic operation of power system. [CO1-LI-Nov/Dec
2015]
PRE REQUEST
POWER SYSTEM
In general each generation plant in any power may have more than one generating
units. Each of the unit may have identical or different capacities. A number of power
plants can be tied together to supply the system load by means of interconnection of the
generating stations.
Interconnected electric power system is more reliable and convenient to operate and
also offers economical operating cost .
It has better regulations characters by all the units are interconnected.
In simply, The generation of power is transfer to the Consumers through the
transmission system.
Generation unit , Transformer Unit, Converter Unit, Transmission Unit, Inverter Unit and
Consumer Point. This combination of all the unit is called the overall power system
units.
SYSTEM LOAD VARIATION
The variation of load on the power station with respect to time.
SYSTEM LOAD
• From system‟s point of view, there are 5 broad category of loads:
1. Domestic
2. Commercial
3. Industrial
4. Agriculture
5. Others - street lights, traction.
Domestic
Lights,
Commercial:
Lightings for shops, advertising hoardings, fans, AC etc.
1. Demand factor = 0.9 to 1.0;
2. Diversity factor = 1.1 to 1.2;
3. Load factor = 0.25 to 0.3
Industrial:
Small scale industries: 0-20kW
Medium scale industries: 20-100kW
Large scale industries: above 100kW
Industrial loads need power over a longer period which remains fairly uniform
throughout the day.
For heavy industries:
1. Demand factor = 0.85 to 0.9;
2. Load factor = 0.7 to 0.8
Agriculture:
Supplying water for irrigation using pumps driven by motors
1. Demand factor = 0.9 to 1;
2. Diversity factor = 1.0 to 1.5;
3. Load factor = 0.15 to 0.25
Other Loads:
a) Bulk supplies,
b) street lights,
c) traction,
d) government loads
which have their own peculiar characteristics
curve .
Base Load:
The unvarying load which occurs almost the whole day on the station
Peak Load:
The various peak demands so load of the station
curve
The load duration curve can be extended to include any period of time
Connected load
systems.
Maximum demand
Demand factor
Average demand
The average of loads occurring on the power station in a given period (day or month or
year) is known as average demand
Daily average demand = (no of units generated per day) / (24 hours)
Yearly average demand = (no of units generated in a year) / (no of hours in a year)
Load factor
The ratio of average load to the maximum demand during a given period is known as
load factor.
Diversity factor
The ratio of the sum of individual maximum demand on power station is known as
diversity factor.
Diversity factor = (sum of individual maximum demand ) / (maximum demand).
Capacity factor
s the ratio of actual energy produced to the maximum possible energy that
could have been produced during a given period.
Capacity factor = (actual energy produced) / (maximum energy that have been
produced)
3. Briefly explain overview of power system control or (plant level and syatem
level controls) ? [CO1-L1-May/June 2015]
fundamental requirement.
1. Adequate „spinning reserve’ must be present to meet the active and reactive power
demand.
3. The power quality must have certain minimum standards within the tolerance or limit
such as,
3. Transmission Control.
the governor and the control of energy supply system variables such as boiler pressure,
temperature and flows.
to speed.
command signal, so that, the steam input of the turbine is changed relative to the load
requirement.
to the required standard and the demand of the reactive power is also met by the
excitation control unit.
against system load and losses, so that, the desired frequency and power interchange
with neighboring systems are maintained.
power frequency.
of the signal is fed to the integrator and it is given to speed changer
which generates the reference speed for the governor.
system by maintaining system voltages, frequency and other system variables within
their acceptable limits.
main objective of real time power system operation requires a process guided
by control and decisions based on constant monitoring of the system condition.
LEVEL 2: Control
sample interval.
future demand.
forecasting is required
for preparing
maintenance schedule
of the generating units,
planning future
expansion of the
-to-day
operation, short term
load forecasting
demand and for
maintaining the required
spinning reserve.
Very short term load forecasting is used for generation and distribution. That is,
economic
Unit Commitment:
The unit commitment problem is to minimize system total operating costs while
simultaneously providing sufficient spinning reserve capacity to satisfy a given security
level. In unit commitment problems, we consider the following terms.
i. Thermal scheduling.
The loading of steam units are allocated to serve the objective of minimum fuel cost.
Thermal scheduling will be assumed that the supply undertaking has got only form
thermal or from steam stations.
ii. Hydrothermal scheduling.
Loading of hydro and thermal units are allocated to serve the objective of minimum fuel
cost is known as hydrothermal scheduling.
