Status of Under Execution Hydro Electric Projects (Above 25 MW) in The Country

The document summarizes the status of 6 major hydroelectric projects in India that are currently under execution and have a capacity of over 25 MW. All projects are experiencing delays and challenges. Key issues include difficult geology impacting tunneling work, slow progress, cash flow problems with contractors, and disruption of work by local protests. The largest project, Tehri PSS, is more than 10 years behind schedule due to geological difficulties, contractor issues, and low funding.

Uploaded by

GD GOENKA MOOT
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views15 pages

Status of Under Execution Hydro Electric Projects (Above 25 MW) in The Country

The document summarizes the status of 6 major hydroelectric projects in India that are currently under execution and have a capacity of over 25 MW. All projects are experiencing delays and challenges. Key issues include difficult geology impacting tunneling work, slow progress, cash flow problems with contractors, and disruption of work by local protests. The largest project, Tehri PSS, is more than 10 years behind schedule due to geological difficulties, contractor issues, and low funding.

Uploaded by

GD GOENKA MOOT
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

Status of Under Execution Hydro Electric Projects (above 25 MW) in the Country

(As on 30.04.2019)

Name of Project State Broad Present Status / Critical Area Remarks/


Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
Central Sector
1 Parbati-II H.P. Dam & Intake Structure- Concreting completed. Poor geology in HRT
NHPC Head Race Tunnel- 28.39 km Excavation out of 31.5km especially in Face-4
11.09.2002 2009-10 completed (TBM-Face).
4x200 = 800 MW 2021-22 Total Overt lining: 26.56 km lining out of 31.5km
Broad Features : (Dec’21) completed.
Dam – 85m High, 109. m Power House: Concreting completed.
long at top, concrete Jiwa Nallah Feeder Tunnel: Completed.
gravity type E&M Works:
HRT- 6m x 31.23km Unit # 1&2 : Unit 1 & 2 have been Synchronized with grid
P.House- Surface at part load on 14.09.2018 & 22.09.2018 respectively
23.5mx 39.7mx 123m. using water from Jiwa Nallah after rectification work of left
Turbine- Pelton pressure shaft. 42 MUs has been generated up to 7th Dec
Swyd.- 13.8/400 kV 2018. Presently the Water Conductor System has been
Cost: emptied for repair of Right Pressure Shaft.
Original:3919.59
Latest: 9394.80 Unit # 3&4: Boxed up.
(04/18 PL) HM Works: About 92% works completed.
Contractors Critical Area: HRT.
Civil : Gammon /
Valecha
HM : Om Metals
E&M : BHEL
2 Tapovan Vishnugad Uttara Barrage: Excavation completed and Concreting 126300 - Completion of HRT.
NTPC khand cum out of 129358 cum completed. - Restoration of TBM
11.08.2004/Nov, 2006 HRT: 9.3 Km excavation completed out of 13.72 Km, TBM - Associated
4x130 = 520 MW 2012-13 struck due to cavity (5.43m completed out of 8.27km). Transmission system.
Broad Features : 2020-21 6.72km concrete lining out of 12.09km completed
Barrage–5 bays of 12m (Dec’20) PH Cavern: Excavation and concreting completed.
HRT- 5.4m x 11.97km Desilting Chamber & Intake: Excavation completed.
P.House- underground TRT: Excavation completed.
Turbine- V.Pelton Surge shaft: Excavation & Lining completed.
Cost: Original: 2978.48 Penstock: Excavation completed and Lining almost
Latest: 3846.30 completed.
Contractors E&M works: Pit liner erection on all 4 units completed.
Civil : Rithwik/L&T / Turbine housing erection of all 4 units completed. Erection
Patel of EOT crane in BVC & service bay completed.
HM : Om Metals Unit #1: Boxed up.
E&M : BHEL Unit #2: Boxed up.
Unit #3: Turbine erection in progress.
Unit #4: Distributor Barrel Concreting completed.
Critical : HRT
3 Tehri PSS, Uttara EPC contract has been awarded on 23.06.11 with - Poor Geology in under
THDC, khand commencement date from 27.07.11. ground works of BVC,
18.7.06 Upstream (Tehri Dam) and Downstream (Koteshwar PAC, TRT, PH Cavern
Nov-11 (Revised 2010-11 Dam), intake and Head Race Tunnels (2 Nos.) already etc.
CCEA) 2021-23 completed alongwith Tehri Stage-I works. - Slow progress of works
4x250=1000 MW (Jun’22) Surge Shafts Upstream (2 nos- 140m).: Excavation, - Cash flow crisis with
Broad Features : Mucking & Rock bolt, Lattice Girder Support work in M/s. HCC.
Surge Shaft: U/s – 2 Progress.
nos. Surge Shafts Downstream (2 Nos): Excavation,
D/s – 2 nos Mucking & Rock Bolt, Lattice Girder Support work in
Power House: U/G progress.
TRT: 2, Dia 9m and
Lenghth 1070m + Butterfly Valve Chamber (BVC 78x10x26m): Excavation
1160m of 5th bench is under progress. Cumulative benching
Turbine: VF reversible excavation is 7942 cum(49.42%).
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
pump turbine Penstock Assembly Chamber (PAC): Crown slashing
Cost: Original: 1657.60 with steel ribs completed. Excavation of 1st bench has been
Latest: 4401.90 completed.
Contractors Power House: Excavation completed.
Turnkey : Alstom, TRT-3(1151 RM): Excavation in Heading 892 RM,
France/ HCC Benching 252.5 RM. Invert Lining-139.9m Overt Lining -
48m completed
TRT-4 (1255 RM): Excavation in Heading-948 RM,
Benching- 527.5 RM Invert Lining-192m completed.
E&M Works: Manufacturing & supplies are in progress.

