Unit Storage and Distribution Reservoirs: Structure
Unit Storage and Distribution Reservoirs: Structure
RESERVOIRS
Structure
16.1 Introduction
Objectives
16.2 Distribution Reservoirs
16.3 Types of Distribution Reservoirs
16.3.1 SurfaceReservoirs
16.3.2 Elevated Resewoirs
16.3.3 Types with Respect to Construction Materials
16.4 Position and Elevation of Reservoirs
16.5 Storage Capacity of Distribution Reservoirs
16.5.1 Balancing Storage
16.5.2 Contingency Storage
16.5.3 Fire Storage
16.6 Design for Storage
16.6.1 Mass Curve Method
16.6.2 Analytical Method
16.7 Guidelines for Design
16.7.1 Economical Depth
16.7.2 Roofing
16.7.3 Walls for Concrete Reservoirs
16.7.4 Floors of Reservoirs
16.7.5 Pipings
16.7.6 Testing for Watertightness
16.8 Elevated Reservoirs
16.8.1 Intz Tanks
16.8.2 Standpipes
16.9 Summary
16.10 Key Words
16.11 Answers to SAQs
16.1 INTRODUCTION
A water supply project consists of taking of raw water from source (river, stream or
reservoir) conveying it to purification units, and finally distribution to the consumers.
Thus, a water supply project consists of
(i) works for collection of water,
(ii) works for conveyance ofwater,
(iii) works for purification and treatment, and
(iv) works for distribution of water to the consumers.
The proper planning consists of an economical efficiently functioning units with
minimum recurring and operational expenditure and trouble. It has been discussed in
earlier units that water demand is not constant. There are several factors, which cause
fluctuations in demand and well planned water supply scheme has to supply watet as and
when required depending upon the demand. Earlier it has been discussed that maximum
daily demand goes as high as 1.8 times the average daily demand, of course only at peak
hours, i.e., for certain hours in the day. We cannot expect purification units to be made to
purify water at double of the average demand at peak periods. Hence, in the system one
or more reservoirs are inserted to furnish elasticity to the distribution system so that
different units to work at a constant average rate.
Distribution reservoirs also called seyice reservoirs are the storage reservoirs, which
-A_-- ---r-J L-- d? l..f-- ...-
r-- A..-'----,l. L
,
..
-, -,A ,
-,
-
,,
:
, .I,.., A..A,-
Water Distribution fire, breakdowns, repairs etc. Thus, helping in absorbing hourly fluctuations in the normal
water demand.
Objectives
The unit will deal with distribution or service reservoirs. After going through this unit,
you will know about
purpose and use of distribution reservoirs,
its suitable position in the system,
different kinds of service or distribution reservoirs,
procedure and guidelines for desi n, and
8
estimation of designed capacity of a distribution reservoir.
Elevated distribution
ELEVATION
.--PLAN
/ explained in Figure 16.1. When the demand for water exceeds the rate of supply, the
water £lows into the distribution system both from the elevated distribution reservoir as
well as water through direct pumping by means of a bypass loop (as shown in Figure
1
.
16.1) by closing valve at A but keeping valves B. C and D open.
When demand for water is less than the rate of supply, then the required demand is met
by water pumped through the bypass loop, while the balance pumped water fills up the
balancing reservoir by closing the valve D but keeping valves A, B and C open to
regulate the flow. '
The main functions served by the distribution reservoirs are summarised below :
(i) They absorb the hourly variations in demand and allow the water treatment
units and pumps to operate at a constant rate. This reduces the running,
maintenance and operational (RMO)costs and improves efficiency.
(ii) They help in maintaining constant pressure in the distribution mains. In their
absence, the pressure falls down as the demand of water increases.
(iii) The pumping of water in shifts is made possible by them without affecting the
supply. Thus, 8 to 12 hours of pumping can be carried out so as to supply the
whole day demand.
(iv) The water stored in these reservoirs can be supplied during emergencies such as
breakdown of pumps, heavy fire demand etc.
(v) They provide an overall economy by reducing the sizes of pumps, pipe lines
and treatment unit and this is the most important aspect of service or
distribution reservoirs.