Scheduling of hydro units are complex because of natural differences I the watersheds,
manmade storage and release elements used to control the flow of water are difficult.
During rainy season, we can utilize hydro generation to a maximum and the remaining
period, hydro generation depends on stored water availability. If availability of water is
not enough to generate power, we must utilize only thermal power generation. Mostly
hydroelectric generation is used to meet out peak loads. There are two types of
hydrothermal scheduling.
a) Long range hydro scheduling
b) Short range hydro scheduling.
Long range hydro scheduling problem involves the long range forecasting of water
availability and the scheduling of reservoir water releases for an interval of time that
depends on the reservoir capacities. Long range hydro scheduling involves
from I week to I year or several years. Long range hydro scheduling involves
optimization of statistical variables such as load, hydraulic inflows and unit availabilities.
Short range hydro scheduling involves from one day to one week or hour-by-hour
scheduling of all generation on a system to achieve minimum production cost foe a
given period.
Assuming load, hydraulic inflows and unit availabilities are known, for a given reservoir
level, we can allocated generation of power using hydro plants to meet out the demand,
to minimize the production cost.
The largest category of hydrothermal system includes a balance between hydroelectric
and thermal generation resources. Hydrothermal scheduling is developed to minimize
thermal generation production cost.
Unit – II
Part – A
4. What is the difference between large and small signal analysis? [CO2-L3-
Nov/Dec 2008]
Large signal analysis is used where voltage and power may undergo sudden changes
of
magnitude that may approach 100 percent of operating values. Usually this type of
analysis leads
to differential equations of non-linear type.
Small signal anaysis is used when variable excursions are relatively small, typically at
most a few percent of normal operating values.
5. What is the exciter? [CO2-L2-May/June 2009]
The exciter is the main component in AVR loop. It delivers the DC power to the
generator field. It must have adequate power capacity and sufficient speed of response
(rise time
10. What are the effects of generator loading in AVR loop? [CO2-L2-May/June
2009]
Added load does not change the basic features of the AVR loop, it will however affect
the values of both gain factor K and the field constant. High f loading will make the
generator
work at higher magnetic saturation levels. This means smaller changes in |E| for
incremental
increases in if, translating into the reduction of K . The Ffield time constant will likewise
decreases as generator loading closing the armature current paths. This circumstance
permits the
formation of transient stator currents the existence of which yields a lower effective field
induction.
13. How is the real power in a power system controlled? [CO2-L2-May/June 2007]
The real power in a power system is being controlled by controlling the driving torque of
the individual turbines of the system.
14. What is the need for large mechanical forces in speed-governing system?
[CO2-L2-May/June 2009]
Very large mechanical forces are needed to position the main valve against the high
stream pressure and these forces are obtained via several stages of hydraulic amplifiers
Unit – II
Part – B
TECHNICAL TERMS
Control area:
Most power systems normally control their generators in unison. The individual control
loops have the same regulation parameters. The individual generator turbines tend to
have the same response characteristics then it is possible to let the control loop in the
whole system which then would be referred to as a control area.
Power Pool:
An association of two or more interconnected electric systems having an agreement to
coordinate operations and planning for improved reliability and efficiencies.
Prime Mover:
The engine, turbine, water wheel, or similar machine that drives an electric generator;
or, for reporting purposes, a device that converts energy to electricity directly (e.g.,
photovoltaic solar and fuel cell(s)).
Pumped-Storage Hydroelectric Plant:
A plant that usually generates electric energy during peak-load periods by using water
previously pumped into an elevated storage reservoir during off-peak periods when
It enables the speed governor system to adjust the speed of the generator unit while in
operation.
steady state speed regulation is obtained with this arrangement. For a given speed
changer position, the per unit steady state speed regulation is defined by
Steady state speed regulation = No-Nr/N Where No = Speed at no - load
N r = Rated speed
N = Speed at rated load
The following basic requirements are to be fulfilled for successful operation of the
system:
1. The generation must be adequate to meet all the load demand
2. The system frequency must be maintained within narrow and rigid limits.
3. The system voltage profile must be maintained within reasonable limits and
4. In case of interconnected operation, the tie line power flows must be maintained at
the specified values.
generation changes to preselected machines in the system after the governors have
accommodated the load change in a random manner.
fulfilled by deriving an error signal from the deviations in the specified tie-line power
flows to the neighboring utilities and adding this signal to the control signal of the load-
frequency control system.
operating condition:
I. Starting fast peaking units.
2. Load shedding for unimportant loads, and
3. Generation rescheduling.
It is apparent from the above that since the voltage specifications are not stringent.
