Rig Inspection ModuSpec
Rig Inspection ModuSpec
Course book
Land rigs - Jack-up rigs - Platform rigs
2
Rig Inspection Workshop Course book 3.0
Table of contents
Table of contents
3
Rig Inspection Workshop Course book 3.0
Table of contents
4
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Chapter 01
Drilling equipment
1 Drawworks introduction.............................................................. 6
2 Rotary table ........................................................................... 44
3 Top drive introduction .............................................................. 53
4 Top drive ............................................................................... 79
5 Swivel ................................................................................... 93
6 Crown and travelling block introduction .................................... 101
7 Crown and travelling block...................................................... 107
8 Driller's console..................................................................... 117
9 Derrick ................................................................................ 124
10 Air winches introduction ......................................................... 143
11 Air winches........................................................................... 152
12 Lifting and handling equipment ............................................... 161
5
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
1 Drawworks introduction
6
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
The drawworks is one of the most important items on the entire rig. The
drawworks is (together with the mud pumps and the BOP) the most costly
component of the rig. The correct operation of the drawworks components is
often not fully understood by the rig crews.
We will explain the main operational issues in this introduction.
7
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
8
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Whip and vibration can cause wire fatigue due to the very small movement
between the wires and the stands of the drill line (see Figure 4 for the wire
specifications). When the lines are 'banging' together in the derrick, this can
cause abrasive wear. Vibration may also cause lateral movement of the
sheaves, thus causing abrasive wear.
9
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
For example, the drill line in use is 1" x 5,000' 6x19 S PRF IPS IWRC. What
does that mean?
1" = diameter of the line (in inches)
5,000' = length of the line (in feet)
6 = amount of strands per line
19 = amount of wires per strand
S = seal pattern
PRF = preformed strands
RRL = Right Regular Lay
IPS = Improved Plow Steel
IWRC = Independent Wire Rope Core
10
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
60 seconds
x stand length (feet) x number of lines
Block speed seconds/stand
11
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Question: There are six sheaves reeved on the crown-block. How many
'lines' are strung?
Answer: Twelve lines.
Question: What is the mechanical advantage rate of this set-up?
Answer: 12:1
Question: When the load on the block is 400,000 lbs, what is the load on
the fastline?
Answer: 33,333 lbs (ignoring the friction)
Question: When the load is lifted 100 feet into the derrick, how much
wire is taken from the drawworks drum?
Answer: 1,200 feet
12
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Fleet angles
Rate A:B Fleet angle
degrees
0.009 0.50
0.013 0.75
0.017 1.00
0.022 1.50
0.026 1.50
0.031 1.50
0.035 2.00
Figure 10 - The drawworks fleet angle and the table showing how to
calculate the fleet angle.
The fastline should line up with the centre of the drawworks drum. The angle
of the wire in relation to the centre line is called the fleet angle. An
excessively large fleet angle will cause wear on the side of the drill line.
13
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Question: How do we calculate the fleet angle (see the right-hand picture of
Figure 10)?
Let's assume that the distance B = 150 feet and distance A = 3 feet. This
means that the ratio between A and B is A:B = 3 : 150 = 0.02. As this is
closest to 0.022, it means a fleet angle of 1.5 degrees.
The maximum fleet angle for smooth drums is 1.5 degrees.
The maximum fleet angle for grooved drums is 2.0 degrees.
The mathematical calculation for the fleet angle is tan W = A:B
14
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
15
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 13 - The Lebus groove with the drill line installed in the
recommended way.
16
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 14
Figure 15
Figure 16
Cutting the line allows worn sections to be removed from the system. Simply
slipping is not recommended, as it does not move the crossover points on
the drum. As the drill line diameter reduces with wear, any worn drill line
(i.e. with a smaller diameter) kept on the drum may result in spooling
problems and further damage.
17
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
1.4 Summary
The most likely effects of wear are the following:
1. Crossover and pick-up points are most critical.
2. The fastline speed/whip/vibration needs to be controlled.
3. The need to carry out a rig-up to verify the fleet angle is correct.
4. Increased maintenance to ensure that the sheave and drum grooves are
in good condition.
5. Increased checks on the drill line diameter.
6. Increases in the cut-and-slip programme to move the critical wear
points.
18
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
19
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Description
The NOV ADS-10D Automated Drawworks System (ADS) is used for hoisting
the travelling equipment of a drilling rig to remove and insert tubulars into
the wellbore. The ADS is a gear-driven drawworks with VFD-controlled AC
motors and multi-plate friction brakes. Optional-resistive (regenerative)
braking via the main motors can be applied to augment the friction brakes.
The drawworks components are mounted on a unitized skid. The driller, at
an operator control station, uses a dedicated joystick and switches in order
to remotely operate the ADS through a Varco Integrated Control Instrument
System® (V-ICIS).
Wire rope drum
The wire rope drum is supported by two bearing carriers mounted to a
structural steel skid. The drum is fitted with Lebus grooving for customer-
specified wire. A crown saver toggle valve is located above the drum. The
valve is located where it can be activated by the wire rope, just short of the
point at which a crown collision would occur. When the valve is activated, it
sends a signal to a crown saver pressure switch that disengages the clutches
and activates the brakes and stops the drum rotating.
Gearboxes (dry sump)
The 1500-horsepower, single-speed, double-reduction gearboxes transfer
power between the AC motors and the wire rope drum. Mounted on the
clutch shaft is a pneumatically released, spring-operated multi-disc clutch
that transmits torque between the first and second gear reduction. The
clutch must be engaged for velocity control by the motors during hoisting
and lowering. Lubricating oil for the gears and bearings is supplied by an
external electrical pump system with a frame-mounted reservoir.
Gearboxes (wet sump)
The wet-sump gearbox is similar to the dry-sump gearbox, apart from the
fact that the lubricating oil for the gears is supplied by the sump inside the
gearbox. Lubricating oil for the bearings is supplied by an external lube
system.
Clutch
The clutch provides the opportunity to disengage the drive motors from the
drum shaft. It is used in ESD situations to reduce the (motor) inertia that
the plate disc brakes must retard. It is also used when electrical repairs or
maintenance tasks are being performed, and when it is necessary to tune
the VFDs by running motors or the change of motors.
AC motors
The ADS uses 1,150-horsepower (continuous rating), variable-speed AC
motors to drive the wire rope drum through the gearboxes. The motors are
coupled to the gearboxes with double-spherical gear drive couplings. The
wide range of motor speed allows the ADS to achieve a broad range of
hoisting speeds. The use of multiple motors increases the hoisting capability.
Motor blowers
The motor blowers provide open-loop, forced-air cooling to the AC motors.
20
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Friction brakes
The brake is a combined spring-/air-operated, multi-plate disc brake. It
applies braking to the drum during operations, as well as parking braking.
Two braking methods are available to the operator: dynamic breaking using
the friction brakes, and regenerative braking through the AC motors. One
brake is mounted at each end of the drum shaft. The rotating brake discs
are spline-coupled to the drum shaft, and the brake housing is attached to
the skid. Each brake has three water-cooled discs for dynamic braking
control and a single, air-cooled brake disc for extra static parking and
emergency stopping capacity.
Rotary encoders
Rotary encoders provide speed and block position information. Encoders are
directly coupled to each motor and coupled to the clutch shaft by means of a
drive belt.
Sensing and feedback devices
Sensing devices are used to monitor the equipment functions. Sensor device
outputs are sent to the control system, where they are processed to provide
feedback for closed-loop control and to display status information to the
Driller. Several types of sensing devices are used.
ADS control system
The ADS control system processes all the data from the operator controls to
the drawworks, and all the feedback from the drawworks to the operator.
The processed data is used to control all the drawworks functions, and to
inform the operator of the drawworks operations and status. The control
system also provides the following safety features:
• drill line protection
• collision protection
• equipment protection
Optional desert kit
An optional desert kit includes sand filters on the blowers and 55ºC ambient-
temperature-rated ancillary motors (blower motors and lubricating-oil pump
motor) and main AC motors.
21
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
22
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
23
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
24
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
25
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
26
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
27
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Component specifications
Size
Height (max.): 101 inches
Width (max.): 120 inches
Length (max.): 296 inches
Weight (max.): 100,000 lbs
AC motor
Power rating (max.): 1,400 horsepower (intermittent)
1,150 horsepower (continuous)
Speed (max.): 3,000 rpm
Cooling (each motor): 3,000 square cubic feet per minute of air
Gearbox
Type single-speed double-reduction parallel shaft
Ratios: 10.71:1 overall (dry sump)
10.69:1 overall (wet sump)
2.90:1 first stage (input) (dry sump)
2.77:1 first stage (input) (wet sump)
3.69:1 second stage (dry sump)
3.86:1 second stage (wet sump)
Torque rating: 11,000 ft-lbs input shaft (dry sump)
13,500 ft-lbs input shaft (wet sump)
Weight: 13,000 lbs (dry sump)
14,250 lbs (wet sump)
Brake
Brake size: 4-plate, 36-inch diameter
Dynamic braking type: 3-disc, water-cooled, pressure-applied
brake system
Emergency parking brake type: spring-applied, air-cooled, pneumatically
released multi-disc brake (engages three
dynamic discs and the single air-cooled disc)
Min. rig air pressure required: 135 psi
Max. dynamic braking torque at: 120 psi / 183,750 ft-lbs
Max. particle size: 5 microns (air quality as per ISA Standard
S7.3-1981)
Dew point: 10ºC below minimum ambient temperature,
not to exceed 2ºC in any case.
28
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Brake cooling
Flow rate to each brake: 195 GPM
Brake cooling system: 6.0 M BTU/hr (total continuous) with heat
dissipation capacity required
Power rating: 1,950 horsepower each (150ºF max. outlet water
[continuous] temperature and 50ºF max.
temperature rise)
Water inlet pressure: 40 psi max.
Wire rope drum
Wire rope diameter: as per customer specification
Drum core diameter: as per customer specification
Drum length: as per customer specification
Grooving: Lebus
Wire rope
Type: 6x19 Extra Improved Plow Steel (EIPS)
Specification: API Spec 9A (Wire Rope)
Power requirements (electric and pneumatic)
Control system: 120 V AC / 60 Hz / 15 A
Pressure: 135 psi
29
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
30
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 26
Critical load path.
Figure 27
Typical drawworks with
band brakes.
31
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 28
There should be no
unauthorized welding on
lifting equipment,
including the balance bar.
Perform a wobble test to
check the clearance.
Note: The maximum
clearance for a National
drawworks is 0.020 inch
(= 0.5 mm).
Figure 29
Figure 30
32
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 31
Figure 32
Figure 33
33
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 34
Figure 35
Figure 36
34
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 37
Figure 38
Figure 39
35
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 40
Figure 41
Figure 42
36
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 43
Drawworks should be
fitted with Lebus drums
to make sure the drilling
ling spools correctly,
reducing wear and tear
on the wires.
Figure 44
Figure 45
37
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 46
Figure 47
Figure 48
38
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 49
Figure 50
Figure 51
39
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 52
Figure 53
Figure 54
40
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 55
Figure 56
Damaged, homemade
spliced wires should not
be used for the break-out
line.
Figure 57
41
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 58
Figure 59
Figure 60
42
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 61
Figure 62
Figure 63
Example of a drawworks
on a rig with low
operating standards.
43
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
2 Rotary table
Rotary table checklist
• Take out a permit-to-work (PTW) and isolate.
• Check the condition of the brake housing.
• Check the condition of the chain and sprockets (maximum chain stretch
3% as per API RP 7F).
• Ensure that the electrical cables and junction boxes have an EX rating.
• Check the condition and operation of the gearbox.
• Review any oil analysis reports, record the frequency.
• Review backlash measurement records.
• Function-test at 120 rpm for 30 minutes in a clockwise rotation.
• Function-test in an anticlockwise rotation at slow speed.
• When function testing allow time for the unit to warm through. Then
check the noise and vibration levels. Do not run in reverse for prolonged
periods.
• Check the condition of the main bearing.
• Ensure that the DC motors draw cooling air from outside the hazardous
areas and that spark arrestors are fitted on the discharge side.
• Ensure that there is safety matting fitted around the rotary table.
• Check and record any wear on the master bushings and inserts, and note
down the position of the drill pipe in the slips.
• Check the manual locking system. (*)
Figure 64
44
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 65
Figure 66
Figure 67
45
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 68
Figure 69
Figure 70
46
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 71
Figure 72
Figure 73
47
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 74
Figure 75
Clear indications of
excessive wear on the
tapered inserts and master
bushings; the slips are
also going in too deep.
Figure 76
Disassembled bearing of
the rotary table. Note the
lack of lubrication and the
condition of the balls and
race.
48
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 77
Figure 78
Figure 79
49
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 80
Figure 81
Figure 82
50
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 83
Figure 84
It is becoming more
common to find hydraulic
drives for rotary tables.
Figure 85
51
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 86
Figure 87
Figure 88
52
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
We will 'build up' this top drive and show all its major components: the top
drive assembly, the pipe handler, the retractable dolly and the hydraulic
system.
53
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
54
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
The upper part of the top drive contains the following elements:
1. gearbox
2. gear oil pump
3. gear oil cooler
4. motor coupling
5. drilling motor
6. parking brake
7. blower
8. motor bracket
9. lantern
10. wash pipe
11. S-pipe
12. suspension bail
55
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
56
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
57
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 98
The support frame for the drilling motor.
