0% found this document useful (0 votes)
2K views

Double Storeyed Building Estimation

This document provides an estimate for the construction of a double storey residential building with the following key details: - The building has a ground floor plus one additional floor and a terrace. It includes 5 staircases and 1 lift. - Estimates are provided for various elements of the building including footing, brickwork, concrete work, reinforcement, and electrical, plumbing and finishing works. - Quantities of materials are calculated using mensuration methods from the drawings provided. Standard schedule of rates are used to determine costs. - The total estimated cost of construction is approximately Rs. 6,592,351 including contingencies.

Uploaded by

Suson Dhital
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views

Double Storeyed Building Estimation

This document provides an estimate for the construction of a double storey residential building with the following key details: - The building has a ground floor plus one additional floor and a terrace. It includes 5 staircases and 1 lift. - Estimates are provided for various elements of the building including footing, brickwork, concrete work, reinforcement, and electrical, plumbing and finishing works. - Quantities of materials are calculated using mensuration methods from the drawings provided. Standard schedule of rates are used to determine costs. - The total estimated cost of construction is approximately Rs. 6,592,351 including contingencies.

Uploaded by

Suson Dhital
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 50

DOUBLE

STOREYED
BUILDING
ESTIMATION
PRESENTED BY-
NAFISA NAZNEEN
CHOUDHURY
(CIVIL ENGINEERING
STUDENT OF ASSAM
ENGINEERING COLLEGE)
INTRODUCTION

 In various engineering works it is required beforehand to know the probable


cost of construction which is known as the estimated cost. If money available
is less than the estimated cost, then attempts have to be made to reduce the
cost by changing the specification or by reducing the work.
 The subject matter of estimation is simple but knowledge of drawing of
structures requires special skills like AUTOCAD, STAAD PRO, etc. One
who understands the drawing can find out dimensions such as length,
breadth, height, etc.
 Following requirements are necessary for preparing estimate-

• Drawings like plan, elevation and sections of important points like beam,
staircase, footing, and column.
• Detailed specification of workmanship and properties of materials.
• Standard schedule of rates for the current year.
 The complete work is divided into various items of work such as earthwork
concreting, brickwork, reinforced concrete, plastering etc. The details of
measurements are taken from drawings and entered in respective columns
of prescribed proforma.
 For calculating the cost of the building structure, the rates of materials are
derived from Standard Schedule Rates which comprises of the prices of
list of items in a tabular form.
 Also, LumpSum items in estimate are included in the estimate-

• Water supply and sanitary arrangements.


• Electrical installation like meter, motor, etc.
• Architectural features.
• Contingencies and unforeseen items.
TYPES OF ESTIMATE

 Following are the different types of estimation-

1. Preliminary estimate or Approximate estimate or Abstract Estimate


or Rough Cost Estimate

2. Detailed Estimate or Item Rate Estimate

3. Plinth Area Estimate

4. Cube Rate Estimate or Cubical Content Estimate

5. Approximate Quantity Method Estimate

6. Revised Estimate

7. Supplementary Estimate

8. Supplementary and Revised Estimate

9. Annual Repair or Maintenance Estimate


OBJECTIVE

 Required Quantity of Materials


 Cost of Materials
 Finding cost of various works like Brickwork, RCC, Reinforcement, etc.
METHODOLOGY

 Mensuration Method- This method of measuring lengths, areas,


volumes using mensuration in its meaning is to measure, is widely
used where geometrical figures are thoughtful and where one has to
determine various physical quantities such as area, volume, length,
etc. In estimation it is a common practice to use mensuration method
to calculate quantities of items.
 Centre Line Method- This method consists to find out total length of
centre line of walls. Brickwork has been found out by this method in
this project.
 Engineering Method- With this technique, the system being costed is
broken down into low level components each of which is costed
separately for direct labour, other costs and direct material.
PROBLEM STATEMENT

To perform Double Storeyed Building Estimation and to calculate the


cost of building structure from a given Plan, Elevation and Cross
section of elements present in the building.
Salient features:
1. Utility of building: Residential
complex
2. No of stories: G+1
3. No of staircases: 5
4. No of lifts: 1
5. Type of construction: R.C.C framed
structure
6. Types of walls: brick wall
7. Height of plinth: 0.76 m
Geometric details:
8. Ground floor: 3.3 m
9. Floor to floor height: 3.3 m.
10. Depth of foundation: 1.68 m.
11. Clear Cover: 40 mm in Column, 50 mm in Footing, 25 mm in Beam
and 15 mm in Slab

Materials:
12. Concrete grade: All Concrete Mix M20 (1:1.5:3) unless otherwise
specified
13. All steel grades: Fe 500 grade
14. Bearing Capacity of soil: 18 M.T./m2

All Dimensions in the Drawings are in Feet and Inches.


