Indian Power Sector: Key Imperatives For Transformation
Indian Power Sector: Key Imperatives For Transformation
01 Introduction 05
04 Distribution reforms 26
05 Conclusion 33
Energy is central to our needs across the globe, and Amidst ongoing cooperation among industry, states,
the balance among haves and have-nots, availability governments and international players, it is essential
of clean economical energy for all, energy efficiency to work towards a roadmap for sustainable energy
and innovation demand urgent attention. There is solutions that are able to meet the growing demands
also a need to ensure the long-term sustainability, of the world’s population.
security, affordability and inclusiveness of energy
systems. The energy transition involves public−private This certainly calls for future collaboration between
collaboration, intra-state and inter-state partnership. energy stakeholders, especially for a growing
Needless to say, achieving these goals requires country like India, as India’s energy requirements
supporting policies, technological innovation, large are enormous. At the same time, demand is growing
volumes of investment and a platform that encourages but our resources are limited, both in physical and
multi-stakeholder collaboration. Leaders across the financial terms. It is therefore imperative that these
world understand that the challenges faced by the resources be exploited optimally and that efforts be
energy system cannot be addressed by a single entity. made to flexibilise thermal power plants, renewable
Rather, a common understanding is required among energy, demand-side energy efficiency and green
all stakeholders on the long-term vision for energy energy corridors.
transition and the near-term priorities.
For growing economies, it’s important to look at the
For a sector influenced by several global factors issue of energy transition in the context of the global
and other issues, it is interesting to note that development challenges and climate change. Thus,
energy systems across countries are unique to policymakers need to bring in the element of power
local circumstances, economic structure and innovation for prosperity and introduce catalysts for
socioeconomic priorities, and thus, multiple pathways entrepreneurial ecosystems for climate innovation in
are required to pursue an effective energy system that developing countries.
is local as well as global in its impact.
Collaboration among the stakeholders in the domain
Over the past few years, considering the cycle of of operations, research, financing, integration of
economic development and growth, energy security various forms of energy, and upskilling of resources
and access, and environmental sustainability, is essential. The sector has immense potential, poses
governments of developed or developing nations are unique challenges and thus calls for unique solutions
committing themselves to greater cooperation. that engage governments and the industry.
The Indian power sector has been a key driver for the country’s
socioeconomic growth since independence.
With a customer base of more than 200 million1 and service outreach spanning of nearly 3.28 million sq. km,2 the Indian
power system is one of the largest and most complex power systems in the world. Currently, the system operates as a
‘one nation-one frequency-one market’ after the creation of the national grid post the integration of the five regional grids.
In recent years, substantial growth in installed generation capacity and transmission and distribution infrastructure,
coupled with various government initiatives, has led to a reduction in energy and peak shortages (2% peak deficit in
2017–18 as against a 10% deficit in 2010–11) and surplus generation capacity.
2% 0.8% ~24%
Peak shortage Energy shortage Aggregate technical and
commercial (AT&C) losses
100 GW 60 GW 10 GW 5 MW 175 GW
GoI commitment: Towards a greener and cleaner future
India’s intended nationally determined contribution (INDC) commitments aim to reduce emissions
intensity of GDP by 33–35% by 2030 from the 2005 level and to achieve 40% of installed capacity
from non-fossil fuel by 2030.
1 http://indianpowersector.com
2 http://censusindia.gov.in
3 www.cea.nic.in
4 https://www4.unfccc.int
The Indian power market has also been evolving, with the share of
short-term transactions increasing steadily.6
Bulk electric power supply in India is mainly contracted through long-term arrangements (around 25 years) and the rest
in medium-term contracts (up to 5 years) and short-term contracts (up to 1 year). Power distribution utilities with an
obligation to provide electricity to their consumers mainly rely on long-term/medium-term contracts for supplies, which
accounts for around 89% of the total power market volumes.
MoU/ Competitive
Bilateral Exchange UI
regulated bidding
Nevertheless, to meet the short-term requirements of the market participants, short-term power trading plays an
important role and ensures optimum utilisation of power resources in different regions. The volume of short-term
transaction electricity has increased from 9% of total energy generation in 2009–10 to 11% in 2017–18. During 2009–10
to 2017–18, the volume of short-term transactions of electricity increased at a higher rate (9%) compared with the gross
electricity generation (6%).
However, it has now become essential to deepen the short-term markets by diversifying options. With greater liquidity and
adequate supply on account of new capacity addition, it is essential to serve consumer needs up to desired standards of
supply. Key measures include:
• introduction of forwards and future contracts on the exchange to ensure transparency in price discovery and more
liquidity
• introduction of capacity markets to incentivise peaking generation
• strengthening of ancillary services and trading of transmission rights to alleviate grid frequency issues and bottlenecks
due to transmission barriers and renewable integration into the grid.