Figure 100
The wash pipe with a 3¾-inch ID.
58
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 101
S-pipe ID is 3 inches, pressure rating 7,500
psi.
Figure 102
Suspending compensating system.
59
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
60
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
61
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
62
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
63
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
64
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
65
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 120 -
Retractable dolly.
Figure 121
66
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 122
Gearbox type 2PV40.
Figure 123
Gearbox type 2PV40.
67
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 125
Baylor CM628TUT AC
drilling motor.
Figure 126
AC drilling motor.
68
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
69
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
70
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
71
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 135
Link hanger.
Figure 136
Spring disc package.
72
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 137
Locking cylinder.
Figure 138
The back-up grabber.
73
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
74
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 143
75
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
76
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
A support bracket includes the hydraulic and pneumatic control valve blocks,
instrument junction boxes, pressure switches, etc.
77
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
78
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
4 Top drive
4.1 Top drive checklist
• When was the last overhaul (as per API RP 7L section 4.2) performed
and when were the OEM's safety recommendations carried out? Equally
important, when is the next major overhaul due?
• Inspect the condition of the service loop in the derrick.
• Is there a spare service loop available?
• Is the protection frame well secured?
• Check for oil leakages.
• Review and record the sampling/analysis frequency.
• Are there swivel clearance records and is there a spare wash pipe?
• Is a high-torque DC motor fitted and is it in good condition?
• If it is DC drive, is there a spare DC motor with a special hub and
bearings?
• Are there spare AC motors for the top drives with a VFD system?
• Check the condition of the torque arrestor pins.
• Verify the NDT inspection reports for:
o the pipe handler
o the main shaft/load collar
o the IBOP
o the elevator links
• Check the link tilt operation condition and condition.
• Confirm that the electric cables and junction boxes have an EX rating.
• Are there dolly wheel catchers installed?
• Have the latest Varco or other (OEM) upgrades been implemented?
• Check the records of the swivel bearing clearances and verify if the
swivel is integrated with the top drive.
• Are dropped-objects and post spud procedures in place?
• Are the safety clamps correctly installed on the mud hoses (API Spec 7K
section 9.10.4 Table 8/Figure 10 and IADC Safety Alert 00-24)?
• Are the inspection intervals on the mud hoses as per the OEM
recommendations?
• Check for any exposed wire banding under the outer rubber of the hose
(ISS-059 Inspection Guidelines for high-pressure hoses).
• Is the spare mud hose installed in the derrick? (*)
79
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 151
Figure 152
Figure 153
80
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 154
Clear misalignment
between the top drive and
the centre of the rotary
table. This can be
adjusted on the top drive.
Figure 155
Alignment cylinder to
enable the adjustment of
the top drive in relation to
the well centre.
81
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 156
Figure 157
82
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 158
Figure 159
83
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 160
Commutator of a standard
DC motor.
Figure 161
Commutator of a high-
torque DC motor. Square
section cooling passage,
or perhaps a pineapple?
Easiest way to tell is by
looking here. It also
shows a good quality EX
space heater.
84
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 162
Figure 163
85
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 164
Figure 165
86
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 166
Figure 167
Figure 168
87
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 169
Figure 170
88
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 171
Figure 172
89
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 173
Figure 174
Figure 175
90
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 176
Figure 177
Schematic drawing
showing seal arrangement
in wash pipe assembly.
91
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 178
92
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
5 Swivel
Checklist (independent) swivel:
Figure 179
93
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 180
Figure 181
Figure 182
94
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 183
Figure 184
An alternative procedure is to
place a hydraulic jack under
the shaft. Note that the wash
pipe has been removed.
Alternatively, suspend the
swivel on a chain hoist, land it
on a flat surface, and then
carefully raise it.
95
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 185
Figure 186
96
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 187
Figure 188
Figure 189
97
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 190
Figure 191
98
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 192
Figure 193
99
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 194
New-generation wash
pipe assembly.
Figure 195
Specifications for the commissioning test of the newly designed wash pipe
assembly:
• 2,000 hours at 5,000 psi/150 rpm with Nova Plus mud (including 1,000
hours with 0.006-inch intentional perpendicular misalignment)
• 4 hours at 7,500 psi/150 rpm (test stopped after no failures)
• 4 hours at 7,500 psi/225 rpm (test stopped after no failures)
• 200+ hours at 5,000 psi/150 rpm with Aqua Gel mud (test stopped after
no failures)
100
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
101
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Note: There must be no tension on the drill line and the travelling blocks
need to be hung off.
102
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 200 and Figure 201 - Groove radius and sheave gauges.
The radiuses of the sheaves are measured with sheave gauges. For each type
of sheave the maximum wear is already incorporated in these gauges; for
instance, the 1⅜" sheave has a "+ factor" of 1/32 inch, expressing the
maximum wear.
103
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Some rigs use a single sheave Depicted here is a sheave cluster with a
for the fastline, as these wear set of automatic grease cartridges
faster than all the other sheaves. installed, which reduces the number of
Also, changing the bearings on a visits to the crown block platform for
single sheave is much easier greasing purposes.
than on a cluster of sheaves.
104
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
105
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
106
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
107
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 211
Figure 212
Figure 213
108
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 214
Performing a wobble
test: checking for
poor/worn sheave
bearings or cracked
sheaves. The bar is a
little too long.
Figure 215
Performing a wobble
test; checking for worn
bearings or sheave
bosses loose on the outer
race and the inner race
slack on the pin. One bar
is a little long, the other
simply ridiculous.
Figure 216
109
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 217
Figure 218
Figure 219
110
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 220
Figure 221
Figure 222
111
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 223
Figure 224
Approximately 90% of
the sheaves are
condemned after five
years. The sheave profile
is excessively worn or
too soft, or cracks are
present as on this
sheave (parallel to the
sheave profile).
Figure 225
112
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 226
Figure 227
Figure 228
113
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 229
Long-term storage of
the travelling block in a
vertical position. The
unauthorized welding
used here to secure the
block in the vertical
position can actually
cause severe damage on
the bearings.
Figure 230
114
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 231
Figure 232
115
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
116
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
8 Driller's console
8.1 Driller's console checklist
• Check that all the gauges are working. Record the last calibration date.
They should be tested every three years to 1% full scale (API RP 53
section 12.5.3.g)
• Is the purge air system working? (API RP 14F sections 3.2.3 and 4.3.1.2)
• When was the last recorded purge air alarm test conducted (visual and
audible)?
• Does the driller have a clear view of the monkeyboard and the crew
working it?
• Does the driller have a clear view of the casing stabbing board and the
crew working it?
• Does the load limiter or load management system for the generators
work?
• Are there proper communications with the monkeyboard and casing
stabbing board?
• Check the condition of the compliant electrical cables and junction boxes
and verify their EX feature.
• Is safety glass used on the windows?
• Is the lamp test system operational?
• Are there any non-resettable alarm lights showing? Are the labels on the
control panels engraved (no graffiti)?
• What is the condition of the mud pit level indicators (API RP 53 section
15.7)? (*)
Figure 235
Purge air-protected
control box fitted with
a load management
system.
117
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 236
Figure 237
Figure 238
118
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 239
Figure 240
Figure 241
119
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 242
Figure 243
Figure 244
Another advanced
driller's console installed
on a jack-up rig.
120
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 245
Figure 246
Home-made temperature
thermostat fitted in the
Driller's house. This thing
is not really EX rated!
Figure 247
121
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 248
Figure 249
Figure 250
122
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 251
Condition of a driller's
console found on a rig
operating in areas with
poor standards.
Figure 252
123
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
9 Derrick
9.1 Derrick checklist
• When was the last Category IV derrick inspection performed as per API
RP 4G section 5.1?
• What is the load rating of the derrick (API RP 4G section 15.7)?
• Is there an inspection programme in place?
• Check for bent or damaged beams and cross members (API RP 4G
section 3).
• Inspect the NDT inspection reports for the fingerboard.
• Verify that the fingers are fitted with acceptable safety chains, wire
slings or wire rope.
• Ensure that air hoist cables are not rubbing against any beams or
fingers.
• Make sure load carrying wires are fitted using shackles and pad eyes not
slung across beams.
• Confirm that the illumination in the derrick leaves no dark spots.
• Ensure that all light fittings have secondary retention.
• Is there a dropped-objects procedure in place?
• Is there an inspection programme for the raising lines (land rigs)? How
many raising/lowering cycles are performed between changes (API RP
4G section 4)?
• Is the derrickman correctly secured against falling when working on the
monkeyboard?
• Check the mechanical condition of the Geronimo escape and escape line.
• Check the condition of the derrick ladders and platforms, self-closing
barriers, handrails and back-scratchers (API RP 54 section 9.3.17).
• Are suitable toe boards installed? (API RP 54 section 9.3.19).
• Check the condition of the omnidirectional aircraft-warning lights.
• Review the certification and check the condition of the travelling-block
hang-off lines and shackles (API RP 9B).
• Are wooden bumper blocks covered with a heavy-duty wire mesh (API
RP 54 section 9.2.16)?
• Are all hinged platforms in the derrick secured with safety chains?
• Ensure that snatch block safety wires have a SWL which is at least twice
the SWL of the hoist wires (dynamic impact). (*)
124
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 253
Figure 254
125
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 255
Figure 256
Figure 257
126
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 258
Figure 259
Figure 260
127
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 261
Figure 262
Figure 263
128
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 264
Fingerboard at the
monkeyboard level. None
of these fingers were
secured with an
additional safety sling or
chain. Each of these
unsecured fingers
represents a serious
dropped-object hazard.
Figure 265
Figure 266
129
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 267
Figure 268
Smashed wooden
bumper blocks. No
heavy-duty wire mesh
installed: once again a
serious dropped-object
hazard.
Figure 269
Severely damaged
wooden bumper blocks,
but thanks to the heavy-
duty wire mesh the
wooden splinters did not
fall onto the drill floor.
130
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 270
Figure 271
Figure 272
131
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 273
Self-closing gates
installed at the
monkeyboard level.
Figure 274
132
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 275
Figure 276
Pipe-handling equipment
is becoming more
common on many rigs.
No matter what it does
many of the components
will be the same as other
drilling equipment: pipes,
hoses, pistons, seals,
bearings, chains rollers,
sprocket and wires.
133
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 277
Figure 278
134
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 279
Figure 280
Figure 281
135
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 282
Figure 283
Figure 284
136
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 285
Figure 286
Weekly derrick
inspections should find
and remove these items.
137
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 287
Figure 288
Figure 289
138
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
139
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 290
Figure 291
140
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 292
Figure 293
Figure 294
141
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 295
Figure 296
142
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
143
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
144
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
145
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 306
Spooling device for the
man rider.
146
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 307
Figure 308
Figure 309
147
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
148
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
149
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Valve cabinet
The valve cabinet houses all the main valves and critical components for the
winch. The valve cabinet is totally enclosed for long-term operation in a
corrosive environment.
Hydraulic valves
All the valves for the winch are installed inside the motor side cabinet, to
protect them from any external mechanical and/or chemical damage.
Control panel
The winch can be operated locally from the winch control panel or from the
pendant hydraulic remote control. Both control panels have the following
control functions:
• Emergency stop
• Brake for stopping the winch
• Winch up/down control lever for stepless speed/direction control of the
winch
The control panel is located on the winch. A local main control valve is fitted
into the control panel for the winch system. The valve is equipped with a
winch-hoisting/ pressure-limiting valve and flow-limiting valve for easy
connection to the rig's ring-line system with overcapacity. The control panel
is also equipped with clear operating instructions.
To achieve a better view and communication between the operator and the
man-rider, an extra pendant hydraulic remote-control device is installed. The
pendant remote is fitted with a control valve and an emergency brake valve,
and is hydraulically connected to the main panel by means of a 6-metre-long
multi-hose. Upon request, a cordless radio-operated control system is also
available.
Wire
The winch is equipped with 110 metres of 10-mm rotation-resistant wire.
The wire is fastened to the drum by three bolted clamps. The outer end of
the wire is equipped with a closed spelter socket of an offshore type.
150
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
151
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
11 Air winches
11.1 Air winches checklist
• Check the condition of the brake lining (no oil contamination is allowed).
• Ensure that the brake linkage system and adjustment is correct.
• Make sure that a ball valve is used on the air supply line and that the
handle is within easy reach of the operator.
• Ensure that the free-fall handles on hoist winches have been disabled or
removed.
• Check for oil and air leaks.
• Check the condition of the wire-end termination.
• Check that the winch control handle returns back to neutral when
released.
• Ensure that permanent safe working load (SWL) signs are clearly
displayed.
• Ensure a protective cage is fitted.
• Make certain a spooling device is fitted.
• Confirm the controls correctly indicate "Up" and "Down" functions and
are the same on all winches.
• Check the condition of the winch foundation and foundation bolts, as well
as any NDT inspection records.
• Verify that an exhaust noise suppressor is fitted.
• Check the condition of the snatch blocks and review their inspection
reports.
• Ensure the sheave snatch block is at least eighteen times the diameter of
the wire in use.
• Check the condition of the wire (API RP 9B).
• Confirm that the man-riding winches are fitted with automatic and
manual brakes.
• Confirm that the man-riding winches have non-rotating wire installed.