PLAN OF

 GROUND FLOOR
 FIRST FLOOR
 TERRACE FLOOR

& ELEVATION
GENERAL ABSTRACT OF THE
ESTIMATE OF PROPOSED (G+1)
RESIDENTIAL BUILDING

Date : 26/12/2019

SOR
Sl.
Description Unit Rate Qty Amount
No.
(Rs.)
Cost of Civil Works for Building as
1 per CPWD 2013-14 4,365,939.82
2 30% Escalation for current year 5,675,721.77
Cost of electrical work - 7.5% of civil
3 cost 425,679.13
Cost of plumbing & sanitary work -
4
7.5% of civil cost 425,679.13
Total Rs. 6,527,080.04
Add 1% contingency for unforseen item
5 if any 65,270.80
Grand Total Rs. 6,592,350.84
Say Rs. 6,592,351.00

(Rupees Sixty Five Lakh Ninety Two Thousand Three Hundred Fifty One Only)
FOOTING
FOOTING F1
Feet Inch Metre Reinforcement details
L= 4 0 1.20 D2(Diameter of bars) T(Spacing)
B= 4 0 1.20 10 mm 0.15 m
D= 0 10 0.25
C= 0 6 0.15
G= 0 6 0.15
L1(Length of
0 14 0.36
Column)=
B1(Breadth of
0 9 0.23
Column)=
D1(Depth for
5 7 1.68
Excavation)=
P1(PCC 0 3 0.08
S1(Sand Filling
0 4 0.10
Thickness)=
W1(Bottom Wire
0 6 0.15
Mesh Spacing)=

Nos. of
Total
Sl No. Particulars Calculation Quantity F1 Quantit
Footing
y
1 Earthwork in Excavation ((L+0.3) x (B+0.3) x D1) m3 3.78 m³ 1 3.78 m³
2 1:4:8 PCC ((L+0.15) x (B+0.15) x P1) m3 0.14 m³ 1 0.14 m³
3 Sand Filling ((L+0.15)x(B+0.15)xS1) m3 0.19 m³ 1 0.19 m³
RCC in Footing
a)Upper Rectangular Portion (L1+0.3) x (B1+0.3)xG 0.05 m³
b) Bottom Rectangular Portion (L x B x C) m3 0.22 m³

4 c) Trapezoidal Portion {0.5 (L + (L1+ 0.3 )} x {0.5(B+(B1+0.3)} x (D-C) 0.08 m³


m3
Total 0.35 m³ 1 0.35 m³
Reinforcement
a)Main bar in Foundation
No. of bars
(N2)= 8
Transverse (Q/T)+
direction 1
10.9 kg
L-2 x
5 1.1 m 10.9 kg 1
Clear
Cover (Q)
No. of bars
(N1)= 8
Longitudinal (P/T)+
direction 1
B-2 x
1.1 m
Clear
Cover (P)
Length=P x N1+Q x N2
Weight= Lengthx((D2 x D2)/162)
6 Shuttering Area= 4L x C 0.73 1 0.7 m²
TOTAL QUANTITY IN FOUNDATION