5 www.cea.nic.in
6 https://www.iexindia.com, PwC analysis
• High-volume transport and electric vehicle (EV) integration: The master plan for most Indian cities targets 60–80%
of public transport ridership by 2025–30 mainly through metro rails. Additionally, the government’s ‘National Electric
Mobility Mission Plan’ aims at 100%adoption of EVs by 2030. The Indian Railways also plans to introduce 16,000 km of
new lines, besides the doubling the existing lines of 6,900 km. This would be a key demand driver in the next decade.
• Make in India: This initiative, which aims to boost manufacturing’s share of GDP from 16% to 25% percent by 2022,
would also lead to substantial growth in electricity demand.
• Reduction of aggregate technical and commercial (AT&C) losses: Programs for reduction of AT&C losses like Ujwal
DISCOM Assurance Yojana (UDAY), Integrated Power Development Scheme (IPDS) and Deendayal Upadhyaya Gram
Jyoti Yojana (DDUGJY) have been implemented by the Government. The target is to reduce AT&C losses to about 13%
by the year 2021–22 on an all-India basis, which would lead to reduction in electricity demand.
• Demand-side management (DSM), energy conservation and efficiency improvement programmes: Programmes
for DSM, improvement of energy efficiency and energy conservation measures like standards and labelling, the
Perform-Achieve-Trade (PAT) scheme in industries, energy-efficient lighting solutions and the Super-Efficient Equipment
Programme would reduce power demand.
540
561
612
691
746
835
895
944
987
FY09 FY11 FY13 FY15 FY17 FY09 FY11 FY13 FY15 FY17
FY10 FY12 FY14 FY16 FY18 FY10 FY12 FY14 FY16 FY18
Source: CEA, Energy Statistics 2019, Ministry of Statistics and Programme Implementation
7 http://cea.nic.in/reports/monthly/executivesummary/2019/exe_summary-03.pdf
8 https://www.odi.org/sites/odi.org.uk/files/resource-documents/12407.pdf
8.79 52%
8.3 42%
30% 33%
6.4
5.41 45%
4.42 33%
20% 23%
3.43
2.44 2018 2020 2025 2030
Environmental concerns
One of the biggest challenges involved in the
use of coal as a resource is environmental According to India’s Centre for Science and
contamination. Environment (CSE) reports, coal is responsible for
80% of India’s mercury pollution, 60% of airborne
• Coal combustion at thermal power plants
PM, 45% of SO2 emissions, and 30% of NO levels.
emits mainly carbon dioxide (CO2), sulphur
oxides (SOx), nitrogen oxides (NOx), CFCs,
other trace gases and airborne inorganic particulates such as fly ash and suspended particulate matter (SPM).
• The water runoff from coal washeries carries pollutants that contaminate groundwater, rivers and lakes, thus affecting
aquatic flora and fauna.
Indian coal-fired power plants pose a major risk to the environment as well as to human health in comparison to the plans
in other countries as Indian coal is of poorer quality and has a low calorific value (~15 MJ/kg) and very high ash content
(25 to 45%). In addition, a majority of coal-fired plants are based on inefficient and outdated subcritical technology, which
tends to utilise more coal per MWh of electricity generated. The result is more emissions damaging the environment and
deterioration of public health, animal life as well as plants.
Coal-fired power Water is used for washing coal, Power plants emit Disposal of larger
plants emit several circulating in the boiler furnace to high levels of noise quantities of fly ash
pollutants into produce steam and cool equipment. due to usage of from coal-based
the air, including equipment like plants affects natural
SOx, CO, NOx, Dust from coal-cleaned water boilers, turbines soil properties.
suspended contaminates groundwater. and crushers.
particulate
Soil becomes more
matter, lead and
Hot water, if let out into water alkaline due to the
non-methane
bodies without cooling, causes alkaline nature of fly
hydrocarbons.
a rise in temperature and affects ash.
aquatic flora and fauna.
India’s pollution norms need strengthening compared to those of other major economies, including China. Despite this,
its power plants fail to comply with even the relaxed levels of performance, lacking the basic technologies to control
pollution. Most of the coal-fired power plants in India are yet to retrofit their facilities with pollution control technologies.
Before 2015, India had no standards for either SO2 or NOx. It was in December 2015 that the Ministry of Environment
introduced, emission norms for thermal power stations, including emission and effluent discharge.
Presently, there is enough generation capacity to meet the country’s electricity demand. The peak electricity demand and
supply gap is currently only 0.6%. However, huge capacity addition in recent years has raised concerns related to under-
utilisation of coal-based capacities, leading to stressed assets in the sector. The plant load factor (PLF) of coal-based
plants has reduced to 61.1% in 2018–19 from 78.6% during 2007–08.
