50% found this document useful (2 votes)
884 views

Scaffolding Method Statement

This document provides a method statement and risk assessment for scaffolding works at the Jebel Ali Power Station 'K' Phase III project. It outlines responsibilities, procedures, emergency plans, and a risk assessment. The site manager is responsible for overall safety compliance. The site engineer must ensure all height work training and permit requirements are met. The safety officer provides training and checks controls are implemented. The supervisor conducts toolbox talks.

Uploaded by

rajappan
Copyright
© © All Rights Reserved
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
884 views

Scaffolding Method Statement

This document provides a method statement and risk assessment for scaffolding works at the Jebel Ali Power Station 'K' Phase III project. It outlines responsibilities, procedures, emergency plans, and a risk assessment. The site manager is responsible for overall safety compliance. The site engineer must ensure all height work training and permit requirements are met. The safety officer provides training and checks controls are implemented. The supervisor conducts toolbox talks.

Uploaded by

rajappan
Copyright
© © All Rights Reserved
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 9

Approved Stamp Issuer

DF Document No: K-III-DFE-SG_-GP-20337 Is: 00 Rev: A

A 21-01-2020 HASEEN.M.S FOR APPROVAL

Rev Date Name Note


Employer

Jebel Ali Power Station ‘K’ Phase III

Engineer Contractor

Date Name Scale:

Prepared: 21-01-2020 HASEEN MOHAMMED.M.S N/A


Method Statement And Risk Assessment For
Checked: 21-01-2020 B.S.MUTHUMANICKAM
Scaffolding Works Sheet:
Approved: 21-01-2020 B.S.MUTHUMANICKAM
1 of 15
Supersedes:

Superseded by: Size: A4 PO No.: 3761700035 File:

System: Annex: Document No: M-38-M-P-20337 Rev: A


CUSTOMER:

PROJECT:

Jebel Ali Power Station ‘K’ Phase III

TITLE:

Method Statement and Risk Assessment for Scaffolding Works

PROJECT DOC NUMBER: ED: REV:

A M-38-M-P-20337 00
ISSUE PURPOSE: DATE:

FOR APPROVAL 21-01-2020

DF STAMP: PREPARED DATE:


Haseen Mohammed
21-01-2020
BY:

CHECKED DATE:
B.S.Muthumanickam
BY: 21-01-2020

APPROVED FECHA:
B.S.Muthumanickam
BY: 21-01-2020

www.dfdurofelguera.com Page 2 of 9 APPROVED DOCUMENT BY


Este documento contiene información This document contains information
confidencial y de propiedad de DF. Se confidential and proprietary to DF. It is
transmite confidencialmente y debe ser submitted in confidence and is to be
utilizado únicamente para el propósito used solely for the purpose for which it
para el que se editó y debe ser is furnished and returned upon
devuelto si así se solicita. Este request. This document and such
documento y la información contenida information is not to be reproduced,
en él no puede ser reproducida, transmitted, disclosed, or used
transmitida, desvelada o usada en todo otherwise in whole or in part without
o en parte sin la autorización escrita de the written authorization of DF.
DF.

Date of Printing: 11/7/2020


AUTHOR ISSUER
DOC Nº. M-38-M-P-20337
SIZE A4 LANGUAGE EN ED 00 REV A

PROJECT DOCUMENT NUMBER: M-38-M-P-20337

CHANGES CONTROL SHEET


ED REV DATE SECTIONS CHANGES DESCRIPTIONS
00 A 21-01-2020 ALL FIRST SUBMISSION

Este documento es propiedad de DF y deberá


ser gestionado bajo las restricciones
This document contains proprietary
information of DF and is subject to the
Page 3 of 9
detalladas en la portada restrictions set forth on the title page

Date of Printing: 11/7/2020


TABLE OF CONTENTS

1. PURPOSE 5

2. SCOPE 5

3. DEFINITION 5

4. ABBREVIATION 5

5. RESPONSIBILITY 5

6. PROCEDURE 6

7. EMERGENCY AND EVACUATION 8

8. RISK ASSESSMENT 9

Este documento es propiedad de DF y deberá


ser gestionado bajo las restricciones
This document contains proprietary
information of DF and is subject to the
Page 4 of 9
detalladas en la portada restrictions set forth on the title page

Date of Printing: 11/7/2020


1. PURPOSE

General Method statement and risk Assessment for Scaffolding works activity.

2. SCOPE

This method statement outlines the procedure for using scaffolding associated works in
Jebel Ali Power Station “K” Phase III.

3. DEFINITION

A scaffold is an elevated temporary working platform used to support workers, materials


and tools during construction work. It is being used when it is not possible to perform
works with other safe manner.

4. ABBREVIATION

1. MS - Method Statement
2. RA - Risk Assessment
3. E/E - Employer /Engineer
4. PPE - Personal Protective Equipment
5. HSE - Health Safety and Environment
6. PTW - Permit to Work
7. TBT - Tool Box Talk

5. RESPONSIBILITY

Site Manager:
1. The site manager will be responsible for overall implementation of the
projects.
2. Responsible for the total compliance of the safety requirements.
3. Lead the site activities with site engineer and supervisor.

Site Engineer:
1. Site Engineer is responsible for the height work area activities.