Load frequency control is by far the most important in power system control.
Gt(s) is the TF of the turbine; ΔPV(s) is the change in valve output (due to action).
Pm(s) is the change in the turbine output. The governor can similarly modeled as shown
Fig. The output of the governor is by
Where ΔPref is the reference set power, and Δw/R is the power given by governor
speed characteristic. The hydraulic amplifier transforms this signal Pg into valve/gate
position corresponding to a power PV.
Thus
PV(s) = (Kg/ (1+sTg)) _Pg(s).
5. Explain in detail about lfc control of single area and derive the steady state
frequency error ? [CO2-L2-May/June 2015]
All the individual blocks can now be connected to represent the complete ALFC loop as
The generator is synchronized to a network of very large size. So, the speed or
frequency will be essentially independent of any changes in a power output of the
generator
ie, ΔF(s) =0
the integral controller to change the reference power setting so as to change the speed
set point.
generators in the control area are replaced by a single equivalent generator, and the
ALFC for the area corresponds to this equivalent generator.
6. Explain in detail lfc control of single area and derive the dynamic response?
[CO2-L2-May/June 2007]
In order to calculate an equivalent time constant Teq, Tt is put to 0. This can be done
since for realistic systems the turbine controller time constant Tt is much smaller than
the time constant
7. Explain the model of uncontrolled two area load frequency control system ?
[CO2-L2-May/June 2013]
depicted in Figure.
where
β1 = D1 + 1/ R1
β 2= D2+1/R2
E expression for tie-line flow in a two-area interconnected system Consider a change in
load ΔPD1 in area1. The steady state frequency deviation Δf is the same for both the
areas.
That is Δf =Δf1 =Δf2.
Thus, for area1, we have ΔPm1 -ΔPD1 -ΔP12 = D1Δf
Where, Area 2 ΔP12 is the tie line power flow from Area1to Area 2; and for ΔPm2
+ΔP12 = D2Δf
The mechanical power depends on regulation.
Hence ΔPm1= -Δf 1ΔPm2= -Δf 2 Substituting these equations, yields
(1/R1+ D1) Δf =-ΔP12- ΔPm
(1/R2+ D2) Δf =-ΔP12- ΔPm
Where, 1 and 2 are the composite frequency response characteristic of Area1 and Area
2
respectively. An increase of load in area1 by ΔPD1 results in a frequency reduction in
both areas and a tie-line flow of ΔP12. A positive ΔP12 is indicative of flow from Area1
to Area
2 while a negative ΔP12 means flow from Area 2 to Area1. Similarly, for a change in
Area 2 load by ΔPD2, we have
Δf= -ΔPD2/ β1 + β2
8. Explain in detail about dynamic response of load frequency control loops ?
[CO2-L2-May/June 2012]
evaluated so that the initial response also can be seen for any overshoot.
availability, generation limits, tie line capacities, spinning reserve allocation and area
commitment‟s are important considerations in preparing load dispatch schedules.
B parallel to itself as shown in Fig and the frequency will be restored to its normal value
fs' reducing the change in generation in A to zero.
`
While the initial governor response is the same as for the previous case, the action
of the controller in B will force the generation in area B to absorb the load increment in
area A.
fted parallel
to itself in B till the entire load increment in A is absorbed by B and the frequency is
restored to normal.
-line schedule
is
Where X is the reactance of the line. If the angles change by f1o1, and f102 due to load
changes in areas I and 2 respectively. Then, the tie-line power changes by
DYNAMIC RESPONSE
Let us now turn our attention during the transient period for the sake of simplicity. We
shall assume the two areas to be identical .Further we shall be neglecting the time
constants of generators and turbines as they are negligible as compared to the time
constants of power systems. The equation may be derived for both controlled and
uncontrolled cases. There are four equations with four variables, to be determined for
given PDl and PD2. The dynamic response can be obtained; even though it is a little bit
involved. For simplicity assume that the two areas are equal. Neglect the governor and
turbine dynamics, which means that the dynamics of the system under study is much
slower than the fast acting turbine-governor system in a relative sense. Also assume
that the load does not change with frequency (D, =
No hat both K and ro2 are positive. From the roots of the characteristic equation we
notice the system
is stable and damped.
f the damped oscillations is given by Since Hand fo are constant,
the frequency of oscillations depends upon the regulation parameter R. Low R gives
high K and high damping and vice versa .
system, just as in
the case of a single area system in the uncontrolled mode, has a steady state error but
to a lesser extent and the tie line power deviation and frequency deviation exhibit
oscillations that are damped out later
Unit – III
Part – A
When a number of capacitors are connected in parallel to get the desired capacitance, it
is
known as bank of capacitors. These can be adjusted in steps by switching
(mechanical).
