This document discusses the differences between corrective and preventive actions. Corrective actions address nonconformities that have already occurred to prevent recurrence, while preventive actions address potential nonconformities that have not occurred yet to prevent occurrence. Common misconceptions are that every nonconformity needs documenting, preventive actions are just renamed corrective actions, and major process changes don't qualify. The document provides examples to clarify the differences and outlines the typical processes for corrective, preventive, and developmental actions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views

Corrective Vs Preventive Action

This document discusses the differences between corrective and preventive actions. Corrective actions address nonconformities that have already occurred to prevent recurrence, while preventive actions address potential nonconformities that have not occurred yet to prevent occurrence. Common misconceptions are that every nonconformity needs documenting, preventive actions are just renamed corrective actions, and major process changes don't qualify. The document provides examples to clarify the differences and outlines the typical processes for corrective, preventive, and developmental actions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Corrective vs.

Preventive Action
by Russ Westcott

Quality professionals frequently express confusion as to the difference between corrective and preventive action. A

corrective action deals with a nonconformity that has occurred, and a preventive action addresses the potential for a

nonconformity to occur. Many ISO 9000 registrar auditors tell their clients to use separate procedures and forms to

document each type of action. Nothing in the standard says this must be done, but p. 13 includes the word “prevent”
in the clauses on corrective and preventive action.

On closer reading, however, section 8.5.2 says corrective action eliminates the cause of nonconformities to prevent

recurrence, and section 8.5.3 says preventive action determines and eliminates the causes of potential noncon-

formities … to prevent occurrence. See, there is a difference!

Common Misconceptions

There are three common misconceptions about corrective and preventive action:

1. The standard calls for documenting every occurrence of a nonconformity.


2. A preventive action is really just calling a corrective action something different.
3. The major reengineering of a process, product or service, or the introduction of a new process or equipment, is not a
candidate for preventive action documentation.

One way to dispel these is by separating situations into what I call a patch (a single occurrence of a nonconformity

that involves little risk and needs not be recorded), a corrective action (a more serious nonconformity involving some

risk that requires action to prevent recurrence and must be recorded), a preventive action (a process that can be

improved to prevent occurrence of a nonconformity and is to be documented) or a developmental action (a planned

change to introduce a new process or product in response to strategic objectives, documented as a preventive
action). Consider the examples in Table 1. (Go to www.asq.org, and click on the cover of Quality Progress.)
Corrective Action Process
 Locate and document the root cause of the nonconformity.
 Scan the entire system to ensure no other similar nonconformity could occur.
 Analyze the effect such a nonconformity may have had on a product or service produced before the nonconformity was
discovered, and take action appropriate to the severity of the situation by either recalling the product, notifying the customer,
downgrading or scrapping product.
 Establish thorough follow-up to ensure the correction is effective and recurrence has been prevented.
Preventive Action Process
 Take proactive steps to ensure a potential nonconformity does not occur.
 Employ process and system analysis to determine how to build in safeguards and process changes to prevent
nonconformance. For example, use a failure mode and effects analysis to identify risks and potential deficiencies and to set
priorities for improvement.
Developmental Action Process (Treated as Preventive Actions)
 Initiate an improvement project, with project plans, justification for planned expenditures, resource controls and evaluation.
 Contain a related series of actions, often separated by long periods so you can wait and see progress and results.
 Use a variety of appropriate disciplines at different times during the project.
 Establish a means for communicating what has been done and what has to be done to facilitate communication about changes
to project team members.
 Include a clear trail of actions taken and decisions made to substantiate the decision to proceed, document lessons learned
and avoid needless reinvention on future similar projects.

Documenting and controlling corrective and preventive actions ensure appropriate action is taken within a reasonable

timeframe and the resulting changes work.