• Ensure that no rubber hoses are fitted in the man-riding winch air supply
line.
• Check the maximum pull/speed adjustment on the man-riding winches is
correct.
• Ensure that dedicated man-riding winches are installed in their area of
operation.
• Confirm that there is an accumulator system for the man-riding winches,
if applicable. (*)
152
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 310
Figure 311
Figure 312
153
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 313
Oil-contaminated brake:
the brake lining should be
replaced first.
Figure 314
Figure 315
154
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 316
Figure 317
Figure 318
155
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 319
Overstressed foundation
bolt with a very low-
quality safety pin.
Figure 320
Figure 321
156
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 322
Figure 323
Home-made spooling
device, perfectly suitable
for this application. Notice
the silencer on the air
exhaust.
157
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 324
Figure 325
Home-made spooling
device that operates
satisfactorily.
Figure 326
Automatic line-spooling
device and line-tensioning
system installed. The
drum guard was removed
for this inspection.
158
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 327
Figure 328
A designated man-riding
winch?
Figure 329
159
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 330
Figure 331
Figure 332
160
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
161
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 333
Figure 334
Figure 335
162
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 336
Unauthorized welding of an
extension to the tong arm.
Figure 337
Figure 338
163
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 339
Unauthorized welding to
connect the tong dies on
the casing tong. This
element can shatter into a
thousand pieces under
load!
Figure 340
Figure 341
164
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 342
Figure 343
Figure 344
165
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 345
Figure 346
Unauthorized welding of
the rig number onto the
elevators. This elevator
must be scrapped
immediately.
Figure 347
166
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 348
Figure 349
Unauthorized welding on
the safety clamps.
Figure 350
167
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 351
Figure 352
Figure 353
168
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 354
Rig-made handling
equipment must not be
used.
Figure 355
Figure 356
169
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
Figure 357
Figure 358
Figure 359
170
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
171
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
172
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
173
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
174
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
175
Rig Inspection Workshop Course book 3.0
01 Drilling equipment
176
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Chapter 02
Mud-processing equipment
177
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
1 Mud pumps
1.1 Mud pumps checklist
• Check the condition of the drive chains and sprockets, or belts and
pulleys.
• Confirm the operation of the VFD AC driven pumps.
• Test and record the main and pinion shaft bearing clearances (maximum
clearance is 0.016 inch/0.40 mm).
• Visually inspect the bronze covers on the main shaft eccentric bearings
for cracks or loose pins.
• Verify and record the crosshead slide clearances (National pumps: top
clearance between 0.015 inch/0.38 mm and 0.025 inch/0.63 mm).
• Examine the oil analysis frequency and records.
• Ensure that the pressure relief valves exhaust lines slope downwards at
least 2 degrees or ½ inch per foot (API RP 54 section 9.13.7).
• Check the location of the relief valve on the discharge manifold.
• Ensure the discharge pulsation dampener installed is correctly charged.
• Ascertain the condition of the discharge strainer.
• Inspect the suction and discharge valves and seats.
• Ensure that with 3M (200-bar) systems there are no NPT-threaded
fittings (for connections of 2 inches or more) (API RP 53 sections 8.2.b
and 10.2.1b)
• Examine the suction pulsation dampener (pressure and gas).
• Confirm the condition of the suction strainer.
• Verify that the pony rods are NDT-inspected in between wells.
• Are the discharge manifold studs inspected (NDT/stretch) as per 10%
cycle every year?
• Check the condition of the manifold high-pressure valves.
• Confirm the wall thickness inspection records for high-pressure lines
(minimum 87.5% of the original wall thickness left).
• Verify the condition of the DC motors and AC motors and the last
overhaul records.
• Ascertain the condition of the electrical cables and junction boxes.
• Make sure the crew do not use silicone sealant as gasket material on the
main covers.
• Test the condition of the pony rods and seals for wear and pitting. (*)
178
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 1
Figure 2
Figure 3
179
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 4
Figure 5
Figure 6
180
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 7
Figure 8
Figure 9
181
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 10
Figure 11
Connecting-rod eccentric
bearings. It is difficult to
measure their clearances, as
the rollers are normally
enclosed with a bronze
cage, so feeler gauges
cannot be used.
Figure 12
182
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 13
Figure 14
Figure 15
183
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 16
Figure 17
Figure 18
184
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 19
Figure 20
Figure 21
185
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 22
Figure 23
Figure 24
186
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 25
Figure 26
Figure 27
187
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 28
An NDT inspection
revealed a large crack on
the main crankshaft.
Figure 29
Figure 30
188
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 31
189
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 32
These modern mud pumps have gearbox drives and are using VFD AC
motors instead of DC motors.
190
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 33
Figure 34
Figure 35
191
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 36
Figure 37
192
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 38
Figure 39
193
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 40
Figure 41
Figure 42
194
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 43
Damaged discharge
strainer.
Figure 44
Completely deteriorated
discharge strainer.
Figure 45
195
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 46
Figure 47
196
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 48
Figure 49
Figure 50
Unauthorized welding on
the high-pressure piping
and home-made pad eye
for the safety sling for
the relief valve.
197
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 51
Figure 52
Figure 53
198
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 54
Figure 55
Desperate measures:
welding the fluid ends to
the main body of the
mud pumps. This is not a
long-term solution.
Figure 56
199
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 57
Figure 58
Figure 59
200
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 60
Figure 61
Modification of above
relief valve position
meant that the strainer
could not be removed.
Figure 62
201
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 63
Figure 64
Figure 65
Incident
While bringing mud pump
No. 1 on line after making a
connection the pulsation
dampener bladder ruptured
blowing off the pulsation
dampener cap.
The pulsation dampener was
sheared from the discharge
manifold and the mud pump
sustained significant
damage. Nobody was
injured.
The pulsation dampener cap
was found in the sand
approximately 240 metres
from the mud pump/rig site.
202
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 66
Figure 67
Figure 68
203
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 69
Figure 70
Figure 71
204
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
2 Mud systems
2.1 Mud-mixing system checklist
• Is the ventilation adequate (for the indoor mixing systems)?
• Is the lighting adequate?
• Are the electrical cables and junction boxes suitable?
• Test the pressurized alarms.
• Check the housekeeping standards.
• Inspect the handrails and stairs for damage.
• Examine the condition of the dump valves for leaks.
• Test the condition of the mud agitators for noise and vibration.
• Check the condition of the mud guns.
• Confirm the condition of any butterfly valves.
• Inspect the operation of the pit level indicators.
• Ensure there are no damaged/unsecured gratings and other tripping
hazards.
• Is the trip tank design acceptable (i.e. no more than one barrel per one-
inch height)?
• Test the condition of the desilter, desander and mud cleaners.
• Check the condition and operation of the vacuum degasser.
• Confirm the condition of the mud pits.
• Inspect the suction height of the mud pits.
• Verify that the mud pits are suitable for HP/HT applications.
• Ensure that all the AC motors are EX and certified (API RP 14F section
4).
• Confirm that any fixed fire-fighting system is operational.
• Check the personal protective equipment (PPE), i.e.:
o long-sleeved rubber gloves
o rubber apron
o set of goggles and/or face mask
o eyewash station
o shower
o first-aid safety sheet of chemicals in use
o set of earplugs
• Verify that a high-quality PPE box is available?
• Test the corrosion levels of the hopper funnel and piping.
• Confirm the operation of the hopper venturi arrangement and the
eductors in the vacuum mixing system.
• Check the condition of the surge tanks for cement and barite.
205
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 72
Figure 73
206
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 74
Figure 75
Figure 76
207
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 77
Gap "b":
• For rotary hoses this
dimension shall be
between 6 (152.4 mm)
and 18 inches (457.2
mm) from the inboard
end of the coupling.
• For vibrator hoses,
this dimension shall be
6 (152.4 mm) to 10
inches (254.0 mm)
from the inboard end of
the coupling.
Figure 78
Figure 79
Complete standpipe
manifold constructed
using NPT threaded
fittings, some of which
have been welded around
the threads. This
manifold does not comply
with the API standards. If
there is a connection with
the choke manifold high-
pressure isolation gate
valves should be fitted,
and never check valves.
208
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 80
Figure 81
Figure 82
209
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 83
Figure 84
Figure 85
210
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 86
Figure 87
Figure 88
211
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 89
Figure 90
Figure 91
212
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 92
Figure 93
Figure 94
213
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 95
Figure 96
Figure 97
Unprotected rotating
shafts on the mud pit
agitators.
214
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 98
Figure 99
Figure 100
215
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 101
Figure 102
216
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 103
Figure 104
Example of poor
housekeeping around the
mud pits, resulting in
unnecessary health and
trip hazards.
217
Rig Inspection Workshop Course book 3.0
02 Mud processing equipment
Figure 105
Figure 106
218
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Chapter 03
Engine room and power plant
219
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
1 Diesel engines
1.1 Diesel engines checklist
• Ensure there are sufficient engines and power available for the drilling
programme.
• Look for oil, air, gas and water leaks.
• Verify the date of the last major overhaul (e.g. last 20,000-rhr service).
Check the OEM service hours. More importantly, when are the next
overhauls due?
• Validate the date of the next planned major overhaul.
• Check whether the oil consumption is as per the OEM specifications?
• Confirm that the engine safety devices are tested as per API RP 7C–11F
and API RP 14F section 5.2.5.1? Typical safety devices are the following:
o Low-lubrication-oil pressure
o High-cooling-water temperature
o Overspeed
o Crankcase pressure
• Verify that the overspeed tests are recorded (110% rpm).
• Inspect the condition of the insulation on all engine exhaust lines.
Exhaust insulation is mandatory for marine engines.
• Confirm whether fixed fire protection is available (mandatory on offshore
rigs).
• Validate that crankcase overpressure safety devices are installed on the
crankcase doors (on engines with bores larger than 200 mm).
• Inspect the fitting of and test the operation of the combustion air inlet
safety devices (rig saver valves).
• Verify if suitable a cooling-water treatment is performed (API RP 7C-11F
section 2.8).
• Check the electrical cables and junction boxes.
• Confirm the exhaust gas colour indication (API RP 7C-11F section 9).
• Review the oil-sampling/analysis reports and record the frequency.
• Inspect the condition of the pressure gauges and temperature sensors.
• Check the operation of turbochargers and verify that a spare
turbocharger is available.
• Verify that suitable spark arrestors are installed. All engines within 100
feet of the well head (API RP 7C-11F sections A.3e and A.1).
• Validate the condition of all the starting motors and confirm that a spare
motor is available (API RP 7C-11F section 6.3.4). (*)
220
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 1
Figure 2
Figure 3
221
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 4
Figure 5
Figure 6
EMD two-stroke
engine.
222
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 7
Figure 8
Figure 9
Large surface area.
223
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 10
Figure 11
Figure 12
An engine-monitoring
panel is a good way of
measure the performance
and conditions of the
engine. The temperature
and pressure read-outs
are to be checked several
times per day.
224
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 13
Figure 14
Over-eager painters?
Neither the temperature
nor the pressure can be
read from these illegible
gauges.
Figure 15
225
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 16
Figure 17
Figure 18
226
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 19
Figure 20
227
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 21
Figure 22
228
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 23
Figure 24
An unprotected exhaust
line with turbochargers
and the expansion piece.
Note that the
temperatures of the
exhaust gasses range
from 500 to 700 degrees
Celsius!
Figure 25
229
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 26
Figure 27
Figure 28
230
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 29
A similar model of a
diesel engine as in the
previous picture, but this
time with the correct rig
saver valve installed.
Some Caterpillar engines
have two air inlet
manifolds and, as a
result, two rig saver
valves installed: one in
each air inlet manifold.
Figure 30
231
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 31
Figure 32
232
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 33
Figure 34
Figure 35
233
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 36
Figure 37
Also third-party-owned
engines must have spark
arrestors, rig saver valves
and insulation material
installed on their engines.
Figure 38
234
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 39
Figure 40
Figure 41
Unprotected rotating
equipment on the engines.
This is a very unsafe
practice that has caused
serious accidents and
fatalities on other rigs! The
guards on rotating
equipment are nowadays an
accepted worldwide
standard.
235
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 42
Figure 43
236
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 44
Completely frozen
turbocharger on a
Caterpillar engine. This rig
apparently has an optimistic
mechanic with a can of WD-
40!
Figure 45
237
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 46
Figure 47
Figure 48
Governor 'permanently'
adjusted with a pair of
gripping pliers.
238
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 49
239
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
2 Emergency generators
2.1 Emergency generator checklist
• Verify that the switchboard shows the power available (in kW).
• Ensure the engine is designed to start during a total black-out.
• Test for fuel, oil, air and water leaks.
• Check the condition of the fan, belt and radiator.
• Examine all the gauges and the calibration.
• Ascertain that the emergency generator is tested every week (including
an automatic start).
• Ensure there is no dirt and oil underneath the engine (fire hazard).
• Confirm that there are two independent ways of starting the engine.
• Check the layout of the emergency switchboard.
• Make sure that on MODUs the room is located above the waterline.
• Test the electrical cables and junction boxes.
• Inspect to see if a spark arrestor is installed.
• Examine if a rig saver valve is fitted.
• Verify if there is a pre-heating system for the engine.
• Carry out a test run at maximum load for at least 30 minutes.
• Validate that there is adequate ventilation.
• Confirm that the fuel tank sight-glasses are protected.