Este documento es propiedad de DF y deberá


ser gestionado bajo las restricciones
This document contains proprietary
information of DF and is subject to the
Page 5 of 9
detalladas en la portada restrictions set forth on the title page

Date of Printing: 11/7/2020


2. Ensure that all staff and workers carry out the work are completed the work at
height training from the main contractor.
3. Conduct tool box talks prior to start of the activity for all involved in the work.
4. Ensure that all people working in scaffold shall comply with this MSRA
procedure.
5. Ensure that scaffolders shall use full body hardness at height all the time
during the work period.
6. Ensure that all PPE’s are in good condition.
7. Ensure height work Permit to Work (PTW) is valid before entering the PTW
required area.
8. MSRA to be informed to all workers involved during TBT.

Safety Officer:
2. Responsible for implementation of safety procedure from beginning till end of
the Scaffolding works activity.
3. EHS shall confirmed that the TBT is conducted and records maintained
4. Providing training on the possible hazards to all concerned employees and
workers.
5. Assisting in identification and implementation of risk controls.
6. Carry out safety checks during the hot work activity until the work is
completed.
7. He shall ensure that all staff and workers who are involved in the height work
activity are provided with Scaffolding works training from the main contractor.

Site Supervisor:
1. Conduct tool box talks prior to start of the activity for all involved in the work.
2. The supervisor shall be responsible for execution of works and supervision of
workers.
3. Execute the work in accordance with the approved MSRA and HSE
requirement.

Este documento es propiedad de DF y deberá


ser gestionado bajo las restricciones
This document contains proprietary
information of DF and is subject to the
Page 6 of 9
detalladas en la portada restrictions set forth on the title page

Date of Printing: 11/7/2020


AUTHOR ISSUER
DOC Nº. M-38-M-P-20337
SIZE A4 LANGUAGE EN ED 00 REV A

6. PROCEDURE

1. Scaffolds must be provided for employees engaged in work that cannot be done
safely from the ground or from solid construction.
2. All scaffolds must be erected, dismantled or altered only under the supervision of
a competent person and by skilled and experienced scaffolders. Scaffolder &
scaffolding inspector shall be 3rd party certified from a DAC approved certifying
company.
3. Scaffold shall be erected on the well compacted and level place.
4. Check handrail and toe boards in good condition prior to start working.
5. On all lifts above 1.8 meters prior to handrails and toe boards being fitted full
safety harness shall be attached to an appropriate fall restraint. This also applies
during the dismantling process.
6. Scaffolders during erecting and dismantling scaffolds shall be provided with proper
fall protection measures and shall be provided with suitable PPE’s to protect from
fall hazard.
7. Scaffolds to be inspected by competent scaffolding inspector before starting any
work.
8. Scaffolds cannot be erected or used near energized power lines to avoid any
contact between the scaffold components and these power lines.
9. Scaffolds must have sole board, base plates even when setting on concrete floor.
10. A safe way access, secured adequately for entrance and exit shall be provided. It
is preferable to provide a ladder inside the scaffold to reach to the work platform.
11. Ladders shall be inspected before each use in case of deformity, damage or any
missing parts it should be removed from the work place.
12. Ladders shall extend a minimum of 1 meter beyond the top step-off point.
13. Materials shall not be kept upon a scaffold unless needed for the work within a
reasonable time period.
14. Materials used for the scaffolds shall be stored properly and away from other
materials that might affect.
15. Where materials of the scaffolds are handled manually during erection or
dismantling, no workers shall exist under these materials.

Este documento es propiedad de DF y deberá


ser gestionado bajo las restricciones
This document contains proprietary
information of DF and is subject to the
Page 7 of 9
detalladas en la portada restrictions set forth on the title page

Date of Printing: 11/7/2020


AUTHOR ISSUER
DOC Nº. M-38-M-P-20337
SIZE A4 LANGUAGE EN ED 00 REV A

16. Partially erected or dismantled scaffolds shall not be used, and a prominent
warning tag (Red scaffold Tag) indicating that the scaffold is incomplete and not
safe to be used shall be displayed.
17. Material handling from ground to height shall be done properly (Tool bag, Rope,
Pulley).
18. The complete scaffolds shall be used, after providing scaffold tag (Green Tag)
signed by the approved and competent scaffolding inspector indicating that
scaffolding is ready and safe to use.
19. While using mobile scaffolds the scaffolds wheel brakes must be in the engaged
position.
20. While the mobile scaffold is being moved or repositioned, it is strictly forbidden for
any personnel & material to remain on the scaffold.
21. Proper access shall be provided (No climbing on scaffoldings pipes).

7. EMERGENCY AND EVACUATION

1. Tool Box Talk topic emergency & evacuation shall be conducted prior to start
work.
2. In case of emergency, ensure all employees have evacuated their work place &
assembled at the nearest assembly point.
3. Head count by concerned Engineer and Safety Officer.
4. Head count completed, no person was found missing shall be informed to
EHS/concerned

Este documento es propiedad de DF y deberá


ser gestionado bajo las restricciones
This document contains proprietary
information of DF and is subject to the
Page 8 of 9
detalladas en la portada restrictions set forth on the title page

Date of Printing: 11/7/2020


AUTHOR ISSUER
DOC Nº. M-38-M-P-20337
SIZE A4 LANGUAGE EN ED 00 REV A

8. RISK ASSESSMENT

Este documento es propiedad de DF y deberá


ser gestionado bajo las restricciones
This document contains proprietary
information of DF and is subject to the
Page 9 of 9
detalladas en la portada restrictions set forth on the title page

Date of Printing: 11/7/2020

You might also like