Failure Analysis of Bend Tube Preheater On Heat Recovery Steam Generator
Failure Analysis of Bend Tube Preheater On Heat Recovery Steam Generator
http://iptek.its.ac.id/index.php/jmes/index
Abstract
The combined cycle power plant (PLTGU) is the second largest percentage of electrical production
method which is 26% of all electrical production technology in Indonesia. One of the components in
combined cycle power plant is heat recovery steam generator (HRSG), which serves as heat exchanger
between hot gasses from gas turbine cycle and water from steam turbine cycle. There are four stages
on HRSG, preheater, economizer, evaporator, and superheater. In the present work, there is a case
of thinning on a bend tube preheater which exceed the tolerance limits, therefore the purposes of
this research are determine the cause of failure and determine the failure mechanism on bend tube
preheater. Thinning of bend tube preheater occurred due to corrosion from both the inside surface
and outside surface. Corrosion that occurred on the inside surface of bend tube preheater caused by
reaction between water and metal surface of tube. Corrosion on the outside surface could be happen
caused by reaction between hot gas and metal surface of tube. Largest thinning rate occurred on bend
area of bend tube preheater caused by deformation itself, it induces local reduction of breakdown
potential.
1. Introduction
Combined cycle power plant has both Rankine cycle
by using steam turbine and Brayton cycle by using gas
turbine. One of the components in combined cycle power
plant is heat recovery steam generator (HRSG), which
serves as heat exchanger between hot gasses from gas
turbine cycle and water from steam turbine cycle. There
are four stages on HRSG, preheater, economizer, evapo-
Figure 1. Water and hot gas flow direction on bend tube
rator, and superheater. Preheater serves as preliminary preheater
stage to heat water up to 50◦ C (Figure 1). Bend tube
preheater use Grade ST37.8 from DIN 17177-79 standard
as material specification with dimension specification can
be seen on Figure 2. The initial thickness of bend tube
preheater is 2.9 mm, where the critical thickness is 60%
of initial thickness. After being used for 23 years (1992
- 2015) with standard working condition and operation,
there is a case of thinning on bend tube preheater which
exceed the tolerance limits and have to be replaced. Then,
the purposes of this research are determining the cause
of failure and determine the failure mechanism on bend
tube preheater. Where each of specimen pipes have equal
chemical composition taken as initial condition.
∗ Email:[email protected]
Phone/Fax:+62(31)5922941
The International Journal of Mechanical Engineering and Sciences; Vol.1, No. 1 (2017):37-41
Putro et al./The International Journal of Mechanical Engineering and Sciences/1/1(2017)
Grade St 37.8
Chemical Composition (%) C 0,17 max
Si 0,1 – 0,35
Mn 0,4 – 0,8
P 0,04 max
S 0,04 max
Tensile Test (MPa) Min Yield Point 235
Tensile Strength 360 – 480
Elongation in 50 mm (%) 35
Information Data
Material Type Welded Boiler Tube (DIN 17177-79 ST 37.8)
Tensile Strength (MPa) 325
Using Period 23 years (1992 – 2015)
Outside Diameter (mm) 38
Thickness (mm) 2.9
Working Temperature Limit (oC) 180
Pressure Limit (bar) 5.4
Mass Flow Rate (ton/h) 1500
Pressure Limit High (bar) 75.5
Pressure Limit Low (bar) 5.4
Maintenance Schedule Every 8000 Operating Hours
37
Putro et al./The International Journal of Mechanical Engineering and Sciences/1/1(2017)
After measurement on each sample, the result of critical thickness (1.778 m). The combined 3D images
measurement is combined with 3D file of specimens from results can be seen on Figure 5.
3D scanning. Then, a codification was given to the com-
bined 3D file to show the local thickness of pipes. The red
color in 3D image shows if the location thickness is below
the critical thickness (< 1.778 m), while the green color
in 3D image shows the location thickness is still above the
38
Putro et al./The International Journal of Mechanical Engineering and Sciences/1/1(2017)
39
Putro et al./The International Journal of Mechanical Engineering and Sciences/1/1(2017)
Figure 7. XRD test result from the outer surface of bend tube preheater
The bend-side of pipe is designed to flow the water a temperature up to 50◦ C. Sample that being used in
from the preheater drum to economizer drum. However, microstructure test is sample number 1 from specimen 2A.
the deformation of bend-side itself causes the pipe to be
more susceptible locally to corrosion. The deformation
on bend-side lower the breakdown potential locally, thus
the bend-side of pipe more susceptible to corrosion rather
than straight-side of pipe [3, 4, 5, 6].
Breakdown potential is electrical potential value on
the surface of metals that is needed to determine the state
of corrosion of the metal. By having smaller breakdown
potential locally on bend-side, so that the area is easier to
get into transpassive state and has greater corrosion rate.
Figure 8. Microstructure analysis with 50x magnification
When the oxide layer breakdown, the surface is in direct
contact with water. The potential difference occurs on
the surface of specimen at bend-side area, causing pitting Microstructure test done with 3% Nital as etching
corrosion occurs. Where the surface of metal as anode reagent according to ASTM E407 [7]. The result of mi-
and the metal oxide layer as cathode, so the thinning rate crostructure analysis with 50x magnification (Figure 8)
due to corrosion was greater at bend-side area. showed a formed layer on inner and outer surface of bend
The corrosion rate of a pipe can be determined by tube preheater. The formation of red-brick hematite that
calculating the difference of the thickness at a certain of occurred on inner surface of pipe marked by yellow circle
measured time interval. Corrosion rate can be formulated on figure 8 with a thickness of about 7 micrometer or
as the initial Thickness-Actual Thickness)/(Time Interval). 0.007 millimeter. On the outer surface of pipe formed
By using the corrosion rate formula, we obtained local brownish-black that marked by red circle on figure 8 with
corrosion rate data on each sample. The highest corro- a thickness of about 25 micrometer or 0.025 millimeter.
sion rate occurs on specimen 1B sample 7 with 0.0956 With 50x magnification we can see oxide layer formed
mm/year. Sample 7 is located in bend-side of specimen 1B. on inner and outer surface of bend tube preheater due to
After measuring the inside and outside diameter of each reaction of the specimens with working environment.
sample, we can obtain the comparison of largest thinning With 500x magnification on Figure 9a showed the
due to corrosion that occurred on inner and outer surface establishment of hematite on inner surface with detailed
of bend tube preheater as stated in table 3. From Table image as marked with blue circle, there are not any indi-
3, we know that the largest thinning due to corrosion cation that another oxide layer formed on inner surface.
occurred on the outer surface of bend tube preheater. Figure 9b showed the establishment of magnetite on outer
Microstructure analysis conducted to determine phe- surface with detailed image as marked with green cir-
nomena that occur on specimens due to working condition cle, there are not any indication that another oxide layer
and environment. Material used in bend tube preheater formed on outer surface. With 1000x magnification as
is ST 37.8 with a maximum carbon content 0.17%. The seen on Figure 10, we can conclude that working condi-
outer surface of specimen contact with hot gases from the tion and environment did not change any microstructural
turbine gas combustion with a temperature up to 150◦ element of specimen. So we concluded that there are not
C and the inner surface contact with flowing water with any failure from working condition and operation. The
40
Putro et al./The International Journal of Mechanical Engineering and Sciences/1/1(2017)
Figure 9. Microstructure analysis with 500x magnification [3] Z. Foroulis and H. Uhlig. Effect of cold-work on corro-
(a) inner surface (b) outer surface of bend tube preheater sion of iron and steel in hydrochloric acid. Journal of
the Electrochemical Society, 111(5):522–528, 1964.
41