9 https://www.teriin.org/files/transition-report/files/downloads/Transitions-in-Indian-Electricity-Sector_Report.pdf
10 http://www.mospi.nic.in/sites/default/files/publication_reports/Energy_Statistics_2017r.pdf.pdf
11 www.cea.nic.in
12 www.cea.nic.in
The Ministry of Power constituted an inter-ministerial group for analysing stressed projects in the power sector of India
and made certain policy recommendations. These efforts are addressing the underutilisation scenario of power facilities.
The average capacity addition in thermal plants in FY13–16 was 19.8 GW, which fell to 6.1 GW in FY17–20. The average
closure stood at -277 MW in FY13–16 compared to 2.8 GW in FY17–20. Five key reasons for stalled thermal power projects
across India are:
• on-availability of regular fuel supply arrangements
• lack of power purchase arrangements
• inability of the promoter to infuse equity and service excessive debts
• regulatory and contractual issues
• over-build thermal capacity resulting in lower PLFs.
Thermal gross capacity addition and closure trends and estimates (MW)
20,830 22,461
20,122
16,767
11,551
8,250 8,000 8,000
13 https://powermin.nic.in/en/content/power-sector-glance-all-india
The action of retiring old and inefficient power plants and replacing them with supercritical units will not just conserve
natural resources like land, water and coal, but also reduce the carbon footprint.
2017–22 6.5 GW Less coal-based capacity addition would be required, since 47.9 MW is under
different stages of construction and likely to be commissioned during 2017–22.
14 http://www.cea.nic.in/reports/committee/nep/nep_jan_2018.pdf
In December 2015, MoEF&CC has set standards as per the Central Pollution Control Board (CPCB) recommendations and
after consultation with stakeholders. The norms have been made more stringent for new plants and are the most stringent
for upcoming plants. Moreover, the timelines for plants to meet the new standards were tighter.
• Existing plants – 2 years
• Plants commissioned after 1 January 2017 – from the start of their operations
Source: CEA, New Environmental Norms for Thermal Power Stations in India
This is a critical step taken by GoI to reduce the impact of the coal-based power sector on the environment. In order to
adhere to the above emission standards, significant investments are required from power producers to install pollution
control technologies. Power plants that find it too expensive to comply will either be used sparingly or completely phased
out. The expected environmental benefits of compliance are: reduction in PM, SO2, NO and mercury by 40%, 48%, 48%
and 60% respectively, thus improving the quality of air. Consumption of water by coal-based plants will also be reduced
by 40%.15
15 https://cleanairasia.org/wp-content/uploads/2016/09/06_Sanjeev-Paliwal_CPCB.pdf
• 12th FYP of India emphasised the need to invest in R&D on ultra-supercritical units
• 72 coal power plants (16.5 GW) undergoing life extension, modernisation and renovation
• Institute of Reservoir Studies is carrying out CO2 capture and enhanced oil recovery (EOR) field studies in Gujarat
• National Geological Research Institute (NGRI) is performing feasibility tests for storing CO2 in basalt form.
Steps taken by India towards deploying this technology by acknowledging the importance of coal in its economic growth
alongside the need to reduce CO2 emissions would play a major role in meeting its energy needs while delivering near-
zero emissions. CCS technology would not only enable further use of fossil fuels in a sustainable manner, but also help in
reaching the goals specified in Paris climate targets.
16 https://sustainabledevelopment.un.org/content/documents/3293dadhich_presentation.pdf
17 http://www.cea.nic.in/reports/committee/nep/nep_jan_2018.pdf
14 PwC | Indian power sector: Key imperatives for transformation
Coal-fired power plants based on ultra-SCT that operates at an advanced steam temperature of 1,100º F (600º C) or
above are also being introduced in the country. These plants have a higher capacity (up to 45%) than supercritical plants.
A Few upcoming plants, namely the Khargone Thermal Power Plant (TPP) of NTPC, Jawaharpur Supercritical TPP (STPP)
and ObraC STPP of Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL) already have ultra-supercritical
steam parameters.
Additionally, R&D on advanced ultra-supercritical (A-USC) power plants with steam parameters of pressure ≥300 kg/cm2
and temperature ≥700º C is ongoing in India under the National Mission for Development of Clean Coal Technologies.
With such enhanced steam conditions, the efficiency of the plants is expected to be in the range of 45–47%. India’s
first advanced ultra-supercritical (AUSC) thermal power plant with a capacity of 800 MW at Sipat station of the NTPC in
Chhattisgarh is expected to be commissioned by 2019–2020. This is a collaborative project involving the Indira Gandhi
Centre for Atomic Research (IGCAR), NTPC, Bharat Heavy Electricals Limited (BHEL) and Central Power Research
Institute (CPRI).
