Ansi Neta Ats 2009 PDF
Ansi Neta Ats 2009 PDF
STANDARD FOR
ACCEPTANCE TESTING SPECIFICATIONS for
Electrical Power Equipment
and Systems
Secretariat
InterNational Electrical Testing Association
Approved by
American National Standards Institute
– This page intentionally left blank –
ANSI/NETA ATS-2009
Approval of an American National Standard requires verification by
American ANSI that the requirements for due process, consensus, and other
criteria for approval have been met by the standards developer.
National Consensus is established when, in the judgment of the ANSI Board of
Standard Standards Review, substantial agreement has been reached by directly
and materially affected interests. Substantial agreement means much
more than a simple majority, but not necessarily unanimity. Consensus
requires that all views and objections be considered, and that a concerted
effort be made toward their resolution.
ANSI/NETA ATS-2009
Copyright Information and
Alteration of Content
2009 ANSI/NETA Standard for Acceptance Testing Specifications for Electrical Power
Equipment and Systems (ANSI/NETA ATS-2009) is protected under the copyright laws of
the United States, and all rights are reserved. Further, the ANSI/NETA ATS-2009 may not
be copied, modified, sold, or used except in accordance with such laws and as follows:
Purchasers may reproduce and use all or a portion of the ANSI/NETA ATS-2009 provided
ANSI/NETA Standard for Acceptance Testing Specifications for Electrical Power Equipment
and Systems are clearly identified in writing as the source of all such uses or reproductions.
Section 7 of the ANSI/NETA Standard for Acceptance Testing Specifications for Electrical
Power Equipment and Systems may be reproduced and used on a “cut and paste” basis for the
particular type of equipment to be tested.
The following sections of the ANSI/NETA Standard for Acceptance Testing Specifications for
Electrical Power Equipment and Systems must be incorporated by reference as part of any
subsection:
The purchaser is required to include the above sections with any section(s) of 7.
© Copyright 2009
InterNational Electrical Testing Association
3050 Old Centre Avenue, Suite 102
Portage, MI 49024
E-mail: [email protected] • Web: www.netaworld.org
ANSI/NETA ATS-2009
Standards Review Council
These specifications were submitted for public comment and reviewed by the NETA Standards Review
Council.
ANSI/NETA ATS-2009
NETA Accredited Companies
The following in a lisiting of all NETA Accredited Companies as of the date this document was
approved by ANSI as an American National Standard, February 19, 2009.
ANSI/NETA ATS-2009
NETA Accredited Companies
Magna IV Engineering, Ltd. – BC Cameron Hite
MET Electrical Testing Co., Inc. William McKenzie
Nationwide Electrical Testing, Inc. Shashikant B. Bagle
North Central Electric, Inc. Robert Messina
Northern Electrical Testing, Inc. Lyle Detterman
Orbis Engineering Field Services, Ltd. Lorne Gara
Phasor Engineering Rafael Castro
Potomac Testing, Inc. Ken Bassett
Power & Generation Testing, Inc. Mose Ramieh
Power Engineering Services, Inc. Miles R. Engelke
Power Plus Engineering, Inc. Salvatore Mancuso
Power Products & Solutions, Inc. Ralph Patterson
Power Services, Inc. Gerald Bydash
Power Systems Testing Co. David Huffman
Power Test, Inc. Richard Walker
Power Testing and Energization, Inc. Chris Zavadlov
Powertech Services, Inc. Jean A. Brown
PRIT Service, Inc. Roderic Hageman
Reuter & Hanney, Inc. Michael Reuter
REV Engineering, Ltd. Roland Davidson
Scott Testing, Inc. Russ Sorbello
Shermco Industries, Inc. Ron Widup
Sigma Six Solutions, Inc. John White
Taurus Power and Controls, Inc. Rob Bulfinch
Tony Demaria Electric, Inc. Anthony Demaria
Trace Electrical Services & Testing, LLC Joseph Vasta
Utilities Instrumentation Service, Inc. Gary Walls
Utility Service Corporation Alan Peterson
ANSI/NETA ATS-2009
NOTICE
In no event shall the InterNational Electrical Testing Association be liable to anyone for special, collateral,
incidental, or consequential damages in connection with or arising out of the use of these materials.
This document is subject to periodic review, and users are cautioned to obtain the latest edition. Comments
and suggestions are invited from all users for consideration by the Association in connection with such
review. Any such suggestions will be fully reviewed by the Association after giving the commenter, upon
request, a reasonable opportunity to be heard.
This document should not be confused with federal, state, or municipal specifications or regulations,
insurance requirements, or national safety codes. While the Association recommends reference to or use of
this document by government agencies and others, use of this document is purely voluntary and not binding.
ANSI/NETA ATS-2009
FOREWORD
(This Foreword is not part of American National Standard ANSI/NETA ATS-2009)
The InterNational Electrical Testing Association (NETA) was formed in 1972 to establish uniform testing
procedures for electrical equipment and apparatus. NETA developed specifications for the acceptance of
new electrical apparatus prior to energization and for the maintenance of existing apparatus to determine its
suitability to remain in service. The first NETA Acceptance Testing Specifications for Electrical Power
Equipment and Systems was produced in 1972. Upon completion of this project, the NETA Technical
Committee began work on a maintenance document, and Maintenance Testing Specifications for Electrical
Power Equipment and Systems was published in 1975.
NETA has been an Accredited Standards Developer for the American National Standards Institute since
1996. NETA's scope of standards activity is different from that of the IEEE, NECA, NEMA, and UL. In
matters of testing electrical equipment and systems NETA continues to reference other standards
developers’ documents where applicable. NETA's review and updating of presently published standards
takes into account both national and international standards. NETA’s standards may be used internationally
as well as in the United States. NETA firmly endorses a global standardization. IEC standards as well as
American consensus standards are taken into consideration by NETA's Section Panels and reviewing
committees.
The NETA Acceptance Testing Specifications was developed for use by those responsible for assessing the
suitability for initial energization of electrical power equipment and systems and to specify field tests and
inspections that ensure these systems and apparatus perform satisfactorily, minimizing downtime and
maximizing life expectancy.
Since 1972, several revisions of the Acceptance Testing Specifications have been published; in 1989 the
NETA Technical Committee, with approval of the Board of Directors, set a four-year review and revision
schedule. Unless it involves a significant safety or urgent technical issue, each comment and suggestion for
change is held until the appropriate review period. Each edition includes new and completely revised
sections. The document uses the standard numbering system of ANSI and IEEE. Since 1989, revised
editions of the Acceptance Testing Specifications have been published in 1991, 1995, 1999, 2003, and 2007.
On February 19, 2009, the American National Standards Institute approved the NETA Acceptance Testing
Specifications for Electrical Power Equipment and Systems as an American National Standard.
Suggestions for improvement of this standard are welcome. They should be sent to the InterNational
Electrical Testing Association, 3050 Old Centre Avenue, Suite 102, Portage, MI 49024.
ANSI/NETA ATS-2009
PREFACE
It is recognized by the Association that the needs for acceptance testing of commercial, industrial,
governmental, and other electrical power systems vary widely. Many criteria are used in determining what
equipment is to be tested and to what extent.
To help the user better understand and navigate more efficiently through this document, we offer the
following information:
Notation of Changes
Material included in this edition of the document but not part of the 2007 edition is marked with a black
vertical line in the margin to the left of the insertion of text, deletion of text, or alteration of text.
Section Description
Section 1 General Scope
Section 2 Applicable References
Section 3 Qualifications of Testing Organization and Personnel
Section 4 Division of Responsibility
Section 5 General
Section 6 Power System Studies
Section 7 Inspection and Test Procedures
Section 8 System Function Test
Section 9 Thermographic Survey
Section 10 Electromagnetic Field Testing
Tables Reference Tables
Appendices Various Informational Documents
Section 7 Structure
Section 7 is the main body of the document with specific information on what to do relative to the
inspection and acceptance testing of electrical power distribution equipment and systems. It is not intended
that this document list how to test specific pieces of equipment or systems.
ANSI/NETA ATS-2009
PREFACE (Continued)
Results of Visual and Mechanical Inspections
Some, but not all, visual and mechanical inspections have an associated test value or result. Those items
with an expected result are referenced under Section 3.1 Test Values – Visual and Mechanical. For
example, Section 7.1 Switchgear and Switchboard Assemblies, item 7.1.1.7.2 calls for verifying tightness of
connections using a calibrated torque wrench method. Under the Test Values – Visual and Mechanical
Section 7.1.3.1.2, the expected results for that particular task are listed within Section 3.1, with reference
back to the original task description on item 7.1.1.7.2.
ANSI/NETA ATS-2009
PREFACE (Continued)
Results of Electrical Tests
Each electrical test has a corresponding expected result, and the test and the result have identical numbers. If
the electrical test is item four, the expected result under the Test Values section is also item four. For
example, under Section 7.15.1 Rotating Machinery, AC Induction Motors and Generators, item 7.15.1.2.2
(item 2 within the Electrical Tests section) calls for performing an insulation-resistance test in accordance
with IEEE Standard 43. Under the Test Values – Electrical section, the expected results for that particular
task are listed in the Test Values section under item 2.
ANSI/NETA ATS-2009
PREFACE (Continued)
Optional Tests
The purpose of these specifications is to assure that all tested electrical equipment and systems supplied by
either contractor or owner are operational and within applicable standards and manufacturer’s published
tolerances and that equipment and systems are installed in accordance with design specifications.
Certain tests are assigned an optional classification. The following considerations are used in determining
the use of the optional classification:
Summary
The guidance of an experienced testing professional should be sought when making decisions concerning
the extent of testing. It is necessary to make an informed judgment for each particular system regarding how
extensive a procedure is justified. The approach taken in these specifications is to present a comprehensive
series of tests applicable to most industrial and larger commercial systems. In smaller systems, some of the
tests can be deleted. In other cases, a number of the tests indicated as optional should be performed.
Likewise, guidance of an experienced testing professional should also be sought when making decisions
concerning the results of test data and their significance to the overall analysis of the device or system under
test. Careful consideration of all aspects of test data, including manufacturer’s published data and
recommendations, must be included in the overall assessment of the device or system under test.
The Association encourages comment from users of this document. Please contact the NETA office or your
local NETA Accredited Company.
ANSI/NETA ATS-2009
– This page intentionally left blank –
ANSI/NETA ATS-2009
CONTENTS
ANSI/NETA ATS-2009
CONTENTS (continued)
7.9.1 Protective Relays, Electromechanical and Solid-State .............................................. 94
7.9.2 Protective Relays, Microprocessor-Based .................................................................101
7.10 Instrument Transformers............................................................................................103
7.11.1 Metering Devices .......................................................................................................108
7.11.2 Metering Devices, Microprocessor-Based.................................................................110
7.12.1.1Regulating Apparatus, Voltage, Step Voltage Regulators.........................................112
7.12.1.2Regulating Apparatus, Voltage, Induction Regulators ..............................................117
7.12.2 Regulating Apparatus, Current - Reserved ................................................................121
7.12.3 Regulating Apparatus, Load Tap-Changers...............................................................122
7.13 Grounding Systems....................................................................................................125
7.14 Ground-Fault Protection Systems, Low-Voltage.......................................................127
7.15.1 Rotating Machinery, AC Induction Motors and Generators......................................130
7.15.2 Rotating Machinery, Synchronous Motors and Generators.......................................134
7.15.3 Rotating Machinery, DC Motors and Generators ......................................................140
7.16.1.1Motor Control, Motor Starters, Low-Voltage............................................................143
7.16.1.2Motor Control, Motor Starters, Medium-Voltage......................................................145
7.16.2.1Motor Control, Motor Control Centers, Low-Voltage...............................................149
7.16.2.2Motor Control, Motor Control Centers, Medium-Voltage ........................................150
7.17 Adjustable Speed Drive Systems ...............................................................................151
7.18.1.1Direct-Current Systems, Batteries, Flooded Lead-Acid ............................................154
7.18.1.2Direct-Current Systems, Batteries, Vented Nickel-Cadmium ...................................157
7.18.1.3Direct-Current Systems, Batteries, Valve-Regulated Lead-Acid ..............................160
7.18.2 Direct-Current Systems, Chargers .............................................................................162
7.18.3 Direct-Current Systems, Rectifiers - Reserved..........................................................164
7.19.1 Surge Arresters, Low-Voltage ...................................................................................165
7.19.2 Surge Arresters, Medium- and High-Voltage............................................................167
7.20.1 Capacitors and Reactors, Capacitors..........................................................................169
7.20.2 Capacitors and Reactors, Capacitor Control Devices - Reserved..............................171
7.20.3.1Capacitors and Reactors, Reactors, Shunt and Current-Limiting, Dry-Type ............172
7.20.3.2Capacitors and Reactors, Reactors, Shunt and Current-Limiting, Liquid-Filled.......174
7.21 Outdoor Bus Structures..............................................................................................178
7.22.1 Emergency Systems, Engine Generator.....................................................................180
7.22.2 Emergency Systems, Uninterruptible Power Systems...............................................182
7.22.3 Emergency Systems, Automatic Transfer Switches ..................................................185
7.23 Communications - Reserved ......................................................................................188
7.24.1 Automatic Circuit Reclosers and Line Sectionalizers,
Automatic Circuit Reclosers, Oil/Vacuum ..........................................................189
7.24.2 Automatic Circuit Reclosers and Line Sectionalizers,
Automatic Line Sectionalizers, Oil......................................................................193
7.25 Fiber-Optic Cables .....................................................................................................196
8. SYSTEM FUNCTION TESTS....................................................................................................197
9. THERMOGRAPHIC SURVEY ..................................................................................................198
10. ELECTROMAGNETIC FIELD TESTING ................................................................................199
11. CORONA STUDIES - Reserved .................................................................................................201
ANSI/NETA ATS-2009
CONTENTS (continued)
TABLES
100.1 Insulation Resistance Test Values, Electrical Apparatus and Systems.....................................204
100.2 Switchgear Withstand Test Voltages ........................................................................................205
100.3 Recommended Dissipation Factor/Power Factor at 20° C; Liquid-Filled Transformers,
Regulators, and Reactors, Acceptance Test Values..................................................................206
100.4 Insulating Fluid Limits
100.4.1 Test Limits for New Insulating Oil Received in New Equipment ........................207
100.4.2 Test Limits for Silicone Insulating Liquid in New Transformers .........................207
100.4.3 Typical Values for Less-Flammable Hydrocarbon Insulating Liquid...................208
100.5 Transformer Insulation Resistance, Acceptance Testing..........................................................209
100.6 Medium-Voltage Cables, Acceptance Test Values
100.6.1 DC Test Voltages ..................................................................................................210
100.6.2 AC Test Voltages ..................................................................................................211
100.6.3 Partial Discharge Requirements ............................................................................212
100.6.4 Very Low Frequency Testing Levels ....................................................................212
100.7 Inverse Time Trip Test at 300% of Rated Continuous Current,
Molded-Case Circuit Breakers..................................................................................................213
100.8 Instantaneous Trip Tolerances for Field Testing of Circuit Breakers.......................................214
100.9 Instrument Transformer Dielectric Tests, Field Acceptance ....................................................215
100.10 Maximum Allowable Vibration Amplitude..............................................................................216
100.11 Reserved ...............................................................................................................................217
100.12 US Standard Fasteners, Bolt Torque Values for Electrical Connections
100.12.1 Heat-Treated Steel - Cadmium or Zinc Plated ......................................................218
100.12.2 Silicon Bronze Fasteners .......................................................................................219
100.12.3 Aluminum Alloy Fasteners ...................................................................................219
100.12.4 Stainless Steel Fasteners........................................................................................220
100.13 SF6 Gas Tests ............................................................................................................................221
100.14 Insulation Resistance Conversion Factors
100.14.1 Test Temperatures to 20° C...................................................................................222
100.14.2 Test Temperatures to 40° C...................................................................................223
100.15 High-Potential Test Voltage, Automatic Circuit Reclosers......................................................224
100.16 High-Potential Test Voltage for Acceptance Test of Line Sectionalizers ................................225
100.17 Dielectric Withstand Test Voltages, Metal-Enclosed Bus........................................................226
100.18 Thermographic Survey, Suggested Actions Based on Temperature Rise ................................227
100.19 Dielectric Withstand Test Voltages, Electrical Apparatus Other than Inductive Equipment...228
100.20 Rated Control Voltages and their Ranges for Circuit Breakers
100.20.1 Circuit Breakers.....................................................................................................229
100.20.2 Solenoid-Operated Devices ...................................................................................230
100.21 Accuracy of IEC Class TP Current Transformers Error Limit .................................................231
100.22 Minimum Radii for Power Cable, Single & Multiple Conductor Cables with Interlocked
Armor, Smooth or Corrugated Aluminum Sheath or Lead Sheath...........................................232
ANSI/NETA ATS-2009
CONTENTS (continued)
APPENDICES
Appendix A - Definitions.........................................................................................................................235
Appendix B - Reserved............................................................................................................................237
Appendix C - About the InterNational Electrical Testing Association ...................................................238
Appendix D - Form for Comments..........................................................................................................240
Appendix E - Form for Proposals ............................................................................................................241
ANSI/NETA ATS-2009
1. GENERAL SCOPE
1. These specifications cover the suggested field tests and inspections that are available to assess
the suitability for initial energization of electrical power equipment and systems.
2. The purpose of these specifications is to assure that tested electrical equipment and systems are
operational, are within applicable standards and manufacturer's tolerances, and are installed in
accordance with design specifications.
3. The work specified in these specifications may involve hazardous voltages, materials,
operations, and equipment. These specifications do not purport to address all of the safety
issues associated with their use. It is the responsibility of the user to review all applicable
regulatory limitations prior to the use of these specifications
Page 1
ANSI/NETA ATS-2009
2. APPLICABLE REFERENCES
2.1 Codes, Standards, and Specifications
All inspections and field tests shall be in accordance with the latest edition of the following codes,
standards, and specifications except as provided otherwise herein.
1. American National Standards Institute – ANSI
ASTM D92 Standard Test Method for Flash and Fire Points by Cleveland Open Cup
Tester
ASTM D445 Standard Test Method for Kinematic Viscosity of Transparent and
Opaque Liquids (the Calculation of Dynamic Viscosity)
ASTM D664 Standard Test Method for Acid Number of Petroleum Products by
Potentiometric Titration
ASTM D877 Standard Test Method for Dielectric Breakdown Voltage of Insulating
Liquids using Disk Electrodes
ASTM D924 Standard Test Method for Dissipation Factor (or Power Factor) and
Relative Permittivity (Dielectric Constant) of Electrical Insulating
Liquids
ASTM D971 Standard Test Method for Interfacial Tension of Oil against Water by
the Ring Method
ASTM D974 Standard Test Method for Acid and Base Number by Color-Indicator
Titration
ASTM D1298 Standard Test Method for Density, Relative Density (Specific Gravity),
or API Gravity of Crude Petroleum and Liquid Petroleum Products by
Hydrometer Method
ASTM D1500 Standard Test Method for ASTM Color of Petroleum Products (ASTM
Color Scale)
ASTM D1524 Standard Test Method for Visual Examination of Used Electrical
Insulating Oils of Petroleum Origin in the Field
ASTM D1533 Standard Test Methods for Water in Insulating Liquids by Coulometric
Karl Fischer Titration
ASTM D1816 Standard Test Method for Dielectric Breakdown Voltage of Insulating
Oils of Petroleum Origin Using VDE Electrodes
Page 2
ANSI/NETA ATS-2009
2. APPLICABLE REFERENCES
2.1 Codes, Standards, and Specifications (continued)
ASTM D2029 Standard Test Methods for Water Vapor Content of Electrical Insulating
Gases by Measurement of Dew Point
ASTM D2129 Standard Test Method for Color of Clear Electrical Insulating Liquids
(Platinum-Cobalt Scale)
ASTM D2285 Standard Test Method for Interfacial Tension of Electrical Insulating
Oils of Petroleum Origin against Water by the Drop-Weight Method
ASTM D2477 Standard Test Method for Dielectric Breakdown Voltage and Dielectric
Strength of Insulating Gases at Commercial Power Frequencies
ASTM D2685 Standard Test Method for Air and Carbon Tetrafluoride in Sulfur
Hexafluoride by Gas Chromatography
ASTM D2759 Standard Practice for Sampling Gas from a Transformer under Positive
Pressure
ASTM D3284 Standard Test Method for Combustible Gases in the Gas Space of
Electrical Apparatus Using Portable Meters
ASTM D3612 Standard Test Method for Analysis of Gases Dissolved in Electrical
Insulating Oil by Gas Chromatography
ASTM D3613 Standard Practice for Sampling Electrical Insulating Oils for Gas
Analysis and Determination of Water Content
ANSI/EASA AR100 Recommended Practice for the Repair of Rotating Electrical Apparatus
Page 3
ANSI/NETA ATS-2009
2. APPLICABLE REFERENCES
2.1 Codes, Standards, and Specifications (continued)
6. Institute of Electrical and Electronic Engineers - IEEE
ANSI/IEEE C37 Guides and Standards for Circuit Breakers, Switchgear, Relays,
Compilation Substations, and Fuses
ANSI/IEEE C93.1 Requirements for Power-Line Carrier Coupling Capacitors and Coupling
Capacitor Voltage Transformers (CCVT)
IEEE 81 IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and
Earth Surface Potentials of a Ground System Part I: Normal
Measurements
ANSI/IEEE 81.2 IEEE Guide for Measurement of Impedance and Safety Characteristics of
Large, Extended or Interconnected Grounding Systems
IEEE 141 IEEE Recommended Practice for Electrical Power Distribution for
Industrial Plants (IEEE Red Book)
ANSI/IEEE 241 IEEE Recommended Practice for Electric Power Systems in Commercial
Buildings (Gray Book)
Page 4
ANSI/NETA ATS-2009
2. APPLICABLE REFERENCES
2.1 Codes, Standards, and Specifications (continued)
IEEE 386 IEEE Standard for Separable Insulated Connectors System for Power
Distribution Systems above 600 V
ANSI/IEEE 399 IEEE Recommended Practice for Power Systems Analysis (Brown Book)
ANSI/IEEE 400 IEEE Guide for Field Testing and Evaluation of the Insulation of
Shielded Power Cable Systems
ANSI/IEEE 400.2 IEEE Guide for Field Testing of Shielded Power Cable Systems Using
Very Low Frequency (VLF)
ANSI/IEEE 446 IEEE Recommended Practice for Emergency and Standby Power Systems
for Industrial and Commercial Applications (Orange Book)
ANSI/IEEE 450 IEEE Recommended Practice for Maintenance, Testing, and Replacement
of Vented Lead-Acid Batteries for Stationary Applications
ANSI/IEEE 493 IEEE Recommended Practice for the Design of Reliable Industrial and
Commercial Power Systems (Gold Book)
ANSI/IEEE 519 IEEE Recommended Practices and Requirements for Harmonic Control
in Electrical Power Systems
ANSI/IEEE 602 IEEE Recommended Practice for Electric Systems in Health Care
Facilities (White Book)
ANSI/IEEE 637 IEEE Guide for the Reclamation of Insulating Oil and Criteria for Its Use
IEEE 644 Procedures for Measurement of Power Frequency Electric and Magnetic
Fields from AC Power Lines
ANSI/IEEE 902 IEEE Guide for Maintenance, Operation and Safety of Industrial and
Commercial Power Systems (Yellow Book)
IEEE 1015 IEEE Recommended Practice for Applying Low-Voltage Circuit Breakers
Used in Industrial and Commercial Power Systems (Blue Book)
IEEE 1100 IEEE Recommended Practice for Powering and Grounding Sensitive
Electronic Equipment (Emerald Book)
Page 5
ANSI/NETA ATS-2009
2. APPLICABLE REFERENCES
2.1 Codes, Standards, and Specifications (continued)
ANSI/IEEE 1106 IEEE Recommended Practice for Maintenance, Testing, and Replacement
of Nickel-Cadmium Batteries for Stationary Applications
ANSI/IEEE 1188 IEEE Recommended Practice for Maintenance, Testing, and Replacement
of Valve-Regulated Lead-Acid (VRLA) Batteries for Stationary
Applications
ANSI/ICEA 5-46 kV Shielded Power Cable for Use in the Transmission and
S-93-639/NEMA Distribution of Electric Energy
WC 74
ANSI/ICEA Standard for Concentric Neutral Cables Rated 5,000 - 46,000 Volts
S-94-649
ANSI/ICEA Standard for Utility Shielded Power Cables Rated 5,000 - 46,000 Volts
S-97-682
ANSI/NEMA 84.1 Electrical Power Systems and Equipment Voltage Ratings (60 Hz)
Page 6
ANSI/NETA ATS-2009
2. APPLICABLE REFERENCES
2.1 Codes, Standards, and Specifications (continued)
ANSI/NFPA 70 National Electrical Code
Page 7
ANSI/NETA ATS-2009
2. APPLICABLE REFERENCES
2.2 Other Publications
Manufacturer’s instruction manuals for the equipment to be tested.