Static VAR compensators use switching for var control. These are also called static
VAR
switches or systems. It means that terminology wise SVC=SVS. And we will use these
interchangeably.
1) Saturated reactor
2) Thyristor- Controlled Reactor (TCR)
3) Thyristor Switched capacitor (TSC)
4) Combined TCR and TSC compensator.
All power transformers and many distribution transformers have taps in one or more
windings for changing the turn’s ratio. It is called tap changing transformers.
14. What is the use of off-load tap changer and TCUL ? [CO3-L2-May/June 2014]
The off- load tap changers are used when it is expected that the ratio will need to be
changed only infrequently, because of load growth or some seasonal change.
TCUL is used when changes in ratio may be frequent or when it is undesirably to
deenergize
the transformer to change the tap.
Unit – III
Part – B
Regulator:
of the exciter.
capability limits of the exciter and synchronous generator are not exceeded.
reference voltage; the difference is amplified and fed back to the exciter field winding to
change the excitation current.
varied through a full range of positive to negative values very rapidly with the ultimate
benefit of generator Voltage regulation during transient disturbances.
-phase fully controlled or semi controlled
bridge rectifiers.
rotating, semiconductor diode network which is mounted on the generator shaft itself.
connected in series.
rings and brushes are completely eliminated thus offering smooth and maintenance-free
operation.
-magnet generator serves as the power source for the exciter field.
set reference and utilizes the error signal, if any, to control the gate pulses of the
thyristor network.
4. Explain about ac excitation system? [CO3-L2-May/June 2014]
Ac Excitation System
Exciter and Voltage Regulator:
The function of an exciter is to increase the excitation current for voltage drop and
decrease the same for voltage rise. The voltage change is defined
Exciter Response
Exciter builds up:
s value
by cutting or adding.
AC excitation operations
When the exciter is operated at rated speed at no load, the record of voltage as function
of time with a step change that drives the exciter to its ceiling voltage is called the
exciter build up curve. Such a response curve is show in Figure
Response Curve
Some use 350V and 375V system while some go up to 500V excitation system.
power and provide current to the rotor of the synchronous machine through slip ring .
DC Excitation System
(d) axis and the other set on its quadrature (q) axis.
performance requirement, for the design and coordination of supplementary control and
protective circuits, and for system stability studies related to the planning and purpose
of study.
generator.
as:
i) DC Exciters;
ii) AC Exciters; and
iii) Static Exciters.
This signal is applied to the voltage regulator shown as a block with transfer function
KA/ (1+TAs).
The stabilizing compensator shown in the diagram is used to improve the dynamic
response of the exciter. The input to this block is the exciter voltage and the output is a
stabilizing feedback signal to reduce the excessive overshoot.
acceptable values.
Synchronous Compensators:
em,
can be declutched from their turbine and provide reactive power without producing real
power.
1. Overhead lines and underground cables, when operating at the normal system
voltage, both produce strong electric fields and so generate reactive power.
2. When current flows through a line or cable it produces a magnetic field which absorbs
reactive power.
3. A lightly loaded overhead line is a net generator of reactive power while a heavily
loaded line is a net absorber of reactive power.
4. In the case of cables designed for use at 275 or 400kV the reactive power generated
by the electric field is always greater than the reactive power absorbed by the magnetic
field and so cables are always net generators of reactive power.
5. Transformers always absorb reactive power.
8.Explain how voltage control can be effected by injection of reactive power?
[CO3-L2-May/June 2010]
Reactors
shunt connected, while series connected reactors are used to limit fault currents, shunt
reactors are used for var control.
70% of charging power while the remaining 30% power at no-load can be provided by
the under excited operation of the generator.
cut-out.
Shunt capacitor
Series capacitors
through the capacitor, protective devices like spark gaps and non linear resistors are to
be in corporate.
tor is shown in the figure (b).
Synchronous Compensator
voltage side of a down transformer, the capacitor banks may be distributed between
high and low voltage buses.
harmonic currents from flowing in the transformer and the high voltage system.