Quantity
Total
Item F1 F2 F3 F4 F5 F6 EF1 EF2 EF3 EF4 EF3" EF4" Quantity

E/W in 17.80 21.00 18.88 4.87 12.13 14.80 6.07 7.40


3.78 m³ 4.87 m³ 18.20 m³ 37.00 m³
Excavation m³ m³ m³ m³ m³ m³ m³ m³ 166.78 m³
PCC(1:4:8) 0.14 m³ 0.18 m³ 0.70 m³ 1.45 m³ 0.84 0.17 0.45 0.23 0.29
0.71 m³ m³ 0.65 m³ m³ m³ 0.56 m³ m³ m³ 6.38 m³
Sand Filling 0.19 m³ 0.25 m³ 0.94 m³ 1.93 m³ 1.12 0.23 0.59 0.31 0.39
0.94 m³ m³ 0.87 m³ m³ m³ 0.74 m³ m³ m³ 8.50 m³
RCC (M20) 0.35 m³ 0.51 m³ 2.06 m³ 4.84 m³ 3.41 0.48 1.33 0.69 0.91
2.41 m³ m³ 1.71 m³ m³ m³ 1.85 m³ m³ m³ 20.55 m³
Reinforcement 10.86 kg 8.85 kg 72.08 kg 211.56 kg 135.34 164.39 104.86 33.09 84.22 137.85 42.11 68.93
kg kg kg kg kg kg kg kg 1074.14 kg
Shuttering 0.7 m² 0.9 m² 2.9 m² 5.5 m²
2.4 m² 3.6 m² 6.1 m² 1.7 m² 4.6 m² 5.9 m² 1.0 m² 1.1 m² 36.3 m²

For RCC

Grade of Concrete Ratio Of Cement Ratio of Sand Ratio of Aggregate

M20 1 1.5 3

Total Volume
of Volume of Volume of
Concrete Cement Volume of Sand Aggregate No of Bags
20.55 m³ 5.76 m³ 13.29 m³ 26.59 m³ 166

For PCC
Grade of Concrete Ratio Of Cement Ratio of Sand Ratio of Aggregate
M7.5 1 4 8

Total Volume
of Volume of Volume of
Volume of Sand No of Bags
Concrete Cement Aggregate
6.38 m³ 0.76 m³ 4.65 m³ 9.30 m³ 22
CHAJJA FOR W

Feet Inch Metre Reinforcement Details


Length of window (L)= 8' 0'' 2.40 Diameter of Bars(B) Spacing(T)
Breadth of window 5' 6'' 1.65 10 mm 0.15 m
(B)=
Length of Chajja (L1)= 8' 9'' 2.63
Breadth of Chajja 2' 0'' 0.60
(B1)=
Depth of Chajja (D)= 0' 3'' 0.08
Breadth of Wall (B2)= 0' 9'' 0.23

No. of W on
which chajja Total
Sl No. Particulars Calculations Quantity
provided Quantity
0.12 m³
1 RCC in Chajja L1 x B1 x D 0.12 m³
Reinforcement
Length (P)= B1+ B2 - Clear Cover of
Chajja - Clear Cover of 0.79 m
Beam

a)Main bar in Chajja No.s (Q)= ((L1 - 2 x Clear Cover of


Chajja)/T) + 18
1
1 16.78 kg
2 Length (R)= L1 - 2 x Clear Cover of 2.60 m 16.78 kg
Chajja
b) Distribution bar No.s (S)= ((B1 - Clear Cover of
Chajja)/T) + 1 5
Total Length= Px Q + R x S
Weight= Total Length x D2/162
3 Shuttering Area= 2 x D x B1 + D x L1 + L1 1.87 m² 1 1.87 m²
x B1
TOTAL QUANTITY IN CHAJJA

Quantity
Item Total Quantity
W W1 W2
RCC (M20) 0.12 m³ 0.19 m³ 0.32 m³ 0.62 m³
Reinforcement 16.78 kg 26.04 kg 44.55 kg 87.36 kg
Shuttering 1.87 m² 2.93 m² 5.04 m² 9.84 m²

For RCC

Grade of Concrete Ratio Of Cement Ratio of Sand Ratio of Aggregate


M20 1 1.5 3

Total Volume of
Concrete Volume of Cement Volume of Sand Volume of Aggregate No of Bags

0.62 m³ 0.17 m³ 0.40 m³ 0.80 m³ 5.01


COLUMN
1ST FLOOR LEVEL TO TERRAICE
COLUMN 1

Serial No 1.00 Longitudinal Main bar

`
1ST FLOOR TO Length
TERRAICE LEVEL TERRAICE LEVEL Dia(MM) NO (M)

Column marked C1 Nos 4.00 16.00 4.00 3.30


size Feet Inch Metere
Length 1.00 0.00 0.30 Lateral ties
Spacing
Breadth Dia(MM) (INCH) NO Length
1.00 0.00 0.30
Height 11.00 0.00 3.30 8.00 6.00 23 1.00

