Method Statement of Flooring
Method Statement of Flooring
Corporate Office:
PSP House,
Opp. Celesta Courtyard,
Opp. Lane of Vikramnagar Colony,
ISCON-Ambli Road,
Ahmedabad – 380058.
Tel Nos.: +91 -079 – 2693 6200, 2693 6300, 2693 6400
Fax Nos.: +91–079 – 2693 6500
E Mail: [email protected]
Web: www.pspprojects.com
1|Page
Project: Hospital Project at Sitapur
CONTENTS
1 Introduction
2 Scope of Work
3 References & Standard
4 Material
5 Tools & Tackles
6 Methodology
7 Safety Measurement
Sign
Name
Date
1. Introduction:
This method statement describes the work procedure to be followed for Flooring to be
2|Page
Project: Hospital Project at Sitapur
2. Scope of Work:
The scope of work involves the following:
Flooring, as per the issued GFC drawing.
3. References and Standard:
This procedure is based on the requirements of the approved drawings, technical
specifications, below mention Indian standard & requirement of client &
Architect.
The applicable Indian Standards Codes are as under
1. IS 13630:1993
2. IS 15622:2006
3. IS: 3316:1974
4. IS: 1124:1974
5. IS: 1130:1969
6. IS: 3622:1977
7. Cement & Sand conforming to relevant IS code.
4. Material:
Material used for Flooring is:
Granite, Tiles, Kota (Approved as per Architect/Client)
Cement
Sand
Water
Spacer
Joint Filling Mortar
6. Methodology:
3|Page
Project: Hospital Project at Sitapur
A. Granite Flooring: -
RCC slab or side brick wall shall be cleaned, wetted and mopped before fixing.
Area shall be scrapped/cleaned/washed before starting the mortar bedding. The flooring
pattern shall be finalized.
The bedding for the tile shall be with cement mortar 1:4 (1 cement: 4 coarse sand) or as
specified. The mortar of specified proportion and thickness shall then be evenly and smoothly
spread over the base by use of screed battens to proper level or slope (Wet Area). The
templates to required level and slope to be done well in advance.
Laying of mortar to suitable thickness keeping reference templates in line dori to be
supervised from time to time.
Neat cement paste shall be spreaded over mortar bedding and around the edges of the
stone. Then the stone shall be fixed close to the previous. Stone shall have a hairline
joint. Stone surface shall be pressed tapped gently with the wooden mallets till the stone
is in true line and level. Cement paste of the edges will try to come out from joints,
which should be strapped off. Again joints shall be filled up with neat cement paste to
fill up the gaps and surplus mortar shall be removed.
Curing of flooring for 7 days by sprinkling water or by wetting.
B. Vitrified Flooring: -
In Floor:
Concrete surface shall be cleaned of scales, laitance, set mortar etc. It shall be washed
with clean water.
Marking of the finish level should be marked on the wall by lime with the help of string.
Thaiya of the required finish level should be prepared in advance with the mortar
proportion (1:4).
A bedding of cement mortar (1:4) and average 20 mm thick shall be laid evenly to the
required levels.
The tiles of approved make should be laid on the bedding with a backing of thin cement
paste.
All laid tiles should truly and evenly set & pressed in position to obtain a uniform and run
in perfect straight lines.
The joints & pattern of the tiles should be maintained as per drawing.
Joints should be filled up with approved pigment / cement as per the detail given in the
drawing.
The entire finished surface should be thoroughly cleaned to remove all cement stains etc.
Flooring should be kept wet for 7 days.
In Dado:
4|Page
Project: Hospital Project at Sitapur
with neat cement paste to fill up the gaps and surplus mortar removed. Suitable
color pigment shall be used for joint sealing to match with the stone color.
Flooring shall continue at least 10mm inside the wall plaster line.
Any irregularities (othas) due to natural bends in stones should be restricted to
2mm at joints.
Curing of floor shall be carried out for 7 days by sprinkling water or by wetting.
Polishing
Polishing shall be started after 14 days of completion of flooring work.
Semi mirror polishing activity shall be follow only after adequate curing, the
sequence of polishing will be as under.
One coat with emery stone - 40 no. by polishing m/c (heavy) which should even
out all irregularities (othas) and plus OR minus.
Floor shall be washed and ragada is removed to check the joints. All joints shall
be re grouted with cement paste. Setting shall be allowed for at least 1 days.
Two coat of emery stone - 60 no. by polishing m/c (heavy) which should even out
all irregularities.
One coat of emery- 120 no shall be done by polishing machine to achieve even
surface.
One coat of gutka shall be applied by polishing machine.
Surface is fairly in level and without any scratch or lines of the machining.
One coat by black kapchi and one coat by 120 no synthetic emery stone shall be
done and buffing shall be carried out. Now surface is even and scratch less as per
requirement.
Flooring shall be clean by with Oxalic Acid to achieve the scratch less finished
surface.
6. Safety Measurement:
Proper precautions shall be taken during flooring work. All workers shall use PPE as per
PPE matrix shown in the EHS plan.