Reactor Compensator
network.
the reactor transformer with 200% leakage impedance between primary and secondary
windings.
reactive power required to meet the control objective at the primary side of the
compensator is obtained.
ristic from no load to full
load condition.
generated
due to saturation.
In a three phase system the thyristor controlled inductors are normally delta connected
as shown in Figure to compensate unbalanced loads and the capacitors may be star or
delta connected
Unbalanced loads
the thyristor controlled reactor, the inductive reactance is controlled by the
thyristors.
Unbalanced loads
with the conduction angle such that each successive half cycle is a smaller segment of
a sine wave.
ch case.
input to the firing angle control Static var compensators when installed reduce the
voltage swings at the rolling mill and power system buses in drive system applications.
factor.
power systems since the changes in arc furnace load impedance are rapid.
compensates for the unbalanced reactive load of the furnace and the thyristor controller
will respond quickly in order to minimize the voltage fluctuations or voltage flicker seen
by the system.
TYPES OF SVC
1. Variable impedance type
2. Current source type
3. Voltage source type
The followings are the basic types of reactive power control elements which makes all
or parts of SVC
Saturated reactor
Larger the overall gain of the forward block gain K smaller is the steady state error. But
too large a gain K cans instability
The response depends upon the roots of the characteristic eqn. 1 + G(S) = o.
As there are three time constants, we may write the three roots as S1, S2 and S3. A
typical root locus plot is shown in Figure
Root locus
From the plot, it can be observed that at gain higher than Kc the control loop becomes
ln stable
Unit – IV
Part – A
It is the term describe the total amount of generation availability from all units
synchronized on the system.
These include quick start diesel turbine units as well as most hydro units and pumped
storage hydro units that can be brought online, synchronized and brought up to full
capacity
quickly.
1) Minimum up time,
2) minimum down time crew constraints.
Once the unit is decommited, there is a minimum time before it can be recommended.
If a plant consist of two (or) more units, all the units cannot be turned on at the same
time
since there are not enough crew members to attend both units while starting up.
13. What are the two approaches to treat a thermal unit to operating temperature?
[CO4-L2-May/June 2012]
The first allow the unit boiler to cool down and then heat backup to operating
temperature in time for a scheduled turn on. The second requires that sufficient energy
be input
to the boiler to just maintain operating temperature.
14. What are the techniques for the solution of the unit commitment problem?
[CO4-L2-May/June 2015]
15. What are the assumptions made in dynamic programming problem? [CO4-L2-
Nov/Dec 2007]
A state consists of an array of units with specified units operating and the rest of the
time.
The startup cost of a unit is independent of the time it has been offline. There are no
costs for
shutting down the units.
17. What are the optimization technique for long range hydro scheduling
problem? [CO4-L2-May/June 2014]
1) Dynamic programming
2) composite hydraulic simulation methods
3) statistical production cost method.
Unit – IV
Part – B
power.
buses.
-problems, i.e.,optimum allocation of
generator station at various station load levels and optimum allocation of generation to
each station load level and optimum allocation of generation to each station for various
system load levels.
PRE REQUEST
power generation.
IMPORTANT TERMS
Incremental cost
generation is called incremental
cost.
Pg-pd-pl=0.
Participation factor
factor.
Hydrothermal scheduling
ze the thermal generation cost with the constraints of water
availability.
Scheduled reserve
pumped storage hydro units that can be brought online, synchronized and brought up to
full capacity quickly.
Minimum up time
recommended.
Crew constraints
time since there are not enough crew members to attend both units while starting up.
function, add the constraint function to the objective function after the constraint function
has been multiplied by an undetermined multiplier.
Lagrange function and is shown in Eq(7)
we take the first derivative of the Lagrange function with respect to each of the
independent variables and set the derivatives equal to zero. In this case,there are N+1
variables, the N
When we recognize the inequality constraints, then the necessary conditions may be
expanded slightly as shown in the set of equations making up Eq. 9.
losses.
, is the same as that defined for Eq.10
The same procedure is followed in the formal sense to establish the necessary
conditions for a minimum-cost operating solution, The Lagrange function is shown in
Eq.11.
power outputs, Pi, it must be recognized that the loss in the transmission network, Ploss
is a function of the network impedances and the currents flowing in the network.
independent variables Pi and the load Pload taking the derivative of the Lagrange
function with respect to any one of the N values of Pi results in Eq. 11. collectively as
the coordination equations
losses since this second set involves the computation of the network loss in order to
establish the validity of the solution in satisfying the constraint equation.
here have been two general approaches to the solution of this problem.
for solving the problem and then extending this into the area of computer algorithms.
three units on the same graph, In order to establish the operating points of each of
these three units such that we have minimum cost and at the same time satisfy the
specified
demand, we could use this sketch and a ruler to find the solution.