Sr No 1.00 Terraice level Below plinth level QUANTITY OF MATERIAL FOR


(RCC)

CONCRETE QUANTITY
VOLUME SHUTTERIN OF Ratio 1.00 1.50 3.00 SUMMARY FOR STEEL (IN KG )
Column (RCC) G STEEL
marked
CU.M SQ.M Kg CEMENT SAND STONECHIP 8MM 16M
S M
BAGS CU.M CU.M REINFORCEMENT
C1 1.19 15.84 119.12 9.77 0.51 1.02 35.68 83.44
SUMMARY FOR COLUMN

SUMMARY FOR SUMMARY FOR


BELOW PLINTH LEVEL COLUMN plinth to 1st floor Level
COLUMN
RCC WORK (IN CU.M) 4.14 RCC WORK (IN CU.M) 8.35
SHUTTERING (IN SQ.M) 32.77 SHUTTERING (IN SQ.M) 110.57
REINFORCEMENT 8MM 12MM 16MM REINFORCEMENT (IN 8MM 12MM 16MM
(IN KG) 197.73 183.33 375.11 KG) 313.90 222.93 396.33

SUMMARY FOR SUMMARY FOR


1st floor Level to Terraice Terraice to mumtty level
COLUMN COLUMN

RCC WORK (IN CU.M) 8.35 RCC WORK (IN CU.M) 1.63
SHUTTERING (IN SQ.M) 110.57 SHUTTERING (IN SQ.M) 21.27
REINFORCEMENT (IN 8MM 12MM 16MM REINFORCEMENT (IN 8MM 12MM 16MM
KG) KG) 55.79 55.47 75.85
313.90 222.93 396.33
SLAB
SLAB 1(n)

Distribution bar in shorter span


Serial No 14.00 Main bar in smaller span Main bar in longer span at top Distribution bar in longer span at top

Lengt
Spacing Spacing Length Spacing Length Spacing Length
Floor Level 1st floor level Dia(MM) (INCH) NO h Dia(MM) NO
(INCH) (M) Dia(MM) (INCH) NO (M) Dia(MM) (INCH) NO (M)
(M)

Slab marked S1(n) Nos 1.00 8.00 6.00 17 2.71 8.00 8.00 13 2.76 8.00 6.00 13 2.62 8.00 6.00 13 2.65
size Feet Inch Metere Extra Top in smaller span Extra Top in longer span
Length 8.00 0.00 2.40 Extra top 1 Extra top 2 Extra top 1 Extra top 2

Spacing Spacing Spacing Spacing


Dia(MM) (INCH) NO Length Dia(MM) (INCH) NO Length Dia(MM) (INCH) NO Length Dia(MM) (INCH) NO Length
Breadth 7.00 10.50 2.37

Thickness 4.50 0.11 8.00 12.00 9 0.89 8.00 12.00 9 0.89 8.00 16.00 7 0.90 8.00 16.00 7 0.90

Sr No Floor Level 1st floor level QUANTITY OF MATERIAL FOR (RCC)

CONCRETE QUANTITY
VOLUME OF
Slab marked SHUTTERING Ratio 1.00 1.50 3.00
(RCC) STEEL

CU.M SQ.M Kg CEMENT SAND STONECHIPS


BAGS CU.M CU.M
s1(a) 0.65 5.68 68.60
5.34 0.28 0.56
SUMMARY

2ND FLOOR SUMMARY


1ST FLOOR SUMMARY
RCC WORK (IN CU.M) 22.13
RCC WORK (IN CU.M) 23.74
SHUTTERING (IN SQ.M) 174.92
SHUTTERING (IN SQ.M) 189.04
8MM 10MM 8MM 10MM

REINFORCEMENT (IN KG)


REINFORCEMENT (IN KG) 2469.52 669.39 2184.92 669.39

MUMTTY TOP LEVEL SUMMARY

RCC WORK (IN CU.M) 7.55

SHUTTERING (IN SQ.M) 55.18


8MM 10MM
REINFORCEMENT (IN KG)
534.89 922.29
STAIRCASE
STAIRCASE DETAILS

Slopped Details of
Flight L1 Tread Riser length L3 Mainbar Binder chair

Dia
Dim Dim Spacing Of Length Length
Meter No (m) No (m) Meter Meter No (inch) (m) No Dia Spacing (m) Dia No Length
bar