4 Lata Tapovan, Uttara Infrastructure works are almost completed. Main works to -Works of barrage &
NTPC khand re-start after clearances from Hon ‘ble Supreme Court. HRT yet to start due to
Aug-2012 2017-18 EPC contract for Civil & HM works awarded to M/s L&T on protest by villagers.
3x57= 171 MW 2023-24 17-08-2012. E&M package awarded to M/s BHEL on
Broad Features : (Subject to 07.12.12. -Construction work
Barrage–14 bays of re-start of stopped vide Hon’ble
11m each works) Supreme Court order
HRT- 7.51 Km, 4.7m dia dated 7.5.14.
P.House- underground
Turbine- V.Francis
Cost: Original: 1527.00
Latest: 1801.07
Contractors
Civil & HM : L&T
E&M : BHEL

5 Vishnugad Pipakoti Uttara River diverted on 02.04.2018. -Frequent disruption of


THDC khand Work on construction of coffer dam is in progress. works by local people.
21.08. 2008 2013-14 Development for TBM platform excavation 95% has been - Slow progress of works
4x111= 444 MW 2022-23 completed. - Cash flow crisis with
Broad Features : (Dec’22) Main Access Tunnel (MAT) 407m: Excavation completed M/s. HCC.
Dam – 65m High, upto 397.50m.
89.3m long, concrete HRT (13400m): 432.3m completed by DBM.
gravity Construction of Adits and infrastructure works are under
HRT- 13.4 Km, 8.8m dia progress
Horse shoe shape Desilting Chambers (3 No. X 390m) : Crown Slashing
P. House-Underground completed in DC #1, DC #2 & DC #3 and Benching is
127mx 20.3mx 50m under progress in DC #1 and DC#3.
Turbine- Francis
SWYD- 13.8/420 kV Upstream Surge Shaft: 90.50 RM out of 325.5 RM
Cost:Original: 2491.58 excavation from bottom adit to Upstream Surge Shaft has
Latest: 4105.30 been completed.
Contractors
Civil & HM : HCC Downstream Surge Shaft : 337.17 RM out of 352 RM
E&M : BHEL excavation from adit to Downstream Surge Tank bottom
has been completed.
6 Subansiri Lower Arunachal Dam: - Signing of MoU with
NHPC Pradesh Excavation- 169441 cum completed out of 173000 cum. State Government of
09.09.2003 Assam Concreting: 7.6lacs cum completed out of 19.96 lacs Assam.
8x250= 2000 MW cum.
(1000 MW in 12th Plan) 2009-11 Intake Structure: 261377 cum concreting completed out - Issue of Downstream
Broad Features : 2023-24 of 279454 cum. Impact Assessment &
Dam –116m High, (Subject to Head Race Tunnel (I-VIII): demand for stoppage of
concrete gravity re-start of 7050 m heading excavation completed out of 7124m. works by anti dam
HRT- 8 x 9.5m x 1145m works) 4279 m benching excavation completed out of 7124 m. activists.
Power House- Surface 3199 m concrete overt lining completed out of 7124 m. -Since 16.12.2011
Turbine- Francis Surge Tunnels (8 nos.): 3109 m heading excavation works stopped due to
SWYD- 16/400 kV completed out of 3545 m. agitation by various
Cost: Pressure Shaft- activists of Assam.
Original: 6285.33 Vertical Pressure Shaft Slashing: 199 m excavation out
Latest: 19496.34 of 384 m completed.
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
(04/17 PL) Surface Power House:
Contractors Concreting: 124887 cum out of 302600 cum completed.
Civil : BGS-SGS-Soma E&M Works:
JV / L&T/Alstom Unit #1: Elbow erection (1 to 6) and Turbine stay ring and
HM : Texmaco Spiral case erection completed.
E&M : Alstom Unit #2: Elbow erection (2 to 6) and Turbine stay ring and
Spiral case erection completed.
HM Works:
Erection of diversion tunnel gates 23% completed.
Erection of Intake-5: 17% completed.
Erection of Intake 7 & 8 – 20% completed each.
201 m pressure shaft steel liner erected out of total 1594
m.

Work stopped since 16.12.11 due to agitation launched by


various activists against construction of Subansiri Lower
HE Project. In this regard, as decided in the tripartite
meeting dated 06.12.13, discussions between Expert
Group formed at the request of AASU (All Assam Students
Union) and Experts of Govt. of India & NHPC was held on
23.12.13. Last meeting between Expert Group of Assam
and Experts of Govt. of India was held on 02.06.14 at
Guwahati. Thereafter, meetings with Expert Group of
Assam on 10.12.2014 and on 21.02.2016 & 22.02.2016
with various Stakeholders of Subansiri Lower Project on
11.12.2014 were held to discuss the issues. The meetings
were Co-chaired by Hon’ble MOS (I/C) for Power, Coal
and New & Renewable Energy and Hon’ble MOS (I/C) for
Skill Development, Entrepreneurship, Youth Affairs &
Sports.

