The document describes the process of installing a column formwork system with a climber platform. It includes 8 steps to erect the scaffold base and install components like l-shape columns, walkways, and safety barricades. It provides safety guidelines and notes to ensure proper assembly and use of anchoring positions, bolts, and concrete strength before progressing to the next level. The document aims to clearly explain the safe installation of the column formwork system.

Uploaded by

Made Gilee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
125 views

Column Presentation PDF

The document describes the process of installing a column formwork system with a climber platform. It includes 8 steps to erect the scaffold base and install components like l-shape columns, walkways, and safety barricades. It provides safety guidelines and notes to ensure proper assembly and use of anchoring positions, bolts, and concrete strength before progressing to the next level. The document aims to clearly explain the safe installation of the column formwork system.

Uploaded by

Made Gilee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 18

CNQC MTRA JO

METROLINK WH-3 PROJECT


Column with climber platform
Column Formworks System

1
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

2
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

Warehouse 3 Layout Plan


3
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

1. Erect a scaffold base on column height and width to install L-shape


column base on dimension from drawing. Connection between panel
to panel use M16*40 bolt

4
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

2. Install L-shape waler

5
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

3. Install strongback ,access ladder

6
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

4. Installing walkway bracket and working platform

7
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

5. Installation L shape column done

8
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

9
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

6. Installation climber and Lipped channel , follow dimension as shown in


drawing

10
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

7. Installation secondary bearer and safety barricade

11
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

8. Install working platform

12
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

13
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

Safety Concern
• Ensure that workers assembly formwork panel according to the
drawing
• Ensure all connection parts has tighten
• Ensure tie rod and wing nut install properly and full tight before
casting
• Ensure foot plate and push pull prop install correctly as shown in
drawing
• Ensure working platform fully installed with proper safety barricade
• Please inform to FHS site supervisor or related staff if have any
changes of drawings or need to do any modification works which
effect formwork installation

14
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

15
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

Things to note:
1. Ensure that the Anchoring position mounted on the Panel is
accordance to the drawing provided.
2. Ensure M20*50mm bolt (GR 8.8) is used to tied the wall bracket
to the Recoverable Anchor.
3. Ensure that the Recoverable Anchor has to be removed before
Jumping to next level
4. Ensure Concrete achieve 15MPA before jumping
5. Ensure there are no honeycomb around the anchor ± ø150mm

16
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

Lightly coated grease on recoverable anchor as


shown below:

Applying excessive grease will


cause anchor unable to
integrate with the concrete 17
COLUMN WITH CLIMBER PLATFORM

CNQC MTRA JO

• Recommend number of workers


- Min 4 workers installing column formwork
- Min 2 -3 workers install climber platform
(Actual number of workers depend to site arrangement)

18