Flight1 0 10 0.3 11 0.15 3.69 1.52 12 5 10 110.366 47 8 8 67.68 10 4 2.28

Flight2 1.52 10 0.3 11 0.15 3.69 0 12 5 10 110.366 47 8 8 67.68 10 4 2.28


Reinforcement details Concrete details
MAINBARS CONCRETE VOLUME 3 M³
SIZE WEIGHT
10MM 136.25 RATIO
1 1.5 3
Binder CEMENT SAND AGGREGATE
Size Weight 0.79 0.81 1.62
8mm 53.48
Shuttering details
CEMENT BAGS 23 BAGS TOTAL SHUTTERING AREA 23 M²

CHAIR
SIZE WEIGHT TOTAL QUANTITY OF STEEL= 193 KG
10MM 2.81

FOR STAIRCASE 2
CEMENT
REINFORCEMENT(KG) SAND M³ AGGREGATE M³ SHUTTERING M²
(BAGS)
193 22.77 0.81 1.62 22.97

FOR STAIRCASE 3
CEMENT
REINFORCEMENT(KG) SAND M³ AGGREGATE M³ SHUTTERING M²
(BAGS)
193 22.77 0.81 1.62 22.97

TOTAL TOTAL
TOTAL CEMENT TOTAL TOTAL AGGREGATE SHUTTERING
REINFORCEMENT(KG) (BAGS) SAND M³ M³ AREA M²
577.63 68.30 2.43 4.85 68.91
CALCULATION OF BRICKWORK

 DATA REQUIRED
 LENGTH OF WALL
 BREADTH OF WALL(THICKNESS OF WALL)
 HEIGHT OF WALL

CALCULATION
A= TOTAL VOLUME OF WALL=L X B X H m³
NUMBERS OF BRICKS WITHOUT MORTAR=A/0.002
SO, QUANTITY OF MORTAR=(A)-(NUMBERS OF BRICKS X VOLUME
OF BRICKS WITHOUT MORTAR)
CEMENT: SAND =1:6
CEMENT=MORTAR QUANTITY X 1/7
SAND= MORTAR QUANTITY X 6/7
EXAMPLE

 BRICKWORK FOR BEDROOM FOR 1ST FLOOR


 LENGTH=10.15 M
 BREADTH=0.254M
 HEIGHT=3.30M
 BEDROOM WALL VOLUME=10.15X0.254X3.30 m³ =8.50 m³
 DEDUCTION=1.05 m³(DOOR) + 1.54 m³(WINDOW)
 TOTAL BEDROOM WALL VOLUME=5.91 m³
 NUMBER OF BRICKS WITH MORTAR =5.91/0.002 =2955 NUMBERS
 QUANTITY OF MORTAR= VOLUME OF WALL – (VOLUME BRICKS
WITH OUT MORTAR X NUMBERS OF BRICKS)
 SO, QUANTITY OF MORTAR=5.91-2955 X0.001539=1.37 m³
 CEMENT AND SAND RATIO= 1:6
 CEMENT=1.37 X 1/7 =0.19 m³=6 bags
WOODWORK

Dimension of Doors and Windows


`Calculation For Doors and Windows

For Frame
DESCRIPTIO NUMBE LENGTH BREADTH HEIGHT CALCULAT
N OF ITEMS R (m) (m) (m) ION QUANTITY(m3)
WOODWORK
Salwood door
and windows
chowkaths
formed and
fixed of
thickness 6cm
and width 12cm
(a) Doors
(including 4cm
insertion into
flooring)
D 2.00 1.22 2.32 0.04 0.09
(b) Window
W1 3.00 1.83 1.70 0.05 0.15

Calculation of Door Frame = (2 X (Height of door +0.04)+Length of Door) X Thickness


of frame X Width of frame
Calculation of Window Frame = (2 x Length of Window+2 x Height of Window) x
Thickness of Frame x Width of Frame
Considered, Insertion into flooring = 4cm
Thickness of frame = 6 cm
Width of Frame = 12 cm
For Panel