John C. Cadick, Electrical Safety Handbook, New York: McGraw Hill
Megger, A Stitch in Time…The Complete Guide to Electrical Insulation Testing
Paul Gill, Electrical Power Equipment Maintenance and Testing, New York: Marcel Dekker, Inc.
Kenneth G. Mastrullo, Ray A. Jones, Jane G. Jones, The Electrical Safety Program Book, NFPA
Page 8
ANSI/NETA ATS-2009
2. APPLICABLE REFERENCES
2.3 Contact Information (continued)
Insulated Cable Engineers Association – ICEA
c/o Global Document Engineers
15 Inverness Way East
Englewood, CO 80112
(303) 397-7956
www.icea.net
International Electrotechnical Commission – IEC
Contact through American National Standards Institute
InterNational Electrical Testing Association – NETA
3050 Old Centre Avenue, Suite 102
Portage, MI 49024
(269) 488-6382 or (888) 300-NETA (6382)
www.netaworld.org
Marcel Dekker, Inc.
PO Box 5005
Monticello, NY 12701
(800) 228-160
www.dekker.com
The McGraw-Hill Companies
P.O. Box 182604
Columbus, OH 43272
Phone: (877) 833-5524
www.mcgraw-hill.com
Megger
4271 Bronze Way
Dallas, TX 75237
(214) 723-2861
www.megger.com
National Electrical Manufacturers Association– NEMA
1300 N. 17th St. Suite 1847
Rosslyn, VA 22209
(703) 841-3200
www.nema.org
National Fire Protection Association – NFPA
1 Battery March Park
PO Box 901
Quincy, MA 02269-9101
(617) 984-7247
www.nfpa.org
Page 9
ANSI/NETA ATS-2009
2. APPLICABLE REFERENCES
2.3 Contact Information (continued)
Occupational Safety and Health Administration – OSHA
U.S. Department of Labor
Occupational Safety and Health Administration
Office of Public Affairs - Room N3647
200 Constitution Avenue
Washington, D.C. 20210
(202) 693-1999
www.osha.gov
The Okonite Company
102 Hilltop Road
Ramsey, New Jersey 07446
(201) 825-0300 Fax 201-825-3524
www.okonite.com
Underwriters Laboratories, Inc. – UL
333 Pfingsten Road
Northbrook, IL 60062
(847) 272-8800
www.ul.com
Page 10
ANSI/NETA ATS-2009
3. QUALIFICATIONS OF TESTING ORGANIZATION AND PERSONNEL
3.1 Testing Organization
1. The testing organization shall be an independent, third party entity which can function as an
unbiased testing authority, professionally independent of the manufacturers, suppliers, and
installers of equipment or systems being evaluated.
2. The testing organization shall be regularly engaged in the testing of electrical equipment
devices, installations, and systems.
3. The testing organization shall use technicians who are regularly employed for testing services.
Page 11
ANSI/NETA ATS-2009
4. DIVISION OF RESPONSIBILITY
4.1 The Owner’s Representative
The owner’s representative shall provide the testing organization with the following:
1. A short-circuit analysis, a coordination study, and a protective device setting sheet as described
in Section 6.
2. A complete set of electrical plans and specifications, including all change orders.
5. A determination of who shall provide a suitable and stable source of electrical power to each
test site.
7. Notification of when equipment becomes available for acceptance tests. Work shall be
coordinated to expedite project scheduling.
1. All field technical services, tooling, equipment, instrumentation, and technical supervision to
perform such tests and inspections.
4. A timely notification of any system, material, or workmanship that is found deficient based on
the results of the acceptance tests.
Page 12
ANSI/NETA ATS-2009
5. GENERAL
5.1 Safety and Precautions
All parties involved must be cognizant of industry-standard safety procedures. This document does
not contain any procedures including specific safety procedures. It is recognized that an
overwhelming majority of the tests and inspections recommended in these specifications are
potentially hazardous. Individuals performing these tests shall be qualified and capable of
conducting the tests in a safe manner and with complete knowledge of the hazards involved.
1. Safety practices shall include, but are not limited to, the following requirements:
1. All applicable provisions of the Occupational Safety and Health Act, particularly OSHA
29 CFR Part 1910 and 29 CFR Part 1926.
3. The Electrical Safety Program Book, Kenneth G. Mastrullo, Ray A. Jones, Jane G.
Jones, NFPA.
4. All tests shall be performed with the apparatus de-energized and grounded except where
otherwise specifically required to be ungrounded or energized for certain tests.
5. The testing organization shall have a designated safety representative on the project to
supervise operations with respect to safety. This individual may be the same person described
in 5.1.2.
2. Field test metering used to check power system meter calibration must be more accurate than
the instrument being tested.
3. Accuracy of metering in test equipment shall be appropriate for the test being performed.
4. Waveshape and frequency of test equipment output waveforms shall be appropriate for the test
to be performed and the equipment to be tested.
Page 13
ANSI/NETA ATS-2009
5. GENERAL
5.3 Test Instrument Calibration
1. The testing organization shall have a calibration program which assures that all applicable test
instruments are maintained within rated accuracy for each test instrument calibrated.
2. The firm providing calibration service shall maintain up-to-date instrument calibration
instructions and procedures for each test instrument calibrated.
3. The accuracy shall be directly traceable to the National Institute of Standards and Technology
(NIST).
6. Records which show date and results of instruments calibrated or tested must be kept up to
date.
7. Calibrating standard shall be of better accuracy than that of the instrument tested.
Page 14
ANSI/NETA ATS-2009
5. GENERAL
5.4 Test Report
1. The test report shall include the following:
1. Summary of project.
3. Description of tests.
4. Test data.
2. Equipment identification.
3. Humidity, temperature, and other conditions that may affect the results of the tests
and/or calibrations.
3. The testing organization shall furnish a copy or copies of the complete report to the owner as
specified in the acceptance testing contract.
Page 15
ANSI/NETA ATS-2009
6. POWER SYSTEM STUDIES
6.1 Short-Circuit Studies
1. Scope of Study
Determine the short-circuit current available at each component of the electrical system and the
ability of the component to withstand and/or interrupt the current. Provide an analysis of all
possible operating scenarios which will be or have been influenced by the proposed or
completed additions or changes to the subject system.
2. Procedure
The short-circuit study shall be performed in accordance with the recommended practices and
procedures set forth in ANSI/IEEE 399 and the step-by-step procedures outlined in the short-
circuit calculation chapters of IEEE 141 and ANSI/IEEE 242.
3. Study Report
Results of the short-circuit study shall be summarized in a final report containing the following
items:
2. Tabulations of the data used to model the system components and a corresponding one-
line diagram.
Page 16
ANSI/NETA ATS-2009
6. POWER SYSTEM STUDIES
6.2 Coordination Studies
1. Scope of Study
Determine protective device characteristics, settings, or sizes that provide a balance between
equipment protection and selective device operation that is optimum for the electrical system.
Provide an analysis of all possible operating scenarios which will be or have been influenced by
the proposed or completed additions or changes to the subject system.
2. Procedure
The coordination study shall be performed in accordance with the recommended practices and
procedures set forth in ANSI/IEEE 399 and ANSI/IEEE 242. Protective device selection and
settings shall comply with requirements of NFPA 70 National Electrical Code.
3. Study Report
Results of the coordination study shall be summarized in a final report containing the following
items:
1. Basis, description, purpose, and scope of the study and a corresponding one-line
diagram.
4. Implementation
The owner shall engage an independent testing firm for the purpose of inspecting, setting,
testing, and calibrating the protective relays, circuit breakers, fuses, and other applicable
devices as outlined in this specification.
Page 17
ANSI/NETA ATS-2009
6. POWER SYSTEM STUDIES
6.3 Arc-Flash Hazard Analysis
1. Scope of Study
Determine arc-flash incident energy levels and flash protection boundary distances based on the
results of the Short-Circuit and Coordination Studies. Perform the analysis under worst-case
arc-flash conditions for all modes of operation. Provide an analysis of all possible operating
scenarios which will be or have been influenced by the proposed or completed additions to the
subject system.
2. Procedure
Identify all locations and equipment to be included in the arc-flash hazard analysis.
4. Identify the possible system operating modes including tie-breaker positions, and
parallel generation.
5. Calculate the arcing fault current flowing through each branch for each fault location
using empirical formula in accordance with NFPA, IEEE, or other standards.
6. Determine the time required to clear the arcing fault current using the protective device
settings and associated trip curves.
7. Select the working distances based on system voltage and equipment class.
8. Calculate the incident energy at each fault location at the prescribed working distance.
9. Determine the hazard/risk category (HRC) for the estimated incident energy level.
Page 18
ANSI/NETA ATS-2009
6. POWER SYSTEM STUDIES
6.3 Arc-Flash Hazard Analysis (continued)
10. Calculate the flash protection boundary at each fault location.
11. Document the assessment in reports and one-line diagrams. Place appropriate labels on
the equipment.
3. Study Report
Results of the arc-flash study shall be summarized in a final report containing the following
items:
1. Basis, method of hazard assessment, description, purpose, scope, and date of the study.
2. Tabulations of the data used to model the system components and a corresponding one-
line diagram.
4. Tabulations of equipment incident energies, hazard risk categories, and flash protection
boundaries. The tabulation shall identify and clearly note equipment that exceeds
allowable incident energy ratings.
Page 19
ANSI/NETA ATS-2009
6. POWER SYSTEM STUDIES
6.4 Load-Flow Studies
1. Scope of Study
Determine active and reactive power, voltage, current, and power factor throughout the
electrical system. Provide an analysis of all possible operating scenarios.
2. Procedure
The load-flow study shall be performed in accordance with the recommended practices and
procedures set forth in ANSI/IEEE 399.
3. Study Report
Results of the load-flow study shall be summarized in a final report containing the following
items:
2. Tabulations of the data used to model the system components and a corresponding one-
line diagram.
4. Tabulations of power and current flow versus equipment ratings. The tabulation shall
identify percentage of rated load and the scenario for which the percentage is based.
Overloaded equipment shall be clearly noted.
5. Tabulations of system voltages versus equipment ratings. The tabulation shall identify
percentage of rated voltage and the scenario for which the percentage is based. Voltage
levels outside the ranges recommended by equipment manufacturers, ANSI/IEEE C84.1,
or other appropriate standards shall be clearly noted.
6. Tabulations of system real and reactive power losses with areas of concern clearly noted.
Page 20
ANSI/NETA ATS-2009
6. POWER SYSTEM STUDIES
6.5 Stability Studies
1. Scope of Study
Determine the ability of the electrical system’s synchronous machines to remain in step with
one another following a disturbance. Provide an analysis of disturbances for all possible
operating scenarios which will be or have been influenced by the proposed or completed
additions or changes to the subject system.
2. Procedure
The stability study shall be performed in accordance with the recommended practices and
procedures set forth in ANSI/IEEE 399.
3. Study Report
Results of the stability study shall be summarized in a final report containing the following
items:
2. Tabulations of the data used to model the system components and a corresponding one-
line diagram.
Page 21
ANSI/NETA ATS-2009
6. POWER SYSTEM STUDIES
6.6 Harmonic-Analysis Studies
1. Scope of Study
Determine the impact of nonlinear loads and their associated harmonic contributions on the
voltage and currents throughout the electrical system. Provide an analysis of all possible
operating scenarios which will be or have been influenced by the proposed or completed
additions or changes to the subject system.
2. Procedure
The harmonic-analysis study shall be performed in accordance with the recommended practices
and procedures set forth in ANSI/IEEE 399.
3. Study Report
Results of the harmonic-analysis study shall be summarized in a final report containing the
following items:
2. Tabulations of the data used to model the system components and a corresponding one-
line diagram.
4. Tabulations of rms voltages, peak voltages, rms currents, and total capacitor bank
loading versus associated equipment ratings. Equipment with insufficient ratings shall
be clearly identified for each of the scenarios evaluated.
Page 22
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.1 Switchgear and Switchboard Assemblies
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Verify the unit is clean and all shipping bracing, loose parts, and documentation shipped inside
cubicles have been removed.
5. Verify that fuse and circuit breaker sizes and types correspond to drawings and coordination
study as well as to the circuit breaker’s address for microprocessor-communication packages.
7. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
8. Confirm correct operation and sequencing of electrical and mechanical interlock systems.
9. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
14. Verify that filters are in place and vents are clear.
15. Perform visual and mechanical inspection of instrument transformers in accordance with
Section 7.10.
* Optional
Page 23
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.1 Switchgear and Switchboard Assemblies (continued)
16. Inspect control power transformers.
1. Inspect for physical damage, cracked insulation, broken leads, tightness of connections,
defective wiring, and overall general condition.
2. Verify that primary and secondary fuse or circuit breaker ratings match drawings.
2. Electrical Tests
1. Perform resistance measurements through bolted electrical connections with a low-resistance
ohmmeter, if applicable, in accordance with Section 7.1.1.
3. Perform a dielectric withstand voltage test on each bus section, each phase-to-ground with
phases not under test grounded, in accordance with manufacturer’s published data. If
manufacturer has no recommendation for this test, it shall be in accordance with Table 100.2.
The test voltage shall be applied for one minute.
*4. Perform insulation-resistance tests on control wiring with respect to ground. Applied potential
shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated cable. Test
duration shall be one minute. For units with solid-state components or control devices that can
not tolerate the applied voltage, follow the manufacturer’s recommendation.
7. Determine accuracy of all meters and calibrate watthour meters in accordance with Section
7.11. Verify multipliers.
Page 24
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.1 Switchgear and Switchboard Assemblies (continued)
4. Verify correct secondary voltage by energizing the primary winding with system
voltage. Measure secondary voltage with the secondary wiring disconnected.
5. Verify correct function of control transfer relays located in the switchgear with multiple
control power sources.
9. Voltage Transformers
1. Perform secondary wiring integrity test. Verify correct potential at all devices.
2. Verify secondary voltages by energizing the primary winding with system voltage.
10. Perform current-injection tests on the entire current circuit in each section of switchgear.
1. Perform current tests by secondary injection with magnitudes such that a minimum
current of 1.0 ampere flows in the secondary circuit. Verify correct magnitude of
current at each device in the circuit.
*2. Perform current tests by primary injection with magnitudes such that a minimum of 1.0
ampere flows in the secondary circuit. Verify correct magnitude of current at each
device in the circuit.
13. Perform phasing checks on double-ended or dual-source switchgear to insure correct bus
phasing from each source.
3. Test Values
3.1 Test Values – Visual and Mechanical
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.1.1.7.2)
* Optional
Page 25
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.1 Switchgear and Switchboard Assemblies (continued)
3.2 Test Values – Electrical
3. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
4. Minimum insulation-resistance values of control wiring shall not be less than two megohms.
5. Results of electrical tests on instrument transformers shall be in accordance with Section 7.10.
2. Turns-ratio test results shall not deviate by more than one half percent from either the
adjacent coils or the calculated ratio.
9. Voltage transformers
* Optional
Page 26
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.1 Switchgear and Switchboard Assemblies (continued)
10. Current-injection tests shall prove current wiring is in accordance with design specifications.
13. Phasing checks shall prove the switchgear or switchboard phasing is correct and in accordance
with the system design.
* Optional
Page 27
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.2.1.1 Transformers, Dry Type, Air-Cooled, Low-Voltage, Small
NOTE: This category consists of power transformers with windings rated 600 volts or less and sizes
equal to or less than 167 kVA single-phase or 500 kVA three-phase.
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Verify that resilient mounts are free and that any shipping brackets have been removed.
6. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.2.1.1.1.
4. Verify correct secondary voltage phase-to-phase and phase-to-neutral after energization and
prior to loading.
* Optional
Page 28
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.2.1.1 Transformers, Dry Type, Air-Cooled, Low-Voltage, Small (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.2.1.1.1.6.2)
3. Turns-ratio test results shall not deviate by more than one-half percent from either the adjacent
coils or the calculated ratio.
* Optional
Page 29
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.2.1.2 Transformers, Dry Type, Air-Cooled, Large
NOTE: This category consists of power transformers with windings rated higher than 600 volts and
low-voltage transformers larger than 167 kVA single-phase or 500 kVA three-phase.
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Verify that resilient mounts are free and that any shipping brackets have been removed.
*6. Verify that control and alarm settings on temperature indicators are as specified.
7. Verify that cooling fans operate and that fan motors have correct overcurrent protection.
8. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.2.1.2.1.
3. Perform power-factor or dissipation-factor tests on all windings in accordance with the test
equipment manufacturer’s published data.
*4. Perform a power-factor or dissipation-factor tip-up test on windings greater than 2.5 kV.
* Optional
Page 30
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.2.1.2 Transformers, Dry Type, Air-Cooled, Large (continued)
5. Perform turns-ratio tests at all tap positions.
8. Measure core insulation resistance at 500 volts dc if the core is insulated and the core ground
strap is removable.
*9. Perform an applied voltage test on all high- and low-voltage windings-to-ground. See
ANSI/IEEE C57.12.91, Sections 10.2 and 10.9.
10. Verify correct secondary voltage, phase-to-phase and phase-to-neutral, after energization and
prior to loading.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Control and alarm settings on temperature indicators shall operate within manufacturer’s
recommendations for specified settings. (7.2.1.2.1.6)
4. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.2.1.2.1.8.2)
Page 31
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.2.1.2 Transformers, Dry Type, Air-Cooled, Large (continued)
3. CH and CL power-factor or dissipation-factor values will vary due to support insulators and bus
work utilized on dry transformers. The following shall be expected on CHL power factors:
Power transformers: 2.0 percent or less
Distribution transformers: 5.0 percent or less
Consult transformer manufacturer’s or test equipment manufacturer’s data for additional
information.
4. Power-factor or dissipation-factor tip-up exceeding 1.0 percent shall be investigated.
5. Turns-ratio test results shall not deviate more than one-half percent from either the adjacent
coils or the calculated ratio.
6. The typical excitation current test data pattern for a three-legged core transformer is two similar
current readings and one lower current reading.