Figure 16.2 illustrates this condition : P is a pumping station, B is the reservoir and LM
is the area to be served. PX is the pumping head. During night, water flows into the
reservoir and the hydraulic gradient will be line XB. During day when consumption is
more than the pumpage, the reservoir supplies the deficiency and water flows to the
intermediate area from both directions giving pressure line XYB. With no reservoir or one
located at L, the gradient would have been line XY', steeper than XY, if the size of pipes
remain the same. A reservoir placed near the pumps at L will serve to equalise the pump
load only and will provide reserve supply but it will not have effect on the distribution
system. Hence, better location for the reservoir is at B.
If at all a service reservoir is placed at I,, it will be a small stand pipe or a small elevated
tank. The proper elevation of a reservoir depends on the required pressure in the mains.
Where more than one zone of pressure is employed, a site is selected to serve all but the
highest zone. The highest zone is then operated without a reservoir or with a tank or a
stand pipe.
HOURS -
Figure 163 :Typical Variation in Consumption Rates for a Small Area
Water Distribution Figure 16.3 shows two consecutive days consumption into three 8-hour periods. Since
Sunday is a holiday in most of the places, maximum day demand of a week has been
. taken into consideration.
From midnight until 8 a.m. flow is less than average (% loss in the figure shown), from
8 a.m. until 4 p.m. flow is greater than average (% greater in the figure shown) and from
4 p.m. until midnight, the flow is about the average. Now it can be deduced that during
the period 8 a.m. to 4 p.m. excess flow will have to be from the storage (distribution
reservoir). This amount of water will have to be put back into the reservoir during the
following night in order to fill the reservoir ready for the next day. The maximum
demand figure varies 15% to 40% in excess of the average for the whole day depending
upon the size of the area considered. The lower percentage 'is applicable to large
industrial area of a population one lac or more and the higher percentage applies to a
smaller urban area of population under 20,000.
In the above calculation, minimum storage required to average out the flow of one
particular day has been taken. In practice, storage more than this will be required due to
following reasons :
(i) There will be variations from one day to the next day.
(ii) It may not be always possible to have the service reservoir full every morning at
8.00 a.m.
If double the theoretical requirement is provided then the contents of the service reservoir
above or below the 50% full line can easily be fluctuated and this will give greater
flexibility. Supposing thht an 8 hour maximum flow rate is 30% in excess of the average
flow for the day, then the amount of storage required for the distribution or service
reservoir
= 2 x 0.30 x (1 /3) (day's total consumption) x 125%
= 25% of day's total consumption
i.e., one quarter of the day's consumption. This storage will meet the hourly fluctuation of
flow.
But this much amount of storage may not be sufficient to meet all contingencies.
The storage capacity of balancing or service reservoirs is worked out with the help of
hydrographs of inflow and outflow by mass curve method or by analytical tabular
solution.
Solution
Average daily supply = 200 x 15,000
= 30 x 106 litres = 30 million litres
Average hourly demand = 30 / 24 = 1.25 million litres.
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 8
-
-
6
-
0.70 2.04
-2.59
-
1.25 7.50 4.95
~~-~~
10 1.90 7.24 9.05 1.25 12.50 - 3A5
1 2 3 4 5 6 7 8
9 1.90
- -
10 1.90 7.24 9.05 2.5 10.0 - 0.950
From above table, it is observed that the maximum of excess of demand = 0.32 M1
and the maximum of excess of supply = 0.36 M1.
Therefore, total storage required = 0.32 + 0.36 = 0.69 M1= 680,000 litres (Ans.)
Example 16.3
A town has population of one lakh. It is to be supplied with water at the rate of
200 litres per head per day. The variation in demand is as follows :
6 a.m. to 9 a.m. 40% of total
9 a.m. to 12 noon 10% of total
12 noon to 3 p.m. 10% of total
3 p.m. to 6 p.m. 15% of total
6 p.m. to 9 p.m. 25% of total
Determine the capacity of the service reservoir when the pumping is at a uniform
rate from 6 a.m. to 6 p.m.
Solution
. :. Total daily requirement = 1,00,000 x 200
= 20 x lo6 = 20 MI
Calculation for cumulative demand
Demand and supply lines have been drawn in firm and dotted lines respectively in
Figure 16.4. Two maximum ordinates enclosed between demand and supply lines have
been red out as 5 million litres and 3 million litres respectively.
Storage And
DistributionReservoirs
TIME IN HOURS
Figure 16.4
-
.: Total Storage required = 5 + 3 = 8 million litres (Ans.)