As decided in stakeholders meeting on 11.12.2014, a


Project oversight Committee (POC) was constituted vide
MoP’s OM dated 13.01.2015. Due to difference in opinion
on some issues mainly seismic issues, the Expert Group of
Assam has submitted the final report to MoP & members of
POC from Government of India have also submitted a
separate report to MoP in Jan / Feb’2016.

Matter related to Subansiri Lower HEP was being heard by


Hon’ble National Green Tribunal (NGT), Kolkata. The
judgment has been pronounced by NGT Kolkata
on 16.10.2017.

“In this judgement, NGT has directed MOEF&CC to


constitute a committee of three expert members from the
field of Seismology, Geology and Hydrology and one of
these members shall be from Northeast to examine the
entire matter and reports of various committees
constituted. The Terms of Reference (TOR) of the
committee will be same as made to POC as contained in
OM no. 2/5/2002-NHPC dated 13.01.2015. The
MOEF&CC shall constitute the Committee within one
month and the committee shall give its report in three
months from the constitution of the committee to
MOEF&CC which will be placed before Expert Appraisal
Committee (EAC) for appraisal under Environment Impact
Assessment (EIA) Notification 2006. EAC shall complete
the appraisal within 60 days and place it before the
competent authority for final decision.”
Subsequently, MoEF&CC has constituted a Committee
consisting of three expert members vide order dated
27.11.2017. The committee has to give its report within 3
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
months from date of issue of order.
In the meantime, the Applicant (Sh. Aabhijeet Sharma)
raised objection in NGT, Kolkata on the constitution of
committee by Ministry of Environment, Forest & Climate
Change (MoEF &CC).
NGT, Principal Bench, New Delhi vide order dated
19.11.2018 dismissed the Application (MA) of Sh.
Aabhijeet Sharma. Caveat has been filed by NHPC in
Supreme Court on 22.11.2018. The hearing on Application
filed by Sh. Tularam Gogoi was scheduled to be held on
14.12.2018. On hearing dated 14.12.2018, after hearing
the counsel of Appellant, the court dismissed the
application based on the order given in identical matter of
Sh.Aabhijeet Sharma on 19.11.2018.
Subsequent to order of Hon’ble NGT, Principal Bench,
dated 19.11.2018, 3rd meeting of Expert Committee held
on 12.12.2018 at MoEF & CC, New Delhi. Meeting with the
members of POC-Assam also took place. Applicants (Sh.
Aabhijeet Sharma and Sh. Tularam Gogoi) did not attend
the meeting. Expert Committee visited Subansiri Lower HE
Project on 09.01.2019. Submission of Expert Committee
Report to EAC is awaited.
Meanwhile, Tularam Gogoi has challenged NGT order
dated 14.12.2018 before Hon’ble Supreme Court of India,
praying for setting aside the said order. The matter was
heard on 11.03.2019, wherein Hon’ble Supreme Court has
decided that the order dated 19.11.2018 passed in
Abhijeet Sharma verses Union of India and order dated
14.12.2018 passed in Tularam Gogoi v/s Union of India be
set aside and reverted to NGT for passing a reasoned
order. However, the Hon’ble Supreme Court has allowed
the MoEF&CC to continue with the work of Expert
Committee constituted in pursuance of NGT order dated
16th Oct, 2017.
Signing of MOA with Govt. of Assam:- Signing of MOA with
State of Assam is pending yet. NHPC had sent the draft
MOA, approved by MOP, to the States of Assam and
Arunachal Pradesh in April-03 for their consent / signing of
Agreement. The MOA with Arunachal Pradesh
Government has already been signed on 27.1.2010.
7 Teesta-VI Sikkim Barrage and Desilting: Excavation completed & - Works stalled since
NHPC concreting 98% of 380003 cum completed. April, 2014 due to
27.12.2006 2012-13 HRT: Heading excavation 10650m and benching financial crunch with the
4x125= 500 MW 2023-24 excavation 4270 m out of total 27505 m completed. Overt developer.
Broad Features: (Subject to lining 1550 m completed. - NHPC Ltd. emerged as
Barrage: 34.27m high re-start of Surge Tank: Excavation completed & concreting under H1 bidder during bidding
HRT- 2nos,13.7km long works) progress. process by NCLT.
Pressure shaft: 4nos. Pressure Shaft: Underground excavation of 4 no. Government of India
5.4m dia. 130m av pressure shaft completed, lining of one no. pressure shaft approval recd. on 8.3.19.
length, completed, balance lining under progress.
TRT: 4nos 250m av HM works: 2 nos. radial gates erection in bay 1&2
length, 8.5m dia. completed. Erection of 1st stage embedded parts of radial
PH- Under ground gates in bay 3&4 under progress.
Turbine- Francis Power House: Excavation completed & conc. 21945 /
Cost: Original: 3283.08 44578 cum completed. Concreting to Draft Tube Liners for
Latest : 5748.04 all the 4 nos. Units completed. Erection of spiral casing of
(07/2018 PL) Unit #1 completed.
Contractors Transformer Cavern: Excavation completed & concreting
Civil & HM : Lanco 2539/7101 cum completed.
E&M : Alstom TRT: Excavation & Lining almost completed.
8 Kameng Arunachal All major works related to commissioning of project Rectification works of
NEEPCO Pradesh completed. leakage observed in
02 12 2004 All Units Boxed up. penstock 1&2.
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
4x150 = 600 MW 2009-10 Leakage observed in penstocks during water filling.
Broad Features: 2019-20 Complete NDT of all circumferential joints of pressure shaft
Dam :Bichom-69m (Nov’19) / penstock is in progress along with rectification of defects.
High, 247.3m long.
Tenga – 24.4 High,
103m long.
HRT- 6.7m dia, 14.45
km.
High Pressure Tunnel
(HPT)Total length 3.64
km
Surge Shaft: 25m dia,
70m Height
P.House- semi-U/G
Turbine- Francis