8. Core insulation-resistance values shall not be less than one megohm at 500 volts dc.
9. AC dielectric withstand test voltage shall not exceed 75 percent of factory test voltage for one
minute duration. DC dielectric withstand test voltage shall not exceed 100 percent of the ac rms
test voltage specified in ANSI C57.12.91, Section 10.2 for one minute duration. If no evidence
of distress or insulation failure is observed by the end of the total time of voltage application
during the dielectric withstand test, the test specimen is considered to have passed the test.
10. Phase-to-phase and phase-to-neutral secondary voltages shall be in agreement with nameplate
data.
11. Test results for surge arresters shall be in accordance with Section 7.19.
* Optional
Page 32
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.2.2 Transformers, Liquid-Filled
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
9. Verify that alarm, control, and trip settings on temperature and level indicators are as specified.
10. Verify operation of alarm, control, and trip circuits from temperature and level indicators,
pressure relief device, gas accumulator, and fault pressure relay, if applicable.
11. Verify that cooling fans and pumps operate correctly and have appropriate overcurrent
protection.
12. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
Page 33
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.2.2 Transformers, Liquid-Filled (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.2.2.1.
7. Measure the resistance of each high-voltage winding in each de-energized tap-changer position.
Measure the resistance of each low-voltage winding in each de-energized tap-changer position,
if applicable.
*8. If core ground strap is accessible, remove and measure core insulation resistance at 500 volts
dc.
10. Remove a sample of insulating liquid in accordance with ASTM D 923. Sample shall be tested
for the following.
* Optional
Page 34
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.2.2 Transformers, Liquid-Filled (continued)
*7. Water in insulating liquids: ASTM D 1533. (Required on 25 kV or higher voltages and
on all silicone-filled units.)
11. Remove a sample of insulating liquid in accordance with ASTM D 3613 and perform
dissolved-gas analysis (DGA) in accordance with ANSI/IEEE C57.104 or ASTM D3612.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Alarm, control, and trip circuits from temperature and level indicators as well as pressure relief
device and fault pressure relay shall operate within manufacturer’s recommendations for their
specified settings. (7.2.2.1.10)
4. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.2.2.1.12.2)
6. Liquid levels in the transformer tanks and bushings shall be within indicated tolerances.
(7.2.2.1.13)
* Optional
Page 35
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.2.2 Transformers, Liquid-Filled (continued)
2. Minimum insulation-resistance values of transformer insulation shall be in accordance with
manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.5. Values of insulation resistance less than this table or manufacturer’s recommendations
should be investigated. The polarization index shall not be less than 1.0.
3. Turns-ratio test results shall not deviate by more than one-half percent from either the adjacent
coils or the calculated ratio.
5. Investigate bushing power-factor and capacitance values that vary from nameplate values by
more than ten percent. Hot-collar tests are evaluated on a milliampere/milliwatt loss basis, and
the results should be compared to values of similar bushings.
6. Typical excitation-current test data pattern for a three-legged core transformer is two similar
current readings and one lower current reading.
8. Core insulation values shall be compared to the factory test value but not less than one megohm
at 500 volts dc.
11. Evaluate results of dissolved-gas analysis in accordance with ANSI/IEEE Standard C57.104.
12. Results of electrical tests on instrument transformers shall be in accordance with Section 7.10.
13. Results of surge arrester tests shall be in accordance with Section 7.19.
* Optional
Page 36
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.3.1 Cables, Low-Voltage, Low-Energy
— RESERVED —
* Optional
Page 37
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.3.2 Cables, Low-Voltage, 600-Volt Maximum
1. Visual and Mechanical Inspection
1. Compare cable data with drawings and specifications.
2. Inspect exposed sections of cable for physical damage and correct connection in accordance
with the single-line diagram.
3. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.3.2.1.
2. Perform insulation-resistance test on each conductor with respect to ground and adjacent
conductors. Applied potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc
for 600-volt rated cable. Test duration shall be one minute.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.3.2.1.3.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.3.2.1.3.2)
Page 38
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.3.2 Cables, Low-Voltage, 600-Volt Maximum (continued)
3.2 Test Values – Electrical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value.
* Optional
Page 39
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.3.3 Cables, Medium- and High-Voltage
3. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
6. Verify that visible cable bends meet or exceed ICEA and manufacturer’s minimum published
bending radius.
8. If cables are terminated through window-type current transformers, inspect to verify that neutral
and ground conductors are correctly placed and that shields are correctly terminated for
operation of protective devices.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.3.3.1.
2. Perform an insulation-resistance test individually on each conductor with all other conductors
and shields grounded. Apply voltage in accordance with manufacturer’s published data. In the
absence of manufacturer’s published data, use Table 100.1.
* Optional
Page 40
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.3.3 Cables, Medium- and High-Voltage (continued)
4. In accordance with ICEA, IEC, IEEE and other power cable consensus standards, testing can be
performed by means of direct current, power frequency alternating current, or very low
frequency alternating current. These sources may be used to perform insulation-withstand tests,
and baseline diagnostic tests such as partial discharge analysis, and power factor or dissipation
factor. The selection shall be made after an evaluation of the available test methods and a
review of the installed cable system. Some of the available test methods are listed below.
2. DC insulation resistance
3. Test Values
2. Bolt-torque levels should be in accordance with manufacturer’s published data. In the absence
of manufacturer’s published data, use Table 100.12. (7.3.3.1.3.2)
4. The minimum bend radius to which insulated cables may be bent for permanent training shall
be in accordance with Table 100.22. (7.3.3.1.6)
* Optional
Page 41
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.3.3 Cables, Medium- and High-Voltage (continued)
3.2 Test Values – Electrical
3. Shielding shall exhibit continuity. Investigate resistance values in excess of ten ohms per 1000
feet of cable.
4.1 If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
4.2 Based on the test methodology chosen, refer to applicable standards or manufacturer’s literature
for acceptable values.
* Optional
Page 42
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.4 Metal-Enclosed Busways
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Verify tightness of accessible bolted electrical connections and bus joints by calibrated
torque-wrench method in accordance with manufacturer’s published data or Table
100.12.
7. Examine outdoor busway for removal of “weep-hole” plugs, if applicable, and the correct
installation of joint shield.
2. Electrical Tests
1. Perform resistance measurements through bolted connections and bus joints with a low-
resistance ohmmeter, if applicable, in accordance with Section 7.4.1.
2. Measure insulation resistance of each busway, phase-to-phase and phase-to-ground for one
minute, in accordance with Table 100.1.
3. Perform a dielectric withstand voltage test on each busway, phase-to-ground with phases not
under test grounded, in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.17. Where no dc test value is shown in Table
100.17, ac value shall be used. The test voltage shall be applied for one minute.
5. Perform phasing test on each busway tie section energized by separate sources. Tests must be
performed from their permanent sources.
* Optional
Page 43
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.4 Metal-Enclosed Busways (continued)
6. Verify operation of busway space heaters.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.4.1.5.1)
2. Bolt-torque levels should be in accordance with manufacturer’s published data. In the absence
of manufacturer’s published data, use Table 100.12. (7.4.1.5.2)
Converted values of insulation resistance less than those in Table 100.1 or manufacturer’s
minimum should be investigated. Dielectric withstand voltage tests shall not proceed until
insulation-resistance levels are raised above minimum values.
3. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
4. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values which deviate from those of similar bus connections and sections
by more than 50 percent of the lowest value.
5. Phasing test results shall indicate the phase relationships are in accordance with system design.
* Optional
Page 44
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.1.1 Switches, Air, Low-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Verify correct blade alignment, blade penetration, travel stops, and mechanical operation.
6. Verify that fuse sizes and types are in accordance with drawings, short-circuit studies, and
coordination study.
7. Verify that each fuse has adequate mechanical support and contact integrity.
8. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
12. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.5.1.1.1.
3. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with switch closed, and across each open pole. Apply voltage in accordance with
manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.1.
* Optional
Page 45
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.1.1 Switches, Air, Low-Voltage (continued)
4. Measure fuse resistance.
7. Perform tests on other protective devices in accordance with Section 7.9, if applicable.
3. Test Values
3.1 Test Values – Visual and Mechanical
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.5.1.1.1.8.2)
2. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values that deviate from adjacent poles or similar switches by more than
50 percent of the lowest value.
4. Investigate fuse-resistance values that deviate from each other by more than 15 percent.
* Optional
Page 46
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.1.2 Switches, Air, Medium-Voltage, Metal-Enclosed
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Verify correct blade alignment, blade penetration, travel stops, arc interrupter operation, and
mechanical operation.
6. Verify that fuse sizes and types are in accordance with drawings, short-circuit study, and
coordination study.
7. Verify that expulsion-limiting devices are in place on all holders having expulsion-type
elements.
8. Verify that each fuseholder has adequate mechanical support and contact integrity.
9. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
13. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.5.1.2.1.
* Optional
Page 47
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.1.2 Switches, Air, Medium-Voltage, Metal-Enclosed (continued)
3. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with switch closed, and across each open pole. Apply voltage in accordance with
manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.1.
4. Perform a dielectric withstand voltage test on each pole with switch closed. Test each pole-to-
ground with all other poles grounded. Test voltage shall be in accordance with manufacturer’s
published data. In the absence of manufacturer’s published data, use Table 100.2.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.5.1.2.1.9.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.5.1.2.1.9.2)
2. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. In the absence of manufacturer’s published data,
investigate values that deviate from adjacent poles or similar switches by more than 50 percent
of the lowest value.
4. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
* Optional
Page 48
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.1.2 Switches, Air, Medium-Voltage, Metal-Enclosed (continued)
5. Investigate fuse resistance values that deviate from each other by more than 15 percent.
* Optional
Page 49
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.1.3 Switches, Air, Medium- and High-Voltage, Open
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
6. Verify correct operation and adjustment of motor operator limit switches and mechanical
interlocks, if applicable.
7. Verify correct blade alignment, blade penetration, travel stops, arc interrupter operation, and
mechanical operation.
9. Verify that each fuse has adequate mechanical support and contact integrity, if applicable.
10. Verify that fuse sizes and types are in accordance with drawings, short-circuit study, and
coordination study.
11. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
12. Verify correct operation of all indicating and control devices, if applicable.
13. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
* Optional
Page 50
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.1.3 Switches, Air, Medium- and High-Voltage, Open (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.5.1.3.1.
3. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with switch closed, and across each open pole. Apply voltage in accordance with
manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.1.
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components or control
devices that can not tolerate the applied voltage, follow manufacturer’s recommendation.
5. Perform a dielectric withstand voltage test on each pole with switch closed. Test each pole-to-
ground with all other poles grounded. Test voltage shall be in accordance with manufacturer’s
published data. In the absence of manufacturer’s published data, use Table 100.19.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.5.1.3.1.11.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.5.1.3.1.11.2)
2. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. In the absence of manufacturer’s published data,
investigate values that deviate from adjacent poles or similar switches by more than 50 percent
of the lowest value.
* Optional
Page 51
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.1.3 Switches, Air, Medium- and High-Voltage, Open (continued)
3. Insulation-resistance values shall be in accordance with manufacturer’s published data. In the
absence of manufacturer’s published data, use Table 100.1. Values of insulation resistance less
than this table or manufacturer’s recommendations should be investigated. Dielectric withstand
voltage tests should not proceed until insulation-resistance levels are raised above minimum
values.
4. Minimum insulation-resistance values of control wiring shall not be less than two megohms.
5. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
* Optional
Page 52
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.2 Switches, Oil, Medium-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
6. Verify correct operation and adjustment of motor operator limit switches and mechanical
interlocks, if applicable.
8. Verify that each fuse has adequate mechanical support and contact integrity, if applicable.
9. Verify that fuse sizes and types are in accordance with drawings, short-circuit study, and
coordination study.
10. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
12. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
* Optional
Page 53
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.2 Switches, Oil, Medium-Voltage (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.5.2.1
3. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with switch closed, and across each open pole. Apply voltage in accordance with
manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.1.
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components or control
devices that cannot tolerate the applied voltage, follow manufacturer’s recommendation.
5. Perform a dielectric withstand voltage test on each pole with switch closed. Test each pole-to-
ground with all other poles grounded. Apply voltage in accordance with manufacturer’s
published data. In the absence of manufacturer’s published data, use Table 100.19.
*6. Remove a sample of insulating liquid in accordance with ASTM D 923. Sample shall be tested
in accordance with the referenced standard.
3. Test Values
3.1 Test Values – Visual and Mechanical
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.5.2.1.10.2)
4. Operation counter shall advance one digit per close-open cycle. (7.5.2.1.13)
* Optional
Page 54
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.2 Switches, Oil, Medium-Voltage (continued)
3.2 Test Values – Electrical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value.
2. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values that deviate from adjacent poles or similar switches by more than
50 percent of the lowest value.
4. Insulation-resistance values of control wiring shall not be less than two megohms.
5. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
* Optional
Page 55
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.3 Switches, Vacuum, Medium-Voltage
1. Visual and Mechanical Inspection
6. Verify correct operation and adjustment of motor operator limit switches and mechanical
interlocks, if applicable.
9. Verify that each fuse has adequate support and contact integrity.
10. Verify that fuse sizes and types are in accordance with drawings, the short-circuit study, and the
coordination study.
11. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
13. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
* Optional
Page 56
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.3 Switches, Vacuum, Medium-Voltage (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted electrical connections with a low-resistance
ohmmeter, if applicable. See Section 7.5.3.1
3. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with switch closed, and across each open pole. Apply voltage in accordance with
manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.1.
4. Perform vacuum bottle integrity (dielectric withstand voltage) test across each vacuum bottle
with the contacts in the open position in strict accordance with manufacturer’s published data.
5. Remove a sample of insulating liquid, if applicable, in accordance with ASTM D 923. Sample
shall be tested in accordance with the referenced standard.
*6. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
7. Perform a dielectric withstand voltage test in accordance with manufacturer’s published data.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Critical distances of the operating mechanism shall be in accordance with manufacturer’s
published data. (7.5.3.1.7)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.5.3.1.11.2)
* Optional
Page 57
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.3 Switches, Vacuum, Medium-Voltage (continued)
4. Results of the thermographic survey shall be in accordance with Section 9. (7.5.3.1.11.3)
5. Operation counter shall advance one digit per close-open cycle. (7.5.3.1.14)
2. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values that deviate from adjacent poles or similar switches by more than
50 percent of the lowest value.
4. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the vacuum bottle integrity test, the test specimen is considered to have
passed the test.
6. Insulation-resistance values of control wiring shall not be less than two megohms.
7. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
8. Results of open and close operation from control devices shall be in accordance with system
design.
* Optional
Page 58
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.4 Switches, SF6, Medium-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Inspect and service mechanical operator and SF6 gas insulated system in accordance with the
manufacturer’s published data.
6. Verify correct operation of SF6 gas pressure alarms and limit switches, if applicable, as
recommended by the manufacturer.
9. Verify that each fuse holder has adequate mechanical support and contact integrity.
10. Verify that fuse sizes and types are in accordance with drawings, short-circuit study, and
coordination study.
11. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
12. Verify appropriate contact lubrication on moving current-carrying parts and on moving and
sliding surfaces.
13. Test for SF6 gas leaks in accordance with manufacturer’s published data.
* Optional
Page 59
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.4 Switches, SF6, Medium-Voltage (continued)
2. Electrical Tests
1. Perform resistance measurements through accessible bolted electrical connections with a low-
resistance ohmmeter, if applicable. See Section 7.5.4.1.
3. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with switch closed, and across each open pole. Apply voltage in accordance with
manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.1.
*4. Remove a sample of SF6 gas if provisions are made for sampling and test in accordance with
Table 100.13.
5. Perform a dielectric withstand voltage test across each gas bottle with the switch in the open
position in accordance with manufacturer’s published data.
*6. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
7. Perform a dielectric withstand voltage test in accordance with manufacturer’s published data.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Critical distances of operating mechanism shall be in accordance with manufacturer’s published
data. (7.5.4.1.7)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.5.4.1.11.2)
5. Operation counter shall advance one digit per close-open cycle. (7.5.4.1.14)
* Optional
Page 60
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.4 Switches, SF6, Medium-Voltage (continued)
3.2 Test Values – Electrical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value.
2. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. In the absence of manufacturer’s published data,
investigate values that deviate from adjacent poles or similar switches by more than 50 percent
of the lowest value.
5. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the gas bottle dielectric withstand test, the test specimen is considered to
have passed the test.
6. Insulation-resistance values of control wiring shall not be less than two megohms.
7. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
8. Results of open and close operation from control devices shall be in accordance with system
design.
* Optional
Page 61
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.5 Switches, Cutouts
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Verify correct blade alignment, blade penetration, travel stops, latching mechanism, and
mechanical operation.
6. Verify that each fuseholder has adequate mechanical support and contact integrity.
7. Verify that fuse size and types are in accordance with drawings, short-circuit study, and
coordination study.
8. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.5.5.1.
3. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with switch closed, and across each open pole. Test voltage shall be in accordance with
manufacturer’s published data or Table 100.1.
4. Perform a dielectric withstand voltage test on each pole, phase-to-ground with cutout closed.
Ground adjacent cutouts, if applicable. Test voltage shall be in accordance with manufacturer’s
published data. In the absence of manufacturer’s published data, use Table 100.1.
* Optional
Page 62
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.5.5 Switches, Cutouts (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.5.5.1.8.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.5.5.1.8.2)
2. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values which deviate from adjacent poles or similar switches by more
than 50 percent of the lowest value.
4. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
* Optional
Page 63
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.1 Circuit Breakers, Air, Insulated-Case/Molded-Case
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
6. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
8. Perform adjustments for final protective device settings in accordance with the coordination
study.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.6.1.1.1.
2. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with the circuit breaker closed, and across each open pole. Apply voltage in accordance
with manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.1.
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
Page 64
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.1 Circuit Breakers, Air, Insulated-Case/Molded-Case (continued)
7. Determine ground-fault pickup and time delay by primary current injection.
10. Perform minimum pickup voltage tests on shunt trip and close coils in accordance with
manufacturer’s published data.
11. Verify correct operation of auxiliary features such as trip and pickup indicators, zone
interlocking, electrical close and trip operation, trip-free, anti-pump function, and trip unit
battery condition. Reset all trip logs and indicators.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.6.1.1.1.6.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.6.1.1.1.6.2)
3. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values that deviate from adjacent poles or similar breakers by more than
50 percent of the lowest value.
4. Insulation-resistance values of control wiring shall not be less than two megohms.
* Optional
Page 65
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.1 Circuit Breakers, Air, Insulated-Case/Molded-Case (continued)
5. Long-time pickup values shall be as specified, and the trip characteristic shall not exceed
manufacturer’s published time-current characteristic tolerance band, including adjustment
factors. If manufacturer’s curves are not available, trip times shall not exceed the value shown
in Table 100.7.
6. Short-time pickup values shall be as specified, and the trip characteristic shall not exceed
manufacturer’s published time-current tolerance band.
7. Ground fault pickup values shall be as specified, and the trip characteristic shall not exceed
manufacturer’s published time-current tolerance band.
9. Pickup values and trip characteristics shall be within manufacturer’s published tolerances.
10. Minimum pickup voltage of the shunt trip and close coils shall conform to the manufacturer’s
published data. In the absence of the manufacturer’s published data, refer to Table 100.20.
11. Breaker open, close, trip, trip-free, anti-pump, and auxiliary features shall function as designed.
12. The charging mechanism shall operate in accordance with manufacturer’s published data.
* Optional
Page 66
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.2 Circuit Breakers, Air, Low-Voltage Power
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Verify that all maintenance devices are available for servicing and operating the breaker.
8. Verify that primary and secondary contact wipe and other dimensions vital to satisfactory
operation of the breaker are correct.
9. Perform all mechanical operator and contact alignment tests on both the breaker and its
operating mechanism in accordance with manufacturer’s published data.
10. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
13. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
14. Perform adjustments for final protective device settings in accordance with coordination study
provided by end user.
* Optional
Page 67
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.2 Circuit Breakers, Air, Low-Voltage Power (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.6.1.2.1.
2. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with the circuit breaker closed, and across each open pole. Test voltage shall be in
accordance with manufacturer’s published data. In the absence of manufacturer’s published
data, use Table 100.1.
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
10. Perform minimum pickup voltage tests on shunt trip and close coils in accordance with
manufacturer’s published data.
11. Verify correct operation of any auxiliary features such as trip and pickup indicators, zone
interlocking, electrical close and trip operation, trip-free, antipump function, and trip unit
battery condition. Reset all trip logs and indicators.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.6.1.2.1.10.1).
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.6.1.2.1.10.2)
* Optional
Page 68
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.2 Circuit Breakers, Air, Low-Voltage Power (continued)
3. Results of the thermographic survey shall be in accordance with Section 9. (7.6.1.2.1.10.3)
5. Operations counter shall advance one digit per close-open cycle. (7.6.1.2.1.15)
3. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. In the absence of manufacturer’s published data,
investigate values that deviate from adjacent poles or similar breakers by more than 50 percent
of the lowest value
4. Insulation-resistance values of control wiring shall not be less than two megohms.
5. Long-time pickup values shall be as specified, and the trip characteristic shall not exceed
manufacturer’s published time-current characteristic tolerance band, including adjustment
factors. If manufacturer’s curves are not available, trip times shall not exceed the value shown
in Table 100.7.
6. Short-time pickup values shall be as specified, and the trip characteristic shall not exceed
manufacturer’s published time-current tolerance band.
7. Ground fault pickup values shall be as specified, and the trip characteristic shall not exceed
manufacturer’s published time-current tolerance band.
9. Pickup values and trip characteristic shall be as specified and within manufacturer’s published
tolerances.
