Double Storeyed Building Estimation
Double Storeyed Building Estimation
STOREYED
BUILDING
ESTIMATION
PRESENTED BY-
NAFISA NAZNEEN
CHOUDHURY
(CIVIL ENGINEERING
STUDENT OF ASSAM
ENGINEERING COLLEGE)
INTRODUCTION
• Drawings like plan, elevation and sections of important points like beam,
staircase, footing, and column.
• Detailed specification of workmanship and properties of materials.
• Standard schedule of rates for the current year.
The complete work is divided into various items of work such as earthwork
concreting, brickwork, reinforced concrete, plastering etc. The details of
measurements are taken from drawings and entered in respective columns
of prescribed proforma.
For calculating the cost of the building structure, the rates of materials are
derived from Standard Schedule Rates which comprises of the prices of
list of items in a tabular form.
Also, LumpSum items in estimate are included in the estimate-
6. Revised Estimate
7. Supplementary Estimate
Materials:
12. Concrete grade: All Concrete Mix M20 (1:1.5:3) unless otherwise
specified
13. All steel grades: Fe 500 grade
14. Bearing Capacity of soil: 18 M.T./m2
GROUND FLOOR
FIRST FLOOR
TERRACE FLOOR
& ELEVATION
GENERAL ABSTRACT OF THE
ESTIMATE OF PROPOSED (G+1)
RESIDENTIAL BUILDING
Date : 26/12/2019
SOR
Sl.
Description Unit Rate Qty Amount
No.
(Rs.)
Cost of Civil Works for Building as
1 per CPWD 2013-14 4,365,939.82
2 30% Escalation for current year 5,675,721.77
Cost of electrical work - 7.5% of civil
3 cost 425,679.13
Cost of plumbing & sanitary work -
4
7.5% of civil cost 425,679.13
Total Rs. 6,527,080.04
Add 1% contingency for unforseen item
5 if any 65,270.80
Grand Total Rs. 6,592,350.84
Say Rs. 6,592,351.00
(Rupees Sixty Five Lakh Ninety Two Thousand Three Hundred Fifty One Only)
FOOTING
FOOTING F1
Feet Inch Metre Reinforcement details
L= 4 0 1.20 D2(Diameter of bars) T(Spacing)
B= 4 0 1.20 10 mm 0.15 m
D= 0 10 0.25
C= 0 6 0.15
G= 0 6 0.15
L1(Length of
0 14 0.36
Column)=
B1(Breadth of
0 9 0.23
Column)=
D1(Depth for
5 7 1.68
Excavation)=
P1(PCC 0 3 0.08
S1(Sand Filling
0 4 0.10
Thickness)=
W1(Bottom Wire
0 6 0.15
Mesh Spacing)=
Nos. of
Total
Sl No. Particulars Calculation Quantity F1 Quantit
Footing
y
1 Earthwork in Excavation ((L+0.3) x (B+0.3) x D1) m3 3.78 m³ 1 3.78 m³
2 1:4:8 PCC ((L+0.15) x (B+0.15) x P1) m3 0.14 m³ 1 0.14 m³
3 Sand Filling ((L+0.15)x(B+0.15)xS1) m3 0.19 m³ 1 0.19 m³
RCC in Footing
a)Upper Rectangular Portion (L1+0.3) x (B1+0.3)xG 0.05 m³
b) Bottom Rectangular Portion (L x B x C) m3 0.22 m³
Quantity
Total
Item F1 F2 F3 F4 F5 F6 EF1 EF2 EF3 EF4 EF3" EF4" Quantity
For RCC
M20 1 1.5 3
Total Volume
of Volume of Volume of
Concrete Cement Volume of Sand Aggregate No of Bags
20.55 m³ 5.76 m³ 13.29 m³ 26.59 m³ 166
For PCC
Grade of Concrete Ratio Of Cement Ratio of Sand Ratio of Aggregate
