Pre-Analysis Checks Report
Pre-Analysis Checks Report
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-1
BUILDING DATA
=============
Number of Storeys = 5
Number of Effective Storeys = 5
Number of Rigid Basements = 0
Earthquake Code =
LOAD COMBINATIONS:
==================
No Combination G GP11 GP12 GP21 GP22 GP31 GP32 GP41 GP42 GP51 GP52
Q QP11 QP12 QP21 QP22 QP31 QP32 QP41 QP42 QP51 QP52 +Ex+ -Ex+ +Ex- -Ex-
+Ey+ -Ey+ +Ey- -Ey- +Wx -Wx +Wy -Wy
-- ------------ ------ ------ ------ ------ ------ ------ ------ ------ ------ ------ ------ ---
--- ------ ------ ------ ------ ------ ------ ------ ------ ------ ------ ------ ------ ------ -----
- ------ ------ ------ ------ ------ ------ ------ ------
1 G+Q *F 1.35 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00
1.50 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
2 G+Q 1.00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00
1.00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
3 G+QP11 *F 1.00 0.35 .00 .00 .00 .00 .00 .00 .00 .00 .00
.00 1.50 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
4 G+QP12 *F 1.00 .00 0.35 .00 .00 .00 .00 .00 .00 .00 .00
.00 .00 1.50 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
5 G+QP21 *F 1.00 .00 .00 0.35 .00 .00 .00 .00 .00 .00 .00
.00 .00 .00 1.50 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
6 G+QP22 *F 1.00 .00 .00 .00 0.35 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 1.50 .00 .00 .00 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
7 G+QP31 *F 1.00 .00 .00 .00 .00 0.35 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 1.50 .00 .00 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
8 G+QP32 *F 1.00 .00 .00 .00 .00 .00 0.35 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 1.50 .00 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
9 G+QP41 *F 1.00 .00 .00 .00 .00 .00 .00 0.35 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 1.50 .00 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
10 G+QP42 *F 1.00 .00 .00 .00 .00 .00 .00 .00 0.35 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 1.50 .00 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
11 G+QP51 *F 1.00 .00 .00 .00 .00 .00 .00 .00 .00 0.35 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00 1.50 .00 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
12 G+QP52 *F 1.00 .00 .00 .00 .00 .00 .00 .00 .00 .00 0.35
.00 .00 .00 .00 .00 .00 .00 .00 .00 .00 1.50 .00 .00 .00
.00 .00 .00 .00 .00 .00 .00 .00 .00
13 G+Q+Ex+0.3Ey 1.00 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00
0.80 .00 .00 .00 .00 .00 .00 .00 .00 .00 .00 1.00 .00 .00
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-2
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-3
MATERIALS DATA:
===============
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-4
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-5
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-6
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-7
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-8
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-9
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-10
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-11
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-12
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720 - GEIC (*19Z-2FNF-PL8H-AKNN)
PRE-ANALYSIS CHECKS REPORT Orion Building Design System 18.0 (04.2012) / Page: A1-13
Project: 132_11kV_Asmakh2_SS_Substructure_Rev0_210720