Differentiating with respect to h and equating to zero, we get that for a minimum cost C,
h = l h m 4 @ . . . (16.3)
The economical depth is, therefore, proportional to the fourth root of Q and hence, it
should vary but little for considerable variations in capacity.
Since Q = h?,we have from Eq. (16.3)
h = (c/~c')*.P . . . (16.4)
which gives that h is proportional to J?
From Eq. (16.3), we see that as the cost per unit area increases (because of any reason), h
should also increase, but only in the proportion of @. If the cost of wall varies as h2,
then Eq. (16.3) becomes as
Eq. (16.5) indicates that here h varies at a lesser rate with Q than in Eq. (16.3).
The value of h will then vary with 6.With a fixed bottom elevation, it is to be noted that
the lift of the pump increases with increase in depth thus increasing the operation cost.
Most usual depths for different capacities are as follows :
Capacity (m3) Depth of Water (m)
Upto 3500 2.5 - 3.5
3500 - 15000 3.5 -, 5.0
Over 15000 5.0 - 7.0
But these figures do not apply to water towers or pre-stressed reinforced concrete tanks.
Factors influencing depth for a given storage are :
(i) depth at which suitable foundation conditions are encountered.
(ii) depth at which outlet main has to be laid.
(iii) slope of gound, nature and type of backfill soil.
(iv) the need to make the quantity of excavated material approximately equal to the
amount required for banking or filling so as to reduce carting of surplus
materials.
(v) the shape and size of land available.
16.7.2 Roofing
Water in a distribution or service reservoir is treated water ready for consumption.
Hence, it should not be stored in open space which may cause pollution from the
atmosphere.
Concrete roofs are designed as flat slabs on columns. Construction with cast in-situ-slabs
resting on beams or as a series of precast and pre-stressed beams laid side by side and
grouted together are also common. For ordinary reinforced construction span of 3.5 to
4.5 m, give a thickness in the range of 150 to 200 mm and are more common in use. Use
of precast pre-stressed beams, however, permits the use of spans upto 7.5 m thus reducing
number of columns. Due to temperature changes, the roof may have expansion. Hence,
they are not fixed with the walls but should be free to slide over them. For heat insulation
concrete roof slab is covered with gravel and finally a layer of earth. But if temperature Storage And
DistributionReservoirs
does not go too high, the earth layer may be spared because it increases dead load on the
slab making it more thick and thus, increasing the cost of construction. The gravel layer
helps in drainage of water falling over the roof cover of the tank. Sometimes for larger
spans arched or domed roofs are also made. Roofs are always provided with ventilators to
allow free circulation of air.
16.7.5 Pipings .
The inlet to a service reservoir may be kept at any elevation. If provided at the bottom, a
non-return valve on the inlet pipe work should be provided so that in case of pipe burst,
the water from tank should not flow back through the inlet main. The outlet pipe should
be taken out at low level and can be arranged with its invert at floor level provided a
sump is constructed just in front of the outlet into which debris (if at all present) will be
trapped instead of being swept into the main. The overflow out of service reservoir is an
important safety feature. Diameter or number of outlets should be such that maximum
inflow to the tank under any circumstances should not rise so high to cause uplift
pressure on the roof.
Stop valves must be put on both inlet and outlet mains. These may be made small& in
diameter than the pipeline by some 25% for lesser loss of head. Precautions are to be
taken to lay all pipes beneath the surrounding embankment on solid ground so that
differential settlement is minimised. When a pipe passes under the embankment and then
through the wall of the reservoir, there should be at least two flexible joints incorporated
in the line at the back of the wall to permit settlement of the wall without fracture of the
pipeline.
Figure 165 :Cmss-section of a Dbtributlon Resendr with Sloping and Flat Floors
Flpre 16.6 :Cm-section of a Small RC.C. Distribution Reservoir with Flat Roof and Floor
INTZ TANK.
16.8.2 Stand-pipes
It has been discussed earlier that stand-pipes are small tanks of diameter 10 to 15 metres.
The useful storage of a stand-pipe is the volume above the elevation required to give the
required pressure in the distribution system. The water stored below this level is utilised
in emergency e.g., fire-fighting with the help of booster pumps. Figure 16.8 shows a
typical cross-section of a stand-pipe with connections.
Water Distribution
--
-.