M7.5 1 4 8
Total Volume
of Volume of Volume of
Volume of Sand No of Bags
Concrete Cement Aggregate
6.38 m³ 0.76 m³ 4.65 m³ 9.30 m³ 22
CHAJJA FOR W
No. of W on
which chajja Total
Sl No. Particulars Calculations Quantity
provided Quantity
0.12 m³
1 RCC in Chajja L1 x B1 x D 0.12 m³
Reinforcement
Length (P)= B1+ B2 - Clear Cover of
Chajja - Clear Cover of 0.79 m
Beam
Quantity
Item Total Quantity
W W1 W2
RCC (M20) 0.12 m³ 0.19 m³ 0.32 m³ 0.62 m³
Reinforcement 16.78 kg 26.04 kg 44.55 kg 87.36 kg
Shuttering 1.87 m² 2.93 m² 5.04 m² 9.84 m²
For RCC
Total Volume of
Concrete Volume of Cement Volume of Sand Volume of Aggregate No of Bags
`
1ST FLOOR TO Length
TERRAICE LEVEL TERRAICE LEVEL Dia(MM) NO (M)
CONCRETE QUANTITY
VOLUME SHUTTERIN OF Ratio 1.00 1.50 3.00 SUMMARY FOR STEEL (IN KG )
Column (RCC) G STEEL
marked
CU.M SQ.M Kg CEMENT SAND STONECHIP 8MM 16M
S M
BAGS CU.M CU.M REINFORCEMENT
C1 1.19 15.84 119.12 9.77 0.51 1.02 35.68 83.44
SUMMARY FOR COLUMN
RCC WORK (IN CU.M) 8.35 RCC WORK (IN CU.M) 1.63
SHUTTERING (IN SQ.M) 110.57 SHUTTERING (IN SQ.M) 21.27
REINFORCEMENT (IN 8MM 12MM 16MM REINFORCEMENT (IN 8MM 12MM 16MM
KG) KG) 55.79 55.47 75.85
313.90 222.93 396.33
SLAB
SLAB 1(n)
Lengt
Spacing Spacing Length Spacing Length Spacing Length
Floor Level 1st floor level Dia(MM) (INCH) NO h Dia(MM) NO
(INCH) (M) Dia(MM) (INCH) NO (M) Dia(MM) (INCH) NO (M)
(M)
Slab marked S1(n) Nos 1.00 8.00 6.00 17 2.71 8.00 8.00 13 2.76 8.00 6.00 13 2.62 8.00 6.00 13 2.65
size Feet Inch Metere Extra Top in smaller span Extra Top in longer span
Length 8.00 0.00 2.40 Extra top 1 Extra top 2 Extra top 1 Extra top 2
Thickness 4.50 0.11 8.00 12.00 9 0.89 8.00 12.00 9 0.89 8.00 16.00 7 0.90 8.00 16.00 7 0.90
CONCRETE QUANTITY
VOLUME OF
Slab marked SHUTTERING Ratio 1.00 1.50 3.00
(RCC) STEEL
Slopped Details of
Flight L1 Tread Riser length L3 Mainbar Binder chair
Dia
Dim Dim Spacing Of Length Length
Meter No (m) No (m) Meter Meter No (inch) (m) No Dia Spacing (m) Dia No Length
bar
CHAIR
SIZE WEIGHT TOTAL QUANTITY OF STEEL= 193 KG
10MM 2.81
FOR STAIRCASE 2
CEMENT
REINFORCEMENT(KG) SAND M³ AGGREGATE M³ SHUTTERING M²
(BAGS)
193 22.77 0.81 1.62 22.97
FOR STAIRCASE 3
CEMENT
REINFORCEMENT(KG) SAND M³ AGGREGATE M³ SHUTTERING M²
(BAGS)
193 22.77 0.81 1.62 22.97
TOTAL TOTAL
TOTAL CEMENT TOTAL TOTAL AGGREGATE SHUTTERING
REINFORCEMENT(KG) (BAGS) SAND M³ M³ AREA M²
577.63 68.30 2.43 4.85 68.91
CALCULATION OF BRICKWORK
DATA REQUIRED
LENGTH OF WALL
BREADTH OF WALL(THICKNESS OF WALL)
HEIGHT OF WALL
CALCULATION
A= TOTAL VOLUME OF WALL=L X B X H m³
NUMBERS OF BRICKS WITHOUT MORTAR=A/0.002
SO, QUANTITY OF MORTAR=(A)-(NUMBERS OF BRICKS X VOLUME
OF BRICKS WITHOUT MORTAR)
CEMENT: SAND =1:6
CEMENT=MORTAR QUANTITY X 1/7
SAND= MORTAR QUANTITY X 6/7
EXAMPLE
For Frame