(λ) and find the power outputs of
each of the three units for this value of incremental cost. the three units for this value of
incremental cost.
total power supplied for different incremental cost levels and combinations of units.
accomplish the same objective as we have just done with ruler and graph paper.
between the stored power points to find exact power output for a specified value of
incremental cost rate.
d be to develop an analytical function for the power output as
a function of the incremental cost rate, store this function (or its coefficients) in the
computer, and use this to establish the output of each of the individual units.
iterative type of computation, and we must establish stopping
rules.
,since it is necessary to observe the operating limits on each of the units during the
course of the computation.
-known Newton-Raphson method may be used to project the incremental
cost value to drive the error between the computed and desired generation to zero.
to be solved
repeatedly by moving the generators from one economically optimum schedule to
another as the load changes by a reasonably small amount.
-the base point.
ates how much each
generating unit needs to be moved (i.e.,“participate” in the load change) in order that the
new
function are available (Le., both F; and Fy exist). The incremental cost curve of ith unit
given in the fig.
As the unit load is changed by an amount, the
The total change in generation (=change in total system demand) is, of course, the sum
of the individual unit changes. Let Pd be the total demand on the generators (where
Pload+Ploss&),
Then
The earlier equation, 15, can be used to find the participation factor for each unit as
follows
nto
service to meet the demand.
for operation at any one time is also desired for carrying out the aforesaid task.
in plants to service with the time at which individual units should be taken out from or
returned to service
impose different rules on the scheduling of units, depending on the generation makeup,
load-curve characteristics, and such.
Spinning Reserve
Spinning reserve is the term used to describe the total amount of generation
available from all units synchronized (i.e., spinning) on the system, minus the present
load and losses being supplied.
demand, or that reserve must be capable of making up the loss of the most heavily
loaded unit in a given period of time.
system limitations (often called “bottling” of reserves) and to allow various parts of the
system to run as “islands,” should they become electrically disconnected.
Thermal Unit Constraints
turned off.
erature changes, and this translates
into a time period of some hours required to bring the unit on-line.
As a result of such restrictions in the operation of a thermal plant, various constraints
arise, such as:
1. Minimum up time: once the unit is running, it should not be turned off immediately
2. Minimum down time: once the unit is decommitted, there is a minimum time before it
can be recommitted.
Cc = cold-start cost (MBtu)
F = fuel cost
Cf= fixed cost (includes crew expense, maintenance expenses) (in R)
α = thermal time constant for the unit
t = time (h) the unit was cooled
Start-up cost when banking = Ct x t x F+Cf
Where
Ct = cost (MBtu/h) of maintaining unit at operating temperature
Up to a certain number of hours, the cost of banking will be less than the cost of cooling,
as is illustrated in Figure.
Finally, the capacity limits of thermal units may change frequently, due to maintenance
or unscheduled outages of various equipment in the plant; this must also be taken.
Other Constraints
Hydro-Constraints
-
units.
in an optimal solution.
Must Run
-run status during certain times of the year for reason of
voltage support on the transmission network or for such purposes as supply of steam
for uses outside the steam plant itself.
Fuel Constraints
fuel scheduling” problem system in which some units have limited
fuel, or else have constraints that require them to burn a specified amount of fuel in a
given time, presents a most challenging unit commitment problem.
For the total period of M intervals, the maximum number of possible combinations is (2N
- l)M, which can become a horrid number to think about.
For example, take a 24-h period (e.g., 24 one-hour intervals) and consider systems with
5, 10, 20 and 40 units.
required.
-capacity relationships of typical
utility systems are such that we do not approach these large numbers.
Priority-list schemes,
units.
-down rule or priority-list scheme could be obtained after an exhaustive
enumeration of all unit combinations at each load level.
- load
average production cost of each unit, where the full-load average production cost is
simply the net heat rate at full load multiplied by the fuel cost.
If not, continue as it is
If yes, go to the next step
6. Determine the number of hours H, before the unit will be needed again.
7. Check H< minimum shut down time.
If not, go to the last step If yes, go to the next step
A feasible state is one in which the committed units can supply the required load and
that meets the minimum amount of capacity each period.