- A
--
-
OVERFLOW PlPE
T0 DtST RI BUTION
MAIN
DRAIN PlPE
SAQ 1
Discuss the graphical prwedure for estimating capacity of a distribution reservoir.
(i) when pumping is done continuously for 24 hours.
(ii) when pumping is done for a limited period.
SAQ 2
An overhead tank is to be provided for a town water supply. Given the following
data, calculate the minimum capacity of the tank without any fire demand. Tank is
empty between 12 to 15 hours.
(i) Average water supply = 16,666 litres / hr
(ii) Rate of Pumping = 25,000 litres / hr
(iii) Hours of pumping = 4 to 12 and 15 to 23 hrs.
Storage And
Distribution Reservoirs
SAQ 3
A service water tank is receiving water from the treatment plant at a rate of
200 m3/hr for 24 hours. The high lift pumps are lifting water from the same tank at
following rates: 4-14 hrs @ 120 rn3/hr and 15-24 hrs @ 400 m3/hr. Determine the
capacity for the service water tank.
SAQ 4
Discuss the location and height of distribution reservoirs.
SAQ 5
For a town daily requirement of water for supply to the population is 2 lakhs litres.
The pattern of draw off is as follows :
6 a.m. to 9 a.m. - 30% of day's supply
9 a.m. to 4 p.m. - .35% of day's supply
4 p.m. to 7 p.m. - 25% of day's supply
7 p.m. to 6 a.m. .lo%of day's supply
The pumping is done for 10 hours a day from 8 a.m. to 6 p.m. Find out the storage
.
capacity of the disbibution reservoir for the water supply scheme.
Water Distribution
16.9 SUMMARY
This unit deals with distribution reservoirs. When they are comparatively smaller in size
1
they are called service or distribution tanks. Service reservoirs are put on surface of the
ground or to provide additional head they are put at higher elevation supported on pillars.
Smaller elevated service reservoirs are known as stand-pipes. This unit deals with
procedure to evaluate or estimate capacity of distribution reservoirs with reference to
demand and supply. Details of different components and types with respect to
construction have also been discussed.
Supply Curve
Demand Curve
TIME IN HOURS
Figure 16.9
-
T d a l storage required
= A+B
0 6 AM 6 PM
A mass curves is drawn for the accumulated supply versus time and over this, Storage And
demand curve versus time is super-imposed. The amount of balancing storage is DistributionReservoirs
determined by adding maximum ordinates between the demand and the supply
lines. Figure 16.9 explains the procedure when pumping is done continuously and
Figure 16.10 explains the procedure when pumping is done for a limited period.
SAQ 2
Problem has been solved analytically in table given below.
As given in the question, the tank is empty between 12 and 15 hours. Hence, we
shall start from S1. No. 5. At Serial No. 6 storage is (+) 16,666 again at S. No. 7, it
has reduced by 6666 litres. Hence, net storage'is (16,666-6,666) = 10,000 and so
on proceed S1. No. 8, 9, 1,2, 3 and finally at 4.
Now from Column No.7, it is clear that maximum balance storage is 35,000 litres.
Hence, minimum capacity of the tank should be 35,000 litres (Ans.)
SAQ 3
The problem has been solved in the table given below.
The cumulative supply over demand i.e., excess supply to the tank is 1800 m3.
Hence, the capacity of the tank should be 1800 m3.
1 2 3 4 5 6
-
14 15 Nil 1200 200x 1 =ZOO 3000 (+) 1800
SAQ 4
A distribution reservoir should be located in the centre of the distribution area so
that maximum reach could be served. It should be nearer to the area of heaviest
demand so that friction loss through pipes is minimum. It is preferable to locate
them a&the highest elevation available in the area so that sufficient head is
Water Distribution available in distribution system. Next point to be considered keeping in view of
above points is that they should be placed between pumping station and
distribution area. For more detail, refer Section 16.4.
SAQ 5 -.
Total daily requirement = 200,000 litres
Now the cumulative demand covered is tabulated in the table given below :
TIME IN HOURS
Figure 16.11
-
Total demand is met in 10 hours
.: Rate of supply = 200,000/10 = 20,000 litreshr.
Two maximum ordinates between supply and demand lines are
A = 30,000 litres
B = 42,0001itres
:. Total storage capacity = A + B = 72,000 litres (Ans.)