Cost: Original: 2496.90


Latest: 6179.96
Contractors
Civil : Patel
HM : Om Metals & JSC
JV
E&M : BHEL
9 Ramam-III West Bengal Civil & HM works of Barrage including Part HRT Package - Works affected
NTPC Hydro Ltd. awarded to M/s Simplex –Apex JV on 10.09.14. due to GJMM
10.09.14 2019-20 Civil & HM works of Power House including Part HRT Andolan.
3x40 = 120 MW 2021-22 awarded to M/s SEW Infrastructure Ltd. on 12.12.2014. - Funds flow
Broad Features : (Feb,22) Electro-Mechanical (EM) Package awarded to M/s BHEL in constraints with
Run of the River Feb-2015. the contractor
Scheme First stage river diversion done on 23.03.2016. First phase
Cost : Original: 1381.84 Barrage excavation completed and Raft concreting in
Latest : 1592.34 progress.
Contractors HRT excavation 7% completed.
Civil & HM : Simplex- Excavation of Desilting chamber completed.
Apex JV / Sew Surge Shaft: Excavation 60% completed.
E&M : BHEL Pressure Shaft: Excavation 29% completed
Power House: Excavation 94% completed.
TRC: Excavation 84% and concreting 82% completed
Switchyard : Excavation and filling completed
10 Naitwar Mori Uttara River Diverted on 31.01.2019 -
SJVN Limited khand Desilting Tank : Removal of slide deposit in desilting tank
16.10.2017 2021-22 area is in progress. Cumulative 43,501 cum out of 48,000
2x30=60 MW 2021-22 cum completed.
Broad Features : (Dec,21) Adit 1&2 : Excavation of Adit #1 Completed and that of Adit
Barrage: 30.5m height #2 -24m out of 361m completed.
HRT: 5.6m horse shoe, HRT: Excavation 275.5m completed.
4330m long HM works : LoA issued to M/s GMW Private Ltd. on
Pressure shaft: 4m dia, 18.04.18.
109m long E&M works : Works awarded to M/s. Voith Hydro Pvt. Ltd.
Surge shaft: 18m dia, On 11.06.2018.
51.65m height
Cost : Original: 648.33
Latest : 648.33
Contractors
Civil : JP Associates
HM : GMW
E&M : Voith
11 Pakal Dul J&K Infrastructural works: Excavation of MAT and adit to
CVPPL Powerhouse completed.
03.10.2006 2020-21
4x250 = 1000 MW 2023-24 Dam: Letter of Acceptance issued to M/s Jaiprakash
Broad Features : (Aug.’23) Associates on 21.06.18.
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
Dam – 167m High, Excavation of Diversion Tunnel – 83m out of 808 m
Width-305m), CFRD, completed.
HRT- 2 nos. 7.2m dia
1000m long Power House(157mx20.20mx49m): Letter of Acceptance
S.Shaft-16m dia issued to M/s. AFCON-JP Associates JV on 21.02.18.
200m Height E&M Package: Bids evaluated and are under consideration
P.House- Underground of the Board
(157mx20.20mx49m)
TRT- 5.5m dia, 125m
long.
Cost: Original:8112.12
Latest: 8112.12
Contractors
Civil & HM : Afcons –
JAL - JV
E&M : BHEL
State Sector
12 Parnai J&K The implementation of the project has been undertaken - Slow progress of
JKSPDC by awarding the EPC contract in favour of M/s. Patel works
21.10.2013 2017-18 Engg. Ltd. in 2013. - Land acquisition
3x12.5= 37.5 MW 2021-22 Barrage:- Excavation 21869 cum out of total 30883cum issues at Adit-I to
Broad Features: (Mar,22) completed. HRT & Power
Barrage: 107m Long, HRT (D-shaped, 3.2m diameter, 9.236km long):- 3744m House area.
11.7m High out of 9236m excavation completed.
HRT: D Shape, 9236m Pressure shaft (1no. 2mdia, 1733mlong) :- Excavation
long, 3.2m dia 5761 cum out of 13,824 cum completed.
Surge Shaft: 3.2m Dia Surge shaft (3.2m dia.) : 704cum excavation out of
Power House- Surface- 14000cum completed.
60x12x28
Cost: Original: 640.41
Latest 640.41
Contractors
Civil : Patel & Alstom
E&M : Andritz
13 Lower Kalnai J&K EPC contract awarded to M/s. CPL in Sept., 2013. - Slow progress of
JKSPDC Diversion tunnel has been completed and river diversion works
16.08.2013 2017-18 made on 30.11.2016.
2x24= 48 MW 2022-23 Work on coffer dams has been started
Broad Features: (Subject to Dam:- Excavation work completed for right abutment of
Dam: 110m Span, 49m re-start of the dam bridge. Excavation of left abutment completed
High works) upto 50%.
HRT: D Shape, 3960m HRT:-Adit excavation is in progress.
long, 4m dia After suspending works in January, 2017, works resumed
Surge Shaft: 14m Dia at site since 12th April, 2017. Due to poor progress of the
Power House- Contractor, JKSPDC has revoked the advance payment
55x23.45x32.4 and the performance bank guarantee aggregating to
Cost: Original: 576.87 Rs.79.21 Crores.
Latest 576.87
Contractors
Civil : Coastal
E&M : GE
14 Shahpurkandi Punjab Main Dam: 1286552 cum Excavation out of 1981500 cum
Irrigation Deptt. and 89286 cum concreting out of 1135295 cum completed.
&PSPCL 2015-16 Hydel Channel: 2696210 cum excavation out of 3900000
04.05.2011 2021-22 cum and 22153 cum concreting out of 42864 cum
3x33+3x33+1x8=206 (Nov.21) completed.
MW Works of Dam stopped since 29.08.2014 due to inter-state
Cost: Original: 1835.50 dispute between states of J&K & Punjab on sharing of
Latest 1835.50 waters of river Ravi & tariff. An agreement was signed on
(Power Component) 8.9.2018 between Chief Secretary, Govt. of Jammu &
Contractors Kashmir and Chief Secretary, Govt. of Punjab. The Punjab
Civil & HM : Soma – Cabinet ratified the above agreement. Zero date of the
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
BUREYA JV project is 1st November, 2018 and the project would be
E&M : BHEL completed in 3 years..
15 Uhl-III H.P. All works completed. During Hydro Static pressure Test of
Beas Valley Power Penstock some leakage was observed. Repair work is in
Corporation Ltd. 2006-07 progress.
(HPSEB) 2019-20 Project is Programmed to be commissioned by December,
19.09.02 / (Dec’19) 2019.
(TEC -2x50 MW)
3x33.3 =100 MW
(Revised vide HPSEB
letter dt. 19.01.07.
Broad Features:
HRT-4.15m x 8.47 km
S.Shaft- 13m x 57m
Penstock- 3.4m x
1860m
P.House- Surface
Turbine- V. Francis
Cost: Original: 431.56
Latest: 1281.52
Contractors
Civil : Continental / Abir
HM : PES
E&M : BHEL