• Test the remote operation of the fuel tank valve.
• Check the condition of any starting batteries and battery chargers. (*)
Figure 50
The inspection of
emergency generators
is more or less the
same as ordinary diesel
generators with
additions for Class and
MODU Code.
240
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 51
Figure 52
Figure 53
241
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 54
Figure 55
242
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 56
Figure 57
243
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
3 Air compressors
3.1 Air compressors checklist
• Record the number of the air compressors and the capacity of rig
air/bulk air.
• Verify that there is a separate bulk air compressor present.
• If there is no independent bulk compressor, verify if there are two
reducing valves fitted to supply bulk air.
• Confirm that there are at least three rig air compressors if there is no
bulk air compressor available (on MODUs).
• Check the air dryer capacity is 4ºC above the outlet air temperature.
• Test the EX integrity of the electrical cables and junction boxes.
• Examine the condition of the emergency air compressor (diesel-driven
cold-start compressor).
• Verify that all the relief valve vents are routed towards a safe area by
means of rigid piping.
• Confirm that the air receivers are purpose-built and certified.
• Validate that the air receivers are hydrostatically tested every ten years
(API 510 Chapter 6).
• Check that the relief valves are recertified every two years.
• Inspect the relief valve sizes to see if they are compatible with the size
of the pressure vessels.
• Test the oil-sampling and analysis frequency.
• Validate that the rig carries out wall thickness measurements on the bulk
silos and piping (as a standard, 87.5% of original wall thickness must be
left).
• Verify if the crew tests the high-temperature air shutdown on all the
screw-type compressors. (*)
Figure 58
Well maintained
compressors and air
systems. Offshore, if
there are only two
compressors then a
separate bulk compressor
should be available. Air
supply shall be taken
from a safe area.
244
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 59
Figure 60
Figure 61
245
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 62
Figure 63
Figure 64
246
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 65
Figure 66
A cold-start air
compressor but with an
exposed battery. But
even worse it has no air
filter.
Figure 67
Running reciprocating
compressors without an
air filter is the main
cause of air receiver
explosions.
247
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 68
Figure 69
Figure 70
BOOM!
248
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 71
Figure 72
Figure 73
249
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 74
250
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
4 Cranes
Figure 75
Unauthorized welding
performed on this boom
pin to 'solve' the excessive
play.
Figure 76
Figure 77
251
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 78
Figure 79
Figure 80
252
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 81
Figure 82
Figure 83
253
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 84
Figure 85
Figure 86
254
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 87
Figure 88
Figure 89
255
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 90
Figure 91
Figure 92
256
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 93
PA speakers and
floodlights. These are all
additional safety items but
here not one has a safety
sling fitted.
Figure 94
Figure 95
257
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 96
Figure 97
258
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 98
Figure 99
259
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 100
Figure 101
Standard thimble.
260
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 102
Wedge socket.
Figure 103
Figure 104
261
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 105
Figure 106
Figure 107
262
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 108
Figure 109
263
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 110
Figure 111
Figure 112
264
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 113
Figure 114
Hydraulic clutches on a
link belt crane are prone to
seal a leak on a central
hydraulic cylinder spraying
hydraulic oil over the
clutch shoes.
265
Rig Inspection Workshop Course book 3.0
03 Engine room and power plant
Figure 115
Oops!
266
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Chapter 04
Electrical equipment
267
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 1 - General view of the Baylor 7838 eddy current brake with
low-temperature shaft and reverse junction box.
In Figure 1 there are four field coils installed, which are installed in a static
frame with bearings. The rotor is connected fixed to the shaft which is
connected to the drawworks shaft. The water level inside the eddy current
brake must remain below the bearings, which are sealed and protected from
the 'water spray', but the bearings must not be flooded.
The vent and overflow outlets prevent this flooding. On this drawing there
are three air gap inspection holes, which allow the rig's crew to measure the
clearances between the rotor and the coils on a monthly routine. The air gap
measurements can be used to calculate the eddy current brake's efficiency.
268
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
General explanation
When the steel rotor rotates through the stationary magnetic field, currents
are induced in the rotor. These currents, commonly called 'eddy currents',
produce a magnetic field which interacts with the stationary field.
This field interaction produces a force, which opposes rotor rotation, and
provides the braking torque for the Baylor brake. The braking torque of the
eddy current brake is dependent on the strength of the stationary magnetic
field, rotor speed and rotor temperature.
The torque increases with the magnetic field strength and with the rotor
speed. Torque decreases as the rotor temperature rises and the rotor
expands, which widens the air gap. The strength of the stationary magnetic
field is controlled by the field coil in proportion to the braking requirements.
The eddy currents induced in the rotor produce heat. This rotor heat must be
kept within acceptable limits or the braking torque will be reduced. To
maintain rotor temperature within acceptable limits, a cooling system is
required.
A steady flow of water is directed into the area containing the rotor. The
movement of the rotor through this water as it turns provides the uniform
cooling of the rotor surface. If the flow of cooling water fails while the brake
is in operation, the rotor will become overheated. In this state, the rotor will
be damaged if a safe cooling procedure is not followed.
269
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
The water outlet(s) at the bottom of the brake should not be hardpiped or
otherwise restricted. This should be a free-flowing gravity drain. A funnel-
type drain as illustrated in Figure 3 is preferred. Do not plug, pipe, connect
hoses to, or otherwise obstruct the water overflow outlets, located on the
brake just below the shaft centerline. These overflow outlets provide a
warning of improper water flow conditions.
The eddy current brake allows cooling water to flow over the lower sections
of the magnets and rotor before it exits at the bottom. If the cooling water
outlets are restricted, the water level inside the brake will increase to a level
which could damage the bearing grease seals, and permit water to enter the
bearing cavity with ultimate damage resulting to the bearing.
CAUTION!
The eddy current brake is not designed to operate with the cooling water
internal of the brake at other than atmospheric pressure. For proper brake
operation ensure that brake cooling water flows unrestricted through the
brake with gravity discharge and unrestricted flow back to the cooling water
reservoir.
Radial bearing clearance
Measuring radial bearing clearance upon receipt of a new or factory rebuilt
brake is a method that will allow the prediction or verification of bearing
failures.
Note: In order to carry out this measurement, the brake must be uncoupled
from the drawworks.
270
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
A dial indicator is placed at the top dead center of the shaft's vertical
centerline, and the shaft is lifted. Care must be taken not to apply more
force than one half the combined weights of the rotor and shaft. Care must
also be taken to insure the dial indicator is perfectly vertical and properly
zeroed.
As with any lifting operation, all lifting apparatus must be properly sized, and
qualified personnel must perform the lift. The radial clearance data should be
recorded for future use. This information can be used later to predict bearing
failure.
The bearing manufacturer will indicate that a bearing that is in the process
of failing will undergo microscope surface failures prior to a complete failure.
When this begins to happen it is impossible to observe these surface failures
with a radial clearance measurement, but a large deviation from the original
measurement will indicate the failure process is well underway and a bearing
replacement should be planned.
Shaft alignment
Angular misalignment and offset misalignment between directly-connected
shafts often cause increased bearing loads and vibration, even when the
connection is made by means of flexible coupling. Shaft alignment is
especially critical if the coupling is to be operated at high speed
271
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Cooling-water quality
In order to function properly, the cooling water used in eddy current brakes
must meet four basic requirements:
1. It must adequately transfer heat energy from the rotor to the heat
exchanger used for cooling.
2. It must not form scale or sludge deposits in the brake or in the cooling
system.
3. It must not cause corrosion in the Brake or cooling system.
4. It must not deteriorate any of the seals or gaskets used in the brake or
cooling systems.
These requirements are normally met by combining suitably de-mineralized
water with a reliable corrosion inhibitor. Under extreme operating conditions
it may be necessary to use an antifreeze coolant. In this case the cooling
liquid should be a mixture of the ethylene glycol type antifreeze, de-
mineralized water, and an adequate corrosion inhibitor.
272
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
273
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
full excitation. This can reduce the excitation to the larger capacity brakes
from 21 kW to 7 kW with the reduction of thermal load of field coils.
Operation of the brake at very low speeds during drill assist, with full
excitation, will also contribute to excessive wear to the ID of the rotor and
the OD of the magnets. At very low rotor speeds, with full excitation to the
field coils, the magnetic attraction between magnets and rotor is greater
than the collapse strength of the rotor material.
Pull over will occur where the outer circumference of the rotor drum will pull
down and contact the OD of the magnet. The resultant contact, at slow
speed, will gall and gouge the surfaces of rotor and magnets. This
mechanical contact will increase the air gap between the rotor ID and the
magnet OD such that maximum torque of the brake will be reduced.
In conclusion it should be said that utilizing the Baylor eddy current brake in
the drill assist mode requires specific attention regarding the level of
excitation applied to the field coils.
Note: Continuous operation at full excitation can significantly shorten the
life of the field coils and increase the air gap dimension such that reduced
torque output will result.
National Oilwell Varco manufactures several different types of control systems
for use with the Baylor eddy current brakes. Each control system design
incorporates a different method of supplying reduced voltage to the brake
during drill assist operations.
Cooling-water alarm
A cooling water alarm system is available to monitor flow and temperature
of the coolant to the brake. This system warns the operator whenever
cooling to the brake has been impaired. It can prevent the need for
expensive repairs. Note: This is also required to maintain the hazardous-
area certification on the brake.
Cooling water treatment
The silicate nitrate inhibitor is basically non-polluting. Be sure to follow the
manufacturer's recommendations for applying the inhibitor. Both for new
untreated water and for maintenance of already treated water, the
recommended inhibitor is Nalcool 2000.
Warning! If glycol antifreeze is used, Nalcool 3000 is recommended due to
possible interaction with the glycol, which causes sludge.
Water quality standards with Nalcool
1. Ensure that the water quality meets the water quality standards.
2. Coolant has a pH level of 8.3 after corrosion inhibitor has been added
(the coolant solution turns pink)
3. The recommended nitrite level is 1,500 parts per million.
For long-term storage a 50% solution of Nalcool with clean water is
recommended.
274
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Air gaps
If there is erosion/corrosion in the air gap between the rotor ID and the
magnet OD due to the use of poor quality cooling water, this gap distance
may gradually increase to a point where rated torque will be reduced. In
making any field check of this air gap, it is necessary to allow for any pitting
and for any scale build-up to determine the effective gap distance.
Any scale present does not provide an effective magnetic path so it must be
deducted from the gap distance measurement. This air gap should be
checked monthly. The effective air gap is the average of all measurements
taken. Measurements should be taken at each air gap inspection hole (both
inboard and outboard) and recorded. Then rotate the rotor assembly 90
degrees clockwise and record the measurements. Do this three times.
275
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Finally, rotate rotor assembly another 90 degrees clockwise. This will bring
you back to the original position and readings should agree with first position
readings. Normally, a 50% increase in the air gap will produce a 70%
decrease in rated torque. For the Baylor 7838 eddy current brake, the air
gaps should vary between 0.055 and 0.065".
Coil-readings
During the monthly routine maintenance the individual coils need to be
measured. The values are listed in the table in Figure 9. Note that these
values might differ if the temperature is not close to 20 degrees Celsius.
There is no difference between the inboard and the outboard magnets.
The leads are numbered for convenience in wiring and to assist in proper coil
lead connection to ensure a proper coil polarity. The outboard magnet leads
are F1, F2, F3 and F4. The inboard magnet leads are F5, F6, F7 and F8. If
there is a need to convert an inboard magnet to an outboard one or vice
versa, the following table should be used:
• F1 = F8
• F3 = F6
• F2 = F7
• F4 = F5
Therefore, the inboard and outboard magnets are mechanically and
electrically interchangeable.
Insulation to ground
With the power removed, use a 500 VDC megger to check for grounds.
Wiring and interconnect cables should be at least 1 Mohm to ground.
Individual magnet coils should be at least 5 Mohm to ground. An insulation
resistance meter should be used to check the coils for open or short circuits.
Source of this introduction: NOV Document No. 165-60800
276
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
277
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 10
Schematic showing a
typical Baylor Elmagco
brake and clearances. For
the purpose of this course
we use the Baylor 7838
pressures, temperatures
and clearances.
Figure 11
278
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 12
Figure 13
Figure 14
279
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 15
Figure 16
Figure 17
Breathers are an EX
safety device and must be
maintained as such. They
allow hot humid air to
vent from the coil cavities
during normal operations
and when stopped.
280
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 18
Figure 19
This breather is
completely corroded. It is
meant to be a safety
device.
Figure 20
281
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 21
Figure 22
Figure 23
282
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 24
Figure 25
Figure 26
283
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 27
Figure 28
Figure 29
284
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 30
Figure 31
Procedure:
• Chain the blocks.
• Switch off the system power and battery charger.
• Hit the emergency stop (it will apply full brake from the batteries).
• Record amperage, voltage and time.
• Verify that the system disconnects the battery after three minutes or
when the battery voltage reaches a dangerous level.
• What is a pass of the batteries?
• Give full current for three minutes and not below the danger point
(200V).
285
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
286
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Zone 0: These areas are normally only found on production platforms, not
on drilling rigs.
Zone 1: An area in which an air gas mixture is likely to occur during normal
operations.
287
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 35
Figure 36
288
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 37
Figure 38
289
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 39
Figure 40
290
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 41
Figure 42
Schematic of an EXe
enclosure.