DESCRIPTIO NUMBE LENGTH BREADTH HEIGHT CALCULAT
N OF ITEMS R (m) (m) (m) ION QUANTITY(m3)
WOODWORK
Salwood door
and windows
chowkaths
formed and
fixed of
thickness 6cm
and width 12cm
(a) Doors
(including 4cm
insertion into
flooring)
D 2.00 1.22 2.32 0.04 0.09
(b) Window
W1 3.00 1.83 1.70 0.05 0.15
DESCRIPTION
OF ITEMS NUMBER LENGTH (m) BREADTH (m) HEIGHT (m) CALCULATION QUANTITY(m2)
4cm thick
shuttering
including fittings
(a)Doors
D 2.00 1.22 2.32 2.49 4.97
(b)Windows
W1 3.00 1.83 1.70 2.77 8.30
Detail of Woodwork
Frame Quantity (m3) Panel Quantity (m2)
0.98 42.00
Plastering
15mm thick plaster with 1:6 cement local sand mortar for inside walls
Sl Particular of items Length( Breadth( Height( Quantity
No. Remarks
No. and details of works m) m) m) (m2)
12mm plastering with
1:6 cement local sand
mortor in walls
L=Inner
1 Drawing Room 1.00 21.84 3.36 73.27
Perimeter
Deduct
Sliding Door 1.00 1.83 2.30 4.21
Door D 1.00 1.22 2.30 2.81
W1 1.00 1.83 1.70 3.11
W2 2.00 1.53 1.70 5.20
Total 57.94
Particular of
items and Length(
Sl No. No. Breadth(m) Height(m) Quantity(m2) Remarks
details of m)
works
Outside
1 1 45.628 3.355 153.08
plastering
2 Parking 1 11.56 0.61 7.05
3 Left out 1 1.708 2.44 4.17
deduct
Window
4 1.525 1.71 2.61
opening w2
Door opening
1 1.22 2.318 2.83
D
Window
2 1.83 1.708 3.13
opening w1
Ventilator v 1 0.61 0.915 0.56
NET TOTAL 155.17
Quantities of Items for 20mm plastering with 1:3 cement local sand mortor in walls
Quantity Material Quantity
(m3) Cement (Bags) Sand (m3)
7.74 56 5.81
Particular of
items and
details of Length(
Sl No. works No. m) Breadth(m) Height(m) Quantity(m2) Remarks
1 Sit out 1.00 3.36 2.36 7.92
2 Store room 1.00 2.44 2.39 5.83
3 Kitchen 1.00 4.41 3.39 14.95
Quantities of Items for 6mm plastering with 1:4 cement medium sand mortor in
ceiling of First Floor
Quantity Material Quantity
(m3) Cement (Bags) Sand (m3)
2.78 16 2.22
Materials required
Materials Quantity Unit
Cement 2.50 M³
Sand 3.79 M³
Aggregate 7.66 M³
Reinforcement
16mm 497.45 Kg
12mm 446.98 Kg
8mm 444.44 Kg
LINTEL DETAILS
REINF
MAIN BARS STIRUPS ORCE
LENGTH OF TOTAL LENGTH OF TOTAL MENT CONCRETE
INSIDE ONE MAIN LENGTH ONE LENG TOTAL VOLU VOLUME(M
FLOOR NUMBER DISTANCE(M NO BAR(M) ( M) NO STIRUP(M T H VOLUME(M³ ME(M³) ³
) ) (M) ) )
GROUND FLOOR 173 4 179.86 719.44 1181 0.706 833.786 6.03 0.39 5.63
FIRST FLOOR 180 4 185.85 743.4 1220 0.706 861.32 6.27 0.41 5.86
2ND FLOOR 147 4 151.45 605.8 994 0.706 701.764 5.12 0.33 4.79
FIRST FLOOR 458.89 340.27 1.07 1.60 3.20 180 0.18 180 0.18 64.01
2ND FLOOR 373.95 277.24 0.87 1.31 2.61 147 0.18 147 0.18 52.27
CEMENT BAGS= 85.34 BAGS TOTAL SHUTTERING AREA= 177.8 M²
DETAIL OF QUANTITY OF R.C.C & STEEL
Total wt
Net Weight (Kg.) of bars of bar Total wt
Serial Floor (Kg)
Item of bar
no level including (M.T)