DESCRIPTION
OF ITEMS NUMBER LENGTH (m) BREADTH (m) HEIGHT (m) CALCULATION QUANTITY(m2)
4cm thick
shuttering
including fittings
(a)Doors
D 2.00 1.22 2.32 2.49 4.97

(b)Windows
W1 3.00 1.83 1.70 2.77 8.30

Calculation of Door Panel = (Height of Door) X (Length of Door)-(Surface area


of frame)
Calculation of Window Panel = (Height of Window) X (Length of window)-
(Surface area of frame)
Considered, Thickness of Panel = 4cm
Summary

For Ground Floor


Detail of Woodwork

Frame Quantity (m3) Panel Quantity (m2)


0.91 42.80

For First Floor

Detail of Woodwork
Frame Quantity (m3) Panel Quantity (m2)
0.98 42.00
Plastering

15mm thick plaster with 1:6 cement local sand mortar for inside walls
Sl Particular of items Length( Breadth( Height( Quantity
No. Remarks
No. and details of works m) m) m) (m2)
12mm plastering with
1:6 cement local sand
mortor in walls
L=Inner
1 Drawing Room 1.00 21.84 3.36 73.27
Perimeter
Deduct
Sliding Door 1.00 1.83 2.30 4.21
Door D 1.00 1.22 2.30 2.81
W1 1.00 1.83 1.70 3.11
W2 2.00 1.53 1.70 5.20

Total 57.94

Calculation = (Perimeter of room x Height of room)-(Area of the


doors and windows in that room
Quantities of materials for inside plastering

For Ground Floor


Quantities of Items for 15mm plastering with 1:6 cement local sand
mortar in walls
Quantity Material Quantity
(m3) Cement (Bags) Sand (m3)
10.54 43 9.03

For First Floor


Quantities of Items for 15mm plastering with 1:6 cement local sand
mortar in walls
Quantity Material Quantity
(m3) Cement (Bags) Sand (m3)
13.09 54 11.22

Calculation, For No. of Cement Bags = ((1/7) x quantity)/0.0347


For Volume of sand = ((6/7) x quantity)
20mm thick plaster with 1:3 cement local sand mortar for outside walls

Particular of
items and Length(
Sl No. No. Breadth(m) Height(m) Quantity(m2) Remarks
details of m)
works
Outside
1 1 45.628 3.355 153.08
plastering
2 Parking 1 11.56 0.61 7.05
3 Left out 1 1.708 2.44 4.17
deduct
Window
4 1.525 1.71 2.61
opening w2
Door opening
1 1.22 2.318 2.83
D
Window
2 1.83 1.708 3.13
opening w1
Ventilator v 1 0.61 0.915 0.56
NET TOTAL 155.17

Calculation = (Perimeter of the outer wall x Height of that floor)-(Area of


door and windows at outside walls)
Quantities of materials for outside plastering

For Ground Floor


Quantities of Items for 20mm plastering with 1:3 cement local sand mortor in walls

Quantity Material Quantity


(m3) Cement (Bags) Sand (m3)
4.84 35 3.63

For First Floor

Quantities of Items for 20mm plastering with 1:3 cement local sand mortor in walls
Quantity Material Quantity
(m3) Cement (Bags) Sand (m3)
7.74 56 5.81

Calculation, For No. of Cement Bags = ((1/4) x quantity)/0.0347


For Volume of sand = ((3/4) x quantity)
10mm thick plaster with 1:4 cement local sand mortar for
ceiling

Particular of
items and
details of Length(
Sl No. works No. m) Breadth(m) Height(m) Quantity(m2) Remarks
1 Sit out 1.00 3.36 2.36 7.92
2 Store room 1.00 2.44 2.39 5.83
3 Kitchen 1.00 4.41 3.39 14.95

Calculation = Product of inner dimension of the room


Quantities of materials for ceiling plastering

For Ground Floor


Quantities of Items for 6mm plastering with 1:4 cement medium sand mortor in
ceiling
Quantity Material Quantity
(m3) Cement (Bags) Sand (m3)
2.14 12.30673138 1.71

For First Floor

Quantities of Items for 6mm plastering with 1:4 cement medium sand mortor in
ceiling of First Floor
Quantity Material Quantity
(m3) Cement (Bags) Sand (m3)
2.78 16 2.22