291
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 43
Figure 44
292
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 45
293
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 46
Figure 47
294
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 48
Figure 49
295
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 50
Figure 51
296
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 52
297
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 53
Schematic of a DC motor
showing the requirements
for use in a hazardous
area.
298
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 54
Figure 55
299
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 56
Figure 57
Figure 58
300
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 59
Figure 60
301
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
302
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 61
Figure 62
Figure 63
303
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 64
Figure 65
304
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 66
Using an accommodation
socket outside in a ground
wire power system is not
acceptable.
Figure 67
Figure 68
305
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 69
Figure 70
Figure 71
306
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 72
An example of a well
designed electric-cable
support system.
Figure 73
It is dangerous to repair a
440-volt wire like this.
307
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 74
A 'high-voltage' rag is
used to cover a 440-volt
generator.
Figure 75
Figure 76
308
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 77
An example of a proper
spark arrestor system on
the rotary DC motor.
Notice that the air inlet
has been connected with
steel ducting, so that the
cooling air is coming from
outside the hazardous
area.
Figure 78
Figure 79
309
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 80
Figure 81
Figure 82
310
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 83
Figure 84
Figure 85
311
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 86
No proper separation
between the mud pit room
and the mud pump room.
Figure 87
Figure 88
312
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 89
Figure 90
An example of a 'high-
tech' electrical support
system: rope!
313
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 91
Figure 92
Figure 93
314
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 94
Figure 95
Very dangerous
installation and with poor
termination of electrical
wires.
Figure 96
440-volt termination of
wires in a Zone 1 area,
next to the shakers. This
is very dangerous.
315
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 97
Figure 98
Figure 99
316
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 100
Figure 101
317
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 102
Figure 103
A well-maintained electrical-
isolation board.
318
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 104
Incorrectly terminated
ground wire connections.
Figure 105
319
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 106
Figure 107
320
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 108
Figure 109
Figure 110
321
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 111
Figure 112
Figure 113
A supposedly watertight
fluorescent light with water
inside!
322
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 114
Figure 115
Figure 116
323
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 117
Figure 118
324
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 119
Figure 120
325
Rig Inspection Workshop Course book 3.0
04 Electrical equipment
Figure 121
326
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Chapter 05
Safety equipment
327
Rig Inspection Workshop Course book 3.0
05 Safety equipment
328
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 1
Figure 2
Figure 3
329
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 4
Figure 5
Figure 6
330
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 7
Figure 8
Figure 9
331
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 10
332
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 11
Figure 12
333
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 13
Figure 14
Figure 15
334
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 16
Figure 17
Figure 18
Fire-fighting equipment
storage lockers on a land
rig: a good design and well
maintained.
335
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 19
Figure 20
336
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 21
Figure 22
337
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 23
Figure 24
An unacceptable method of
end-termination: wire knotted
through a chain! Only
approved hook terminations
are acceptable.
338
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 25
Figure 26
Figure 27
339
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 28
Figure 29
Figure 30
340
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 31
Figure 32
341
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 33
Figure 34
Figure 35
A collection of rig-made
lifting caps.
342
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 36
Figure 37
Figure 38
343
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 39
Figure 40
344
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 41
Figure 42
Figure 43
345
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 44
Figure 45
Figure 46
346
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 47
Figure 48
Figure 49
347
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 50
A self-closing valve
installed on the fuel tank
for the emergency
generator. However, this
valve remains in the OPEN
position thanks to the
unauthorized tie-wrap.
Figure 51
Figure 52
348
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 53
Figure 54
Figure 55
349
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 56
Figure 57
Figure 58
350
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 59
Figure 60
Figure 61
351
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 62
Figure 63
352
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 64
Figure 65
Figure 66
353
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 67
Poor organisation of
painting materials. Paint
must be stored in
designated paint stores,
which are normally
protected with a fixed CO2
fire-fighting system.
Figure 68
Figure 69
354
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 70
Figure 71
355
Rig Inspection Workshop Course book 3.0
05 Safety equipment
2 Pollution control
2.1 Pollution control checklist
• Verify the presence of a valid International Oil Pollution Prevention
certificate (IOPP) (applicable to MODUs only).
• Test the operation of the oil/water separator and the contents of the oil
discharge (max. 30 to 40 ppm).
• Confirm that the rig has a zero-discharge policy.
• Validate that the shale shaker dump valves are isolated.
• Check if the mud pit dump valves are isolated.
• Verify that there is an oil spill plan in place.
• Confirm that sufficient equipment is available to handle small oil spills.
• Test the sewage unit to see if it is operational.
• Make certain a waste separation plan is available.
• Ensure that no CFCs are used in the refrigerating plants.
• Confirm that Halon is not used as a fire-fighting agent.
• Verify that there are adequate facilities to store waste oil.
• Ensure there is no direct-overboard dumping of sludge, bilge, dirty oil
and bilge water from the colleting tanks.
• Ascertain that there is a cuttings disposal system in place.
• Make sure the mousehole drains are connected to a collection tank.
• Verify that all the mud pump room drains are connected to a collection
tank.
• Confirm that there is no asbestos material present in the accommodation
or work areas. If yes, post warning notices.
• Inspect the housekeeping and hydraulic-oil spills around the rig.
• Check the garbage management plan (as per MARPOL). (*)
Figure 72
356
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 73
Figure 74
Figure 75
357
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 76
Figure 77
Figure 78
358
Rig Inspection Workshop Course book 3.0
05 Safety equipment
Figure 79
Figure 80
359
Rig Inspection Workshop Course book 3.0
05 Safety equipment
360
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Chapter 06
Marine equipment
361
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
1 Jacking systems
Figure 1
1.1 Introduction
The principle means of jacking a rig include the following:
• rack and pinion drive
• hydraulic continuous recycling
The jacking system on the majority of drilling jackups is usually the rack-
and-pinion type. This system comprises of a number of electrically driven
rack-and-pinion-type jacking assemblies. For example, the rig may support
six jacking units per chord per leg which are housed inside each of the
jackhouse structures.
Each of the jacking pinions is independently driven by an electric motor via a
reduction gearbox which engages with the leg tooth racks of each leg. An
example of this is shown in Figure 2. This illustration indicates two
assemblies. Operationally each of the three chords has three on each side of
the rack-and-pinion tooth rack (total per chord six) with a further six on
each of the chords.
The jacking system is designed to operate in tandem capable of lifting or
lowering the hull. The jacking movement is guided by the upper and lower
guides, which form part of the jackhouse and hull structure.
362
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
363
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
364
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
365
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
366
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
367
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
368
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 9
Manual measuring of the RPV.
369
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
4.2 Scouring
Scouring is defined as the removal of seabed soils by currents and waves.
This can be caused by a natural geological process or by structural
components interrupting the natural flow above the seafloor. Scouring is
described as follows:
• overall scouring which would occur even if no jack-up were there
• global scouring representing a general scouring caused by the water flow
through the base of the jack-up
• local scouring representing the local cone of depression formed by the
increased local flow around an obstruction (such as a pile or spud can)
370
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
371
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
372
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 11
Figure 12
Figure 13
373
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 14
Figure 15
374
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 16
Figure 17
375
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 18
Figure 19
Electric-powered skidding
system for the cantilever.
Figure 20
376
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 21
Figure 22
377
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 23
Figure 24
Figure 25
378
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 26
Figure 27
379
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 28
Figure 29
380
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 30
Figure 31
381
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
382
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
5 General equipment
Figure 33
Figure 34
383
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 35
Figure 36
Fire equipment rescue
box.
384
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 38 - OWS.
Figure 39
Fixed fire- fighting
system.
385
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
386
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
Figure 42
Watertight doors.
Figure 43
Fireman's suits.
387
Rig Inspection Workshop Course book 3.0
06 Marine Equipment
388
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Chapter 07
Well control equipment
389
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 1 - The Cameron type U ram preventer is the ram BOP most
used for surface BOPs.
390
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 3 Figure 4
Cameron 350 Packer lip-plated Extrusion plates control the rubber
design showing the upper and lower extrusion and apply forces to the
extrusion plates. packing rubber to extrude it into any
gaps in the cavities and around the
drill pipes. Rams seal in cavities,
around pipes and against themselves
(Cameron rams).
Figure 5 Figure 6
Cameron blind-shear ram in the OPEN Cameron blind-shear ram in the
position. CLOSE position.
391
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Cameron bonnets have a very complicated system, which allows the bonnets
to be opened and closed hydraulically.
All the ram preventers are wellbore assist. The wellbore pressure will
support the closed ram blocks. The rams are not sealing at the bottom of
the cavity. Allow wellbore pressure to get behind the ram blocks providing
significant support. As a result of this, the wellbore pressure should always
be bled off completely after a pressure test before the rams are opened.
A good practice is to first open the gate valves located in the choke and kill
lines. The total pressurized area of the bore of the rams is much larger,
more than twenty times larger (for 13⅝-inch ram BOPs), than the
pressurized area of the gate valves.
Opening the ram blocks even with 'low pressure' underneath them can
create cracks on the piston hubs, and can deform the aft side of the ram
blocks. Opening the rams with wellbore pressure using 1,500 psi of opening
pressure might blow the ram rubbers from the ram block. Opening the rams
with wellbore pressure of 3,000 psi might shear the ram shaft attachment
(hub) with the ram blocks.
Calculate the force on the ram blocks of a 13⅝-inch BOP when there is just
500 psi left, and see how much force there is still left on the ram blocks.
Next, calculate the force on the 13⅝-inch BOP when the rams are pressure
tested to 10,000 psi. If you check your calculator, you will now realise how
important it is to STAY AWAY from the BOPs during pressure testing.
392
Rig Inspection Workshop Course book 3.0
07 Well control equipment
1.5 FlexPackers
Advantages:
1. FlexPackers will seal on three of four pipe sizes.
2. FlexPackers fit into a standard set of fixed pipe ram blocks.
3. Slightly better hang-off capacity than VBRs.
Disadvantages:
393
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 15
Different types
of Cameron
shear blind
rams.
To improve the shear force, either large bore bonnets or booster cylinders
can be installed.
Figure 16
Modern
Cameron TL
with different
styles of
locking
systems and
bonnets.
394
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Note: The shear rams can only shear drill pipe, not tool joints, heavy-weight
drill pipe or drill collars! Frequently, it will be difficult enough to shear the
newer and stronger drill pipes.
Note: There should be sufficient distance between the stick-up tool joint and
the bottom of the shear rams, so as to not try and cut the tool joint. On
most rigs the LPR (lower pipe ram) will be the hang-off ram.
Take note that you have to turn the ram blocks upside down prior to
installing the blade seals, which have Left and Right stamped on them.
395
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Clearances between the top of the cavity and the ram blocks must be
measured frequently, as too much clearance might result in the loss of low-
pressure sealing.
396
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Modern Shaffer BOPs of the NXT type are now commonly used as surface
BOPs.
The other major manufacturer of ram BOPs is Hydril. Hydril BOPs are
predominantly subsea BOPs.
397
Rig Inspection Workshop Course book 3.0
07 Well control equipment
2 Ram preventers
2.1 Ram preventers checklist
• Record the date of the last five-yearly major service (API RP 53 section
17.10.3).
• Verify that the ram BOP is suitable for H2S operations (NACE 0175).
• Check the API certification package (API RP 53 section 17.13.2).
• Test the condition of the control hoses and verify that they are fire-
resistant (API RP 53 section 12.5.2).
• Inspect the NDT records for the piston hubs and bonnet bolts.
• Examine the NDT records for the ram blocks and shear ram blades.
• Record the cavity and ram block clearance measurements.
• Verify that the rig crew understands how best to store spare parts and
increase shelve life (API RP 53 sections 6.4 and 6.5).
• Ensure the BOP is suitable for HT/HP applications.
• Confirm that the correct variable-bore rams are fitted.
• Ascertain that the capacity of the blind/shear ram is sufficient.
• Verify that there sufficient space to hang off on pipe rams and shear in a
safe manner.
• Check that the condition of the elastomers is as new (API RP 53 section
19.5).
• Record the date of the last test of the hydraulic circuits at 300 psi/20
bars and 3,000 psi/200 bars in order to check the integrity of the circuit
seals (API RP 53 section 18.3.2.5).
• Test the condition of the (blind) flanges and their studs (API RP 53
section 17.11).
• Inspect the condition of bore (key seating).
• Record the date of the last pressure test to full working pressure (API RP
53 section 17.3.2).
• Confirm the condition of all the hydraulic torque tools (API RP 53 section
17.11.4).
• Check the ram configuration.
• Verify that the ram-locking system is operational and check the date of
the last function test (API RP 53 section 17.5.8). (*)
398
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 22
Figure 23
Figure 24
399
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 25
Non-Cameron-
authorized repairs.
After the bonnet bolt
threads were damaged,
a sleeve was fitted.
There is no guarantee
that this repair will
handle the bolt torque
or well bore pressures.
A new bonnet is the
only solution.
Figure 26
Figure 27
400
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 28
Figure 29
Figure 30
401
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 31
Figure 32
Figure 33
402
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 34
Figure 35
Figure 36
403
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 37
Figure 38
Figure 39
404
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 40
Figure 41
Figure 42
405
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 43
Figure 44
Figure 45
Measuring the
clearance between the
ram block and the top
of the ram cavity, after
the ram rubbers had
been removed.