10. Minimum pickup voltage of the shunt trip and close coils shall conform to the manufacturer’s
published data. In the absence of the manufacturer’s published data, refer to Table 100.20.
11. Auxiliary features shall operate in accordance with manufacturer’s published data.
* Optional
Page 69
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.2 Circuit Breakers, Air, Low-Voltage Power (continued)
12. The charging mechanism shall operate in accordance with manufacturer’s published data.
* Optional
Page 70
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.3 Circuit Breakers, Air, Medium-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications
4. Verify that all maintenance devices are available for servicing and operating the breaker.
8. If recommended by manufacturer, slow close/open breaker and check for binding, friction,
contact alignment, and penetration. Verify that contact sequence is in accordance with
manufacturer’s published data. In the absence of manufacturer’s published data, refer to
ANSI/IEEE C37.04.
9. Perform all mechanical operation tests on the operating mechanism in accordance with
manufacturer’s published data.
10. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
14. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
* Optional
Page 71
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.3 Circuit Breakers, Air, Medium-Voltage (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable. See Section 7.6.1.3.1.
2. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with circuit breaker closed, and across each open pole. Apply voltage in accordance
with manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.1.
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components or control
devices that can not tolerate the applied voltage, follow manufacturer’s recommendation.
6. Perform minimum pickup voltage tests on trip and close coils in accordance with
manufacturer’s published data.
*7. Perform power-factor or dissipation-factor tests with breaker in both the open and closed
positions.
*8. Perform power-factor or dissipation-factor tests on each bushing equipped with a power-factor/
capacitance tap. In the absence of a power-factor/ capacitance tap, perform hot-collar tests.
These tests shall be in accordance with the test equipment manufacturer’s published data.
9. Perform a dielectric withstand voltage test on each phase with the circuit breaker closed and the
poles not under test grounded. Apply voltage in accordance with manufacturer’s published data.
In the absence of manufacturer’s published data, use Table 100.19.
* Optional
Page 72
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.3 Circuit Breakers, Air, Medium-Voltage (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Mechanical operation and contact alignment shall be in accordance with manufacturer’s
published data. (7.6.1.3.1.9)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.6.1.3.1.10.2)
5. Travel and velocity values shall be in accordance with manufacturer’s published data.
(7.6.1.3.1.15)
6. Operations counter shall advance one digit per close-open cycle. (7.6.1.3.1.16)
3. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. In the absence of manufacturer’s published data,
investigate values that deviate from adjacent poles or similar breakers by more than 50 percent
of the lowest value.
4. Insulation-resistance values of control wiring shall not be less than two megohms.
5. Breaker mechanism charge, close, open, trip, trip-free, and antipump features shall function as
designed.
6. Minimum pickup voltage of the trip and close coils shall conform to the manufacturer’s
published data. In the absence of the manufacturer’s published data, refer to Table 100.20.
* Optional
Page 73
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.1.3 Circuit Breakers, Air, Medium-Voltage (continued)
7. Power-factor or dissipation-factor values shall be compared with previous test results of similar
breakers or manufacturer’s published data.
9. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the circuit breaker is considered to have passed
the test.
12. The results of instrument transformer tests shall be in accordance with Section 7.10.
* Optional
Page 74
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.2 Circuit Breakers, Oil, Medium- and High-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Verify that all maintenance devices such as special tools and gauges specified by the
manufacturer are available for servicing and operating the breaker.
8. Inspect hydraulic system and air compressor in accordance with manufacturer’s published data.
9. Test alarms and pressure-limit switches for pneumatic and hydraulic operators as recommended
by the manufacturer.
10. Perform mechanical operation tests on the operating mechanism in accordance with
manufacturer’s published data.
1. Remove oil. Lower tanks or remove manhole covers as necessary. Inspect bottom of
tank for broken parts and debris.
2. Inspect lift rod and toggle assemblies, contacts, interrupters, bumpers, dashpots, bushing
current transformers, tank liners, and gaskets.
3. Verify that contact sequence is in accordance with manufacturer’s published data. In the
absence of manufacturer’s published data, refer to ANSI/IEEE C37.04.
* Optional
Page 75
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.2 Circuit Breakers, Oil, Medium- and High-Voltage (continued)
12. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
16. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.6.2.1.
2. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with circuit-breaker closed, and across each open pole. Test voltage shall be in
accordance with manufacturer’s published data. In the absence of manufacturer’s published
data, use Table 100.1.
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
* Optional
Page 76
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.2 Circuit Breakers, Oil, Medium- and High-Voltage (continued)
5. Remove a sample of insulating liquid in accordance with ASTM D 923. Sample shall be tested
in accordance with the referenced standard.
6. Perform minimum pickup voltage tests on trip and close coils in accordance with
manufacturer’s published data.
7. Verify correct operation of any auxiliary features such as electrical close and trip operation,
trip-free, antipump function.
8. Trip circuit breaker by operation of each protective device. Reset all trip logs and indicators.
9. Perform power-factor or dissipation-factor tests on each pole with breaker open and each phase
with breaker closed. Determine tank loss index.
10. Perform power-factor or dissipation-factor tests on each bushing equipped with a power-factor/
capacitance tap. In the absence of a power-factor/ capacitance tap, perform hot-collar tests.
These tests shall be in accordance with the test equipment manufacturer’s published data.
*11. Perform a dielectric withstand voltage test in accordance with manufacturer’s published data.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Settings for alarm, pressure, and limit switches shall be in accordance with owner’s
specifications. In the absence of owner’s specifications use manufacturer’s published data.
(7.6.2.1.9)
* Optional
Page 77
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.2 Circuit Breakers, Oil, Medium- and High-Voltage (continued)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.6.2.1.12.2)
5. Travel and velocity values shall be in accordance with manufacturer’s published data.
(7.6.2.1.15)
6. Operations counter shall advance one digit per close-open cycle. (7.6.2.1.17)
3. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values that deviate from adjacent poles or similar breakers by more than
50 percent of the lowest value.
4. Insulation-resistance values of control wiring shall not be less than two megohms.
6. Minimum pickup voltage of the trip and close coils shall conform to the manufacturer’s
published data. In the absence of the manufacturer’s published data, refer to Table 100.20.
10. Power-factor or dissipation-factor and capacitance values shall be within ten percent of
nameplate rating for bushings. Hot collar tests are evaluated on a milliampere/milliwatt loss
basis, and the results should be compared to values of similar bushings.
* Optional
Page 78
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.2 Circuit Breakers, Oil, Medium- and High-Voltage (continued)
11. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
13. Results of electrical tests on instrument transformers shall be in accordance with Section 7.10.
* Optional
Page 79
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.3 Circuit Breakers, Vacuum, Medium-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Verify that all maintenance devices such as special tools and gauges specified by the
manufacturer are available for servicing and operating the breaker.
6. Perform all mechanical operation tests on the operating mechanism in accordance with
manufacturer’s published data.
8. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
*11. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
* Optional
Page 80
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.3 Circuit Breakers, Vacuum, Medium-Voltage (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.6.3.1.
2. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with the circuit breaker closed, and across each open pole. Test voltage shall be in
accordance with manufacturer’s published data. In the absence of manufacturer’s published
data, use Table 100.1.
*3. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
5. Perform minimum pickup voltage tests on trip and close coils in accordance with
manufacturer’s published data.
6. Verify correct operation of any auxiliary features such as electrical close and trip operation,
trip-free, and antipump function.
7. Trip circuit breaker by operation of each protective device. Reset all trip logs and indicators.
*8. Perform power-factor or dissipation-factor tests on each pole with the breaker open and each
phase with the breaker closed.
*9. Perform power-factor or dissipation-factor tests on each bushing equipped with a power-factor/
capacitance tap. In the absence of a power-factor/ capacitance tap, perform hot-collar tests.
These tests shall be in accordance with the test equipment manufacturer’s published data.
10. Perform vacuum bottle integrity (dielectric withstand voltage) test across each vacuum bottle
with the breaker in the open position in strict accordance with manufacturer’s published data.
11. Perform a dielectric withstand voltage test in accordance with manufacturer’s published data.
* Optional
Page 81
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.3 Circuit Breakers, Vacuum, Medium-Voltage (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Critical distance measurements such as contact gap shall be in accordance with the
manufacturer’s published data. (7.6.3.1.7)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.6.3.1.8.2)
5. Travel and velocity values shall be in accordance with manufacturer’s published data.
(7.6.3.1.12)
6. Operation counter shall advance one digit per close-open cycle. (7.6.3.1.13)
3. Insulation-resistance values of control wiring shall not be less than two megohms.
4. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. In the absence of manufacturer’s published data,
investigate values that deviate from adjacent poles or similar breakers by more than 50 percent
of the lowest value.
5. Minimum pickup voltage of the trip and close coils shall conform to the manufacturer’s
published data. In the absence of the manufacturer’s published data, refer to Table 100.20.
* Optional
Page 82
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.3 Circuit Breakers, Vacuum, Medium-Voltage (continued)
8. Power-factor or dissipation-factor values shall be compared to manufacturer’s published data.
In the absence of manufacturer’s published data the comparison shall be made to similar
breakers.
10. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the vacuum bottle integrity test, the test specimen is considered to have
passed the test.
11. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
13. Results of instrument transformer tests shall be in accordance with Section 7.10.
* Optional
Page 83
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.4 Circuit Breakers, SF6
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Verify that all maintenance devices such as special tools and gauges specified by the
manufacturer are available for servicing and operating the breaker.
*6. When provisions are made for sampling, remove a sample of SF6 gas and test in accordance
with Table 100.13. Do not break seal or distort “sealed-for-life” interrupters.
7. Inspect operating mechanism and/or hydraulic or pneumatic system and SF6 gas-insulated
system in accordance with manufacturer’s published data.
8. Test for SF6 gas leaks in accordance with manufacturer’s published data.
9. Verify correct operation of alarms and pressure-limit switches for pneumatic, hydraulic, and
SF6 gas pressure in accordance with manufacturer’s published data.
10. If recommended by manufacturer, slow close/open breaker and check for binding, friction,
contact alignment, and penetration. Verify that contact sequence is in accordance with
manufacturer’s published data. In the absence of manufacturer’s published data, refer to
ANSI/IEEE C37.04.
11. Perform all mechanical operation tests on the operating mechanism in accordance with the
manufacturer’s published data.
12. Inspect all bolted electrical connections for high resistance using one or more of the following
methods:
13. Verify the appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
* Optional
Page 84
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.4 Circuit Breakers, SF6 (continued)
15. Record as-found and as-left operation counter readings.
2. Electrical Tests
1. Perform resistance measurements through all bolted connections with a low-resistance
ohmmeter, if applicable, in accordance with Section 7.6.4.1.
2. Perform insulation-resistance tests in accordance with Table 100.1 from each pole-to-ground
with breaker closed and across open poles at each phase. For single-tank breakers, perform
insulation resistance tests in accordance with Table 100.1 from pole-to-pole.
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components or for control
devices that can not tolerate the voltage, follow manufacturer’s recommendation.
5. Perform minimum pickup voltage tests on trip and close coils in accordance with
manufacturer’s published data.
6. Verify correct operation of any auxiliary features such as electrical close and trip operation,
trip-free, and antipump function. Reset all trip logs and indicators.
8. Perform power-factor or dissipation-factor tests on each pole with the breaker open and on each
phase with the breaker closed.
*10. Perform a dielectric withstand voltage test in accordance with manufacturer’s published data.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. SF6 gas shall have values in accordance with Table 100.13. (7.6.4.1.6)
2. Results of the SF6 gas leak test shall confirm that no SF6 gas leak exists. (7.6.4.1.8)
* Optional
Page 85
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.4 Circuit Breakers, SF6 (continued)
3. Settings for alarm, pressure, and limit switches shall be in accordance with manufacturer’s
published data. (7.6.4.1.9)
5. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.6.4.1.12.2)
7. Circuit breaker travel and velocity values shall be in accordance with manufacturer’s published
data. (7.6.4.1.14)
8. Operations counter shall advance one digit per close-open cycle. (7.6.4.1.15)
3. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. In the absence of manufacturer’s published data,
investigate values that deviate from adjacent poles or similar breakers by more than 50 percent
of the lowest value.
4. Insulation-resistance values of control wiring shall not be less than two megohms.
5. Minimum pickup voltage of the trip and close coils shall conform to the manufacturer’s
published data. In the absence of the manufacturer’s published data, refer to Table 100.20.
7. Protective devices shall operate the breaker per the system design.
* Optional
Page 86
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.6.4 Circuit Breakers, SF6 (continued)
9. Power-factor or dissipation-factor and capacitance test values shall be within ten percent of
nameplate rating for bushings. Hot collar tests are evaluated on a milliampere/milliwatt loss
basis, and the results shall be compared to values of similar bushings.
10. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
12. Results of electrical tests on instrument transformers shall be in accordance with Section 7.10.
* Optional
Page 87
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.7 Circuit Switchers
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Verify both the circuit switcher and its operating mechanism mechanically operate in
accordance with the manufacturer’s published data.
6. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
9. Verify operation of isolating switch is in accordance with system design and manufacturer’s
published data.
10. Verify all interlocking systems operate and sequence per system design and manufacturer’s
published data.
11. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
2. Electrical Tests
1. Perform resistance measurements through all connections with a low-resistance ohmmeter, if
applicable, in accordance with Section 7.7.1.
* Optional
Page 88
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.7 Circuit Switchers (continued)
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
5. Perform minimum pickup voltage tests on trip and close coils in accordance with
manufacturer’s published data.
6. Verify correct operation of any auxiliary features such as electrical close and trip operation,
trip-free, and anti-pump function. Reset all trip logs and indicators.
9. Perform a dielectric withstand voltage test in accordance with the manufacturer’s published
data.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.7.1.6.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.7.1.6.2)
4. SF6 interrupters shall operate in accordance with manufacturer’s published data. (7.7.1.7)
6. Isolating switch shall operate in accordance with system and manufacturer’s design. (7.7.1.9)
7. Interlocking systems shall operate in accordance with system and manufacturer’s design.
(7.7.1.10)
8. Operation counter shall advance one digit per close-open cycle. (7.7.1.12)
* Optional
Page 89
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.7 Circuit Switchers (continued)
3.2 Test Values – Electrical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value.
2. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. In the absence of manufacturer’s published data,
investigate values that deviate from adjacent poles or similar breakers by more than 50 percent
of the lowest value.
4. Insulation-resistance values of control wiring shall not be less than two megohms.
5. Minimum pickup voltage of the trip and close coils shall conform to the manufacturer’s
published data. In the absence of the manufacturer’s published data, refer to Table 100.20.
7. Protective devices shall operate the circuit switcher in accordance with the system design.
9. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the circuit switcher is considered to have passed
the test.
* Optional
Page 90
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.8 Network Protectors, 600-Volt Class
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
7. Verify that maintenance devices are available for servicing and operating the network protector.
8. Verify that primary and secondary contact wipe and other dimensions vital to satisfactory
operation of the network protector are correct.
9. Perform mechanical operator and contact alignment tests on both the network protector and its
operating mechanism.
10. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
13. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
15. Perform a leak test on submersible enclosure in accordance with manufacturer’s published data.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.8.1.
* Optional
Page 91
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.8 Network Protectors, 600-Volt Class (continued)
2. Perform insulation-resistance tests for one minute on each pole, phase-to-phase and phase-to-
ground with network protector closed, and across each open pole. Apply voltage in accordance
with manufacturer’s published data. In the absence of manufacturer’s published data, use Table
100.1.
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
8. Verify that the motor can charge the closing mechanism at the minimum voltage specified by
the manufacturer.
9. Measure minimum pickup voltage of the trip actuator. Verify that the actuator resets correctly.
10. Calibrate the network protector relays in accordance with Section 7.9.
4. Verify the protector will close with voltage on the transformer side only.
5. Verify the protector will open when the source feeder breaker is opened.
12. Verify phase rotation, phasing, and synchronized operation as required by the application.
3. Test Values
3.1 Test Values – Visual and Mechanical
* Optional
Page 92
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.8 Network Protectors, 600-Volt Class (continued)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.8.1.10.2)
4. Operations counter shall advance one digit per close-open cycle. (7.8.1.14)
3. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. In the absence of manufacturer’s published data,
investigate values that deviate from adjacent poles or similar protectors by more than 50
percent of the lowest value.
4. Insulation-resistance values of control wiring shall not be less than two megohms.
6. Investigate fuse resistance values that deviate from each other by more than 15 percent.
7. Minimum pickup voltage of the motor control relay shall be in accordance with manufacturer’s
published data, but not more than 75 percent of rated control circuit voltage.
8. Minimum operating voltage of the motor on the closing mechanism shall not exceed 75 percent
of rated control circuit voltage.
9. Trip actuator minimum pickup voltage shall not exceed 7.5 percent of rated control circuit
voltage.
10. Results of network protector relay calibrations shall be in accordance with Section 7.9.
12. Phase rotation, phasing, and synchronizing shall be in accordance with system design
requirements.
* Optional
Page 93
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.9.1 Protective Relays, Electromechanical and Solid-State
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
2. Inspect relays and cases for physical damage. Remove shipping restraint material.
4. Relay Case
3. Clean cover glass. Inspect shorting hardware, connection paddles, and knife switches.
5. Relay
1. Inspect relay for foreign material, particularly in disk slots of the damping and
electromagnets.
3. Inspect spiral spring convolutions. Inspect disk and contacts for freedom of movement
and correct travel. Verify tightness of mounting hardware and connections. Burnish
contacts. Inspect bearings and pivots.
2. Electrical Tests
1. Perform an insulation-resistance test on each circuit-to-frame. Procedures for performing
insulation-resistance tests on solid-state relays shall be determined from the relay
manufacturer’s published data.
* Optional
Page 94
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.9.1 Protective Relays, Electromechanical and Solid-State (continued)
3. Functional Operation
1. 2/62 Timing Relay
2. 21 Distance Relay
3. Determine offset.
3. 24 Volts/Hertz Relay
3. Determine live line, live bus, dead line, and dead bus set points.
5. Verify dead bus/live line, dead line/live bus and dead bus/dead line control functions.
5. 27 Undervoltage Relay
3. Determine time delay at a second point on the timing curve for inverse time relays.
* Optional
Page 95
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.9.1 Protective Relays, Electromechanical and Solid-State (continued)
1. Determine minimum pickup at maximum torque angle.
5. Verify time delay at a second point on the timing curve for inverse time relays.
3. Determine offset.
2. Determine positive sequence voltage to open the normally closed contact (undervoltage
trip).
* Optional
Page 96
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.9.1 Protective Relays, Electromechanical and Solid-State (continued)
3. Verify negative sequence trip.
4. Determine time delay to close the normally open contact with sudden application of 120
percent of pickup.
5. Determine time delay to close the normally closed contact upon removal of voltage
when previously set to rated system voltage.
1. Determine pickup.
2. Determine dropout.
* Optional
Page 97
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.9.1 Protective Relays, Electromechanical and Solid-State (continued)
2. Determine time delay to close the contact with sudden application of 120 percent of
pickup.
1. Determine voltage difference to close the contacts with one source at rated voltage.
6. Determine overcurrent unit time delay at two points on the time current curve.
Page 98
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.9.1 Protective Relays, Electromechanical and Solid-State (continued)
22. 81 Frequency Relay
24. 87 Differential
3. Determine slope.
4. Control Verification
1. Functional tests
Verify that each of the relay contacts performs its intended function in the control scheme
including breaker trip tests, close inhibit tests, 86 lockout tests, and alarm functions. Refer to
Section 8.0.
2. In-service monitoring
After the equipment is initially energized, measure magnitude and phase angle of all inputs and
compare to expected values.
5. Test Values
1. When not otherwise specified, use manufacturer’s recommended tolerances.
* Optional
Page 99
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.9.1 Protective Relays, Electromechanical and Solid-State (continued)
2. When critical test points are specified, the relay shall be calibrated to those points even though
other test points may be out of tolerance.
* Optional
Page 100
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.9.2 Protective Relays, Microprocessor-Based
1. Visual and Mechanical Inspection
1. Record model number, style number, serial number, firmware revision, software revision, and
rated control voltage.
4. Clean the front panel and remove foreign material from the case.
8. Download settings from the relay. Print a copy of the settings for the report and compare the
settings to those specified in the coordination study.
2. Electrical Tests
1. Perform insulation-resistance tests from each circuit to the grounded frame in accordance with
manufacturer’s published data.
2. Apply voltage or current to all analog inputs and verify correct registration of the relay meter
functions.
3. Functional Operation
Check functional operation of each element used in the protection scheme as described for
electromechanical and solid-state relays in 7.9.1.3.
4. Control Verification
1. Functional tests
2. Check all output contacts or SCRs, preferably by operating the controlled device such as
circuit breaker, auxiliary relay, or alarm.
4. For pilot schemes, perform a loop-back test to check the receive and transmit
communication circuits.
* Optional
Page 101
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.9.2 Protective Relays, Microprocessor-Based (continued)
5. For pilot schemes, perform satellite synchronized end-to-end tests.
6. For pilot schemes with direct transfer trip (DTT), perform transmit and received DTT at
each terminal.
7. Upon completion of testing, reset all min/max recorders, communications statistics, fault
counters, sequence of events recorder, and all event records.
2. In-service monitoring
After the equipment is initially energized, measure magnitude and phase angle of all inputs and
compare to expected values.
* Optional
Page 102
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.10 Instrument Transformers
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Verify that adequate clearances exist between primary and secondary circuit wiring.
6. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
7. Verify that all required grounding and shorting connections provide contact.
9. Verify correct primary and secondary fuse sizes for voltage transformers.
10. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
2. Perform insulation-resistance test of each current transformer and its secondary wiring with
respect to ground at 1000 volts dc for one minute. For units with solid-state components that
cannot tolerate the applied voltage, follow manufacturer’s recommendations.
3. Perform a polarity test of each current transformer in accordance with ANSI/IEEE C57.13.1.
4. Perform a ratio-verification test using the voltage or current method in accordance with
ANSI/IEEE C57.13.1.
5. Perform an excitation test on transformers used for relaying applications in accordance with
ANSI/IEEE C57.13.1.
* Optional
Page 103
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.10 Instrument Transformers (continued)
6. Measure current circuit burdens at transformer terminals in accordance with ANSI/IEEE
C57.13.1.
7. When applicable, perform insulation-resistance tests on the primary winding with the secondary
grounded. Test voltages shall be in accordance with Table 100.5.
8. When applicable, perform dielectric withstand tests on the primary winding with the secondary
grounded. Test voltages shall be in accordance with Table 100.9.
10. Verify that current transformer secondary circuits are grounded and have only one grounding
point in accordance with ANSI/IEEE C57.13.3. That grounding point should be located as
specified by the engineer in the project drawings.
3. Perform a polarity test on each transformer to verify the polarity marks or H1- X1 relationship
as applicable.
*6. Perform a dielectric withstand test on the primary windings with the secondary windings
connected to ground. The dielectric voltage shall be in accordance with Table 100.9. The test
voltage shall be applied for one minute.
8. Verify that voltage transformer secondary circuits are grounded and have only one grounding
point in accordance with ANSI/IEEE C57.13.3. The grounding point should be located as
specified by the engineer in the project drawings.
* Optional
Page 104
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.10 Instrument Transformers (continued)
2.3 Electrical Tests - Coupling-Capacitor Voltage Transformers
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.10.1.
3. Perform a polarity test on each transformer to verify the polarity marking. See ANSI/IEEE
C93.1 for standard polarity marking.
*6. Perform a dielectric withstand test on the primary windings with the secondary windings
connected to ground. The dielectric voltage shall be in accordance with Table 100.9. The test
voltage shall be applied for one minute.
9. Verify that the coupling-capacitor voltage transformer circuits are grounded and have only one
grounding point in accordance with ANSI/IEEE C57.13.3. That grounding point should be
located as specified by the engineer in the project drawings.
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.10.1.6.2)
* Optional
Page 105
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.10 Instrument Transformers (continued)
3.2.1 Test Values – Current Transformers – Electrical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value.
2. Insulation-resistance values of instrument transformers shall not be less than values shown in
Table 100.5.
5. Excitation results shall match the curve supplied by the manufacturer or be in accordance with
ANSI C57.13.1.
8. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the primary winding is considered to have
passed the test.
10. Test results shall indicate that the circuits have only one grounding point.
Page 106
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.10 Instrument Transformers (continued)
6. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the primary windings are considered to have
passed the test.
8. Test results shall indicate that the circuits are grounded at only one point.
2. Insulation-resistance values of instrument transformers shall not be less than values shown in
Table 100.5.
6. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
9. Test results shall indicate that the circuits are grounded at only one point.
* Optional
Page 107
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.11.1 Metering Devices
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
3. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
4. Inspect cover gasket, cover glass, condition of spiral spring, disk clearance, contacts, and case-
shorting contacts, as applicable.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.11.1.1.
5. Verify that current transformer and voltage transformer secondary circuits are intact.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.11.1.1.3.1)
2. Bolt-torque levels should be in accordance with manufacturer’s published data. In the absence
of manufacturer’s published data, use Table 100.12. (7.11.1.1.3.2)
* Optional
Page 108
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.11.1 Metering Devices (continued)
3. Results of the thermographic survey shall be in accordance with Section 9. (7.11.1.3.3)
5. Test results shall confirm the integrity of the secondary circuits of current and voltage
transformers.
* Optional
Page 109
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.11.2 Metering Devices, Microprocessor-Based
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Record model number, serial number, firmware revision, software revision, and rated control
voltage.
7. Record passwords.
9. Verify unit is connected in accordance with manufacturer’s instructions and project drawings.
10. Set all required parameters including instrument transformer ratios, system type, frequency,
power demand methods/intervals, and communications requirements.
2. Electrical Tests
1. Apply voltage or current as appropriate to each analog input and verify correct measurement
and indication.
2. Confirm correct operation and setting of each auxiliary input/output feature including
mechanical relay, digital, and analog.
3. After initial system energization, confirm measurements and indications are consistent with
loads present.
* Optional
Page 110
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.11.2 Metering Devices, Microprocessor-Based (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Nameplate data shall be per drawings and specifications. (7.11.2.1.1)
3. Display and indicating devices shall operate per manufacturer’s published data. (7.11.2.1.6)
2. All auxiliary input/output features shall operate per settings and manufacturer’s published data.
* Optional
Page 111
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.1.1 Regulating Apparatus, Voltage, Step Voltage Regulators
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Verify removal of any shipping bracing and vent plugs after final placement.
8. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
9. Verify correct operation of motor and drive train and automatic motor cutoff at maximum lower
and raise positions.
12. Perform specific inspections and mechanical tests as recommended by the manufacturer.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.12.1.1.1.
* Optional
Page 112
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.1.1 Regulating Apparatus, Voltage, Step Voltage Regulators (continued)
3. Perform insulation power-factor or dissipation-factor tests on windings in accordance with test
equipment manufacturer’s published data.
5. Measure winding resistance of source windings in the neutral position. Measure the resistance
of all taps on load windings.
*7. If the regulator has a separate tap-changer compartment, test for the presence of oxygen in the
gas blanket in the main tank.
8. Perform turns-ratio test on each voltage step position. Verify that the indicator correctly
identifies all tap positions.
10. Verify operation and accuracy of bandwidth, time delay, voltage, and line-drop compensation
functions of regulator control device.
11. If regulator has a separate tap-changer compartment, sample insulating liquid in the main tank
in accordance with ASTM D 3613 and perform dissolved-gas analysis in accordance with
ANSI/IEEE C57.104 or ASTM D 3612.
12. Remove a sample of insulating liquid from the main tank or common tank in accordance with
ASTM D 923. Sample shall be tested in accordance with the referenced standard.
* Optional
Page 113
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.1.1 Regulating Apparatus, Voltage, Step Voltage Regulators (continued)
*8. PPM water: ASTM D 1533
Required when the regulator voltage is 25 kV or higher and on all silicone-filled units.
13. Remove a sample of insulating liquid from the tap-changer tank in accordance with
ASTM D 923. Sample shall be tested in accordance with the referenced standard.
*14. Remove a sample of insulating liquid from the tap-changer compartment or common tank in
accordance with ASTM D 3613 and perform dissolved gas analysis in accordance with
ANSI/IEEE C57.104 or ASTM D 3612.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Auxiliary devices should operate in accordance with system design. (7.12.1.1.1.7)
3. Bolt-torque levels should be in accordance with manufacturer’s published data. In the absence
of manufacturer’s published data, use Table 100.12. (7.12.1.1.1.8.2)
5. Motor, drive train, and automatic cutoff should operate in accordance with manufacturer’s
design. (7.12.1.1.1.9)
6. Liquid level in tanks and bushings should be within indicated tolerances. (7.12.1.1.1.10)
7. The operation counter shall move incrementally for each operation performed. (7.12.1.1.1.13)
* Optional
Page 114
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.1.1 Regulating Apparatus, Voltage, Step Voltage Regulators (continued)
2. Insulation-resistance values shall be in accordance with manufacturer’s published data. In the
absence of manufacturer’s published data, use Table 100.5. Values of insulation resistance less
than this table or manufacturer’s recommendations should be investigated. Resistance values
shall be temperature corrected in accordance with Table 100.14. The polarization index shall be
compared to manufacturer’s factory test results. If manufacturer’s test results are not available
the polarization index value shall not be less than 1.0.
5. Consult manufacturer if winding-resistance values vary by more than one percent from test
results of adjacent windings.
8. Turns-ratio test results shall maintain a normal deviation between each voltage step and shall
not deviate more than one-half percent from the calculated voltage ratio.
10. Operation and accuracy of bandwidth, time-delay, voltage, and live drop compensation
functions shall be as specified.
11. Results of dissolved-gas analysis of insulating liquid on the main tank of regulators having a
separate tap-changer compartment shall be evaluated in accordance with ANSI/IEEE C57.104
or ASTM D 3612
12. Results of insulating liquid tests on the main tank of regulators having a separate tap-changer
compartment or the common tank of single tank voltage regulators shall be in accordance with
Table 100.4.
13. Results of insulating liquid tests on the tap-changer tank of regulators having a separate tap-
changer compartment shall be in accordance with Table 100.4.
14. Results of dissolved gas analysis shall be evaluated in accordance with ANSI/IEEE C57.104 or
ASTM D 3612.
.
* Optional
Page 115
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.1.1 Regulating Apparatus, Voltage, Step Voltage Regulators (continued)
15. Heaters shall be operational.
* Optional
Page 116
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.1.2 Regulating Apparatus, Voltage, Induction Regulators
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Verify removal of any shipping bracing and vent plugs after final placement.
8. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
9. Verify correct operation of motor and drive train and automatic motor cutoff at maximum lower
and raise positions.
11. Verify appropriate liquid level in all tanks and bushings, if applicable.
12. Perform specific inspections and mechanical tests as recommended by the manufacturer.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.12.1.2.1.
* Optional
Page 117
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.1.2 Regulating Apparatus, Voltage, Induction Regulators (continued)
4. Perform power-factor or dissipation-factor tests on each bushing equipped with a power-factor/
capacitance tap. In the absence of a power-factor/ capacitance tap, perform hot-collar tests.
These tests shall be in accordance with the test equipment manufacturer’s published data.
8. Sample insulating liquid, if applicable, in accordance with ASTM D 923. Sample shall be
tested in accordance with the referenced standard.
*9. Remove a sample of insulating liquid, if applicable, in accordance with ASTM D 3613 and
perform dissolved gas analysis in accordance with ASTM D 3612 or ANSI.IEEE C57.104.
*10. Test for the presence of oxygen in the gas blanket of liquid-filled regulators.
* Optional
Page 118
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.1.2 Regulating Apparatus, Voltage, Induction Regulators (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Auxiliary devices shall operate in accordance with system design. (7.12.1.2.1.7)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.12.1.2.1.8.2)
5. Motor, drive train, and automatic cutoff shall operate in accordance with manufacturer’s design
intent. Automatic motor cutoff should operate at maximum lower and maximum raise positions.
(7.12.1.2.1.9)
6. Liquid level in tanks and bushings shall be within indicated tolerances. (7.12.1.2.1.11)
5. The regulation shall be a linear ratio throughout the range between the maximum raise and the
maximum lower positions.
* Optional
Page 119
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.1.2 Regulating Apparatus, Voltage, Induction Regulators (continued)
7. Consult the manufacturer if winding-resistance values vary by more than one percent from
measurements of adjacent windings.
* Optional
Page 120
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.2 Regulating Apparatus, Current
— RESERVED —
* Optional
Page 121
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.3 Regulating Apparatus, Load Tap-Changers
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
7. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
9. Verify correct operation of motor and drive train and automatic motor cutoff at maximum lower
and maximum raise positions.
11. Perform specific inspections and mechanical tests as recommended by the manufacturer.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.12.3.1.
2. Perform insulation-resistance tests in any off-neutral position in accordance with Section 7.2.2.
* Optional
Page 122
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.3 Regulating Apparatus, Load Tap-Changers (continued)
5. Perform special tests and adjustments as recommended by the manufacturer.
7. Remove a sample of insulating liquid in accordance with ASTM D 923. The sample shall be
tested for the following in accordance with the referenced standard.
8. Remove a sample of insulating liquid in accordance with ASTM D 3613 and perform dissolved
gas analysis in accordance with ANSI/IEEE C57.104 or ASTM D 3612.
*9. Perform vacuum bottle integrity tests (dielectric withstand voltage) across each vacuum bottle
with the contacts in the open position in strict accordance with manufacturer’s published data.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.12.3.1.7.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.12.3.1.7.2)
5. Motor, drive train, and automatic cutoff shall operate in accordance with manufacturer’s design
intent and automatic motor cutoff shall operate at maximum lower and maximum raise
positions.(7.12.3.1.9)
7. Operation counter shall have had an incremental change in accordance with tap-changer
operation. (7.12.3.1.13)
* Optional
Page 123
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.12.3 Regulating Apparatus, Load Tap-Changers (continued)
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value.
4. Consult the manufacturer if winding-resistance values vary by more than one percent from
measurements of adjacent windings.
5. Special tests and adjustments shall be in accordance with manufacturer’s published data.
6. Turns-ratio test results shall maintain a normal deviation between each voltage step and shall
not deviate more than one-half percent from the calculated voltage ratio.
9. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
* Optional
Page 124
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.13 Grounding Systems
1. Visual and Mechanical Inspection
1. Verify ground system is in compliance with drawings, specifications, and NFPA 70 National
Electrical Code Article 250.
3. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
4. Inspect anchorage.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with section 7.13.1.
3. Perform point-to-point tests to determine the resistance between the main grounding system and
all major electrical equipment frames, system neutral, and derived neutral points.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Grounding system electrical and mechanical connections shall be free of corrosion. (7.13.1.2)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.13.1.3.2)
* Optional
Page 125
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.13 Grounding Systems (continued)
2. The resistance between the main grounding electrode and ground shall be no greater than five
ohms for large commercial or industrial systems and 1.0 ohm or less for generating or
transmission station grounds unless otherwise specified by the owner. (Reference ANSI/IEEE
Standard 142)
* Optional
Page 126
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.14 Ground-Fault Protection Systems, Low-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
2. Inspect the components for damage and errors in polarity or conductor routing.
1. Verify that ground connection is made on the source side of the neutral disconnect link
and on the source side of any ground fault sensor.
2. Verify that the neutral sensors are connected with correct polarity on both primary and
secondary.
3. Verify that all phase conductors and the neutral pass through the sensor in the same
direction for zero sequence systems.
4. Verify that grounding conductors do not pass through the zero sequence sensors.
4. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
6. Verify that the control power transformer has adequate capacity for the system.
7. Set pickup and time-delay settings in accordance with the settings provided in the owner’s
specifications. Record appropriate operation and test sequences as required by NFPA 70,
National Electrical Code, Article 230.95.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.14.1.
2. Measure the system neutral-to-ground insulation resistance with the neutral disconnect link
temporarily removed. Replace the neutral disconnect link after testing.
* Optional
Page 127
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.14 Ground-Fault Protection Systems, Low-Voltage (continued)
*3. Perform insulation resistance test on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components or control
devices that cannot tolerate the applied voltage, follow manufacturer’s recommendation.
4. Perform ground fault protective device pickup tests using primary injection.
5. For summation type systems utilizing phase and neutral current transformers, verify correct
polarities by applying current to each phase-neutral current transformer pair. This test also
applies to molded-case breakers utilizing an external neutral current transformer.
6. Measure time delay of the ground fault protective device at a value equal to or greater than 150
percent of the pickup value.
7. Verify reduced control voltage tripping capability is 55 percent for ac systems and 80 percent
for dc systems.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.14.1.4.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.14.1.4.2)
3. Insulation-resistance values of control wiring shall not be less than two megohms.
4. Results of pickup test shall be greater than 90 percent of the ground fault protection device
pickup setting and less than 1200 amperes or 125 percent of the pickup setting, whichever is
smaller.
* Optional
Page 128
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.14 Ground-Fault Protection Systems, Low-Voltage (continued)
5. The ground fault protective device shall operate when current direction is the same relative to
polarity marks in the two current transformers. The ground fault protective device shall not
operate when current direction is opposite relative to polarity marks in the two current
transformers.
6. Relay timing shall be in accordance with manufacturer’s published data but must be no longer
than one second at 3000 amperes in accordance with ANSI/NFPA 70, National Electrical
Code, Article 230.95.
7. The circuit interrupting device shall operate when control voltage is 55 percent of nominal
voltage for ac circuits and 80 percent of nominal voltage for dc circuits.
8. Results of zone-blocking tests shall be in accordance with manufacturer’s published data and
design specifications.
* Optional
Page 129
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.1 Rotating Machinery, AC Induction Motors and Generators
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Inspect air baffles, filter media, cooling fans, slip rings, brushes, and brush rigging.
5. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
6. Perform special tests such as air-gap spacing and machine alignment, if applicable.
3. Perform dc dielectric withstand voltage tests on machines rated at 2300 volts and greater in
accordance with ANSI/IEEE Standard 95.
4. Perform phase-to-phase stator resistance test on machines 2300 volts and greater.
* Optional
Page 130
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.1 Rotating Machinery, AC Induction Motors and Generators (continued)
*6. Perform power-factor tip-up tests.
9. Test surge protection devices in accordance with Section 7.19 and Section 7.20.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Inspection (7.15.1.4)
1. Air baffles shall be clean and installed in accordance with manufacturer’s published
data.
2. Filter media shall be clean and installed in accordance with manufacturer’s published
data.
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.15.1.1.5.2)
* Optional
Page 131
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.1 Rotating Machinery, AC Induction Motors and Generators (continued)
5. Air-gap spacing and machine alignment shall be in accordance with manufacturer’s published
data. (7.15.1.1.6)
2. The dielectric absorption ratio or polarization index shall not be less than 1.0. The
recommended minimum insulation resistance (IR 1 min) test results in megohms shall be
corrected to 40° C and read as follows:
1. IR 1 min = kV + 1 for most windings made before 1970, all field windings, and others not
described in 2.2 and 2.3.
2. IR 1 min = 100 megohms for most dc armature and ac windings built after 1970 (form-
wound coils).
3. IR 1 min = 5 megohms for most machines and random-wound stator coils and form-
wound coils rated below 1 kV.
NOTE: Dielectric withstand voltage and surge comparison tests shall not be performed
on machines having values lower than those indicated above.
3. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
4. Investigate phase-to-phase stator resistance values that deviate by more than five percent.
7. If no evidence of distress, insulation failure, or lack of waveform nesting is observed by the end
of the total time of voltage application during the surge comparison test, the test specimen is
considered to have passed the test.
Page 132
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.1 Rotating Machinery, AC Induction Motors and Generators (continued)
9. Test results of surge protection devices shall be in accordance with Section 7.19 and Section
7.20.
10. Test results of motor starter equipment shall be in accordance with Section 7.16.
11. RTD circuits shall conform to design intent and machine protection device manufacturer’s
published data.
13. Vibration amplitudes of the uncoupled and unloaded machine shall not exceed values shown in
Table 100.10. If values exceed those in Table 100.10, perform complete vibration analysis.
* Optional
Page 133
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.2 Rotating Machinery, Synchronous Motors and Generators
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Inspect air baffles, filter media, cooling fans, slip rings, brushes, and brush rigging.
5. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.15.2.1.
3. Perform dc dielectric withstand voltage tests on machines rated at 2300 volts and greater in
accordance with ANSI/IEEE Standard 95.
4. Perform phase-to-phase stator resistance test on machines 2300 volts and greater.
* Optional
Page 134
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.2 Rotating Machinery, Synchronous Motors and Generators (continued)
*6. Perform power-factor tip-up tests.
9. Test surge protection devices in accordance with Section 7.19 and Section 7.20.
14. Perform insulation-resistance tests on the main rotating field winding, the exciter-field winding,
and the exciter-armature winding in accordance with ANSI/IEEE Standard 43.
*16. Perform a high-potential test on the excitation system in accordance with ANSI/IEEE Standard
421.3.
*18. Perform front-to-back resistance tests on diodes and gating tests of silicon-controlled rectifiers
for field application semiconductors.
19. Prior to re-energizing, apply voltage to the exciter supply and adjust exciter-field current to
nameplate value.
20. Verify that the field application timer and the enable timer for the power-factor relay have been
tested and set to the motor drive manufacturer’s recommended values.
*21. Record stator current, stator voltage, and field current for the complete acceleration period
including stabilization time for a normally loaded starting condition. From the recording
determine the following information:
* Optional
Page 135
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.2 Rotating Machinery, Synchronous Motors and Generators (continued)
4. Locked-rotor current.
*22. Plot a V-curve of stator current versus excitation current at approximately 50 percent load to
check correct exciter operation.
*23. If the range of exciter adjustment and machine loading permit, reduce excitation to cause power
factor to fall below the trip value of the power-factor relay. Verify relay operation.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Inspection (7.15.2.1.4)
1. Air baffles shall be clean and installed in accordance with manufacturer’s published
data.
2. Filter media shall be clean and installed in accordance with manufacturer’s published
data.
2. Compare bolted connection resistance values to values of similar connections. Investigate any
values that deviate from similar bolted connections by more than 50 percent of the lowest
value. (7.15.2.1.5.1)
3. Bolt-torque levels should be in accordance with manufacturer’s published data. In the absence
of manufacturer’s published data, use Table 100.12. (7.15.2.1.5.2)
Page 136
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.2 Rotating Machinery, Synchronous Motors and Generators (continued)
5. Air-gap spacing and machine alignment shall be in accordance with manufacturer’s published
data. (7.15.2.1.6)
2. The dielectric absorption ratio or polarization index shall not be less than 1.0. The
recommended minimum insulation resistance (IR 1 min) test results in megohms shall be
corrected to 40° C and read as follows:
1. IR 1 min = kV + 1 for most windings made before 1970, all field windings, and others not
described in 2.2 and 2.3.
