Remote Deposit Capture Project Part 1: Project Integration Management
Remote Deposit Capture Project Part 1: Project Integration Management
Tasks
1. Research information on remote deposit capture. Who is using it, and how does it work?
Do you think it’s an important feature to provide for banking customers? Why or why
not? How much do you think customers would be willing to pay for this service?
Summarize your response in a two-page paper citing at least two references.
2. Several managers at Blue Bank are not sure that they should invest in remote deposit
capture. The bank prides itself on being customer-oriented, having several large bank
buildings, ATMs and remote bank sites in many grocery stores, primarily throughout the
Midwest. Many of its customers have banked with Blue Bank their whole lives, but less
than half of them use any of its current Internet banking services. The new VP of IT was
hired to prepare Blue Bank for the future and to reduce the loss of younger customers
who have moved to banks that are more progressive. Based on this information and
research on the current banking industry, identify three potential strengths,
weaknesses, opportunities, and threats that Blue Bank may be experiencing.
3. Prepare the financial section of a business case for the Remote Deposit Capture Project.
Assume the project will take 6 months to complete and cost about $500,000 (year 0
costs). Annual operating costs would be about $150,000 per year for three years.
Estimated benefits are about $400,000 per year for three years. Use the business case
spreadsheet template to help calculate the NPV, ROI, and year in which payback occurs.
Assume a 6.5 percent discount rate.
4. Prepare a project charter for the Remote Deposit Capture Project. Assume the project
will take 6 months to complete and cost about $500,000. Use the project charter
template and examples of project charters in Chapters 3 and 4 as guidelines. Assume
that the project sponsor will be the new VP of IT, Harold Johnson, you will be the project
manager, and you will have people from marketing and IT supporting the project on a
part-time basis. The VP of Marketing, Tricia Young, is also a key stakeholder in the
project and head of a project steering committee formed to oversee this project.
5. You know that people will be requesting changes to the project and want to make sure
you have a good integrated change control process in place. You also know that you
want to address change requests as quickly as possible. Review the template for a
change request form provided on the companion Web site (change_request.doc). Write
a one- to two-page paper describing how you plan to manage changes on this project in
a timely manner. Address who will be involved in making change control decisions, what
paperwork/electronic systems will be used to collect and respond to changes, and other
related issues.
Tasks
1. Develop a scope statement for the project. Use the template file and the example in
Chapter 3 as guides. Be as specific as possible in describing product characteristics,
requirements, and deliverables.
2. Develop a work breakdown structure (WBS) for the project. Break down the work to
level 2 or level 3, as appropriate. Use the template file and samples in Chapters 3 and 5
as guides. Print the WBS in list form as a Word file. Be sure to base your WBS on the
project charter, scope statement, and other relevant information.
3. Use the WBS you developed in Task 2 above to create a Gantt chart in Project 2007 for
the project. Use the outline numbering feature to display the outline numbers (click
Tools on the menu bar, click Options, and then click Show outline number). Do not enter
any durations or dependencies. Print the resulting Gantt chart on one page, being sure
to display the entire Task Name column.
4. Develop a strategy for scope verification and change control for this project. Write a
two-page paper summarizing key points of the strategy.
Part 3: Project Time Management
One of your duties as the project manager is to lead your team in developing a schedule. Mike
and Sophie are the information technology professionals. The marketing professionals are
Carlos and Joanna, and John is the purchasing specialist. Don’t forget that you have only six
months to complete the project and a budget of $500,000. Dorian, the project sponsor, had
told you that it is important to finish on time and within budget, but it is even more important
to provide a high-quality service and avoid any potential technical or user problems after
implementation. Blue Bank wants to attract new customers with remote deposit capture and
avoid losing current customers, so quality and customer service is key. The team decides to
focus on key milestones in developing the schedule, being sure that suppliers know their roles
on this project and that adequate testing is done.
Tasks
1. Review the WBS and Gantt chart you created for Tasks 2 and 3 in Part 2 above. Propose
three to five additional activities you think should be added to help you estimate
resources and durations. Write a one-page paper describing these new activities.
2. Identify at least eight milestones for this project. Write a one-page paper describing
each milestone using the SMART criteria.
3. Using the Gantt chart you created for Task 3 in Part 2 above, and the new activities and
milestones you proposed in Tasks 1 and 2 above, estimate the task durations and enter
dependencies, as appropriate. Remember that your schedule goal for the project is six
months. Print the Gantt chart and network diagram.
4. Write a one-page paper summarizing how you would assign people to each activity.
Include a table or matrix listing how many hours each person would work on each task.
These resource assignments should make sense given the duration estimates made in
Task 3 above.
5. Assume that your project team starts falling behind schedule. Describe strategies for
making up lost time and avoiding schedule slips in the future.