GoI has taken an initiative to set up Ultra Mega Power Projects (UMPPs), each having a capacity of 4 GW or above in
2005–06. the projects have been awarded to developers through tariff-based competitive bidding. These projects utilise
SCT to ensure high efficiency and lower CO2 emissions. Out of 16 UMPPs identified in various parts of country, 4 projects
were awarded:18
• Sasan UMPP, Madhya Pradesh
• Mundra UMPP, Gujarat
• Krishnapatnam UMPP, Andhra Pradesh
• Tilaiya UMPP, Jharkhand.
Sub-total
7 8 36 51 35,230 41.5
(supercritical)
Thus, more and more power projects are being brought into the supercritical fold in the country. Implementation of
this technology helps India to achieve its goals and balance the increasing demand for electricity, as well as improve
coal utilisation efficiency and reduce emissions from coal-fired power plants. Increased efficiency from these installed
supercritical units reduces in fuel consumption, which eventually translates into a lower fuel cost per kWh of the units.
18 https://powermin.nic.in/sites/default/files/uploads/MOP_Annual_Report_Eng_2018-19.pdf
The decision will boost competitiveness and mining efficiency of private players through the use of the best possible
technologies. The sector will now attract higher investments, and this will have a positive economic impact on coal
bearing areas in terms of infrastructure development, employment creation and business opportunities.19
19 Source: Manish Yadav, et al. Commercial Coal Mining in India Opened for Private Sector: A Boon or Inutile
As discussed earlier, the last few years have witnessed large-scale renewable capacity additions with commissioning of
8,619 MW of renewable capacity in FY 2018–19 alone. As of November 2019, the total installed renewable capacity in India
is approximately 83 GW or 23 % of India’s total installed capacity of around 357 GW. This is expected to increase to 450
GW by FY 2030, which will be approximately 54% of the total installed capacity.
This large-scale renewable capacity addition is likely to have huge implications on the reliability and stability of the Indian
power system.
The contribution of renewable capacity in India’s generation mix is expected to grow from 22% in 2019 to 54% by 2030.
100%
80%
60%
40%
20%
0%
FY16 FY17 FY18 FY19 FY20 FY22
Small hydro power Wind power Bio power Small hydro
Diesel, 1
RES*, 78
RES, 175
Nuclear, 7
Coal, 217
Coal, 200 Gas, 25
Hydro, 45 Nuclear, 10
Gas, 26
Hydro, 55
Anternative scenario – installed capacity (2030): 831 GW Forecasted installed capacity (2027): 617 GW
Coal, 267
Coal, 233 RES, 275
RES, 450
Hydro, 73
Gas, 24 Hydro, 67
Nuclear, 17
Gas, 26 Nuclear, 17
Assuming 50% RE target achieved and coal generation picks up Assuming retirement of 22.7 GW + 25.5 GW*
Daily variation in solar energy output is more or less predictable but change in weather (cloud, rain) may limit generation
for short periods of time. Wind energy is less predictable and subject to daily and seasonal weather patterns. This can
pose serious challenges if the output corresponds to a lower load.
100%
80%
60%
40%
20%
0%
FY16 FY17 FY18 FY19 FY20 FY22
Small hydro power Wind power Bio power Small hydro
Source: CEA report on installed capacity
Highest wind power generation – 33 TWh in July Highest solar power generation – 18 TWh in July
40
30 32
30 23
18 20 18
20 15 17
14
17 7 6 7
10 13 15 14 15 15
11 9 10 15
16 15
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Solar Wind
The highest solar output is observed in the dry summer months and wind power generation is the highest during the
monsoon months. The highest average monthly RE generation occurs in June and July (each 31%) and the lowest in
November (15%), when wind generation is at its lowest level.
Considering the total installed wind capacity of Southern India, a wind generation drop from 2,000 MW to 200 MW, in a
duration of 1–1.5 hours, usually translates to fall of around 1.5 Hz in system frequency.
With high RE penetration, system inertia will decrease due to the reduced rotating mass of conventional machines
(primarily coal-fired thermal generators). It is also important to note that older machines, which will retire, have a much
higher inertia (4 MW-seconds/MVA) as compared to the newer units (2.5-3.0 MW-seconds/MVA). This means the system
will have less time to react to power deficit contingency and restore the frequency to reference level. This would have an
impact on the frequency fall immediately following a large contingency (inertial response) and before primary response
effect comes into play. Hence, the generation that serves the net load, in aggregate, needs to be more flexible in order to
smoothen the load curve and balance the variability in the system due to high RE integration.