6 8 10 12 16 20 25 32 5% extra
Net Concrete volume Net Quantity of materials for R.C.C Net Shuttering in all
(R.C.C) including 5% floors including 5%
Serial Floor
Item extra Cement Sand Stone chips extra
no level
Cubic cubic cubic Square
C.F.T Bag C.F.T C.F.T S.F.T
Metre metre metre metre
Below Foundation 21.58 762.0 170.0 8.923 315.1 17.846 630.2 38.12 410.3
existing Tie beam 14.65 517.3 121.7 6.388 225.6 12.775 451.2 173.59 1868.5
1 ground Column 4.35 153.5 13.7 0.720 25.4 1.441 50.9 34.41 370.4
level
Column 8.77 309.6 76.5 4.016 141.8 8.033 283.7 116.10 1249.7
Beam 17.28 610.3 151.8 7.972 281.5 15.943 563.0 170.51 1835.3
E.G.L. to Slab 24.94 880.7 183.5 9.632 340.2 19.265 680.3 198.49 2136.6
2 1st floor Staircase 3.11 109.8 23.7 1.245 44.0 2.491 88.0 24.12 259.6
level Lintel 5.91 208.8 31.9 1.674 59.1 3.347 118.2 64.60 695.3
Chajja 0.27 9.5 1.7 0.090 3.2 0.181 6.4 2.9 30.8
Column 8.77 309.6 60.8 3.192 112.7 6.385 225.5 116.10 1249.7
Beam 17.28 610.3 129.2 6.781 239.5 13.561 478.9 178.63 1922.7
1st floor
Slab 23.24 820.6 175.2 9.199 324.9 18.398 649.7 183.67 1977.0
level to
3 Staircase 3.11 109.8 23.7 1.245 44.0 2.491 88.0 24.12 259.6
terrace
level Lintel 6.15 217.3 31.0 1.627 57.5 3.254 114.9 67.21 723.4
Chajja 0.39 13.9 2.5 0.134 4.7 0.268 9.5 4.82 51.9
Column 1.71 60.4 12.9 0.677 23.9 1.354 47.8 22.33 240.4
Mumty Beam 5.28 186.5 37.2 1.952 68.9 3.904 137.9 60.10 646.9
4
top Slab 7.93 280.0 68.3 3.588 126.7 7.177 253.4 57.94 623.7
Lintel 5.03 177.6 0.9 0.049 1.7 0.098 3.5 60.13 647.3
Date : 26/12/2019
SOR
Sl.
Description Unit Rate Qty Amount
No.
(Rs.)
Cost of Civil Works for Building as
1 per CPWD 2013-14 4,365,939.82
2 30% Escalation for current year 5,675,721.77
Cost of electrical work - 7.5% of civil
3 cost 425,679.13
Cost of plumbing & sanitary work -
4
7.5% of civil cost 425,679.13
Total Rs. 6,527,080.04
Add 1% contingency for unforseen item
5 if any 65,270.80
Grand Total Rs. 6,592,350.84
Say Rs. 6,592,351.00
(Rupees Sixty Five Lakh Ninety Two Thousand Three Hundred Fifty One Only)
CONCLUSION
This project includes the layout of G+1 residential building using Auto Cad
and concludes with the cost estimate for the entire project. The estimate of
the G+1 residential building was prepared successfully
In this, we have come to a conclusion that center line method of estimating
is the most suitable method for the considered plan as the walls of the
building are of similar cross section and have less number of junction.
The cost estimate for the project has been calculated using center line
method in Microsoft Excel. For the Abstract cost CPWD 2013-14 schedule
of the rates has been followed and total cost Rs 65,92,351.00 (Sixty Five
Lakh Ninety Two Thousand Three Hundred and Fifty One Only) has been
calculated. has been calculated.
THANK YOU