8.Explain in detail about Forward DP Approach? [CO4-L2-May/June 2015]
-programming algorithm to run backward in time starting
from the final hour to be studied, back to the initial hour.
For example, if the start-up cost of a unit is a function of the time it has been off-line
(i.e., its temperature), then a forward dynamic-program approach is more suitable since
the previous history of the unit can be computed at each stage.
actical reasons for going forward.
The recursive algorithm to compute the minimum cost in hour K with combinati
Fcost(K,I)= min[Pcost(K,I)+Scost(K-1,L:K,I)+Fcost(K-1,L)] ----------------------------------
(20)
Where
Fcost(K, I ) = least total cost to arrive at state ( K , I )
Pcost(KI, ) = production cost for state ( K ,I )
Scost(K - 1, L: K , I)= transition cost from state (K - 1, L) to state ( K , I )
State (K, 1) is the Zth combination in hour K. For the forward dynamic programming
approach, we define a strategy as the transition, or path, from one state at a given hour
to a state at the next hour.
Note that two new variables, X and N, have been introduced in Figure.
X = number of states to search each period
N = number of strategies, or paths, to save at each step
These variables allow control of the computational effort (see below Figure).For
complete enumeration, the maximum number of the value of X or N is 2n – 1
Unit – V
Part – A
The objective is to maximize the probability that estimate the state variable x, is the true
value of the state variable vector (i.e, to maximize the P(x)=x).
The objective is to minimize the sum of the squares of the weighted deviations of the
estimated measurements from the actual measurement.
The objective is to minimize the expected value of the squares of the deviations of the
estimated components of the state variable vector from the corresponding components
of the true
state variable vector.
Some units are given a must run status during certain times of the year for reason of
voltage support on the transmission network.
A system in which some units have limited fuel or else have constraints that require
them
to burn a specified amount of fuel in a given time.
are assumed
13. What are the assumptions made in priority list method? [CO5-L2-May/June
2013]
No load cost are zero unit input-output characteristics are linear between zero output
and
full load there are no other restrictions startup cost are affixed amount.
If the start up cost of a unit is a function of the unit is a function of the time it has been
offline, then a forward dynamic program approach is more suitable since the previous
history of
the unit can be computed at each stage.
It has the necessity of forcing the dynamic programming solution to search over a small
number of commitment states to reduce the number of combinations that must be
tested in each
period.
16. What are the known values in short term hydro scheduling problem? [CO5-L2-
May/June 2010]
17. What are the functions of security constraints optimal power flow? [CO5-L2-
May/June 2013]
In this function, contingency analysis is combined with an optimal power flow which
seeks to make changes to the optimal dispatch of generation. As well as other
adjustments, so
that when a security analysis is run, no contingency result in violations.
This is the state that the power system is in prior to any contingency. It is optimal with
respect to economic operation but may not be secure.
This is the state of the power system after a contingency has occurred.
20. What are the priorities for operation of modern power system? [CO5-L2-
May/June 2010]
Operate the system in such a way that power is delivered reliably. Within the constraints
placed on the system operation by reliability considerations, the system will be operated
most
economically.
Many outages become very difficult to solve if it is desired to present the results quickly.
Easiest way to provide quick calculation of possible overloads is linear sensitivity
factors.
It is used to apply to the testing for overloads when transmission circuits are lost.
In order to simplify the calculations and memory storage the system is sub divided into 3
sub systems called as external equivalencing.
Unit – V
Part – B
INTRODUCTION
These requirements led to the development and application of more advanced solid
state modular electronic instruments, computer based direct control and date
processing systems.
PRE REQUEST
factors
the software resides on the vendor‟s computer and control center personnel access
it from the Internet.
terminal units (RTUs) for the purpose of allowing operators to observe and control
physical plants.
4800 bits/s with the RTU responding to periodic requests initiated from the master
station (polling) every 2 to 10 s, depending on the criticality of the data.
b) Supervisory control: Allows operator to remotely control devices, e.g., open and close
circuit breakers. A “select before operate” procedure is used for greater safety.
f) Load shed: Provides both automatic and operator-initiated tripping of load in response
to system emergencies.
g) Trending: Plots measurements on selected time scales.
dual computer system configured in primary and standby modes is most common.
SCADA functions are listed below without stating which computer has specific
responsibility.