406
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 46
Figure 47
Figure 48
407
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 49
Figure 50
Figure 51
408
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 52
Figure 53
Figure 54
409
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 55
Figure 56
Figure 57
410
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 58
Figure 59
Figure 60
411
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 61
Figure 62
How do we abandon
the rig now?
Figure 63
BOP in subzero
operations. Steam-
heated, but escaping
steam turns into ice.
412
Rig Inspection Workshop Course book 3.0
07 Well control equipment
413
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Both the inner vertical section and the other section are important for the
proper sealing operations. It is normal to have small pieces of rubber
missing from the tapered inner section, and this does not affect the sealing
of the annular BOP.
414
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Every time a tool joint passes through the closed annular BOP element a
surge occurs, as the element is compressed by the tool joint. The annular
BOP regulator is located at least 100 feet away from the BOP. Consequently,
the annular regulator response is too slow to protect the element from
excessive wear. To solve this problem most rigs (even land-rigs!) nowadays
have installed a surge bottle.
When we install a stripping bottle we have to ensure it is installed as close
as possible to the annular preventer. Every time a tool joint passes through
the closed annular preventer, the stripping bottle will compensate for the
fluid increase to prevent too high pressure surges, which can cause rapid
wear of the annular elements
To perform stripping operations with minimum wear we should use the fol-
lowing procedure:
1. Install a 10-US-gallon surge bottle as close as possible to the annular
BOP.
2. Ensure the stripping bottle is precharged to approximate 400 psi.
3. Reduce the annular BOP closing pressure as low as possible until the
element starts to leak slightly, in order to lubricate and cool the element.
4. File off the tong marks from the tool joints.
5. Apply grease (no pipe dope as this will damage the element) onto the
tool joints.
6. Reduce the lowering of the drill pipe to approximately 1 foot per second.
415
Rig Inspection Workshop Course book 3.0
07 Well control equipment
416
Rig Inspection Workshop Course book 3.0
07 Well control equipment
417
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 77 Figure 78
Cutaway view Hydril GK preventer. Hydril GK control circuit with
surge bottle.
Warning! Never leave a bull plug in the secondary chamber as this will
completely destroy the annular preventer!
418
Rig Inspection Workshop Course book 3.0
07 Well control equipment
419
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Cameron annular BOPs differ from the Hydril and Shaffer BOPs as
follows:
Figure 85
Shaffer annular element with fingers,
which can cause damage if closed on a
large casing string, without using a lower
closing pressure. Shaffer elements colour
code for Nitrile rubber is blue and for
Natural rubber elements it is red.
420
Rig Inspection Workshop Course book 3.0
07 Well control equipment
4 Annular preventers
4.1 Annular preventer checklist
• Record the date of the last major overhaul (API RP 53 section 17.10.3).
• Verify that the annular preventer is suitable for H2S operations (NACE
0175).
• Confirm that there is a spare element and seal kit present.
• Make sure the rig crew understands the correct method of storing the
seals and elements?
• Check that the hydraulic seals are replaced every three years (OEM).
• Validate that the control hoses are at least 1-inch ID (preferably 1½
inch).
• Verify that a stripping (surge) accumulator bottle (of 11 US gallons) has
been installed (API RP 53 section 21.2).
• Check the stripping bottle precharge pressure (ca. 400 psi/27.6 bars).
• Confirm that the elements close within 30 seconds if smaller than 18¾
inches, or within 45 seconds if larger than 18¾ inches. Note: Elements
must relax to full bore within 30 minutes (API Spec 16D [2005] section
5.1.1).
• Make certain the rig crew understands that Cameron annular preventers
require 3,000-psi/200-bar operating pressure from the annular preventer
regulator.
• Test for any damage to the bore surfaces.
• Verify that the stationary seal weep holes are open.
• Inspect the condition of the fitted element.
• Check NDT inspection records of the lifting eyes.
• Verify that the rig crew understands that there is a special element for
the Shaffer annular preventers in case the sealing on large objects is
required?
• Confirm that no unauthorized welding has been performed on any well
control equipment (API RP 53 section 17.11.7). (*)
421
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 86
Severely corroded BX
ring on top of the
annular preventer. The
top of the annular
element is important
because in an
emergency we might
have to install either
another annular BOP or
a snubbing unit.
Figure 87
Damaged BX sealing
area on top of the
annular preventer. If
needed, this can be
repaired in situ by a
Vetco engineer using a
cold-welding method.
Figure 88
422
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 89
Figure 90
Figure 91
It is often difficult to
remove the Hydril
screw-type annular
preventer cap.
423
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 92
Figure 93
Figure 94
424
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 95
Figure 96
Figure 97
Bottom of a Shaffer
element tested to the
point of destruction.
API recommends
testing the annular
element periodically
only to 70% of the
working pressure. Only
during an acceptance
test may we be
required by the
operator to test the
annular BOP to full
working pressure.
425
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 98
Figure 99
Figure 100
426
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 101
Improper storage of
the annular preventer
element. It is not
protected from sunlight
or fluorescent light, and
is becoming egg-
shaped because of the
weight coming from the
top.
Figure 102
As a result of
unauthorized welding,
this annular element's
main housing has been
completely destroyed
during a pressure
testing.
427
Rig Inspection Workshop Course book 3.0
07 Well control equipment
5 Gate valves
5.1 Gate valves checklist
• Record the date of the last five-yearly major service (API RP 53 section
17.10.3).
• Verify that this service include the HCR actuators.
• Check that the HCR valves are installed on the outside of the BOP.
• Confirm that the crew uses OEM-recommended grease in the valves.
• Validate that the valve handles are colour-coded and all present.
• Ensure that the HCRs are fitted with valves containing a handle to allow
mechanical override?
• Verify that there are sufficient spare valves of all sizes in stock.
• Confirm that the gate valves are trimmed for H2S.
• If fitted, check the condition of all the check valves (non-return valves)
in the kill line.
• Ascertain the kill line diameter is more than 3 inches/75 mm for
pressures of 5,000 psi/345 bars and above.
• Make sure grease nipples covers are fitted.
Figure 103
428
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 104
Figure 105
Figure 106
429
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 107
Figure 108
Figure 109
430
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 110
Note: The hand wheel of the HCR valve cannot open the valve.
431
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Two manual chokes and two remote chokes are installed. The buffer tank is
divided into two sections. The high-pressure vent line or so-called 'panic-
line' is not present.
The choke and kill manifold on MODUs, or the choke manifold on land rigs,
are installed to circulate the kick or influx out while maintaining a constant
pressure on the casing. If the chokes are opened too far, the pressure in the
casing will drop, and this will increase the influx of the kick. If the chokes
are not opened far enough, the pressure of the casing might rise too high,
and the formation at the casing shoe might fracture. This might cause an
external blow-out outside the casing.
432
Rig Inspection Workshop Course book 3.0
07 Well control equipment
None of the chokes needs to hold pressure, but they must hold a
'backpressure' on the casing while passing fluid. None of these chokes need
to be pressure-tested during the routine tests.
433
Rig Inspection Workshop Course book 3.0
07 Well control equipment
The orifices are called 'Beans' named after his their inventor, John Bean.
These positive-displacement chokes are unable to hold pressure.
There are different pressure ratings for these valves. The valves up to a
10,000-psi working pressure (10M) will have grease nipples installed, with
NPT fittings connected to the body. This means that there might be contact
between the threads and the (aggressive) drilling fluids.
The grease nipples of the valves above 10M will have so-called 'auto-clave'
grease fittings installed, where the fitting seals on a seat instead of the
threads. There will be no contact between the mud and the threads.
Regardless of the type of grease nipple installed, it is a very good practice to
cycle the valves before removing the grease caps, in order to remove any
trapped pressure from the body. Next, we have to train the rig personnel not
to stand in front of the grease fittings when they remove these caps.
434
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 119 - Grease nipple (10M). Figure 120 - Grease nipple (15M).
The grease nipples can also be used to vent the pressure from the body
using pins to lift the balls of the check valves. The valves upstream the
chokes (seen from the BOP up to the chokes) must have the same pressure
rating as the ram BOPs (API Spec 16C). For the valves downstream the
chokes (seen from the chokes venting to the mud/gas separator or to the
overboard/flare pit), there is no pressure rating but a temperature rating.
Due to excessive expansion of the gas from the kick straight after the
chokes, a severe temperature drop is very likely since expansion requires a
lot of heat. So, the valves downstream the chokes have a special
temperature rating and code.
435
Rig Inspection Workshop Course book 3.0
07 Well control equipment
436
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Material Classification
We can use this chart to determine the actual material based on the
materials classification
Conclusion
The above tables will provide us with the codes used on the gate valves, for
what purpose or what temperature rating these valves are purposely built
for. If the rig is operating in a H2S zone, the code for the valves should be
DD or higher. Even on existing rigs, if the well conditions change or the rig is
upgraded to high-temperature operations, we have to consider whether we
should order special grease that is fit for purpose.
The piping of the choke and kill manifold must not have sharp bends or
elbows installed. Due to the increasing speed of the mud in sharp elbows,
the gas bubbles are compressed until they implode. The kinetic energy from
the inside of the bubble will attack the wall of the pipe, which we call erosion
437
Rig Inspection Workshop Course book 3.0
07 Well control equipment
(cavitations). The standard 90-degree elbows for piping is only 1.5 times the
diameter.
Note: API recognized this problem, and in their standards, the minimum
radius of 90-degree elbows in the piping of the choke and kill line must be at
least 10 times the nominal diameter of the pipe in use, both upstream
and downstream the chokes.
As this observation is not very practical, target blocks are often installed. At
the blind flanges of these targets lead plugs are installed, whose purpose it
is to absorb the kinetic energy of the gas bubbles thus preventing erosion
of the walls of the piping.
Clearly visible is the impact of the implosions in the lead. The lead is doing
what it is designed for!
Sometimes there are small air pockets behind the lead plugs. During
pressure testing through very small channels, a pressure build-up behind the
lead plugs is possible. Next, the pressure is rapidly vented and the trapped
pressure pushes the lead plugs out. The solution to this problem is not to
remove the lead plugs and thus loose their absorption capacity, but to drill a
few ¼ inch holes in the lead to vent any trapped pressure.
438
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 123
Lead plugs might be pushed
out due to trapped pressure.
Drill pressure-equalizing holes in the lead plug to prevent them from 'travel-
ling' through the system.
439
Rig Inspection Workshop Course book 3.0
07 Well control equipment
440
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 124
Figure 125
Figure 126
441
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 127
Figure 128
Figure 129
Weekly greasing is
necessary. Ensure that the
valves are cycled first to
remove any trapped
pressure in the body. Only
OEM-recommended grease
must be used.
442
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 130
Figure 131
Figure 132
Three-inch NPT-threaded
bull plug: a recipe for a
serious accident.
443
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 133
Short-radius 90-degree
elbows and severely
corroded studs on flanges
have made this section a
severe safety hazard.
Figure 134
Figure 135
444
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 136
Figure 137
Figure 138
445
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 139
Figure 140
446
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 141
Figure 142
Figure 143
447
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 144
Figure 145
448
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 146
Figure 147
449
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 148
Figure 149
450
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 150
Figure 151
Home-made crossover
welding with NPT threads.
It is extremely dangerous
to fabricate home-made
equipment for high-
pressure equipment.
Figure 152
451
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 153
Figure 154
452
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 155
Figure 156
453
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 157 - Diagram of the nitrogen back-up system for the supply
of emergency air.
454
Rig Inspection Workshop Course book 3.0
07 Well control equipment
455
Rig Inspection Workshop Course book 3.0
07 Well control equipment
456
Rig Inspection Workshop Course book 3.0
07 Well control equipment
The BOP HPU (hydraulic power unit) consists of three hydraulic circuits:
1. The accumulator circuit
2. The manifold circuit
3. The annular BOP circuit
The accumulator circuit pressure is 3,000 psi for most rigs. This circuit feeds
both the manifold and the annular BOP circuit. The manifold circuit is
normally regulated down to 1,500 psi. On most rigs the regulator for this
circuit is a manual regulator without a remote function. Several modern rigs
have made this manifold regulator remotely controlled as well - this is a
great help in case a drill string has to be hung off. The rams and the choke
and kill HCR valves are connected to the manifold circuit.
The annular preventer circuit is regulated down from 800 to 1,500 psi,
depending on the type of annular preventer that is installed. The regulator
for the annular preventer must be remotely operated from at least two
remote-operated stations. Only the annular preventer is connected to the
annular BOP circuit.
On the manifold a bypass valve is installed, that can bypass the manifold
regulator to create 3,000 psi on the complete manifold system, in case
shearing operations are required, or extra pressure is required for the pipe
rams to seal better. On this modern manifold this is not the case, as the
shear blind rams have their own independent regulator installed. This is an
extra facility which is not required by the standards, but it is a very good
drilling practice.
The HPU has two independent pump systems for the BOP HPU: one or two
electric-driven triplex pumps and two or three air-operated pumps. The
triplex pumps must start at 90% of the working pressure, which is 2,700 psi.
As it has a much higher capacity, the triplex pump will start first. The triplex
pumps will kick out at 3,000 psi. The start/stop function is controlled by an
electric-hydraulic switch.
This means that it will positively discharge liquid from the suction source to
the discharge, regardless of the discharge pressure involved.