90 76 76
80 73
70
60
% times
50
40
30 20
20 11 12 13 12
7
10
0
< 49.9 Hz 49.9 - 50.05 Hz > 50.05 Hz
90
80 72 76 76 80 72 76
70 67
70
60
% times
60
% times
50 50
40 40
30 20 30 19 20
20 20 13
10 8 11 12 13 12
10 7 12 12
0 0
< 49.9 Hz 49.9 - 50.05 Hz > 50.05 Hz < 49.9 Hz 49.9 - 50.05 Hz > 50.05 Hz
2016–17 2017–18 2018–19 2016–17 2017–18 2018–19
90 80 76 72
67
80 72 76 76 70
70 60
% times
% times
60 50
50 40
40
30 30
20 19
20 18 20 12 13 12
13 13
10 9 11 12 10 7
0 0
< 49.9 Hz 49.9 - 50.05 Hz > 50.05 Hz < 49.9 Hz 49.9 - 50.05 Hz > 50.05 Hz
2016–17 2017–18 2018–19 2016–17 2017–18 2018–19
50
40
30 19
20 9 12 12 12 12
10
0
< 49.9 Hz 49.9 - 50.05 Hz > 50.05 Hz
2016–17 2017–18 2018–19
225.8
220.8
221.1
217.8
215.7
240.0
210.3
209.5
208.1
207.2
205.6
205.0
205.2
205.2
205.4
205.4
204.6
203.7
202.8
202.4
200.3
199.4
196.9
195.4
194.8
220.0
200.0
215.4
211.3
210.4
207.9
207.2
180.0
198.8
196.9
194.4
194.4
194.2
193.3
192.6
191.2
188.9
188.7
179.6
160.0
172.8
160.9
156.9
140.0
147.5
55-60 GW demand
146.0
141.4
137.1
138.3
In order to meet its net demand, India will need a ramp-up of 55−60 GW in 6 hours with RE penetration of 175 GW.
At present, the summer ramp-up is estimated to be 170 MW/min during evening peak
hours and the winter ramp-up is estimated to be 200 MW/min in the morning.
The present capacity of thermal sources can provide 1396 MW/min ramp-up capacity. Hydro generation can provide
a high ramp-up (2506 MW/min but generation will be subject to weather and monthly patterns). Region-wise ramp-up
capacity of thermal and hydro are given below:
Region Installed capacity for ramp-up (MW) % MW/min Ramp-up capacity (MW/min)
Total 1,395.653
Installed capacity range (MW) Installed capacity for ramp-up (MW) % MW/min Ramp-up capacity (MW/min)
Total 2,506
Source: POSOCO operational report on optimisation of hydro resources and facilitating RE integration in India, 2017
India further commits to increase its RE capacity to 450 GW. This target is over five times its current renewable capacity
(82.5 GW) and more than India’s total installed electricity capacity (362 GW). According to CEA’s draft report on ‘Optimal
generation capacity mix for 2029-30’, if the target of 450 GW is met, RE will account for 54% of the total generation mix.
This will have a massive impact on grid stability and will require a much higher ramp-up/ramp-down requirement to meet
the net load. It will also require additional flexible reserves like pumped hydro, battery, hydro and ancillary services for
meeting the net load and maintaining grid security and stability. In the present load supply scenario, the Indian power
sector uses only slow tertiary reserves to meet the ramp-up/ramp-down requirement.
Unit commitment,
Generation day-ahead scheduling
rescheduling
Inertial Slow tertiary
Continuum to
adequacy, portfolio
balancing, market
Time
The reserve capacity currently required to integrate variable renewable sources in the grid and ensure operations within
prescribed frequency bandwidth (49.9−50.05 Hz).
Primary 4 • Maintain at the national level considering outage of the largest generating station
• Source from all possible generating stations irrespective of ownership
Tertiary 5.2 • Maintain in a decentralised manner in state control area for at least 50% of
largest-sized generating unit as a tertiary reserve within state control area
At present, there are 75 Reserves Regulation Ancillary Services (RRAS) providers (thermal sources), as identified by the
CERC, with a total installed capacity of 68.4 GW (NER – 6 GW, ER - 10.9 GW, NR − 16.2 GW, SR − 13.9 GW, WR − 26.8
GW). Energy ramped up through RRAS for India is 4,811 MU, with the western region being the highest.
2103
993 913
603
200
Eastern region Northeast region North region South region Western region
MU
Up-regulation Down-regulation
The table below presents a comparison of the existing AS market and the proposed changes by CERC.