Tasks
1. Prepare and print a one-page cost estimate for the project, similar to the one provided
in Figure 7-1 in Chapter 7. Use the WBS you created earlier, modified, if needed, to
make sure you are including outsourced hardware and labor costs. Be sure to document
assumptions you make in preparing the cost estimate. Assume a labor rate of $60/hour
for the project manager and $50/hour for other project team members. Assume twice
those numbers for outsourced labor.
2. Using the cost estimate you created above, prepare a cost baseline by allocating the
costs by WBS for each month of the project.
3. Assume you have completed three months of the project. The BAC was $500,000 for
this six-month project. Also assume the following:
PV= $250,000
EV= $230,000
AC= $300,000
Using this information, write a one- to two-page report that answers the following
questions:
a. What is the cost variance, schedule variance, cost performance index (CPI), and
schedule performance index (SPI) for the project?
b. Use the CPI to calculate the estimate at completion (EAC) for this project. Use
the SPI to estimate how long it will take to finish this project. Sketch an earned
value chart using the above information, including the EAC point. See Figure 7-5
as a guide. Write a paragraph explaining what this chart shows.
c. How is the project doing? Is it ahead of schedule or behind schedule? Is it under
budget or over budget? Is it way off track or not? Should you alert your senior
management and ask for assistance? Should you talk to your sponsor before the
meeting to discuss this data?
4. You notice that several of the tasks that involve suppliers have taken longer to complete
and cost more than planned. You have talked to the people in charge of those areas
several times, but everyone says they are doing the best they can. Write a one-page
paper describing corrective action you could take to address this problem.
Tasks
1. Develop a list of quality standards or requirements related to meeting the stakeholder
expectations, focusing on both senior management and customer expectations. Provide
a brief description of at least four different requirements. For example, a requirement
might be that the new feature is available 24 hours a day, 7 days a week, and that the
time it takes to properly scan one check is less than ten seconds.
2. You have decided to expand the testing program to observe several potential customers
using early versions of the system to get their feedback. Write a one- to two-page paper
describing how this testing might work. Try to find information on how real companies
get customer feedback such as this.
3. After analyzing results of early customer testing of the new system, you decide to create a
Pareto diagram to easily see what problems or suggestions users reported. Use the
template for a Pareto diagram and the following information to create it.
# of Times
Problems/Suggestions
Requested
Make showing check scanned image the default 18/td>
Allow scanning multiple checks at once 30
No confirmation message after scanning check 15
Show simple checkbox to select account to make
25
deposit into
Show running total for all checks scanned 9
Add video/animation for instructions 3
Tasks
Prepare a RACI chart to help clarify roles and responsibilities for these customer-testing
tasks. Document key assumptions you make in preparing the chart.
2. Senior management has asked you to plan for the support required in the first year for
the remote capture system after the project is completed. Assume that there will be
two phone service people working 24-7 all year, one person providing online support
24-7 all year, four marketing people working on promotions full-time the first six
months, two marketing people working on promotions the last six months, and one
internal IT person providing technical support half-time all year. Create a resource
histogram, similar to the one in Figure 9-6, based on this information.
3. The marketing people are having problems deciding on a promotional strategy for the
new remote capture service. The two people responsible for the campaign simply
cannot agree on an approach. One wants to focus primarily on an online campaign,
while the other thinks a more traditional approach (having people on-site at the various
banks the first week the service is available, giving away free scanners at various banks,
having radio and television advertising of the service) is best. You tried meeting with
them both together, but it’s clear that neither of them wants to give up his/her idea.
Write a one-page paper summarizing the actions you could take the way you could work
with the key people involved. Be sure to address how you would understand each
person’s point of view while creating a realistic solution.
Tasks
1. Create an issue log for the project. List at least three issues and related information
based on the scenario presented.
2. In addition to written weekly status reports, what else might you suggest to improve
project communications? Summarize your ideas in a one-page paper.
3. Since many of the Code Corp.’s people work in other countries and in a virtual
environment, they are used to coding applications that are very well defined and
communicated by non-face-to-face methods. Research best practices for
communications in this type of environment. Summarize your findings in a one- to two-
page paper, citing at least two references.
4. Write a one- to two-page paper describing how you might approach two of the conflicts
described above. Explain the conflict-handling mode you are suggesting and why you
think it would work.
Tasks
1. Create a risk register for the project, using Table 11-6 as a guide. Identify six potential
risks, including at least two positive risks.
2. Plot the six risks on a probability/impact matrix, using Figure 11-6 as a guide. Assign a
numeric value for the probability of each risk, and its impact on meeting the main
project objectives. Use a scale of 1 to 10 to assign the values, with 1 being lowest and 10
being highest. For a simple risk factor calculation, multiply these two values (the
probability score and the impact score). Enter the new data in the risk register. Write
your rationale for how you determined the scores for one of the negative risks and one
of the positive risks.
3. Develop a response strategy for one of the negative risks and one of the positive risks.
Enter the information in the risk register. Write a separate paragraph describing what
specific tasks would need to be done to implement the strategy. In addition, include
time and cost estimates for each strategy.