16 Sawra Kuddu H.P. Barrage: Excavation completed & concreting is under - HRT is critical
H.P. Power Corpn. Ltd. advance stage of completion.
Clearance: 10.11.2004 2011-12 HRT: Excavation completed and 10135 m out of 10835 m
3x37= 111 MW 2019-20 overt lining completed. Steel Liner erection 260m out of
Broad Features: (Nov,19) 530m completed.
Diversion Structure: Surge Shaft: Excavation & Lining completed.
10.45m high Piano Key Pressure shaft: Excavation & lining completed.
Weir. Power House: Excavation completed and concreting
HRT- D-Shaped, 5m almost completed.
dia, 11.145Km long. TRT: lining completed.
Power House- Under E&M: All units boxed up.
ground Critical : HRT.
Turbine- 500 rpm VF.
Switchyard: 220 Kv.
Cost: Original: 558.53
Latest: 1181.90
Contractors
Civil & HM : HCC /
Patel
E&M : Andritz
17 Shongtong Karcham H.P. River Diversion achieved on 10.02.2017. -Issues with Army
H.P. Power Corpn. Ltd. Barrage: Excavation under progress. authorities for shifting of
Clearance: 16.08.2012 2016-17 HRT: Heading excavation of HRT 4.5 km out of 7.712km ammunition depot.
3x150= 450 MW 2023-25 completed. - Slow progress of works
Broad Features: (Apr’24) Surge shaft: 95m out of 100m pilot hole completed.
Intake Tunnel: 4 Nos. Power House: 83% excavation of Power House
Horse shoe 6.4m dia completed.
192 to 280m length
HRT- Circular, 10.5m Works hampered in some portion of HRT due to re-location
dia, 8096m long. of Army ammunition depot. Issue is under resolution
Power House- Under between Army, GoHP & HPPCL.
ground
Turbine- VF. Works are stalled since 18.04.2017 due to pending
Switchyard: 400 Kv. payment. Further, 125 out of 171 labour / workmen have
Cost: Original: 2807.83 been laid off by M/s. Patel Engg. Ltd w.e.f. 18.05.2017 to
Latest: 2807.83 21.07.2017. Work has now been resumed partially.
Contractors
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
Civil & HM : Patel
E&M : Andritz
18 Vyasi Uttarakhand Civil Works: -Dam and E&M works
UJVNL Dam : Excavation completed. 2.26 Lakh cum out of 3.6 are Critical.
25.10.2011 (TEC) 2014-15 lakh cum of Concreting completed. -Local issues.
2x60= 120 MW 2020-21 Diversion Channel : Completed.
Broad Features: (Jun,20) Head Race Tunnel (2.7 Km): Excavation of HRT
Dam: Conc. Gravity completed. 2551.05m Overt Lining and 1718.75m Invert
H- 86m L-207.2m Lining out of 2655m has been done.
HRT- Circular, 7m dia, Pressure Shaft: 4139cum out of 5000cum Excavation
2.7Km long. completed.
Power House- Surface Surge Shaft : Excavation completed. Concreting-250cum
Turbine- VF. out of 6626cum completed.
Switchyard: 220 Kv. Power House: 2,58,500 cum out of 270,000cum
Cost: Original: 936.23 Excavation completed. 8938 cum out of 17,800 cum
Latest: 936.23 Concreting of Sub structure completed. Erection of Draft
Contractors Tube in both the units is in progress.
Civil : Gammon / MPCC
E&M : BHEL
19 Koyna Left Bank PSS Maha Civil Works: -Slow progress of works.
WRD, Mah. rashtra Excavation of intake structure 4781 cum out of 14105 cum -Funds constraints due
20.02.2004 and lining 2485 cum out of 3381 cum completed. to increase in Project
2x40 = 80 MW 2014-15 Excavation of Switchyard completed. Excavation of cost. RCE under
Broad Features: 2022-23 Approach tunnel & Ventilation tunnel is in progress. approval.
Water from the existing (Subject to Tail surge shaft : Excavation in soft strata completed.
Shivaji Sagar Lake re-start of Excavation for inclined / vertical / lateral shafts in hard rock
(Koyna reservoir) works) 6448 / 9223 cum completed.
is to be utilized for TRT : 364 / 24003 cum excavation completed.
generation. Machine Hall : Underground Excavation is under
Intake Tunnel: Dia – progress. 22600 cum excavation out of 55050 cum
7.20 M completed.
Length – 235.5 M E&M works:
(including Lake tap) The contract for details engineering manufacturing supply,