Eligibility of RRAS Only regional entities whose All inter-state/intra-state generating (public or private)
tariff for full capacity is resources
determined
Schedule of RRAS The State Load Dispatch Traded in day-ahead bidding in power exchanges. Final
Centre (SLDC) schedules settlement done through a real-time market
power from RRAS as per merit Generators will bid simultaneously in day-ahead energy
order stack and day-ahead AS market
Pricing methods Fixed, variable, mark-up price Pricing of AS with respect to the opportunity lost by the
determined by CERC RRAS in foregoing the energy market or other AS market
RE reserves as tertiary Not allowed to participate Whether RE resources will be considered or not is to be
notified at a later date
At present, India has the capacity of 9 GW as reactive energy support. Per unit cost of providing such support is 14-16
paise/kVARh.20
20 www.erpc.gov.in
Synchronous condenser capability in India As per the Indian Electricity Grid Code (IEGC) clause 6.6,
the pricing of VAR is done as follows:
Region Number of Number of Capacity
• The Regional Entity except Generating Stations pays for
stations units (MW)
VAR drawal when voltage at the metering point is below
East 2 10 2,100 97%.
North 5 11 1,188 • The Regional Entity except Generating Stations gets
paid for VAR return when voltage is below 97%.
South 10 39 2,867
• The Regional Entity except Generating Stations gets
West 8 27 2,904 paid for VAR drawal when voltage is above 103%.
Northeast 0 0 0 • The Regional Entity except Generating Stations pays for
Total 25 87 9,059 VAR return when voltage is above 103.
Stations with black start capacity Black start drills in the last five years
33 black start drills have taken place in the last five years in India, with a majority of the plants owned by the state power
utility of Odisha (17). The rest of the drills took place at plants owned by Damodar Valley Corporation (DVC), NHPC and
state utilities of Jharkhand, West Bengal and DVC.
The table below represents projected installed capacities for 2021–22 from renewable and coal-based thermal plants
corresponding to specific scenarios such as:
1. maximum demand
2. maximum RES
3. the MTL on some specific days (highest demand day, lowest demand day, highest RE day, highest ramp down day,
highest ramp up day, lowest MTL day).
21 http://www.cea.nic.in/reports/others/thermal/trm/flexible_operation.pdf
Source: Flexible operation of thermal plant for integration of renewable generation, CEA
The MTL of thermal units decreases during the high cumulative RE generation months, i.e. May–August; whereas it
increases during low cumulative RE generation months, i.e. October–February. Also, the least efficient coal plants will be
rarely dispatched in a high-RE scenario.
Challenges Recommendation
Meeting net load (high • Additional flexible source addition (pumped storage, battery, hydro,
ramp-up/ramp-down) demand side management)
• Deeper short-term markets and ancillary markets
Meeting variability and • Full implementation of secondary and fast tertiary RRAS
intermittency • Strong enforcement of regulations like DSM regulations
• Co-ordinated scheduling and despatch
Maintaining • Joint operation of solar and hydro energies because of their complementary nature
MTL of • Flexible power from hydro and gas, with both sources generating less during the
conventional day and more during peak hours compared to the present trend of generation
generators • Flexible power from pump/battery storage and coal to provide peak support
• RE curtailment
Existing power • Improve volume, liquidity and flexibility of the power market
market design • Design of new power market structure with key characteristics such as:
(90% long-term – retail competition
access [LTA], no – compulsory participation in exchange
mature market for – introducing financial products (forwards, futures and options) and financial
ancillary, short-term transmission rights (FTR)
or capacity market) – zonal pricing
– security-constrained economic despatch
– gate closure closer to real-time (e.g. one hour ahead)
– implementation of capacity market
– competitive ancillary market
The viability of the power sector depends on the financial health and operational efficiency of distribution utilities.
Supply of power at heavily subsidised rates, delayed receipt of subsidies and inefficient power purchase have resulted
in poor financial health of DISCOMs. Some of the key challenges faced by distribution companies (DISCOMS) are
highlighted below.
22 https://indianpowersector.com/home/electricity-board/electricity-distribution/
23 Credit rating report for West Bengal State Electricity Distribution Corporation dated October
29,2018, Credit rating report for Bangalore Electricity Supply Company Ltd dated March
12,2019 and Credit rating report for Gujarat State Electricity Company Ltd dated March 20,2019
• Pradhan Mantri Sahaj Bijli Har Ghar Yojana – • Ujwal DISCOM Assurance Yojana
“Saubhagya” • Financial Restructuring Programme (FRP)
• Rajiv Gandhi Grameen Vidyutikaran Yojana • National Electricity Fund (NEF)
• Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY)
• Integrated Power Development Scheme (IPDS)
• Power System Development Fund (PSDF)
• Restructured Accelerated Power Development and
Reforms Programme (R-APDRP)
Rajiv Gandhi 2005 ~50,000 • Electrification of all villages and Electrification (as on
Grameen habitations March 2013)
Vidyutikaran • Providing access to electricity to all • Village electrification –
Yojana rural households 1,06,474
• Free access to be provided to BPL • BPL households –
families 2,05,15,472
Pradhan Mantri 2017 16,320 • Universal household electrification • 2.63 crore households
Sahaj Bijli Har (in both rural and urban areas) by have been electrified up
Ghar Yojana – providing last mile connectivity to March 2019
“Saubhagya” • Provide electricity to about 3 crore
households
UDAY 2015 The states shall • Financial turnaround • Decrease in AT&C losses
take over 75% of • Operational improvement from 20.7% in FY16 to
DISCOM debt as 18.7% in FY18
• Reduction of cost of generation
on 30 September • Reduced book losses to
2015 over two • Development of renewable energy
INR 15,049 crore in FY18
years. 50% of • Energy efficiency and conservation from INR 51,480 crore in
DISCOM debt FY16
shall be taken
• Reduction in average
over in 2015–16
cost of supply (ACS)
and 25% in
− aggregate revenue
2016–17.