457
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 161
The electric-hydraulic
switch that starts/stops
the triplex pumps
contains mini-switches to
change its setting.
The air-driven pumps must start at 85% of their working pressure, which is
2,550 psi. The air pumps normally will kick out at 2,850 psi. The start/stop
function of these pumps is controlled by the pneumatic pump governor.
Both the air pumps and the triplex pumps have check valves installed in the
discharge lines, to prevent fluid from flowing back from the accumulators to
the mixture/storage tank. With this set-up another type of pump governor is
used. Most older and surface BOP HPUs use pump governors as shown in
Figure 163.
Figure 163
Pump governor which controls the
start/stop function of the air pumps.
458
Rig Inspection Workshop Course book 3.0
07 Well control equipment
This schematic provides a clear indication of the different air and hydraulic
circuits.
459
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Accumulator bottles
Most accumulator systems for the surface BOPs have a working pressure of
3,000 psi. Some high-pressure shear circuits work with 5,000-psi
accumulator bottles. The accumulators are precharged with an inert gas
(nitrogen) to provide a 'constant' pressure and to drive out the hydraulic
fluid quickly. There are four different types of accumulators available:
1. the bag-type accumulator (normally 11-US-gallon bottles are installed)
2. the float-type accumulator preventer (varying from 15 to 85 US gallons)
3. the spherical-type accumulator (normally containing either a bag or a
float of 85 US gallons)
4. the piston-type accumulator, which comes in various sizes
460
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Bladder-type accumulators are precharged from the top. The actual fluid
that is usable for this type of accumulators depends on the closing ratio of
the ram BOPs, and varies from 4 to 5 US gallons.
The disadvantage here is that the accumulators are very large; if one
accumulator fails, a lot of capacity will be lost at once.
461
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 169
462
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Regulators
We need regulators to reduce the accumulator pressure into the pressure for
our other two main circuits, the annular BOP circuit and the manifold circuit,
which connect the rams and the HCR gate valves. There are four types of
regulators available:
1. Air-operated regulators called AKRs (air-controlled regulators), which are
remotely operated from the remote panels. AKRs are installed on the
annular BOP circuit.
2. Manual operated regulators called MKRs (manually controlled regulators),
which are normally installed at the manifold circuit.
3. The air-operated regulator with an air motor called TR (true reading)
regulator, which is installed on modern HPUs for the annular BOP circuit.
4. The hydraulically operated regulators, which we normally install in the
subsea pods for subsea BOP control circuits.
Situation A Situation B
463
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Situation A Situation B
In situation B, the pressure is coming down from the output venting to the
vent port. If the air pressure is lost, the supply pressure will be isolated and
the outlet pressure vents to zero psi. Consequently, the closed annular
preventer will be opened by the force of the large rubber element. A blow-out
will be the result!
464
Rig Inspection Workshop Course book 3.0
07 Well control equipment
465
Rig Inspection Workshop Course book 3.0
07 Well control equipment
There are two different ways to use control valves: either manipulator-type
valves on the subsea BOP control panels, or selector-type valves used on the
surface BOP HPU systems. You cannot see the difference from the outside;
only the inserts are different.
466
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Remote-control panels
467
Rig Inspection Workshop Course book 3.0
07 Well control equipment
For all surface BOPs on MODUs, and on most modern rigs, the old-fashioned
panels have been replaced for the electro-pneumatic panels. This panel
provides a valve position indication, so the driller knows exactly what the
position of the BOP components is.
468
Rig Inspection Workshop Course book 3.0
07 Well control equipment
9 BOP HPU
9.1 BOP HPU checklist
• Record the date of the last accumulator capacity test as per API RP 16E,
API RP 53 section 17.7.1 and API Spec 16D (2005) sections 5.1.2 and
5.1.4
• Verify that the rubber hoses are not fitted in the main accumulator
supply system. Note: This is a single-point failure.
• Confirm that the unit is divided into four equal banks with isolation and
drain valves on the bottle or racks (API Spec 16D section 5.1.3.2).
• Ensure that only TR-type regulators are used. Note: AKR-type regulators
are no longer acceptable.
• In case of MODUs, check that the following alarms are present (API Spec
16D section 4.3.3.1.g.g):
o Accumulator low-pressure alarm
o Rig air low-pressure alarm
o Emergency power engaged
o Pump-running indication
• Verify that the accumulator pre-charge pressure is at least 1,000 psi/69
bar.
• Confirm that the accumulator bottles are hydrostatically tested every 10
years (API 510 section 6.5 and API Spec 16D section 3.1.2.3).
• Make sure the unit located is in a safe place as per API Spec 16D section
2.2.4.6 (i.e. not on the drill floor).
• Check the pressure control circuits.
• Verify that the triplex pump starts pumping at 2,700 psi/186 bars and
stops pumping at 3,000 psi/200 bars.
• Confirm that there is an emergency air back-up system fitted (API Spec
16D section 1.5).
• If electrically operated, verify that the system has a battery back-up
system (UPS) for the remote-control panels.
• Check that the shear-blind valve panel has extra protection such as a
fool's box (API Spec 16D section 2.2.2.7).
• Verify that there are safety signs posted on equipment that starts
without warning (Equipment Starts Automatically).
• Check the calibration records for the pressure gauges (API RP 53
sections 12.3.6 and 12.5.2).
• Make sure only engraved signs are used on panels (i.e. no graffiti). (*)
469
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 183
Figure 184
Figure 185
470
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 186
Figure 187
Figure 188
471
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 189
Accumulator bottles
adequately marked with
safety signs and
identification numbers.
Figure 190
Figure 191
472
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 192
Figure 193
Figure 194
473
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 195
Figure 196
474
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 197
No manually operated
valves should be installed
on the discharge side of the
triplex pumps, between the
pump and relief valve. If
we start the pumps with
this valve still closed, the
discharge lines might blow
up! A check valve is
present to prevent the
pressurized fluid from
venting back to the tank.
Figure 198
475
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 199
Figure 200
Another example of an
illegal restriction for the
shear blind rams. The
remote operation of the
shear-blind rams is no
longer possible.
476
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 201
Figure 202
Figure 203
477
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 204
Figure 205
The failsafe-type TR
regulator. When rig air is
lost, the latest-set pressure
output remains. Manual
adjustment is also possible,
and should be preset before
starting operations.
Figure 206
478
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 207
Figure 208
479
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 209
Figure 210
A remote-control panel
with the valve position
indication is required on all
offshore rigs.
480
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 211
Soluble-oil/water mixture
tank. Any contamination
with lubricating oil will lead
to the growth of bacteria
and fungus. Most land rigs
use hydraulic oil in the well
control systems.
Figure 212
Figure 213
481
Rig Inspection Workshop Course book 3.0
07 Well control equipment
Figure 214
Figure 215
When water/soluble-oil
mixtures are used, a
refractometer can be used
to measure the correct
solution of the BOP fluid.
Between 2 and 5% is
recommended. It is
important that the fluid
sample temperature is
20°C.
482
Rig Inspection Workshop Course book 3.0
Appendices
Chapter 08
Appendices
483
Rig Inspection Workshop Course book 3.0
Appendices
1 Appendix 1
Drive Chains Inspections
A roller chain drive requires proper and timely maintenance to deliver satis-
factory performance and service life.
484
Rig Inspection Workshop Course book 3.0
Appendices
485
Rig Inspection Workshop Course book 3.0
Appendices
Chain wear
The maximum wear in most chain drives is considered 3% wear elongation.
With 3% wear the chain does not engage the sprocket properly.
On drives with sprockets with more than 66 teeth the allowable wear is
limited to 200/N (N = number of teeth on the largest sprocket) and may be
substantially less than 3%).
On fixed-centre non-adjustable drives the allowable wear elongation is
limited to one half of one chain pitch.
486
Rig Inspection Workshop Course book 3.0
Appendices
Sprocket wear
A worn-out sprocket is not nearly as well defined as a worn-out chain. Check
for roughness, reduced tooth thickness and visibly hooked sprocket tooth
tips.
The pitch of a new chain is much shorter than the effective pitch of the worn
sprocket, so the total chain load is concentrated on the final sprocket tooth
before disengagement.
Then, when the chain disengages from the sprocket, the roller is jerked out
of the hooked portion of the sprocket tooth and that results in a shock load
on the chain as the load is transferred from one tooth to the next.
487
Rig Inspection Workshop Course book 3.0
Appendices
Sprocket misalignment
Inspection for significant wear on the inside surfaces of the chain roller link
plates and on the sprocket flange faces. This wear indicates misalignment.
If 5% or more of the link plate thickness is worn away, or if there are
sharp gauges in the link plate surface, the chain should be replaced
immediately.
If 10% or more sprocket tooth flange thickness is worn away, the
sprocket should be replaced.
The maximum amount of axial misalignment is obtained from the following
formula:
Maximum offset - 0.045 P inch (P = chain pitch in inches)
Chain tension
Measure the total mid-span movement. If this exceeds the tabulated limit,
adjust the centre distance to obtain the desired amount of slack.
If the elongation exceeds the available adjustment and wear elongation still
has not exceeded 3% of the functional limit, remove two pitches and rein-
stall the chain. If the minimum adjustment will not permit shortening two
pitches, the chain may be shortened one pitch by using an offset link or off-
set section.
Recommended possible mid-span movement AC in inches
Tangent length between sprockets in inches
Drive centre 10 20 50 50 70 100
line
Horizontal to 0.4 - 0.5 0.8 - 1.2 1.2 - 1.8 2.0 - 3.0 2.8 - 4.2 4.0 - 6.0
45 degrees
45 degrees to 0.2 - 0.3 0.4 - 0.6 0.5 - 0.9 1.0 - 1.5 1.4 - 2.1 2.0 - 3.0
vertical
488
Rig Inspection Workshop Course book 3.0
Appendices
Guards
Inspect the guards to ensure they are not bent or deformed so that intended
clearance is reduced. Any designed openings in the guard (mesh) must not
be enlarged. The guards must not be deformed or damaged, especially
around the mounting points. Make sure all the fasteners are secure and all
safeguarding devices such as pressure sensors and interlocks are
functioning.
489
Rig Inspection Workshop Course book 3.0
Appendices
490
Rig Inspection Workshop Course book 3.0
Appendices
491
Rig Inspection Workshop Course book 3.0
Appendices
492
Rig Inspection Workshop Course book 3.0
Appendices
2 Appendix 2
API RP 8B Explanations and Category of
Inspections
493
Rig Inspection Workshop Course book 3.0
Appendices
Drilling hooks
(other than sucker- I II III IV
rod hooks)
Travelling blocks,
hook block and
I II III IV
block-to-hook
adapter
Casing elevators,
tubing elevators,
drill-pipe elevators II III IV
and drill-collar
elevators
Sucker-rod
II II III IV
elevators
Rotary swivel-bail
I II III IV
adapters
Spiders, if capable
of being used as I II III IV
elevators
Dead-line tie-down/
I II III IV
wire line anchors
Kelly spinners, if
capable of being
I II III IV
used as hoisting
equipment
Riser- and
wellhead-running
tools, if capable of II III IV
being used as
hoisting equipment.
Safety clamps, if
capable of being
I II III IV
used as hoisting
equipment.
NOTE: The above recommended frequencies apply for equipment in use during the specified
period.
494
Rig Inspection Workshop Course book 3.0
Appendices
495
Rig Inspection Workshop Course book 3.0
Appendices
3 Appendix 3
Electrical Hazardous Areas: Explanation
3.1 Overview
It is an undeniable fact that drilling units are involved in the exploration and
production of hydrocarbons. In other words, drilling rigs are engaged in the
search and recovery of petroleum products, including highly combustible
gases.
Now what are the precautions we take in order to minimize the risks, which
come with this potentially dangerous business? These precautions are:
• Identify the areas where combustible gases might occur or might be
present.
• Close the boundaries of those areas.
• Ventilate and alarm those areas.
• Make sure no equipment in those areas can generate sparks or initiate
explosions.
• If the situation gets out of control, initiate a total rig shutdown.
It will be no surprise that Class Rules (ABS Rules for Building and Classing
MODUs) and Statutory Regulations (2001 IMO MODU Code) address these
areas of concern.
Hazardous areas are all those areas where, due to the possible (continuous
or intermitted) presence of a flammable atmosphere arising from the drilling
or well-testing operations, the use of machinery or electrical equipment
without proper consideration may lead to fire hazard or explosion.
Hazardous areas are classified in three different zones: Zone 0, Zone 1 and
Zone 2.
Zone 0 areas are normally only found on production platforms, not on
MODUs.
496
Rig Inspection Workshop Course book 3.0
Appendices
Air locks are regarded as hazardous areas. A gastight door contains a seal
made out of rubber, cotton or another material.
497
Rig Inspection Workshop Course book 3.0
Appendices
When we run into gas, we want to dispose of the gas to an outdoor area; on
top of that we want to be informed about it.
Ventilation
Enclosed hazardous spaces should be ventilated in such a manner that the
enclosed hazardous spaces are maintained with under-pressure in relation to
the less hazardous/non-hazardous spaces and non-hazardous enclosed
spaces are maintained in overpressure to adjacent hazardous spaces.
The philosophy behind this is obvious: no explosive gases must be able
escape/migrate to other areas. Non-hazardous gases are allowed to enter
the hazardous area, not the other way round.