Calculation, For No. of Cement Bags = ((1/5) x quantity)/0.0347


For Volume of sand = ((4/5) x quantity)
BEAM
TIE BEAM 5
Inside distance(m)= 16.52
Centre to centre distance(m)= 16.75
Out side distance(m)= 16.98
Number of stirup= 91
Extra(m)= 9.14

Sl no Particulars Calculation Quantity Unit


Reinforcement
I)MAINBARS 17.72 70.89 m
II)STIRUPS 91 101.23 m
III)EXTRA 4 9.14 m
1 Total reinforcement 0.06 m³
Cement concrete
I)TOTAL VOLUME 1.38 m³
ii)volume of
concrete 1.32 m³
A)CEMENT 0.24 m³
B)SAND 0.36 m³
2 C)AGGREGATE 0.72 m³
Shuttering details for ground floor
Beam size Total length(m) Face1 Face2 Face3 Total area(m²)
L(m) B(m) L(m) B(m) L(m) B(m)
9x14 166.89 166.89 0.38 166.89 0.23 166.89 0.38 165.32

Materials required
Materials Quantity Unit
Cement 2.50 M³
Sand 3.79 M³
Aggregate 7.66 M³
Reinforcement
16mm 497.45 Kg
12mm 446.98 Kg
8mm 444.44 Kg
LINTEL DETAILS

REINF
MAIN BARS STIRUPS ORCE
LENGTH OF TOTAL LENGTH OF TOTAL MENT CONCRETE
INSIDE ONE MAIN LENGTH ONE LENG TOTAL VOLU VOLUME(M
FLOOR NUMBER DISTANCE(M NO BAR(M) ( M) NO STIRUP(M T H VOLUME(M³ ME(M³) ³
) ) (M) ) )

GROUND FLOOR 173 4 179.86 719.44 1181 0.706 833.786 6.03 0.39 5.63

FIRST FLOOR 180 4 185.85 743.4 1220 0.706 861.32 6.27 0.41 5.86

2ND FLOOR 147 4 151.45 605.8 994 0.706 701.764 5.12 0.33 4.79

MATERIAL REQUIRED FOR LINTEL

REINFORCEMENT CEMENT CONCRETE SHUTTERING DETAILS


FACE1 FACE2
AGG
R TOTAL
10MM 8MM CEMENT SAND(M³) EGAT L(M) B(M) L(M) B(M) AREA(M²)
GROND FLOOR (M³) E(M³)
444.10 329.40 1.02 1.54 3.07 173 0.18 173 0.18 61.52

FIRST FLOOR 458.89 340.27 1.07 1.60 3.20 180 0.18 180 0.18 64.01
2ND FLOOR 373.95 277.24 0.87 1.31 2.61 147 0.18 147 0.18 52.27
CEMENT BAGS= 85.34 BAGS TOTAL SHUTTERING AREA= 177.8 M²
DETAIL OF QUANTITY OF R.C.C & STEEL

Total wt
Net Weight (Kg.) of bars of bar Total wt
Serial Floor (Kg)
Item of bar
no level including (M.T)
6 8 10 12 16 20 25 32 5% extra

Below Foundation 0 23 91 696 0 0 0 0 851 0.851


existing Tie beam 0 444 0 447 497 0 0 0 1458 1.458
1 ground Column 0 198 0 183 375 0 0 0 794 0.794
level
Column 0 314 0 223 396 0 0 0 980 0.980
Beam 0 572 0 85 1605 0 0 0 2375 2.375
E.G.L. to Slab 0 2470 669 0 0 0 0 0 3296 3.296
2 1st floor Staircase 0 53 139 0 0 0 0 0 202 0.202
level Lintel 0 329 444 0 0 0 0 0 812 0.812
Chajja 0 0 35 0 0 0 0 0 37 0.037

Column 0 314 0 223 396 0 0 0 980 0.980


Beam 0 462 0 48 1244 0 0 0 1841 1.841
1st floor
Slab 0 2185 669 0 0 0 0 0 2997 2.997
level to
3 Staircase 0 53 139 0 0 0 0 0 202 0.202
terrace
level Lintel 0 340 459 0 0 0 0 0 839 0.839
Chajja 0 0 52 0 0 0 0 0 55 0.055