requirement (ARR) gap
Balance 25% of from INR. 0.58/kWh (in
the DISCOM debt FY16) to INR 0.17/kWh
was to be issued (FY18)
as state-backed
• Increase in billed energy
DISCOM bonds or
from 694 BU to 824 BU
repriced by banks.
(FY16 vs FY18)
24 As on June 30,2018
01 Issue separate licences for the distribution system and supply of electricity
Wire and supply segregation: The Revised Electricity Bill, 2018, proposes issuing and granting of separate licences for
maintenance of the distribution network (distribution licence) and for the supply of electricity (supply licence), in order to
introduce competition and ensure value to the end consumers. It also provides for a transfer scheme to be notified by the
state government for such segregation. This will provide the consumer with more options in terms of choosing a supplier,
as more than one supply licensee can share space within the same distribution area. The segregation of wires and supply
business is expected to benefit all the stakeholders and is expected to improve the network performance and the viability
of the distributors and the suppliers. The benefits of the proposed amendments are given below.
Though the proposed amendments are yet to be implemented, the mindset of consumers requires to be reformed for
changes to be brought to the power sector. In addition, experiences from other countries which have implemented
such reforms are to be considered and have to be imbibed to ensure smooth and efficient implementation of the
proposed amendments.
The UK has one of the most successfully implemented models in the retail electricity sector. One of the significant
highlights in terms of the privatisation process was the formation of the Electricity Pool of England and Wales, which
was functioned by the national transmission company. The pool worked as a clearinghouse between generators
and wholesale consumers of electricity (primarily the rural electrification companies [RECs]). However, several flaws
gradually became prominent in the system, and hence, there was a requirement for several regulatory interferences
to control the monopolistic behaviour and avert re-integration in the electricity industry.
From April 1990 to May 1999, competition came into action in the supply market in three phases. The retail side
has two divisions comprising ‘franchise’ and ‘non-franchise’ customers. Non-franchise customers were given the
opportunity to opt for their supplier among any of the twelve RECs or from the pool of retailers.
The Utilities Act, 2000, eliminated the then present distribution/retail licences, and with this, a UK-wide licence came
into action with the provision for all the suppliers to serve customers nationwide. It also made a division in the supply
and distribution businesses of former public electricity suppliers (PES). To smoothen the process, price controllers
were introduced to facilitate all categories of consumers to take advantage of the competitive market.
Source: Joint Report by Forum of Regulators (FoR) and PwC titled ‘Introducing competition in retail electricity
supply in India’
Tariff policy amendments: GoI proposes to enact an amendment to the Tariff Policy, 2016, to ensure round the clock
electricity to all the citizens of the country. The policy is currently pending with the Union Cabinet. Here are some of the
key provisions under the proposed new tariff policy:
• The DISCOMs/licensees need to ensure before the respective commissions that they have signed long-term and
medium-term PPAs to meet the power requirements.
• A penalty is proposed to be levied on DISCOMs for voluntary load shedding and the amount will be credited to the
account of the respective consumers.
• Enable CEA to set rules of service and penalty for not meeting the set standards.
• AT&C losses to be capped at 15% for computation of tariff.
• Simplification and rationalisation of retail tariff by maintaining a lower number of categories and sub-categories of
consumers and making them harmonious across all states.
Despite the proposed amendments covering various issues such as AT&C losses, unaffordable electricity, etc., a clear
road map in terms of its execution and resolution for any procedural and legal issues also needs to be drawn. The
amendments, coupled with the supportive resolutions, are expected to pave way for the progress of the power distribution
sector in India.
Technology interventions in DISCOMs: The smart combination of IT and operational technology (OT) in DISCOMs will
allow optimisation on both the supply and demand side to achieve the goal of ensuring 24x7 uninterrupted power supply
to consumers. Some of the key technology interventions include, but not limited to, benefits such as:
• advanced metering infrastructure and meter data management (MDM) system
• IT-based metering, billing and collection system, customer relation management (CRM) and enterprise resource
planning (ERP) system
• advanced business analytics and forecasting to ensure optimal resource planning in power procurement.