The following conditions prevail for non-hazardous enclosed spaces adjacent
to hazardous areas:
Ventilation is such that the air flow with the door open
goes from the non-hazardous space into the Zone-2
ZONE 2 location.
498
Rig Inspection Workshop Course book 3.0
Appendices
The means provided for stopping the power ventilation servicing hazardous
areas should be entirely separate from the means provided for stopping
ventilation of other spaces.
Bear this in mind: The last thing we want to do in case of fire somewhere
outside the hazardous areas is to stop the ventilation of the hazardous
areas!
When we run into flammable gas we do not want it to be ignited. That is why
strict rules and regulations apply to mechanical and electrical equipment in
hazardous areas.
Electrical equipment
All the electrical equipment should be properly earth-bonded. Bolted
connections are not considered earth-bonded; only welded connections are
regarded as such. Electric cables have to be properly secured. Splices in
cables in hazardous areas should be avoided.
The equipment should be certified for the intended zone. This means that
the equipment is to be linked to a certificate via a label or tag, indicating
that an independent certifying body has carried out type-approval tests on it
and has certified it as suitable for the intended use.
Needless to say, there should be no departure from the design thus tested
and approved.
499
Rig Inspection Workshop Course book 3.0
Appendices
As Zone 1
Explosion-proof (EXd)
This equipment is located in heavy enclosures which can stand the forces of
an internal explosion. The flanges of EXd enclosures have large sealing
surfaces in order to create a flamepath.
There is no gasket between the flanges but a very small clearance of
approximately 0.1 mm. Therefore, do not get confused and mix up
explosion-proof junction boxes with watertight junction boxes!
When an explosion takes place inside the box the pressure will be relieved
via the flamepath to the outside atmosphere. Due to this very small
clearance an expansion of the gases takes place which extinguishes all
flames.
Flamepaths are prone to corrosion and their maintenance should be
incorporated in the unit's planned maintenance system. Flamepaths are to
be opened up on a yearly basis and have their flanges cleaned and coated
with some kind of Vaseline to protect them against the salty environment.
500
Rig Inspection Workshop Course book 3.0
Appendices
Mechanical equipment
Mechanical equipment in hazardous areas should be limited to that
necessary for operational purposes.
Ventilators
Ventilation of hazardous areas should be maintained by non-sparking fans.
This also goes for the supply and exhaust ventilators for the hazardous
spaces which are located outside on deck. Their electric motors should
obviously be explosion-proof. For an extensive list of requirements regarding
design, material and type test, refer to ABS MODU Rules 4 (Chapter 11:
Non-Sparking Fans).
Diesel engines
Internal-combustion engines on the rig have to be provided with spark
arrestors in their exhaust uptakes. Diesel engines are normally not located in
hazardous zones, unless they are essential for operational purposes. Such
installations will be subject to special consideration from the side of the
Class and the Flag State Administration. If so, their hot parts should be
properly insulated.
Dampeners which close on overspend trip should be installed in the intakes
for combustion air, smothering the engine in case of drawing in combustible
gas.
501
Rig Inspection Workshop Course book 3.0
Appendices
Third-party equipment
We already discussed about well-testing equipment, but what about mud-
logging containers, wire line units, etc. that are shipped to the rig to be
located in a hazardous area?
Standard North Sea practice, implemented by coastal states, follows the
steps as listed below:
• The portable cabins should be A-60 insulated.
• Entrance should be via an air lock.
• Ventilation is to be drawn from a non-hazardous area.
• Power is to be shut down upon loss of ventilation/overpressure.
• Start the interlock to facilitate ample pre-purge time prior to restoration
of power.
• Fire- and gas-alarmed cabins with the signals/alarms linked into the fire
and gas panel of the rig.
• PA and rig alarm system must be extended to the portable
cabin/container.
The moment the explosion hazard extends outside the hazardous zones, a
total rig shutdown should be initiated. For that purpose two shutdown
buttons for main generator and emergency generator prime movers should
be provided at strategic locations.
One of these locations is normally the rig floor, the other one has to be
outside the hazardous areas, for instance the drilling office inside the
accommodation. The following facilities should be operable after a total rig
shutdown.
502
Rig Inspection Workshop Course book 3.0
Appendices
Intake dampeners in the system will close automatically upon gas detection,
or their closure is manually initiated via the fire and gas panel, hence
preventing the ingress of gases.
The accommodation bulkhead facing the rig floor should be of A-60 rating,
including portholes. Now a temporary safe refuge (TSR) is created. The crew
should muster inside the accommodation. Hand-held GMDSS radios
(including recharging facilities) have to be provided at the muster stations.
When lifeboats are outside the "shade" of the accommodation they should
be shielded off by bulkheads against heat radiation from the rig floor,
making an embarkation feasible.
503
Rig Inspection Workshop Course book 3.0
Appendices
Another group can be used in Zones 1 and 2 and a much smaller group in
Zones 0, 1 and 2. The zone is used to select the types of protection, which is
allowed. The substance present within the process is used to specify the EX
equipment with temperature rating and gas group being of prime
importance.
The selection of the equipment for one industry or plant cannot be taken as
suitable for a similarly looking location within another. The drilling industry
has one advantage on this point: the groups of gases and substances
expected to be found are the same throughout the world and therefore
similar EX equipment will be located in similar locations on many drilling
units worldwide.
Drilling has evolved a set of recommended practices for the zoning of the
drilling units. These practices are widely used and make the work of the
electrical-maintenance staff easier in knowing that one rig is very much the
same as the next. However, each rig has to have a defined plan, accepted
and passed by the certifying authority as complying with their and all
published oilfield recommended practices.
Specification of the EX equipment, apart from the electrical function which it
is to perform, must take the following into account:
• the zone in which it is to be fitted
• the gas or substance expected
• the surface temperature allowed for the EX equipment
Once the electrical equipment has been specified it is handed over to the
electrician to be fitted. The engineer has to select the equipment to be safe,
but it must be installed correctly or all the expensive EX equipment will not
provide the level of safety expected. The installation of the EX equipment,
which may look neat and tidy, well marked and up to the visual standards
expected, may have hidden faults, which will make it unfit for use in the
hazardous zone.
Several points which would infringe the certification and make the
equipment unsafe are the following:
• The cable glands are of an incorrect type.
• Glands are incorrectly fitted.
• The removal or non-fitting of seals and gaskets.
• The equipment has been moved for whatever reason. It may well have
been taken from one zone to another and not be certified for the new
zone.
• EX equipment is mounted too close to another piece of EX equipment.
• Cable entries are not correctly blanked.
• Mounting holes have been drilled through the enclosure to make a fixing
point.
• Cables are terminated incorrectly inside the enclosure.
• Too many cables are inside the enclosure.
• Spare cable cores are not terminated to earth.
• Not all the cover bolts have been fitted.
• Not all the cover bolts are of the correct specification or type.
• The gap between joints on EXd equipment is above the maximum gap
permissible.
• The correct identification of the equipment has not been added to the
rig's EX equipment register.
504
Rig Inspection Workshop Course book 3.0
Appendices
505
Rig Inspection Workshop Course book 3.0
Appendices
Definitions
The subject of EX equipment has many statements and designations. They
all are very important and can easily cause confusion. A list of the major
statements is given below.
EX equipment Electrical equipment designed for use in areas where
potentially explosive atmospheres may exist.
Hazardous area Area or space where potentially explosive atmospheres
may exist at some time.
Zone Area designation defined by the length of time during
which potentially explosive atmospheres might exist at
that point or area.
Classification The society which provides the rules according to
society which the installation is built and maintained, thereby
allowing insurance cover for the installation to be is-
sued, e.g. ABS, DNV, Lloyd's and others.
Certification The company, which tests electrical equipment and
authority issues a certificate to indicate the equipment, satisfies
the requirement for EX equipment, e.g. UL, FM,
CENELEC, BASEEFA and others.
EX type The method in which the equipment provides protec-
tion against the ignition of potentially explosive atmos-
pheres.
Division USA designation of the area defined by the length of
time and probability that potentially explosive atmos-
pheres may exist at that area.
MODU Code The IMO code for the construction and equipment for
mobile offshore drilling units (MODUs).
IMO International Marine Organization for the improvement
of safety standards, regulations and the issuing of
guidelines on marine safety.
Mobile Offshore Drilling Units and land rigs are predominately engaged in
the drilling for hydrocarbons, oil and gas. They are designed for this
purpose and all the equipment is designed, installed and maintained for the
expected gases.
506
Rig Inspection Workshop Course book 3.0
Appendices
The main area of concern is formed by the drilling fluids and the area
around the well opening. With correct use of drilling fluid, major gas
releases are minimized. However, the equipment which is located in the
potentially hazardous areas must be designed and maintained for the time
the well gives problems and gas is present on the rig and within the mud
system.
507
Rig Inspection Workshop Course book 3.0
Appendices
Definition EXd
The type of protection in which parts that can ignite an explosive
atmosphere are placed in an enclosure, which can withstand the pressure,
developed during an internal explosion of an explosive mixture; and which
prevents the transmission of the explosion of the explosive atmosphere
surrounding the enclosure.
BS 5501 part 5
Definition EXe
The type of protection by which measures are applied so as to prevent
(with a higher degree of security) the possibility of excessive
temperatures and the occurrence of arcs and sparks in the interior and on
external parts of an electrical apparatus which does not produce excessive
temperatures in normal service.
BS 5501 part 6
Definition EXm
A type of protection in which the parts which could ignite an atmosphere
(by sparking or heat) are enclosed in a compound in such a way that this
explosive atmosphere cannot ignite.
BS 5501 part 8
Definition EXi
A circuit in which no spark or thermal effect produced under prescribed
test conditions (which include normal operation and specified fault
conditions) is capable of causing ignition of the explosive atmosphere.
However, the method by which intrinsic safety is achieved makes it
necessary to ensure that not only the electrical apparatus exposed to the
potentially explosive atmosphere, but also the associated electrical
apparatus with which it is connected, is suitably constructed.
BS 5501 part 7
508
Rig Inspection Workshop Course book 3.0
Appendices
Definition EXn
A type of protection applied to an electrical apparatus in such a way that,
in normal operations, it is not capable of igniting a surrounding explosive
atmosphere so that a fault capable of causing ignition is not likely to
occur.
BS 5501 part 3
Definition EXo
A type of protection in which the electrical apparatuses or part of the
electrical apparatuses are immersed in oil in such a way that an
explosive atmosphere, which may be above the oil or outside the
enclosure, cannot be ignited.
BS 5501 part 2
Definition EXp
A type of protection by which the entry of a surrounding atmosphere into
the enclosure of electrical apparatus is prevented by maintaining, inside
the enclosure, a protective gas at a higher pressure than the surrounding
atmosphere.
The overpressure is maintained either with or without a continuous flow
of protective gas.
BS 5501 part 3
Definition EXq
A type of protection in which the enclosure of electric apparatus is filled
with a material in a finely granulated state, so that in the intended
conditions of service, any arc occurring within the enclosure of an
electrical apparatus will not ignite the surrounding atmosphere. No
ignition shall be caused either by flame or excessive temperature on the
surface of the enclosure.
BS 5501 part 4
509
Rig Inspection Workshop Course book 3.0
Appendices
Definition EXs
Apparatus which does not quite meet the requirements of a particular
British Standard may be certified under BASEEFA standard "Special
protection EXs" providing it is established that, after close scrutiny of the
design and testing of the apparatus, it is capable of operating safely in
the hazard which it was designed for.
EEXed IIc T6
• EEX: equipment for hazardous area, European standard
• ed: type of protection used. In this case, dual protection: increased
safety + flameproof enclosure
• IIc: classification of the flammable material which may be present in the
atmosphere. In this case, hydrogen sulphide gas.
• T6: maximum temperature of the enclosure surface. In this case: 85°C.
510
Rig Inspection Workshop Course book 3.0
Appendices
References
• API RP 505 and API RP 14F
• IEC publication 50-426/529
• IEC 600 79-10/79-14/79-17
• ISA RP-12.1.01/RP-12.6/RP-12.24.01
• ISA S12.4/S12.13 S51.1
• NEC articles 500 through 505 and article 550
• NFPA 496 and 497
• UL 913
PROTECTION CONCEPTS
ZONE HAZARD PROTECTION CONCEPTS
0 An explosive gas/air mixture is EXia or EXs
continuously present for long
periods
1 An explosive gas/air mixture is EXd, EXe, EXib, EXp, EXia, EXs
likely to occur in normal
operation.
2 An explosive gas/air mixture is All concepts suitable for: Zone 0
not likely to occur in normal and 1, EXn, EXo and EXq
operation.
511
Rig Inspection Workshop Course book 3.0
Appendices
512
Rig Inspection Workshop Course book 3.0
Appendices
CERTIFICATION CODE
(CENELEC marking information - example [EEx ia] IIC T4)
[ E EX ia ] IIC T4
Associated Certified to Explosion- Protection Associated Apparatus Temperature
apparatus* the protected concept (IS) apparatus* group (gas classification
CENELEC group) (not Gp I)
standard
Examples:
IP 67 = Ingress Protection: dust-tight and protected against immersion
IP 56 = Ingress Protection: dust-protected and protected against heavy seas
513
Rig Inspection Workshop Course book 3.0
Appendices
514