HRT: Dia – 7.20 M supervision erection, testing commissioning and putting
Length – 80 M into commercial use of pump turbine, generator motor and
Penstock – 2 nos , associated equipments is signed with M/s IVRCL Ltd.,
Dia – 2.9M Pune on 16.12.2010. Further TG set has been ordered as
Length – 10 M each under:
P.House – Underground Turbine/Pump: M/s Litosroj Power, Slovenia (European
Turbine – Reversible Union)
Cost: Original: 245.02 Generator/Motor: M/s Koncar Power, Plant & Electric
Latest: 1494.94 Traction Engineering, Croatia (European Union).
Contractors EOT Crane :- Works awarded to M/s Pedvak Cranes
Civil & HM : BT Patil – Private Limited Hyderabad on 12.04.2013.
Malaxmi JV / Patel
E&M : Litostroj Slovania
& Koncar, Croatia
20 Polavaram Andhra Spillway, Earth cum Rockfill Dam, Power House
APGENCO / Irrigation Pradesh Foundations Works awarded in March, 2013 to M/s.
Deptt., A.P. 2017-18 Transtroy- JSC EC UES JV.
21.07.2010/ 2021-23 ECRF DAM: Earth work of 508.06 L.Cum /833.169L.Cum
25.02.2009 (Mar,23) is completed.
12x80= 960 MW Diaphragm Wall concreting – completed.
SPILLWAY: Excavation-838.80 L Cum out of 1115.59 L
Cost: Cum completed. Concreting 9.60 L Cum out of 36.79 L
Original: 4956.39 cum completed.
Latest: 5338.95 Gates: Radial Gate fabrication – 11010 MT completed out
(Power Component) of 18000 MT (61.17%).
Contractors Power House: Earth work of 106.36 L Cum / 114 L.Cum is
Civil : Navyug completed & embankment of 9.79 L.Cum / 10 L.Cum is
HM : PES completed.
E&M : GE B) The LoA for works of Power House on turnkey basis
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
was issued to M/s Navayuga Engineering company limited
on 06.12.2017. The contract agreement was signed on
06.01.2018 and the zero date of the contract commenced
from 06.01.2018.
It is programmed to commission the first there (3) units
within 46 month from zero date and the balance 9 units at
an interval of 2 months thereafter.
21 Pallivasal Kerala Intake structure: Excavation – 28398/33492 cum - Poor Geology.
KSEB completed. -Contractual Issues.
2x30= 60 MW 2010-11 Leading channel of Water conductor system replaced by -Works stopped by the
31.01.2007 2021-22 cut & cover/soil tunnel and accordingly intake is shifted. civil contractor from
Broad Features: (Dec,21) HRT: Excavation –2858/3330 m completed. 22.07.2015.
HRT: 3.50m X 3396m Overt conc. 1637/3330 m completed. After resuming the work
Surge Shaft: 7.0m X Invert Conc.. – 1637/3330 m completed. on 11.04.2017, the
49m Surge Tank/Forebay: Exc.–7640/13400 cum. contractor stopped work
Pressure Shaft: 2.50m Conc.423/843 cum. w.e.f. 10.04.2018
X 1019.20m Pressure Shaft: Excavation completed. Fabrication of demanding an enhanced
Penstock: 2.nos., steel liner completed and erection of 96/1096 m claim. The Board has
1161.20m each. completed. served a termination
Power House: Surface Surface penstock: Excavation –109354/122600 cum. notice on 13.09.2018 at
Turbine : Pelton Concreting- 11641/12850 cum. Fabrication completed and the risk and cost of the
S.Yard: 220kV – Single 1177m out of 2036m erection completed. contractor. The
bus Power House: Excavation completed. Concreting contractor has filed a
Cost: Original: 222.00 3980/11225cum. writ petition in the
Latest : 550.00 Tail race Channel (2 Nos.): Excavation & lining Hon’ble High Court of
Contractors completed. Kerala challenging the
Single Package(Except E&M Works: 75% supply completed. Erection yet to start. termination order and
Intake & balance Tunneling the court has issued an
works) interim stay order on
ESSAR – DEC – CPPL enforcement of
JV termination order and
-M/s Bumi-Zillion JV the case is pending in
(for Intake works & the Hon’ble High Court.
balance Tunneling Retendering of balance
works) works is in progress.
Phase II Intake works &
balance Tunneling works
have been accorded to
M/s. Zillion JV on
05.01.2018. Work is in
progress.