Deployment of AMI infrastructure: As per the draft plan prepared by CEA, GoI plans to replace all traditional meters
with smart meters by 2022. The Energy Efficiency Services Limited’s (EESL) Smart Meter National Programme (SMNP) has
taken up the task of replacing 25 crore conventional meters with smart meters across India. These meters are expected
to ease integration in the power sector, reduce capital loss and enhance efficiency in billing and collection. The rollout has
been proposed under the build-own-operate-transfer (BOOT) model where EESL takes up all the capital and operational
expenditure with zero investment from states and utilities and recovers the cost of these smart meters through savings
monetisation, enhanced billing accuracy, avoided meter costs and other losses caused due to inefficiencies. As of August
2019, around 5 lakh meters have already been installed by EESL in the states of Uttar Pradesh, Delhi, Haryana, Bihar and
Andhra Pradesh.26
Proposed amendments in the Electricity Act, 2003: Proposed amendments in the National Tariff Policy, 2016:
• promotion of smart grid in general • meters compatible with time of day (ToD) tariff to be
• installation of smart meters for specific installed on priority
consumers to ensure proper accounting • smart pre-paid meters mandatory for all large consumers
• two-way smart meters to be installed for all ‘prosumers’
Leveraging blockchain technology for distributed energy generation and supply: The increasing use of smart
applications increases the flow of information in various directions, which makes the electric grid vulnerable to hackers.
Blockchain technology addresses this issue by managing transactions through a decentralised tamper-proof ledger and
offers an efficient, secure and cost-effective solution. Blockchains can make the smart meters infrastructure more robust
by providing accurate data to the supplier, without the need for a direct link to specific users. With the rapid increase in
usage of electric vehicles (EVs) in the country, blockchain can help in peer-to-peer (P2P) sharing and interconnectivity,
thereby balancing the demand from multiple sources and direct sharing and making the grid smarter and modular.
The electricity regulator of a large state in India has recently approved a pilot project for P2P
transactions of power from rooftop solar systems, using blockchain-based technology. Under this
pilot project, the designated government agencies will carry out P2P transactions for the trading of
rooftop solar power installed in government buildings. The fees for the blockchain technology will be
recovered in the ARR of the concerned distribution licensee. The results will be evaluated to formulate
appropriate regulations to further promote P2P trading of solar energy in the state.
26 https://www.eeslindia.org/
• Retirement of older coal assets • Focus on development of flexible • Segregation of wire and supply
in a time-bound manner to avoid sources addition to the grid, viz. business to introduce competition
supply/demand mismatch pump storage project (PSP), which is envisaged to improve
battery, hydro network performance, services
• Adherence to stricter
to customer, and viability of
environment norms leading to • Expansion of ancillary market
distribution and suppliers
reduction in emissions products by full implementation of
secondary and tertiary RRAS • Introduction of UDAY 2.0 to
• Implementation of sustainable
aid revival of financial health of
technologies to address carbon • Flexible operation of RE in
DISCOMs
emission issues complementarity with thermal,
hydro, and balancing sources, • Amendments to tariff policies to
• Focus on supercritical technology
viz. PSP and battery pave the way for advancement
to attain higher efficiency and
of the distribution sector
reduce fuel consumption • Design of new power market
structure with key characteristics • Deployment of advanced
• Commercialisation of coal mining
like retail competition, zonal metering infrastructure (AMI) to
pricing, gate closure, FTR and increase collection efficiency
capacity market and reduce losses
• Leveraging advanced
technologies to improve efficiency
and robustness of system
Way ahead
In India, PwC has offices in these cities: Ahmedabad, Bengaluru, Bhopal, Chennai, Delhi NCR, Hyderabad, Kolkata,
Mumbai, Pune and Raipur. For more information about PwC India’s service offerings, visit www.pwc.in
PwC refers to the PwC network and/or one or more of its member firms, each of which is a separate legal entity.
Please see www.pwc.com/structure for further details.
Acknowledgements
Contributors Editorial support Design and layout
Roseleena Parveen Dion D’Souza Faaiz Gul
Sahil S Sharna Saptarshi Dutta Harshpal Singh
Vasavi Manchiraju
Akash Kalore
Maddineni Venkata Ramya
Contact us
Yogesh Daruka Subhrajit Datta Ray
Partner, Power and Utilities and Mining Director, Power and Utilities
PwC India PwC India
Direct: +91 (33) 4404 4288 Direct: +91 (33) 4404 4221
Email: [email protected] Mobile: +91 9903828701
Email: [email protected]