2. IR 1 min = 100 megohms for most dc armature and ac windings built after 1970 (form-
wound coils).
3. IR 1 min = 5 megohms for most machines and random-wound stator coils and form-
wound coils rated below 1 kV.
NOTE: Dielectric withstand voltage and surge comparison tests shall not be performed
on machines having values lower than those indicated above.
3. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
4. Investigate phase-to-phase stator resistance values that deviate by more than five percent.
7. If no evidence of distress, insulation failure, or lack of waveform nesting is observed by the end
of the total time of voltage application during the surge comparison test, the test specimen is
considered to have passed the test.
Page 137
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.2 Rotating Machinery, Synchronous Motors and Generators (continued)
9. Test results of surge protection devices shall be in accordance with Section 7.19 and Section
7.20.
10. Test results of motor starter equipment shall be in accordance with Section 7.16.
11. RTD circuits shall be in accordance with system design intent and machine protection device
manufacturer’s published data.
13. Vibration amplitudes of the uncoupled and unloaded machine shall not exceed values shown in
Table 100.10. If values exceed those in Table 100.10, perform complete vibration analysis.
14. The recommended minimum insulation resistance (IR1 min) test results in megohms shall be
corrected to 40° C and read as follows:
1. IR 1 min = kV + 1 for most windings made before 1970, all field windings, and others not
described in 2.2 and 2.3.
2. IR 1 min = 100 megohms for most dc armature and ac windings built after 1970 (form-
wound coils).
3. IR 1 min = 5 megohms for most machines and random-wound stator coils and form-
wound coils rated below 1 kV.
NOTE: Dielectric withstand voltage, high-potential, and surge comparison tests shall
not be performed on machines having values lower than those indicated above.
15. The pole-pole AC voltage drop shall not exceed 10 percent variance between poles.
16. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the winding is considered to have passed the
test.
17. The measured resistance values of motor-field windings, exciter-stator windings, exciter-rotor
windings, and field-discharge resistors shall be compared to manufacturer’s published data. In
the absence of manufacturer’s published data, the comparison shall be made to similar
machines.
18. Resistance test results of diodes and gating tests of silicon-controlled rectifiers shall be in
accordance with industry standards and system design requirements.
19. Exciter power supply shall allow exciter-field current to be adjusted to nameplate value.
* Optional
Page 138
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.2 Rotating Machinery, Synchronous Motors and Generators (continued)
20. Application timer and enable timer for power-factor relay test results shall comply with
manufacturer’s recommended values.
23. When reduced excitation falls below trip value for the power-factor relay, the relay shall
operate.
* Optional
Page 139
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.3 Rotating Machinery, DC Motors and Generators
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
4. Inspect air baffles, field media, cooling fans, brushes, and brush rigging.
5. Inspect bolted electrical connections for high resistance using one of the following methods:
7. Perform special tests such as air-gap spacing and machine alignment, if applicable.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.15.3.1.
2. Perform insulation-resistance tests on all windings in accordance with ANSI/IEEE Standard 43.
5. Measure armature running current and field current or voltage. Compare to nameplate.
7. Verify that all protective devices are in accordance with Section 7.16.
* Optional
Page 140
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.3 Rotating Machinery, DC Motors and Generators (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Inspection (7.15.3.1.4)
1. Air baffles shall be clean and installed in accordance with manufacturer’s published
data.
2. Filter media shall be clean and installed in accordance with manufacturer’s published
data.
2. Compare bolted connection resistance values to values of similar connections. Investigate any
values that deviate from similar bolted connections by more than 50 percent of the lowest
value. (7.15.3.1.5.1)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.15.3.1.5.2)
6. Air-gap spacing and machine alignment shall be in accordance with manufacturer’s published
data. (7.15.3.1.7)
* Optional
Page 141
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.15.3 Rotating Machinery, DC Motors and Generators (continued)
2. The dielectric absorption ratio or polarization index shall not be less than 1.0. The
recommended minimum insulation resistance (IR1 min) test results in megohms shall be
corrected to 40° C and read as follows:
1. IR 1 min = kV + 1 for most windings made before 1970, all field windings, and others not
described in 2.2 and 2.3.
2. IR 1 min = 100 megohms for most dc armature and ac windings built after 1970 (form-
wound coils).
3. IR 1 min = 5 megohms for most machines and random-wound stator coils and form-
wound coils rated below 1 kV.
NOTE: Dielectric withstand voltage and surge comparison tests shall not be performed
on machines having values lower than those indicated above.
3. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the winding is considered to have passed the
test.
4. The pole-to-pole voltage drop shall not exceed five percent variance between poles.
5. Measured running current and field current or voltage shall be comparable to nameplate data.
6. Vibration amplitudes of the uncoupled and unloaded machine shall not exceed values shown in
Table 100.10. If values exceed those in Table 100.10, perform complete vibration analysis.
7. Test results of motor starter equipment shall be in accordance with Section 7.16.
* Optional
Page 142
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.16.1.1 Motor Control, Motor Starters, Low-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Inspect contactors.
2. Verify contact gap, wipe, alignment, and pressure are in accordance with manufacturer’s
published data.
7. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
8. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.16.1.1.1.
* Optional
Page 143
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.16.1.1 Motor Control, Motor Starters, Low-Voltage (continued)
*3. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
4. Test motor protection devices in accordance with manufacturer’s published data. In the
absence of manufacturer’s published data, use Section 7.9.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.16.1.1.1.7.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.16.1.1.1.7.2)
3. Insulation-resistance values of control wiring shall not be less than two megohms.
4. Motor protection parameters shall be in accordance with manufacturer’s published data. In the
absence of manufacturer’s published data, use Section 7.9.
* Optional
Page 144
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.16.1.2 Motor Control, Motor Starters, Medium-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
6. Test all electrical and mechanical interlock systems for correct operation and sequencing.
8. Exercise all active components and confirm correct operation of all indicating devices.
9. Inspect contactors.
2. Verify contact gap, wipe, alignment, and pressure are in accordance with manufacturer’s
published data.
10. Verify overload protection rating is correct for its application. Set adjustable or programmable
devices according to the protective device coordination study.
11. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
* Optional
Page 145
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.16.1.2 Motor Control, Motor Starters, Medium-Voltage (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.16.1.2.1.
*3. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
*4. Perform a dielectric withstand voltage test in accordance with manufacturer’s published data. In
the absence of manufacturer’s published data, use Table 100.9.
5. Perform vacuum bottle integrity test (dielectric withstand voltage), if applicable, across each
vacuum bottle with the contacts in the open position in strict accordance with manufacturer’s
published data. Do not exceed maximum voltage stipulated for this test.
9. Energize contactor using an auxiliary source. Adjust armature to minimize operating vibration
where applicable.
13. Test motor protection devices in accordance with manufacturer’s published data. In the absence
of manufacturer’s published data, use Section 7.9.
* Optional
Page 146
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.16.1.2 Motor Control, Motor Starters, Medium-Voltage (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.16.1.2.1.5.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.16.1.2.1.5.2)
4. Electrical and mechanical interlocks shall operate in accordance with system design.
(7.16.1.2.1.6)
5. Barrier and shutter installation and operation shall be in accordance with manufacturer’s design.
(7.16.1.2.1.7)
3. Insulation-resistance values of control wiring shall not be less than two megohms.
4. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
5. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the vacuum bottle integrity test, the vacuum bottle is considered to have
passed the test.
6. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values which deviate from those of similar connections by more than 50
percent of the lowest value.
7. Resistance values of blowout coils shall be in accordance with manufacturer’s published data.
* Optional
Page 147
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.16.1.2 Motor Control, Motor Starters, Medium-Voltage (continued)
8. Resistance values shall not deviate by more than 15 percent between identical fuses.
10. Control power transformer rest results shall be in accordance with Section 7.1.2.8.
11. Starting transformer test results shall be in accordance with Section 7.2.1.
12. Starting reactor test results shall be in accordance with Section 7.20.3.
13. Motor protection parameters shall be in accordance with manufacturer’s published data.
14. System function test results shall be in accordance with manufacturer’s published data and
system design.
* Optional
Page 148
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.16.2.1 Motor Control, Motor Control Centers, Low-Voltage
1. Refer to Section 7.1 for appropriate inspections and tests of the motor control center bus.
2. Refer to Section 7.5.1.2 for appropriate inspections and tests of the motor control center
switches.
3. Refer to Section 7.6 for appropriate inspections and tests of the motor control center circuit
breakers.
4. Refer to Section 7.16.1.2 for appropriate inspections and tests of the motor control center
starters.
* Optional
Page 149
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.16.2.2 Motor Control, Motor Control Centers, Medium-Voltage
1. Refer to Section 7.1 for appropriate inspections and tests of the motor control center bus.
2. Refer to Section 7.5.1.1 for appropriate inspections and tests of the motor control center
switches.
3. Refer to Section 7.6.1.1 for appropriate inspections and tests of the motor control center circuit
breakers.
4. Refer to Section 7.16.1.1 for appropriate inspections and tests of the motor control center
starters.
* Optional
Page 150
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.17 Adjustable Speed Drive Systems
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Ensure vent path openings are free from debris and that heat transfer surfaces are clean.
6. Verify correct connections of circuit boards, wiring, disconnects, and ribbon cables.
2. If drive is used to operate multiple motors, verify individual overload element ratings are
correct for their application.
3. Apply minimum and maximum speed setpoints. Verify setpoints are within limitations
of the load coupled to the motor
8. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.17.1.
2. Test the motor overload relay elements by injecting primary current through the overload
circuit and monitoring trip time of the overload element.
3. Test input circuit breaker by primary injection in accordance with Section 7.6.
* Optional
Page 151
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.17 Adjustable Speed Drive Systems (continued)
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
5. Test for the following parameters in accordance with relay calibration procedures outlined in
Section 7.9 or as recommended by the manufacturer:
7. Perform startup of drive in accordance with manufacturer’s published data. Calibrate drive to
the system’s minimum and maximum speed control signals.
1. Slowly vary drive speed between minimum and maximum. Observe motor and load for
unusual noise or vibration.
2. Verify operation of drive from remote start/stop and speed control signals.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.17.1.8.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.17.1.8.2)
* Optional
Page 152
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.17 Adjustable Speed Drive Systems (continued)
3. Results of the thermographic survey shall be in accordance with Section 9. (7.17.1.8.3)
2. Overload test trip times at 300 percent of overload element rating shall be in accordance with
manufacturer’s published time-current curve.
3. Input circuit breaker test results shall be in accordance with Section 7.6.
4. Insulation-resistance values of control wiring shall not be less than two megohms.
* Optional
Page 153
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.1.1 Direct-Current Systems, Batteries, Flooded Lead-Acid
1. Visual and Mechanical Inspection
1. Verify that batteries are adequately located.
6. Verify adequacy of battery support racks, mounting, anchorage, alignment, grounding and
clearances.
7. Verify electrolyte level. Measure electrolyte specific gravity and temperature levels.
12. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through all bolted connections with a low-resistance
ohmmeter, if applicable, in accordance with Section 7.18.1.1.1.
2. Measure charger float and equalizing voltage levels. Adjust to battery manufacturer’s
recommended settings.
4. Measure each cell voltage and total battery voltage with charger energized and in float mode of
operation.
* Optional
Page 154
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.1.1 Direct-Current Systems, Batteries, Flooded Lead-Acid (continued)
5. Measure intercell connection resistances.
7. Perform a load test in accordance with manufacturer’s published data or ANSI/IEEE 450.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Electrolyte level and specific gravity shall be within normal limits. (7.18.1.1.1.7)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.18.1.1.1.12.2)
2. Charger float and equalize voltage levels shall be in accordance with battery manufacturer’s
published data.
3. The results of charger functions and alarms shall be in accordance with manufacturer’s
published data.
4. Cell voltages shall be within 0.05 volt of each other or in accordance with manufacturer’s
published data.
6. Cell internal ohmic values (resistance, impedance, or conductance) shall not vary by more than
25 percent between identical cells that are in a fully charged state.
7. Results of load tests shall be in accordance with manufacturer’s published data or ANSI/IEEE
450.
* Optional
Page 155
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.1.1 Direct-Current Systems, Batteries, Flooded Lead-Acid (continued)
8. Voltage measured from positive-to-ground shall be equal in magnitude to the voltage measured
from negative-to-ground.
* Optional
Page 156
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.1.2 Direct-Current Systems, Batteries, Vented Nickel-Cadmium
1. Visual and Mechanical Inspection
1. Verify that batteries are adequately located.
10. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through all bolted connections with a low-resistance
ohmmeter, if applicable, in accordance with Section 7.18.1.2.1.
2. Measure charger float and equalizing voltage levels. Adjust to battery manufacturer’s
recommended settings.
4. Measure each cell voltage and total battery voltage with charger energized and in float mode of
operation.
* Optional
Page 157
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.1.2 Direct-Current Systems, Batteries, Vented Nickel-Cadmium (continued)
6. Perform internal ohmic measurement tests.
7. Perform a load test in accordance with manufacturer’s published data or ANSI/IEEE 1106.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Electrolyte level shall be within normal limits. (7.18.1.2.1.7)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.18.1.2.1.10.2)
2. Charger float and equalize voltage levels shall be in accordance with battery manufacturer’s
published data.
3. The results of charger functions and alarms shall be in accordance with manufacturer’s
published data.
4. Cell voltages shall be within 0.05 volt of each other or in accordance with manufacturer’s
published data.
6. Cell internal ohmic values (resistance, impedance, or conductance) shall not vary by more than
25 percent between identical cells that are in a fully charged state, or shall be in accordance
with manufacturer’s published data.
7. Results of load tests shall be in accordance with manufacturer’s published data or ANSI/IEEE
1106.
* Optional
Page 158
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.1.2 Direct-Current Systems, Batteries, Vented Nickel-Cadmium (continued)
8. Voltage measured from positive-to-ground shall be equal in magnitude to the voltage measured
from negative-to-ground.
* Optional
Page 159
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.1.3 Direct-Current Systems, Batteries, Valve-Regulated Lead-Acid
1. Visual and Mechanical Inspection
1. Verify that batteries are adequately located.
9. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through all bolted connections with a low-resistance
ohmmeter, if applicable, in accordance with Section 7.18.1.3.1.
5. Measure each monoblock/cell voltage and total battery voltage with charger energized and in
float mode of operation.
* Optional
Page 160
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.1.3 Direct-Current Systems, Batteries, Valve-Regulated Lead-Acid (continued)
7. Perform internal ohmic measurement tests.
8. Perform a load test in accordance with manufacturer’s published data or ANSI/IEEE 1188.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.18.1.3.9.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.18.1.3.9.2)
2. Negative post temperature shall be within manufacturer’s published data or IEEE 1188.
3. Charger float and equalize voltage levels shall be in accordance with the battery
manufacturer’s published data.
4. Results of charger functions and alarms shall be in accordance with manufacturer’s published
data.
7. Monoblock/cell internal ohmic values (resistance, impedance, or conductance) shall not vary
by more than 25 percent between identical monoblocks/cells in a fully charged state.
8. Results of load tests shall be in accordance with manufacturer’s published data or IEEE 1188.
* Optional
Page 161
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.2 Direct-Current Systems, Chargers
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Inspect all bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through all bolted connections with a low-resistance
ohmmeter, if applicable, in accordance with Section 7.18.2.1.
2. Verify float voltage, equalize voltage, and high voltage shutdown settings.
8. Measure and record ac ripple current and voltage imposed on the battery.
* Optional
Page 162
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.2 Direct-Current Systems, Chargers (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.18.2.1.5.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.18.2.1.5.2)
2. Float and equalize voltage settings shall be in accordance with the battery manufacturer’s
published data.
4. Results of load sharing between parallel chargers shall be in accordance with system design
specifications.
6. Results of alarm operation shall be in accordance with manufacturer’s published data and
system design.
7. Input and output voltage shall be in accordance with manufacturer’s published data.
8. AC ripple current and voltage imposed on the battery shall be in accordance with
manufacturer’s published data.
* Optional
Page 163
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.18.3 Direct-Current Systems, Rectifiers
— RESERVED —
* Optional
Page 164
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.19.1 Surge Arresters, Low-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
6. Verify that the ground lead on each device is individually attached to a ground bus or ground
electrode.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.19.1.1.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.19.1.1.5.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.19.1.1.5.2)
* Optional
Page 165
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.19.1 Surge Arresters, Low-Voltage (continued)
2. Insulation-resistance values shall be in accordance with manufacturer’s published data. In the
absence of manufacturer’s published data, use Table 100.1. Values of insulation resistance less
than this table or manufacturer’s recommendations should be investigated.
3. Resistance between the arrester ground terminal and the ground system shall be less than 0.5
ohm and in accordance with Section 7.13.
* Optional
Page 166
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.19.2 Surge Arresters, Medium- and High-Voltage
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
6. Verify that the ground lead on each device is individually attached to a ground bus or ground
electrode.
7. Verify that the stroke counter is correctly mounted and electrically connected, if applicable.
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.19.2.1.
* Optional
Page 167
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.19.2 Surge Arresters, Medium- and High-Voltage (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.19.2.1.5.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.19.2.1.5.2)
3. Resistance between the arrester ground terminal and the ground system shall be less than 0.5
ohm and in accordance with Section 7.13.
4. Watts-loss values are evaluated on a comparison basis with similar units and test equipment
manufacturer’s published data.
* Optional
Page 168
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.20.1 Capacitors and Reactors, Capacitors
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
6. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable. See Section 7.20.1.1.
2. Perform insulation-resistance tests from phase terminal(s) to case for one minute. Apply voltage
in accordance with manufacturer’s published data. In the absence of manufacturer’s published
data, use Table 100.1.
* Optional
Page 169
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.20.1 Capacitors and Reactors, Capacitors (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.20.1.1.6.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.20.1.1.6.2)
* Optional
Page 170
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.20.2 Capacitors and Reactors, Capacitor Control Devices
— RESERVED —
* Optional
Page 171
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.20.3.1 Capacitors and Reactors, Reactors, Shunt and Current-Limiting, Dry-Type
1. Visual and Mechanical Inspections
1. Compare equipment nameplate data with drawings and specifications.
5. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.20.3.1.1.
* Optional
Page 172
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.20.3.1 Capacitors and Reactors, Reactors, Shunt and Current-Limiting, Dry-Type (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.20.3.1.1.5.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.20.3.1.1.5.2)
4. AC dielectric withstand test voltage shall not exceed 75 percent of factory test voltage for one
minute duration. DC dielectric withstand test voltage shall not exceed 100 percent of the factory
rms test voltage for one minute duration. If no evidence of distress or insulation failure is
observed by the end of the total time of voltage application during the dielectric withstand test,
the test specimen is considered to have passed the test.
* Optional
Page 173
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.20.3.2 Capacitors and Reactors, Reactors, Shunt and Current-Limiting, Liquid-Filled
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
8. Verify that cooling fans and pumps operate correctly and that fan and pump motors have
correct overcurrent protection, if applicable.
9. Verify operation of all alarm, control, and trip circuits from temperature and level indicators,
pressure relief device, and fault pressure relay, if applicable.
10. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
13. Perform specific inspections and mechanical tests as recommended by the manufacturer.
* Optional
Page 174
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.20.3.2 Capacitors and Reactors, Reactors, Shunt and Current-Limiting, Liquid-Filled (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.20.3.2.1.
7. Remove a sample of insulating liquid in accordance with ASTM D-923. Sample shall be tested
for the following:
*7. Water in insulating liquids: ASTM D-1533. (Required on 25 kV or higher voltages and
on all silicone-filled units.)
*8. Measure power factor or dissipation factor in accordance with ASTM D-924.
8. Remove a sample of insulating liquid in accordance with ASTM D-3613 and perform
dissolved-gas analysis in accordance with ANSI/IEEE C57.104 or ASTM D-3612.
* Optional
Page 175
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.20.3.2 Capacitors and Reactors, Reactors, Shunt and Current-Limiting, Liquid-Filled (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Operation of temperature devices shall be in accordance with system requirements.
(7.20.3.2.1.7)
2. Operation of pumps and fans shall be in accordance with manufacturer’s recommendations and
system design. (7.20.3.2.1.8)
4. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.20.3.2.1.10.2)
7. Positive pressure shall be indicated on the pressure gauge for gas-blanketed reactors.
(7.20.3.2.1.12)
5. Consult the manufacturer if winding-resistance values vary more than one percent from factory
tests.
* Optional
Page 176
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.20.3.2 Capacitors and Reactors, Reactors, Shunt and Current-Limiting, Liquid-Filled (continued)
6. Investigate presence of oxygen in the nitrogen gas blanket.
* Optional
Page 177
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.21 Outdoor Bus Structures
1. Visual and Mechanical Inspection
1. Compare bus arrangement with drawings and specifications.
5. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.21.1.
*2. Measure insulation resistance of each bus, phase-to-ground with other phases grounded. Apply
voltage in accordance with manufacturer’s published data. In the absence of manufacturer’s
published data, use Table 100.1.
3. Perform dielectric withstand voltage test on each bus phase, phase-to-ground with other phases
grounded. Apply voltage in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.19. Potential application shall be for one minute.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.21.1.5.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.21.1.5.2)
* Optional
Page 178
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.21 Outdoor Bus Structures (continued)
3.2 Test Values – Electrical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value.
3. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
* Optional
Page 179
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.22.1 Emergency Systems, Engine Generator
NOTE: Other than protective shutdowns, the prime mover is not addressed in these specifications.