22 Thottiyar Kerala Civil Works: -Works are stand still


KSEB Weir: 3320 cum excavation out of total 10200 cum and since 2015 due to
1x30 + 1x10= 40 MW 2012-13 3056 Cum concreting out of 10928 Cum completed. Contractual Issues.
05.06.2008 2020-21 Approach Channel & Intake: Excavation-3184 cum out of Accordingly the
Broad Features: (Dec’20) 9584 cum done. contractor put forwarded
Weir: 222m Long 11 Power Tunnel : Excavation completed. a proposal for
blocks 7.5m height Power House, switchyard & allied works: 31790 cum foreclosure of the project
Tunnel: Circular 2.6m excavation out of 43690 cum and 2733 cum concreting out due to their financial
dia 199m long. of 16209 m done. stringency.
Power House: Surface
Turbine : Vertical Pelton -Civil & HM works was
Cost: Original: 136.79 re-awarded to the L1
Latest: 195.55 bidder- M/s PRIL- Sri
Contractors Sarvana Industries Pvt.
Civil & HM : PRIL- Sri Ltd. on 05.01.2018.
Sarvana Industries
Progress of works badly
affected due to heavy
rain and flood in Aug.’18.
Tendering process for
balance Electrical works
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
under process.
23 Kundah Pumped Tamil Nadu Civil & HM Works: LOI issued to M/s Patel Engg. Ltd. for
storage Phase-I Package-I & M/s Kundah PSP Consortium for Package-II
TANGEDCO 2022-23 on 15-02-2018.
1x125= 125 MW 2022-23 Excavation of balance MAT, balance CCVT, Adits to TRT,
Cost: Original: 488.48 TRSS, Power House top/bottom, Pressure Shaft bottom
Latest: 989.80 have been completed.
Contractors HRT portal: Benching under progress.
Civil & HM : Patel / Power House: Pilot Tunnel for main PH Cavern &
Kundah PSP Transformer Cavern have been completed. Slashing is
under progress.
TRT: Excavation under progress.
E&M works: Award of works is under progress.
Private Sector
24 Ratle J&K EPC Contract for Civil & HM works awarded to M/s GVK - Presently works are
Ratle Hydro Electric Projects & Technical Services Limited on 04.07.2013. The under hold.
Project Pvt. Ltd. 2017-18 infrastructure works of Road & Bridges was under progress
19.12.2012 2023-24 and erection of upstream Bridge completed & downstream - Local Issues
4x205+1x30= 850 MW (Subject to Bridge was in progress. Works have been suspended at
Broad Features : re-start of Project site due to frequent local disturbances since
Dam Height-133m works) 11.07.2014. Power Development Department, GoJK have
Length-194.8m been requested to resolve the various critical issues
Spillway-Radia Gate-(5) including 1) resolving of disturbance at site 2) restoration of
Size-10.75x1420 m congenial atmosphere and 3) IWT issues for resumption of
Diversion Tunnel:2 works at site.
Nos., Circular (Right
back) Excavation of DT1 (298m out of 472m)
Pressure Tunnel:11m & DT2 (192m out of 552m) completed.
dia each.
Pressure Shaft : 6.6 m Govt. of J&K, PDD have terminated PPA on 09.02.2017
each steel lined. and directed JKSPDC to take over the project. JV of
P.House-Underground JKSPDC & NHPC formed for implementation of
Turbine- Francis project.
Average Gross Head-
100.39m The State Govt. has decided to develop the project through
Addl. Unit(30MW) JKSPDC. The matter is now pending adjudication before
Housed in Main P.H. the Arbitration Tribunal constituted by the Hon’ble High
Cavity) court of J&K State in terms of the PPA.
Rated Head-98.9m
Cost :
Original: 5517.02
Latest 6275.00
(09/2013)
Contractors
Civil & HM : GVK
E&M : Alstom
25 Sorang H.P. All Civil Works completed. - Repair of penstock
Himachal Sorang Power work
corporation Ltd. 2011-12 Both the units are boxed up. During the filling of water
June, 2006/ 2019-20 conductor system in 1st week of Nov., 2013, leakage
2x50= 100 MW (Dec’19) occurred in penstock due to cracks. Rectification work
Broad Features: completed in April, 2015. Unit #1 synchronized with grid on
HRT- 1.5 km 30.10.2015, however, could not be commissioned due to
Trench Weir-59 m non-availability of rated discharge.
P.House- underground On 18-11-2015 when Unit # 2 was under trial run, there
Turbine- Pelton was rupture in the surface penstock pipe. The incidence
Gross Head-626 m caused loss of lives and property.
SWYD- 11/400 kV The rectification work is under progress. Land acquisition
(GIS) for new alignment of Penstock & other infrastructure is
Cost: Original: 586.00 completed.
Latest: 586.00
Contractors
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
Civil & HM : NCC –
Maytas – SS JV
E&M : Voith Siemens
26 Tangnu Romai-I H.P. Civil works awarded on 14.06.2010 to M/s Sai Urja Hydel - Slow progress of
M/s Tangnu Romai Project (P) Ltd. works HRT critical,
Power generation 2014-15 Barrage and Diversion Cannel: 26211 cum out of 93800 poor geology.
2x22= 44 MW 2021-22 cum excavation completed. - Works are stalled due
30.11.2007 (TEC by (Subject to Desilting Chambers & SFTPC: Excavation completed. to finance issues since
HPSEB) re-start of SFT excavation 420 / 450.66 m completed. Jan, 2015.
Broad Features: works) HRT: 2826m out of 6300m excavation completed. - Developer have
Barrage at EL + 2555 m Power House, Switchyard & Misc.: 60275 m3 out of initiated the sale of the
HRT-3.1m dia & 7.220 Project and are in the
km length 72000 m3 excavation completed. process of negotiating
Surge Shaft- 5m dia, In February-2015, due to land slide the steel bridge on with Potential Buyers.
Top Level 2570 m & Pabbar River, connecting Project components has been
Bottom Level 2520 m completely damaged. The restoration works are
Penstock- 2 m dia & completed.
609.3 m length
P.House- Surface
Turbine – Vertical
Francis
Cost:
Original: 255.00
Latest: 641.89
Contractors
Civil & HM : Sai Urja
E&M : Andritz
27 Bajoli Holi H.P. Civil Works: 75% works completed. -Slow progress of works
M/s GMR Bajoli Holi Dam: Excavation 1,56,221cum of 1,71,100cum completed. -Poor approach roads
Hydro Power Pvt. 2018-19 1,22,935 cum out of 2,10,000 cum concreting completed. -Power evacuation
Limited 2019-20 HRT: 15.3 km excavation out of 16km completed. 5.1 km system is critical.
31.12.2011 (Mar,20) lining out of 15.9 km completed. - Due to excessive
3x60= 180 MW Surge Shaft: Excavation completed. Lining-11m snowfall on 6th & 7th Feb
Broad Features completed. 2019, in the entire region
Dam Height-66 M Pressure shaft: Excavation completed. Lining-2117cum up to Chamba, access
Dam Length-178 M out of 20500 cum completed. roads got severely
Desilting Chamber- 2 Power house: Excavation completed. 37359 cum out of damaged. Power Supply
Nos. 49720cum concreting done. remained completely cut
240 Mx14.5 MX 10.8 M off to the entire region
HRT- Length-15.538 HM Works: 57% works completed. during 6th ~25th Feb
Km., 5.6 M dia 2019.
P.H. –Surface E&M Works: 72% works completed.
Cost: Original 1696.93
Latest 2205.00
Contractors
Civil & HM : Gammon
E&M : Alstom
28 Tidong-I H.P. Barrage & River Diversion Works: Common Excavation - Slow progress of
M/s Statkraft India Pvt. completed and 71700.84/73409.00 open cut rock works.
Ltd. 2013-14 excavation completed. 32349 cum out of 37647 cum - Transmission Line
2x50 = 100 MW 2021-22 concreting done. critical.
28.07.2006 (Oct. 21) Head Regulator & Desilting arrangement: Common
Broad Features: excavation completed. 9763 cum open cut rock excavation
HRT–D-3.5m L- 8461 m out of 10,000 cum completed.
P.H. Surface HRT (8526m): Excavation completed and 1879m lining
Turbine –Vertical Pelton completed.
Cost: Original 543.15 Surge Shaft: Excavation completed.
Latest 1286.27 Pressure Shaft: Excavation completed
Contractors Power house and Tail race channel- 87709 cum out of
Civil & HM : SCL 92500 cum excavation completed.
Infratech / Himalaya 11237 cum out of 16156 cum concreting completed.
E&M : Alstom
M/s Statkraft India Pvt Ltd has acquired the 100% equity of
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
the project on 04.09.2018 and remobilization of manpower
on the project is in progress. Presently project is
scheduled to be commissioned by October 2021.