Column 0 56 0 55 76 0 0 0 196 0.196


Mumty Beam 0 416 0 32 234 0 0 0 717 0.717
4
top Slab 0 535 922 0 0 0 0 0 1530 1.530
Lintel 0 277 374 0 0 0 0 0 684 0.684

0 9042 3995 1992 4825 0 0 20847 20.85


DETAIL OF QUANTITY OF R.C.C & STEEL

Net Concrete volume Net Quantity of materials for R.C.C Net Shuttering in all
(R.C.C) including 5% floors including 5%
Serial Floor
Item extra Cement Sand Stone chips extra
no level
Cubic cubic cubic Square
C.F.T Bag C.F.T C.F.T S.F.T
Metre metre metre metre
Below Foundation 21.58 762.0 170.0 8.923 315.1 17.846 630.2 38.12 410.3
existing Tie beam 14.65 517.3 121.7 6.388 225.6 12.775 451.2 173.59 1868.5
1 ground Column 4.35 153.5 13.7 0.720 25.4 1.441 50.9 34.41 370.4
level
Column 8.77 309.6 76.5 4.016 141.8 8.033 283.7 116.10 1249.7
Beam 17.28 610.3 151.8 7.972 281.5 15.943 563.0 170.51 1835.3
E.G.L. to Slab 24.94 880.7 183.5 9.632 340.2 19.265 680.3 198.49 2136.6
2 1st floor Staircase 3.11 109.8 23.7 1.245 44.0 2.491 88.0 24.12 259.6
level Lintel 5.91 208.8 31.9 1.674 59.1 3.347 118.2 64.60 695.3
Chajja 0.27 9.5 1.7 0.090 3.2 0.181 6.4 2.9 30.8

Column 8.77 309.6 60.8 3.192 112.7 6.385 225.5 116.10 1249.7
Beam 17.28 610.3 129.2 6.781 239.5 13.561 478.9 178.63 1922.7
1st floor
Slab 23.24 820.6 175.2 9.199 324.9 18.398 649.7 183.67 1977.0
level to
3 Staircase 3.11 109.8 23.7 1.245 44.0 2.491 88.0 24.12 259.6
terrace
level Lintel 6.15 217.3 31.0 1.627 57.5 3.254 114.9 67.21 723.4
Chajja 0.39 13.9 2.5 0.134 4.7 0.268 9.5 4.82 51.9

Column 1.71 60.4 12.9 0.677 23.9 1.354 47.8 22.33 240.4
Mumty Beam 5.28 186.5 37.2 1.952 68.9 3.904 137.9 60.10 646.9
4
top Slab 7.93 280.0 68.3 3.588 126.7 7.177 253.4 57.94 623.7
Lintel 5.03 177.6 0.9 0.049 1.7 0.098 3.5 60.13 647.3

166.21 6347.42 1316.28 69.10 2440.41 138.21 4880.83 1597.84 17198.995


GENERAL ABSTRACT OF THE ESTIMATE OF PROPOSED
(G+1) RESIDENTIAL BUILDING

Date : 26/12/2019

SOR
Sl.
Description Unit Rate Qty Amount
No.
(Rs.)
Cost of Civil Works for Building as
1 per CPWD 2013-14 4,365,939.82
2 30% Escalation for current year 5,675,721.77
Cost of electrical work - 7.5% of civil
3 cost 425,679.13
Cost of plumbing & sanitary work -
4
7.5% of civil cost 425,679.13
Total Rs. 6,527,080.04
Add 1% contingency for unforseen item
5 if any 65,270.80
Grand Total Rs. 6,592,350.84
Say Rs. 6,592,351.00

(Rupees Sixty Five Lakh Ninety Two Thousand Three Hundred Fifty One Only)
CONCLUSION

 This project includes the layout of G+1 residential building using Auto Cad
and concludes with the cost estimate for the entire project. The estimate of
the G+1 residential building was prepared successfully
 In this, we have come to a conclusion that center line method of estimating
is the most suitable method for the considered plan as the walls of the
building are of similar cross section and have less number of junction.
 The cost estimate for the project has been calculated using center line
method in Microsoft Excel. For the Abstract cost CPWD 2013-14 schedule
of the rates has been followed and total cost Rs 65,92,351.00 (Sixty Five
Lakh Ninety Two Thousand Three Hundred and Fifty One Only) has been
calculated. has been calculated.
THANK YOU

You might also like