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
3. Verify phase rotation, phasing, and synchronized operation as required by the application.
4. Functionally test engine shutdown for low oil pressure, overtemperature, overspeed, and other
protection features as applicable.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Anchorage, alignment, and grounding should be in accordance with manufacturer’s published
data and system design. (7.22.1.1.3)
* Optional
Page 180
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.22.1 Emergency Systems, Engine Generator (continued)
3.2 Test Values – Electrical
1. The dielectric absorption ratio or polarization shall be compared to previously obtained results
and should not be less than 1.0. The recommended minimum insulation resistance (IR 1 min) test
results in megohms shall be corrected to 40° C and read as follows:
1. IR 1 min = kV + 1 for most windings made before 1970, all field windings, and others not
described in 2.2 and 2.3.
2. IR 1 min = 100 megohms for most dc armature and ac windings built after 1970 (form-
wound coils).
3. IR 1 min = 5 megohms for most machines and random-wound stator coils and form-
wound coils rated below 1 kV.
NOTE: Dielectric withstand voltage and surge comparison tests shall not be performed
on machines having values lower than those indicated above.
2. Protective relay device test results shall be in accordance with Section 7.9.
3. Phase rotation, phasing, and synchronizing shall be in accordance with system design
requirements.
4. Low oil pressure, overtemperature, overspeed, and other protection features shall operate in
accordance with manufacturer’s published data and system design requirements.
5. Vibration levels shall be in accordance with manufacturer’s published data and shall be
compared to baseline data.
6. Performance tests shall conform to manufacturer’s published data and ANSI/NFPA Standard
110.
7. Governor and regulator shall operate in accordance with manufacturer’s published data and
system design requirements.
* Optional
Page 181
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.22.2 Emergency Systems, Uninterruptible Power Systems
NOTE: There are many configurations of uninterruptible power supply installations. Some are as
simple as a static switch selecting between two highly reliable sources, while others are complex
systems using a combination of rectifiers, batteries, inverters, motor/generators, static switches, and
bypass switches. It is the intent of these specifications to list possible tests of the major components
of the system and more specifically the system as a whole. It is important that the manufacturer’s
recommended commissioning tests be performed.
6. Test all electrical and mechanical interlock systems for correct operation and sequencing.
7. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
* Optional
Page 182
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.22.2 Emergency Systems, Uninterruptible Power Systems (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.22.2.1.
2. Test static transfer from inverter to bypass and back. Use normal load, if possible.
4. Test dc undervoltage trip level on inverter input breaker. Set according to manufacturer’s
published data.
7. Perform electrical tests for UPS system breakers in accordance with Section 7.6.
8. Perform electrical tests for UPS system automatic transfer switches in accordance with
Section 7.22.3.
9. Perform electrical tests for UPS system batteries in accordance with Section 7.18.
10. Perform electrical tests for UPS rotating machinery in accordance with Section 7.15.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Electrical and mechanical interlock systems shall operate in accordance with system design
requirements. (7.22.2.1.6)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.22.2.1.7.2)
* Optional
Page 183
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.22.2 Emergency Systems, Uninterruptible Power Systems (continued)
3.2 Test Values – Electrical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value.
* Optional
Page 184
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.22.3 Emergency Systems, Automatic Transfer Switches
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Verify appropriate lubrication on moving current-carrying parts and on moving and sliding
surfaces.
8. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
10. Verify positive mechanical interlocking between normal and alternate sources.
* Optional
Page 185
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.22.3 Emergency Systems, Automatic Transfer Switches (continued)
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.22.3.1.
*2. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components or for control
devices that cannot tolerate the applied voltage, follow manufacturer’s recommendation.
5. Calibrate and set all relays and timers in accordance with Section 7.9.
6. Verify phase rotation, phasing, and synchronized operation as required by the application.
* Optional
Page 186
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.22.3 Emergency Systems, Automatic Transfer Switches (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Compare bolted connection resistance values to values of similar connections. Investigate
values which deviate from those of similar bolted connections by more than 50 percent of the
lowest value. (7.22.3.1.8.1)
2. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.22.3.1.8.2)
2. Insulation-resistance values of control wiring shall not be less than two meghoms.
3. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values that deviate from adjacent poles or similar switches by more than
50 percent of the lowest value.
6. Phase rotation, phasing, and synchonization shall be in accordance with system design
specifications.
8. Operation and timing shall be in accordance with manufacturer’s and system design
requirements.
* Optional
Page 187
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.23 Communications
— RESERVED —
* Optional
Page 188
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.24.1 Automatic Circuit Reclosers and Line Sectionalizers,
Automatic Circuit Reclosers, Oil/Vacuum
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Perform all mechanical operation and contact alignment tests on both the recloser and its
operating mechanism in accordance with manufacturer’s published data.
6. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.24.1.1.
*4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied
potential shall be 500 volts dc for 300-volt rated cable and 1000 volts dc for 600-volt rated
cable. Test duration shall be one minute. For units with solid-state components, follow
manufacturer’s recommendation.
* Optional
Page 189
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.24.1 Automatic Circuit Reclosers and Line Sectionalizers,
Automatic Circuit Reclosers, Oil/Vacuum (continued)
5. Remove a sample of insulating liquid, if applicable, in accordance with ASTM D 923. Sample
shall be tested in accordance with the referenced standard.
6. Perform minimum pickup voltage tests on trip and close coils in accordance with
manufacturer’s published data.
*7. Perform power-factor or dissipation-factor tests on each pole with the recloser open and each
phase with the recloser closed.
9. Perform vacuum bottle integrity test (dielectric withstand voltage), if applicable, across each
vacuum bottle with the contacts in the open position in strict accordance with manufacturer’s
published data.
10. Perform dielectric withstand voltage tests on each pole-to-ground and pole-to-pole with recloser
in closed position.
13. Test all metering and instrumentation in accordance with Section 7.11.
* Optional
Page 190
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.24.1 Automatic Circuit Reclosers and Line Sectionalizers,
Automatic Circuit Reclosers, Oil/Vacuum (continued)
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Mechanical operation and contact alignment shall be in accordance with manufacturer’s
published data. (7.24.1.1.5)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.24.1.1.6.2)
3. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values that deviate from adjacent poles or similar reclosers by more than
50 percent of the lowest value.
4. Insulation-resistance values of control wiring shall not be less than two megohms.
6. Minimum pickup voltage of the trip and close coils shall conform to the manufacturer’s
published data. In the absence of the manufacturer’s published data, refer to Table 100.20.
* Optional
Page 191
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.24.1 Automatic Circuit Reclosers and Line Sectionalizers,
Automatic Circuit Reclosers, Oil/Vacuum (continued)
8. Power-factor or dissipation-factor and capacitance values shall be within ten percent of
nameplate rating for bushings. Hot collar tests are evaluated on a milliampere/milliwatt loss
basis, and the results shall be compared to values of similar bushings.
9. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the vacuum bottle integrity test, the test specimen is considered to have
passed the test
10. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
12. Protective device function test results shall be in accordance with Section 7.9.
13. Metering and instrumentation test results shall be in accordance with Section 7.11.
14. Instrument transformer test results shall be in accordance with Section 7.10.
* Optional
Page 192
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.24.2 Automatic Circuit Reclosers and Line Sectionalizers,
Automatic Line Sectionalizers, Oil
1. Visual and Mechanical Inspection
1. Compare equipment nameplate data with drawings and specifications.
5. Perform all mechanical operation and contact alignment tests on both the sectionalizer and its
operating mechanism in accordance with manufacturer’s published data.
6. Inspect bolted electrical connections for high resistance using one or more of the following
methods:
2. Electrical Tests
1. Perform resistance measurements through bolted connections with a low-resistance ohmmeter,
if applicable, in accordance with Section 7.24.2.1.
4. Remove a sample of insulating liquid in accordance with ASTM D 923. The sample shall be
tested in accordance with the referenced standard.
* Optional
Page 193
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.24.2 Automatic Circuit Reclosers and Line Sectionalizers,
Automatic Line Sectionalizers, Oil (continued)
5. Perform dielectric withstand voltage tests on each pole-to-ground and pole-to-pole with recloser
in closed position.
6. Test sectionalizer counting function by application of simulated fault current (greater than 160
percent of continuous current rating).
*9. Perform power-factor or dissipation-factor tests on each pole with the recloser open and each
phase with the recloser closed.
*10. Perform power-factor or dissipation-factor tests on each bushing equipped with a power-factor/
capacitance tap. In the absence of a power-factor/ capacitance tap, perform hot-collar tests.
These tests shall be in accordance with the test equipment manufacturer’s published data.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Mechanical operation and contact alignment shall be in accordance with manufacturer’s
published data. (7.24.2.1.5)
3. Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence of
manufacturer’s published data, use Table 100.12. (7.24.2.1.6.2)
* Optional
Page 194
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.24.2 Automatic Circuit Reclosers and Line Sectionalizers,
Automatic Line Sectionalizers, Oil (continued)
3. Microhm or dc millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s published data is not
available, investigate values that deviate from adjacent poles or similar switches by more than
50 percent of the lowest value.
5. If no evidence of distress or insulation failure is observed by the end of the total time of voltage
application during the dielectric withstand test, the test specimen is considered to have passed
the test.
8. Reset timing of trip actuator shall operate in accordance with manufacturer’s published data.
10. Power-factor or dissipation-factor and capacitance values shall be within ten percent of
nameplate rating for bushings. Hot collar tests are evaluated on a milliampere/milliwatt loss
basis, and the results should be compared to values of similar bushings.
* Optional
Page 195
ANSI/NETA ATS-2009
7. INSPECTION AND TEST PROCEDURES
7.25 Fiber-Optic Cables
1. Visual and Mechanical Inspection
1. Compare cable, connector, and splice data with drawings and specifications.
2. Optical Tests
1. Perform cable length measurement, fiber fracture inspection, and construction defect inspection
using an optical time domain reflectometer.
2. Perform connector and splice integrity test using an optical time domain reflectometer.
3. Perform cable attenuation loss measurement with an optical power loss test set.
4. Perform connector and splice attenuation loss measurement from both ends of the optical cable
with an optical power loss test set.
3. Test Values
3.1 Test Values – Visual and Mechanical
1. Cable and connections shall not have been subjected to physical or mechanical damage.
(7.25.1.1)
2. Connectors and splices shall be installed in accordance with industry standards. (7.25.1.2)
2. The optical time domain reflectometer signal shall be analyzed for excessive connection, splice,
or cable backscatter by viewing the reflected power/distance graph.
3. Attenuation loss measurement shall be expressed in dB/km. Losses shall be within the
manufacturer’s recommendations when no local site specifications are available.
4. Attenuation loss measurement shall be expressed in dB/km. Losses shall be within the
manufacturer’s recommendations when no local site specifications are available.
* Optional
Page 196
ANSI/NETA ATS-2009
8. SYSTEM FUNCTION TESTS
NOTE: It is the purpose of system function tests to prove the correct interaction of all sensing,
processing, and action devices. Perform system function tests upon completion of the acceptance tests
on specified equipment.
1. Develop test parameters and perform tests for the purpose of evaluating performance of all
integral components and their functioning as a complete unit within design requirements and
manufacturer’s published data.
2. Verify the correct operation of all interlock safety devices for fail-safe functions in addition to
design function.
3. Verify the correct operation of all sensing devices, alarms, and indicating devices.
Page 197
ANSI/NETA ATS-2009
9. THERMOGRAPHIC SURVEY
1. Visual and Mechanical Inspection
1. Perform thermographic survey when load is applied to the system.
2. Remove all necessary covers prior to thermographic inspection. Use appropriate caution, safety
devices, and personal protective equipment.
*3. Perform a follow-up thermographic survey within 12 months of final acceptance by the owner.
2. Report
Provide a report which includes the following:
1. Description of equipment to be tested.
2. Discrepancies.
3. Temperature difference between the area of concern and the reference area.
8. Recommended action.
3. Test Parameters
1. Inspect distribution systems with imaging equipment capable of detecting a minimum
temperature difference of 1° C at 30° C.
2. Equipment shall detect emitted radiation and convert detected radiation to visual signal.
4. Test Results
Suggested actions based on temperature rise can be found in Table 100.18.
Page 198
ANSI/NETA ATS-2009
10. ELECTROMAGNETIC FIELD TESTING
1. Scope of Services
Determine the vector-valued quantity of magnetic flux density for power frequency magnetic fields
over a predetermined space or area.
2. Procedure
1. Take detailed measurements of the magnetic flux density, vector direction, and temporal
variations at the locations or over the area, as necessary.
1. Perform spot measurements of the magnetic fields (40 to 800 Hertz) at grid intervals one
meter above the floor throughout the office. Record x, y, z, and resultant magnetic flux
density values for each measurement point.
2. Take additional detailed spot measurements directly at floor level and at two meters
above the floor at grid point locations directly on the wall surface separating measured
area from suspected magnetic field source.
3. If measured magnetic flux densities at any perimeter wall appear to be above 3.0 to 5.0
mG, take additional spot measurements of the adjoining space utilizing the same
measurement grid spacing at one meter above floor.
4. Take a benchmark magnetic flux density reading at a specific point in the immediate
area of the suspected magnetic field source.
2. Obtain and record other related electrical system information including current measurements
for each phase, neutral, and net current as available for the involved electrical system for use in
correcting any wiring deficiencies and in completing the design of a shielding installation or
other suitable mitigation proposal.
3. The magnetic field evaluation shall be performed in accordance with the recommended
practices and procedures in accordance with IEEE 644.
Page 199
ANSI/NETA ATS-2009
10. ELECTROMAGNETIC FIELD TESTING (continued)
3. Survey Report
1. Results of the survey shall be summarized in a report containing the following items:
Page 200
ANSI/NETA ATS-2009
11.0 CORONA STUDIES
— RESERVED —
Page 201
ANSI/NETA ATS-2009
– This page intentionally left blank –
Page 202
ANSI/NETA ATS-2009
Tables
Page 203
ANSI/NETA ATS-2009
TABLE 100.1
In the absence of consensus standards dealing with insulation-resistance tests, the Standards Review Council suggests
the above representative values.
See Table 100.14 for temperature correction factors.
Test results are dependent on the temperature of the insulating material and the humidity of the surrounding environment
at the time of the test.
Insulation-resistance test data may be used to establish a trending pattern. Deviations from the baseline information
permit evaluation of the insulation.
Page 204
ANSI/NETA ATS-2009
TABLE 100.2
Derived from ANSI/IEEE C37.20.1-1993, Paragraph 5.5, Standard for Metal-Enclosed Low-Voltage Power Circuit-
Breaker Switchgear, C37.20.2-1993, Paragraph 5.5, Standard for Metal-Clad and Station-Type Cubicle Switchgear and
C37.20.3-1987 (R1992), Paragraph 5.5, Standard for Metal-Enclosed Interrupter Switchgear, and includes 0.75
multiplier with fraction rounded down.
The column headed “DC” is given as a reference only for those using dc tests to verify the integrity of connected cable
installations without disconnecting the cables from the switchgear. It represents values believed to be appropriate and
approximately equivalent to the corresponding power frequency withstand test values specified for voltage rating of
switchgear. The presence of this column in no way implies any requirement for a dc withstand test on ac equipment or
that a dc withstand test represents an acceptable alternative to the low-frequency withstand tests specified in these
specifications, either for design tests, production tests, conformance tests, or field tests. When making dc tests, the
voltage should be raised to the test value in discrete steps and held for a period of one minute.
† Because of the variable voltage distribution encountered when making dc withstand tests, the manufacturer should be
contacted for recommendations before applying dc withstand tests to the switchgear. Voltage transformers above 34.5
kV should be disconnected when testing with dc. Refer to ANSI/IEEE C57.13-1993 (IEEE Standard Requirements for
Instrument Transformers) paragraph 8.8.2.
Page 205
ANSI/NETA ATS-2009
TABLE 100.3
In the absence of consensus standards dealing with transformer dissipation-factor or power-factor values, the NETA
Standards Review Council suggests the above representative values.
Page 206
ANSI/NETA ATS-2009
TABLE 100.4
ANSI/IEEE C57.106-2002, Guide for Acceptance and Maintenance of Insulating Oil in Equipment, Tables 1, 2, and 3.
Table 100.4.2
Test Limits for Silicone Insulating Liquid in New Transformers
Test ASTM Method Acceptable Values
Dielectric breakdown, kV minimum D877 30
Visual D2129 clear, free of particles
Water content, ppm maximum D1533 50
Dissipation/power factor, 60 hertz, % D924 0.1
max. @ 25° C
Viscosity, cSt @ 25° C D445 47.5 – 52.5
Fire point, ° C, minimum D92 340
Neutralization number, D974 0.01
mg KOH/g max.
ANSI/IEEE C57.111-1989 (R1995), Guide for Acceptance of Silicone Insulating Fluid and Its Maintenance in Transformers,
Table 2.
Page 207
ANSI/NETA ATS-2009
TABLE 100.4 (continued)
ANSI/IEEE C57.121-1998, IEEE Guide for Acceptance and Maintenance of Less Flammable Hydrocarbon Fluid in
Transformers, Table 3.
The test limits shown in this table apply to less-flammable hydrocarbon fluids as a class. Specific typical values for each
brand of fluid should be obtained from each fluid manufacturer.
a. If the purpose of the HMWH installation is to comply with the NFPA 70 National Electrical Code, this value is the
minimum for compliance with NEC Article 450.23.
Page 208
ANSI/NETA ATS-2009
TABLE 100.5
In the absence of consensus standards, the NETA Standards Review Council suggests the above representative
values.
See Table 100.14 for temperature correction factors.
NOTE: Since insulation resistance depends on insulation rating (kV) and winding capacity (kVA), values
obtained should be compared to manufacturer’s published data.
Page 209
ANSI/NETA ATS-2009
TABLE 100.6
Medium-Voltage Cables
Acceptance Test Values
Table 100.6.1
DC Test Voltages
Maximum DC Field
Nominal Test Voltages, kV
Insulation Thickness During/After
mils (mm) Installation
Rated Voltage 100% 133% 100% 133%
Phase-to-Phase Conductor Size Insulation Insulation Insulation Insulation
kV AWG or kcmil (mm) Level Level Level Level
8-1000 (8.4-507) 90 (2.29) 115 (2.92) 28 36
5
Above 1000 (507) 140 (3.56) 140 (3.56) 28 36
6-1000 (13.3-507) 115 (2.92) 140 (3.56) 36 44
8
Above 1000 (507) 175 (4.45) 175 (4.45) 36 44
2-1000 (33.6-507) 175 (4.45) 220 (5.59) 56 64
15
Above 1000 (507) 220 (5.59) 220 (5.59) 56 64
25 1-2000 (42.4-1013) 260 (6.60) 320 (8.13) 80 96
28 1-2000 (42.4-1013) 280 (7.11) 345 (8.76) 84 100
35 1/0-2000 (53.5-1013) 345 (8.76) 420 (10.7) 100 124
46 4/0-2000 (107.2-1013) 445 (11.3) 580 (14.7) 132 172
69 4/0-2000 (107.2-1013) 650 195
Tables derived from ANSI/ICEA S 93-639/NEMA WC 74-2000, 5-46 kV Shielded Power Cable for Use in the
Transmission and Distribution of Electric Energy; ANSI/ICEA S-94-649-2000, Standard for Concentric Neutral Cables
Rated 5,000 - 46,000 Volts; ANSI/ICEA S-97-682-2000, Standard for Utility Shielded Power Cables Rated 5,000 -
46,000 Volts; and The Okonite Company, High-Voltage Proof Testing.
DC test voltages are applied to discover gross problems such as incorrectly installed accessories or mechanical damage.
The dc field test voltages listed above are intended for cable designed in accordance with ICEA specifications. When
older cables or other types/classes of cables or accessories are connected to the system, voltages lower than those shown
may be necessary. Consult the manufacturers of the cables and accessories before applying the test voltage.
Page 210
ANSI/NETA ATS-2009
TABLE 100.6 (continued)
Medium-Voltage Cables
Acceptance Test Values
Table 100.6.2
AC Test Voltages
Nominal
Insulation Thickness
Mils (mm) AC Test Voltage, kV
Tables derived from ANSI/ICEA S 93-639/NEMA WC 74-2000, 5-46 kV Shielded Power Cable for Use in the
Transmission and Distribution of Electric Energy; ANSI/ICEA S-94-649-2000, Standard for Concentric Neutral
Cables Rated 5,000 - 46,000 Volts; ANSI/ICEA S-97-682-2000, Standard for Utility Shielded Power Cables Rated
5,000 - 46,000 Volts.
Page 211
ANSI/NETA ATS-2009
TABLE 100.6 (continued)
Medium-Voltage Cables
Acceptance Test Values
Table 100.6.3
Partial Discharge Requirements for Semiconduction Coating and Semiconducting, Nonmetalic Tape
Designs Only
Rated Circuit Voltage
Phase-to-Phase Minimum Partial Discharge Extinction Level, kV
Volts 100% Insulation Level 133% Insulation Level
2001-5000 4 5
5001-8000 6 8
8001-15000 11 15
In the absence of consensus standards the NETA Standards Review Council suggests the above
representative values.
ANSI/ICEA S 93-639/NEMA WC 74-2000, 5-46 kV Shielded Power Cable for Use in the Transmission
and Distribution of Electric Energy.
Table 100.6.4
Very Low Frequency Testing Levels
0.1 Hz Test Voltage (rms)
In the absence of consensus standards the NETA Standards Review Council suggests the above
representative values.