• Manage communication circuit configuration
• Downline load RTU files
• Maintain scan tables and perform polling
• Check and correct message errors
Automatic generation control (AGC) consists of two major and several minor
functions that operate online in real time to adjust the generation against load at
minimum cost.
derivative of the cost of unit generation so that the units would be loaded according to
their costs, thus meeting the third objective.
deration because the different units may
have different response rates and it may be necessary to move the faster generators
more to obtain an acceptable response.
capability. Older RTUs are equipped with modems to provide the communication link
back to the ECC, whereas newer RTUs generally have intranet or internet capability.
ocated within the RTU, on command from the ECC, open or close selected
control circuits to perform a supervisory action.
1. Data acquisition
2. Information display.
3. Supervisory Control (CBs:ON/OFF, Generator: stop/start, RAISE/LOWER command)
4. Information storage and result display.
5. Sequence of events acquisition
auxiliary
devices, etc.
-and a station-wide interlocking
bar
MONITORING FUNCTIONS:
PROTECTION FUNCTIONS:
indication and relay operating time and setting and reading of relay parameters.
COMMUNICATION TECHNOLOGIES
telemetry. Telemetry is the
measurement of a quantity in such a way so as to allow interpretation of that
measurement at a distance from the primary detector.
includes
provision for converting the measure into a representative quantity of another kind that
can be transmitted conveniently for measurement at a distance.
converters, as illustrated.
wires; although simple and economic for short distances, it suffers from reliability
problems due to breakage, water ingress, and ground potential risk during faults
located
inside the substations. One disadvantage of PLC is that the communication cannot be
made through open disconnects, i.e., when the transmission line is outaged.
addition, PLC is susceptible to line noise and requires careful signal-to-noise ratio
analysis.
t to power system
control.
Reserve monitor:
-V, δ,P,Q.
1. System monitoring.
2. Contingency analysis.
3. Security constrained optimal power flow
Security Assessment
acceptable state and second, whether the system would respond in an acceptable
manner and reach an acceptable state following any one of a pre-defined contingency
set.
contingency is the unexpected failure of a transmission line, transformer, or
generator.
fault, or short-circuit, to one of
these components.
Security Control
security control starts with a specific state: the current state if executing the real-time
network sequence; a postulated state if executing a study sequence
1. Determine the state of the system based on either current or postulated conditions.
2. Process a list of contingencies to determine the consequences of each contingency
on the system in its specified state.
Topology processor:
Processes real-time status measurements to determine an electrical connectivity (bus)
model of the power system network.
• State estimator:
Uses real-time status and analog measurements to determine the „„best‟‟ estimate of
the state of the power system. It uses a redundant set of measurements; calculates
voltages, phase angles, and power flows for all components in the system; and reports
overload conditions.
• Power flow:
Determines the steady-state conditions of the power system network for a specified
generation and load pattern. Calculates voltages, phase angles, and flows across the
entire system.
Contingency analysis:
Assesses the impact of a set of contingencies on the state of the power system and
identifies potentially harmful contingencies that cause operating limit violations.
Optimal power flow: Recommends controller actions to optimize a specified objective
function (such as system operating cost or losses) subject to a set of power system
operating constraints.
• Security enhancement:
Recommends corrective control actions to be taken to alleviate an existing or potential
overload in the system while ensuring minimal operational cost
• Preventive action:
Recommends control actions to be taken in a “preventive” mode before a
contingency occurs to preclude an overload situation if the contingency were to occur.
• Bus load forecasting:
Uses real-time measurements to adaptively forecast loads for the electrical connectivity
(bus) model of the power system network
• Transmission loss factors:
Determines incremental loss sensitivities for generating units;
calculates the impact on losses if the output of a unit were to be increased by 1 MW.
• Short-circuit analysis:
Determines fault currents for single-phase and three-phase faults for fault locations
across the entire power system network
6.Explain state transition diagram showing various state transition and control
strategies or various operating states? [CO5-L1-May/June 2015]
Operating states
1. Normal state
2. Alert state
3. Emergency state
4. Extremis state
5. Restorative state
Normal state:
A system is said to be in normal if both load and operating constraints are satisfied .It is
one in which the total demand on the system is met by satisfying all the operating
constraints.
Alert state:
Emergency state:
Extremis state:
islanding.
the generating units are strained beyond their capacity .
Restorative state:
alert state or secure state
.The latter is a slow process.
secure state .
Emergency state:
id to be in emergency state if one or more operating constraints are
violated, but the load constraint is satisfied .
tions,
disconnection of faulted section or load sharing.
Extremis state:
Restorative state:
secure state .
done using restorative control action.