Page 212
ANSI/NETA ATS-2009
TABLE 100.7
Derived from Table 5-3, NEMA Standard AB 4-1996, Guidelines for Inspection and Preventive Maintenance of Molded-
Case Circuit Breakers Used in Commercial and Industrial Applications.
a. Trip times may be substantially longer for integrally-fused circuit breakers if tested with the fuses replaced by solid
links (shorting bars).
Page 213
ANSI/NETA ATS-2009
TABLE 100.8
Page 214
ANSI/NETA ATS-2009
TABLE 100.9
Table 100.9 is derived from Paragraph 8.8.2 and Tables 2 of ANSI/IEEE C57.13-1993, Standard Requirements for
Instrument Transformers.
+ Periodic dc potential tests are not recommended for transformers rated higher than 34.5 kV.
* DC potential tests are not recommended for transformers rated higher than 200 kV BIL. DC tests may prove
beneficial as a reference for future testing. In such cases the test direct voltage shall not exceed the original factory
test rms alternating voltages.
Page 215
ANSI/NETA ATS-2009
TABLE 100.10
Derived from NEMA publication MG 1–2006, Section 7.8.1, Table 7–1. Table is unfiltered vibration limits for resiliently
mounted machines. For machines with rigid mounting multiply the limiting values by 0.8.
Page 216
ANSI/NETA ATS-2009
TABLE 100.11
— RESERVED —
Page 217
ANSI/NETA ATS-2009
TABLE 100.12.1
US Standard Fasteners a
Heat-Treated Steel – Cadmium or Zinc Plated b
Grade SAE 1&2 SAE 5 SAE 7 SAE 8
Head Marking
Minimum Tensile
(Strength) 64K 105K 133K 150K
(lbf/in2)
Bolt Diameter Torque (Pound-Feet)
(Inches)
1/4 4 6 8 8
5/16 7 11 15 18
3/8 12 20 27 30
7/16 19 32 44 48
1/2 30 48 68 74
9/16 42 70 96 105
5/8 59 96 135 145
3/4 96 160 225 235
7/8 150 240 350 380
1.0 225 370 530 570
Page 218
ANSI/NETA ATS-2009
TABLE 100.12.2
US Standard Fasteners a
Silicon Bronze Fasteners b c
Torque (Pound-Feet)
Bolt Diameter (Inches) Nonlubricated Lubricated
5/16 15 10
3/8 20 15
1/2 40 25
5/8 55 40
3/4 70 60
a. Consult manufacturer for equipment supplied with metric fasteners.
b. Table is based on national coarse thread pitch.
c. This table is based on bronze alloy bolts having a minimum tensile strength of 70,000 pounds per square inch.
TABLE 100.12.3
US Standard Fasteners a
Aluminum Alloy Fasteners b c
Torque (Pound-Feet)
Bolt Diameter (Inches) Lubricated
5/16 10
3/8 14
1/2 25
5/8 40
3/4 60
a. Consult manufacturer for equipment supplied with metric fasteners.
b. Table is based on national coarse thread pitch.
c. This table is based on aluminum alloy bolts having a minimum tensile strength of 55,000 pounds per
square inch.
Page 219
ANSI/NETA ATS-2009
TABLE 100.12.4
US Standard Fasteners a
Stainless Steel Fasteners b c
Torque (Pound-Feet)
Bolt Diameter (Inches) Uncoated
5/16 15
3/8 20
1/2 40
5/8 55
3/4 70
Tables in 100.12 are compiled from Penn-Union Catalogue and Square D Company, Anderson Products Division, General
Catalog: Class 3910 Distribution Technical Data, Class 3930 Reference Data Substation Connector Products.
Page 220
ANSI/NETA ATS-2009
TABLE 100.13
Page 221
ANSI/NETA ATS-2009
TABLE 100.14
Insulation Resistance Conversion Factors (20° C)
Table 100.14.1
Test Temperatures to 20° C
Temperature Multiplier
Apparatus Containing Apparatus Containing
°C °F
Immersed Oil Insulation Solid Insulation
-10 14 0.125 0.25
-5 23 0.180 0.32
0 32 0.25 0.40
5 41 0.36 0.50
10 50 0.50 0.63
15 59 0.75 0.81
20 68 1.00 1.00
25 77 1.40 1.25
30 86 1.98 1.58
35 95 2.80 2.00
40 104 3.95 2.50
45 113 5.60 3.15
50 122 7.85 3.98
55 131 11.20 5.00
60 140 15.85 6.30
65 149 22.40 7.90
70 158 31.75 10.00
75 167 44.70 12.60
80 176 63.50 15.80
85 185 89.789 20.00
90 194 127.00 25.20
95 203 180.00 31.60
100 212 254.00 40.00
105 221 359.15 50.40
110 230 509.00 63.20
Derived from Stitch in Time…The Complete Guide to Electrical Insulation Testing, Megger.
Formula: Example: Resistance test on oil-immersion insulation at 104° F
Rc = Ra x K Ra = 2 megohms @ 104° F
Where: Rc is resistance corrected to 20° C K = 3.95
Ra is measured resistance at test Rc = Ra x K
temperature Rc = 2.0 x 3.95
K is applicable multiplier Rc = 7.90 megohms @ 20° C
Page 222
ANSI/NETA ATS-2009
TABLE 100.14 (continued)
Derived from Megger’s Stitch in Time…The Complete Guide to Electrical Insulation Testing and ANSI/IEEE 43-2000,
IEEE Recommended Practice for Testing Insulation Resistance of Rotating Machinery.
Notes: The insulation resistance coefficient is based on the halving of the insulation resistance to the change in temperature.
Apparatus Containing Immersed Oil Insulation Table uses 10° C change with temperature halving.
Apparatus Containing Solid Insulation Table uses 15° C change with temperature halving.
Page 223
ANSI/NETA ATS-2009
TABLE 100.15
Derived from ANSI/IEEE C37.61-1973(R1992), Standard Guide for the Application, Operation, and Maintenance of
Automatic Circuit Reclosers and from C37.60-1981(R1992), Standard Requirements for Overhead, Pad-Mounted, Dry-
Vault, and Submersible Automatic Circuit Reclosers and Fault Interrupters for AC Systems.
Page 224
ANSI/NETA ATS-2009
TABLE 100.16
Derived from ANSI/IEEE C37.63-1984(R1990) Table 2 (Standard Requirements for Overhead, Pad-Mounted, Dry-
Vault, and Submersible Automatic Line Sectionalizers of ac Systems).
In the absence of consensus standards, the NETA Standards Review Council suggests the above representative values.
NOTE: Values of ac voltage given are dry test one minute factory test values.
Page 225
ANSI/NETA ATS-2009
TABLE 100.17
Derived from ANSI/IEEE C37.23-1987, Tables 3A, 3B, 3C, 3D and paragraph 6.4.2. The table includes a 0.75 multiplier
with fractions rounded down.
NOTE:
The presence of the column headed “DC” does not imply any requirement for a dc withstand test on ac equipment. This
column is given as a reference only for those using dc tests and represents values believed to be appropriate and
approximately equivalent to the corresponding power frequency withstand test values specified for each class of bus.
Direct current withstand tests are recommended for flexible bus to avoid the loss of insulation life that may result from
the dielectric heating that occurs with rated frequency withstand testing.
Because of the variable voltage distribution encountered when making dc withstand tests and variances in leakage
currents associated with various insulation systems, the manufacturer should be consulted for recommendations before
applying dc withstand tests to this equipment.
Page 226
ANSI/NETA ATS-2009
TABLE 100.18
Thermographic Survey
Suggested Actions Based on Temperature Rise
Temperature difference (ΔT) based
Temperature difference (ΔT) based upon comparisons between
on comparisons between similar component and ambient air
components under similar loading. temperatures. Recommended Action
Possible deficiency; warrants
1ºC - 3ºC 1ºC - 10ºC
investigation
Indicates probable deficiency; repair
4ºC - 15ºC 11ºC - 20ºC
as time permits
Monitor until corrective measures
-- -- -- 21ºC - 40ºC
can be accomplished
Major discrepancy; repair
>15ºC >40ºC
immediately
Temperature specifications vary depending on the exact type of equipment. Even in the same class of equipment (i.e.,
cables) there are various temperature ratings. Heating is generally related to the square of the current; therefore, the load
current will have a major impact on ΔT. In the absence of consensus standards for ΔT, the values in this table will provide
reasonable guidelines.
An alternative method of evaluation is the standards-based temperature rating system as discussed in Chapter 8.9.2,
Conducting an IR Thermographic Inspection, Electrical Power Systems Maintenance and Testing, by Paul Gill, PE, 1998.
It is a necessary and valid requirement that the person performing the electrical inspection be thoroughly trained and
experienced concerning the apparatus and systems being evaluated as well as knowledgeable of thermographic
methodology.
Page 227
ANSI/NETA ATS-2009
TABLE 100.19
In the absence of consensus standards, the NETA Standards Review Council suggests the above representative values.
a. Intermediate voltage ratings are placed in the next higher insulation class.
Page 228
ANSI/NETA ATS-2009
TABLE 100.20
100.20.1
Rated Control Voltages and their Ranges for Circuit Breakers
Direct Current Voltage Ranges Alternating Current
(1)(2)(3)(5) Voltage Ranges
Volts, dc (8)(9) (1)(2)(3)(4)(8)
Closing and Auxiliary Rated Control Voltage Closing, Tripping, and
Functions (60 Hz) Auxiliary Functions
(11) Outdoor Opening
Rated Control Indoor Circuit Circuit Functions
Voltage Breakers Breakers All Types Single Phase Single Phase
24 (6) --- --- 14–28 120 104–127 (7)
48 (6) 38–56 36–56 28–56 240 208–254 (7)
125 100–140 90–140 70–140
250 200–280 180–280 140–280 Polyphase Polyphase
--- --- --- --- 208Y/120 180Y/104–220Y/127
--- --- --- --- 240 208–254
Derived from Table 8, ANSI C37.06-2000, AC High-Voltage Circuit Breakers Rated on a Symmetrical Current Basis
— Preferred Ratings and Related Required Capabilities.
Notes:
(1) Electrically operated motors, contactors, solenoids, valves, and the like, need not carry a nameplate voltage rating that
corresponds to the control voltage rating shown in the table as long as these components perform the intended duty
cycle (usually intermittent) in the voltage range specified.
(2) Relays, motors, or other auxiliary equipment that function as a part of the control for a device shall be subject to the
voltage limits imposed by this standard, whether mounted at the device or at a remote location.
(3) Circuit breaker devices, in some applications, may be exposed to control voltages exceeding those specified here due
to abnormal conditions such as abrupt changes in line loading. Such applications require specific study, and the
manufacturer should be consulted. Also, application of switchgear devices containing solid-state control, exposed
continuously to control voltages approaching the upper limits of ranges specified herein, require specific attention and
the manufacturer should be consulted before application is made.
(4) Includes supply for pump or compressor motors. Note that rated voltages for motors and their operating ranges are
covered by ANSI/NEMA MG-1-1978.
(5) It is recommended that the coils of closing, auxiliary, and tripping devices that are connected continually to one dc
potential should be connected to the negative control bus so as to minimize electrolytic deterioration.
(6) 24-volt or 48-volt tripping, closing, and auxiliary functions are recommended only when the device is located near the
battery or where special effort is made to ensure the adequacy of conductors between battery and control terminals.
24-volt closing is not recommended.
(7) Includes heater circuits
Page 229
ANSI/NETA ATS-2009
TABLE 100.20 (continued)
100.20.2
Rated Control Voltages and their Ranges for Circuit Breakers
Solenoid-Operated Devices
Closing Voltage Ranges
Rated Voltage for Power Supply
125 dc 90 - 115 or 105 - 130
250 dc 180 - 230 or 210 - 260
230 ac 190 - 230 or 210 - 260
Some solenoid operating mechanisms are not capable of satisfactory performance over the range of voltage specified in the
standard; moreover, two ranges of voltage may be required for such mechanisms to achieve an acceptable standard of
performance.
The preferred method of obtaining the double range of closing voltage is by use of tapped coils. Otherwise it will be
necessary to designate one of the two closing voltage ranges listed above as representing the condition existing at the
device location due to battery or lead voltage drop or control power transformer regulation. Also, caution should be
exercised to ensure that the maximum voltage of the range used is not exceeded.
Page 230
ANSI/NETA ATS-2009
TABLE 100.21
There are four different TP classifications to meet different functional requirements as follows:
1. Class TPS low leakage flux design ct.
2. Class TPX closed core ct for specified transient duty cycle.
3. Class TPY gapped (low remanance) ct for specified transient duty cycle
4. Class TPZ linear ct (no remanence).
The error limit for TPS ct in terms of turn ratio error is ± .25% and the excitation voltage under limiting conditions should
not be less than the specified value; furthermore, this value is such that an increase of 10% in magnitude does not result in
an increase in the corresponding peak instantaneous exciting current exceeding 100%. In other words, the ct should not be
in saturated state at the specified maximum operating voltage.
The accuracy limit conditions are specified on the rating plate. The required rating plate information is shown in the table
below. (The obvious information such as rated primary and secondary currents are not shown).
Page 231
ANSI/NETA ATS-2009
TABLE 100.22
Page 232
ANSI/NETA ATS-2009
TABLE 100.22
Minimum Radii for Power Cable
Single & Multiple Conductor Cables with Interlocked Armor,
Smooth or Corrugated Aluminum Sheath or Lead Sheath
Notes
Specific references from Appendix I:
1. Interlocked-Armor and Metallic-Sheathed Cables
1.1 The minimum bending radius for interlocked-armored cables, smooth or corrugated aluminum sheath or lead sheath
shall be in accordance with Table 100.22.
3. Tape-Shielded Cables
3.1 The minimum bending radius for tape-shielded cables given above applies to helically applied flat or corrugated tape
or longitudinally applied corrugated tape-shielded cables.
3.2 The minimum bending radius for a single-conductor cable is twelve times the overall diameter.
3.3 For multiple-conductor or multiplexed single-conductor cables having individually taped shielded conductors, the
minimum bending radius is twelve times the diameter of the individual conductors or seven times the overall diameter,
whichever is greater.
3.4 For multiple-conductor cables having an overall tape shield over the assembly, the minimum bending radius is twelve
times the overall diameter of the cable.
4. Wire-Shielded Cables
4.1 The minimum bending radius for a single-conductor cable is eight times the overall diameter.
4.2 For multiple-conductor or multiplexed single-conductor cables having wire-shielded individual conductors, the
minimum bending radius is eight times the diameter of the individual conductors or five times the overall diameter,
whichever is greater.
4.3 For multiple-conductor cables having a wire shield over the assembly, the minimum bending radius is eight times the
overall diameter of the cable.
Page 233
ANSI/NETA ATS-2009
— This page intentionally left blank —
Page 234
ANSI/NETA ATS-2009
APPENDIX A
Definitions
NETA recognizes the IEEE 100, The Authoritative Dictionary of IEEE Standards Terms, as its official
source for electrical definitions. The definitions in the list provided by NETA are either not included in the
IEEE reference or are more specific to electrical testing and to this document.
NETA defines equipment voltage ratings in accordance with ANSI/NEMA C37.84.1 American National
Standard for Electrical Power Systems and Equipment – Voltage Ratings (60 Hertz).
As-found
Condition of the equipment when taken out of service, prior to testing.
As-left
Condition of equipment at the completion of inspection and testing. As-left values refer to test values
obtained after any corrective action or design change has been performed on the device under test.
Comment
Suggested revision, addition, or deletion in an existing section of the NETA specifications.
Electrical tests
Electrical tests involve application of electrical signals and observation of the response. It may be, for
example, applying a potential across an insulation system and measuring the resultant leakage current
magnitude or power factor or dissipation factor. It may also involve application of voltage and/or current to
metering and relaying equipment to check for correct response.
Equipment condition
Suitability of the equipment for continued operation in the intended environment as determined by
evaluation of the results of inspections and tests.
Exercise
To operate equipment in such a manner that it performs all its intended functions to allow observation,
testing, measurement, and diagnosis of its operational condition.
Extra-high voltage
A class of nominal system voltages greater than 230,000 volts.
High voltage
A class of nominal system voltages equal to or greater than 100,000 volts and equal to or less than 230,000
volts.
Inspection
Examination or measurement to verify whether an item or activity conforms to specified requirements.
Interim amendment
A interim amendment is made by NETA’s Standards Review Council when there is a potential hazard prior
to review by the Section Panel or the public.
Page 235
ANSI/NETA ATS-2009
APPENDIX A
Definitions (continued)
Low voltage
A class of nominal system voltages 1000 volts or less.
Manufacturer’s published data
Data provided by the manufacturer concerning a specific piece of equipment.
Mechanical inspection
Observation of the mechanical operation of equipment not requiring electrical stimulation, such as manual
operation of circuit breaker trip and close functions. It may also include tightening of hardware, cleaning,
and lubricating.
Medium voltage
A class of nominal system voltages greater than 1000 volts and less than 100,000 volts.
Proposal
Draft of a section that is currently “reserved” in one of the NETA specifications.
Ready-to-test condition
Having the equipment which is to be tested isolated, source and load disconnected, the equipment grounded,
and control and operating sources identified.
Shall
Indicates a mandatory requirement and is used when the testing firm has control over the result.
Should
Indicates that a provision is not mandatory but is recommended as good practice.
System voltage
The root-mean-square (rms) phase-to-phase voltage of a portion of an alternating-current electric system.
Each system voltage pertains to a portion of the system that is bounded by transformers or utilization
equipment.
Verify
To investigate by observation or by test to determine that a particular condition exists.
Visual inspection
Qualitative observation of physical characteristics, including cleanliness, physical integrity, evidence of
overheating, lubrication, etc.
Page 236
ANSI/NETA ATS-2009
APPENDIX B
— RESERVED —
Page 237
ANSI/NETA ATS-2009
APPENDIX C
The InterNational Electrical Testing Association (NETA) is an accredited standards developer for the
American National Standards Institute (ANSI) and defines the standards by which electrical equipment is
deemed safe and reliable. NETA Certified Technicians conduct the tests that ensure this equipment meets
the Association’s stringent specifications. NETA is the leading source of specifications, procedures, testing,
and requirements, not only for commissioning new equipment but for testing the reliability and performance
of existing equipment.
CERTIFICATION
Certification of competency is particularly important in the electrical testing industry. Inherent in the
determination of the equipment’s serviceability is the prerequisite that individuals performing the tests be
capable of conducting the tests in a safe manner and with complete knowledge of the hazards involved.
They must also evaluate the test data and make an informed judgement on the continued serviceability,
deterioration, or nonserviceability of the specific equipment. NETA, a nationally-recognized certification
agency, provides recognition of four levels of competency within the electrical testing industry in
accordance with ANSI/NETA ETT-2000 Standard for Certification of Electrical Testing Technicians.
• The NETA Technician has broad-based knowledge -- this person is trained to inspect, test, maintain, and
calibrate all types of electrical equipment in all types of industries.
• NETA Technicians meet stringent educational and experience requirements in accordance with
ANSI/NETA ETT-2000 Standard for Certification of Electrical Testing Technicians.
• A Registered Professional Engineer will review all engineering reports.
• All tests will be performed objectively, according to NETA specifications, using calibrated instruments
traceable to the National Institute of Science and Technology (NIST).
• The firm is a well-established, full-service electrical testing business.
Page 238
ANSI/NETA ATS-2009
APPENDIX C
EDUCATIONAL PROGRAMS
PowerTest, NETA's annual technical conference, draws hundreds of qualified industry professionals from
around the globe. This conference provides a forum for current industry advances, critical informational
updates, networking, and more. Regular attendees include technicians from electrical testing and
maintenance companies, consultants, engineers, architects, and plant personnel directly involved in
electrical testing and maintenance. Paper presentations from field-experienced industry experts share
practical knowledge and experience while in-depth seminars offer interactive training. At the Trade Show
attendees enjoy the highest-quality gathering of industry-specific suppliers displaying state-of-the-art
products and services directly related to the electrical testing industry. Attendance of PowerTest is the best
opportunity for interaction and input in a professional technical environment.
Page 239
ANSI/NETA ATS-2009
APPENDIX D
I hereby grant NETA the nonexclusive, royalty-free rights, including nonexclusive, royalty-free rights in copyright,
in this material; I understand that I acquire no rights in any publication of NETA in which this proposal in this or
another similar analogous form is used.
Signature (required)
A comment that does not include all required information may be rejected by the Standards Review Council for that
reason. Must use separate form for each comment. All comments must be typed or printed neatly. Illegible
comments will be interpreted to the best of the staff’s ability.
This form is available electronically on NETA’s website at www.netaworld.org under Standards Activities.
Send to: Standards Review Council
3050 Old Centre Avenue, Suite 102, Portage, MI 49024
Phone: 888.300.6382 FAX: 269.488.6383 Email: [email protected]
Page 240
ANSI/NETA ATS-2009
APPENDIX E
Anyone may propose a new section for this document using the following form:
Date
Name Tel No.
Company Fax No.
Address E-Mail
Please indicate organization represented (if any)
NETA document title Year
Section/Number
I hereby grant NETA the nonexclusive, royalty-free rights, including nonexclusive, royalty-free rights in
copyright, in this proposal. I understand that I acquire no rights in any publication of NETA in which this
proposal in this or another similar analogous form is used.
Signature (required)
This form is available electronically on NETA’s website at www.netaworld.org under Standards Activities.
Send to:
Standards Review Council
3050 Old Centre Avenue, Suite 102
Portage, MI 49024
Phone: 888.300.6382 FAX: 269.488.6383
Email: [email protected]
Page 241
ANSI/NETA ATS-2009