29 Phata Byung Uttara Dam concreting: 17800/18000 cum concreting - Works severely
M/s Lanco khand completed. affected due to flash
06.10.2008 P.H.: Excavation completed & Concreting in progress. floods in June, 2013.
2x38 MW = 76 MW 2012-13 HRT: Excavation almost completed. 1400 m Lining has - Works are stalled
Broad Features: 2021-22 been completed. since July, 2017 due
Dam – 26m high (Subject to Excavation and lining of Intake-I & Intake-II completed. to Funds constraints
HRT- 3.2 m dia & re-start of Pressure shaft: Excavation completed & lining is under with the developer
9.38 km length works) progress.
Turbine – Frances TRT: Excacation 178/235m completed.
Cost: Original: 520.00 E&M Works: Pit liner erection of units completed. EOT
Latest : 1225.53 Crane installed and Commissioned.
Contractors
Civil : Lanco
HM : Cimmco
E&M : Alstom
30 Singoli Bhatwari Uttara River diversion – completed. - Works severely
M/s L&T khand Dam & Dykes/Barrage: Excavation almost completed and affected due to flash
11.07.2008 concreting 65730.85 / 70220 cum completed. floods in June, 2013.
3x33 MW = 99 MW 2012-13 HRT: Excavation completed - HRT Critical
Broad Features: 2019-20 Overt Concrete Lining 7099m / 11257m completed.
Barrage-FRL 1017 m, (Mar,20) Invert Lining: 7099m / 11257m completed.
MDDL 1009 m, Pressure Shaft:: Excavation completed.
Barrage Top 1020m Power House: Excavation completed & concreting 29009/
HRT- 4.65m dia & 29959cum completed.
11.870m length Surge Tank: Excavation completed. 4113.93cum out of
Surge Shaft-10 m dia & 5349cum concreting completed.
102.85 m length E&M Works: Erection of spiral casing of Unit#1 is in
Pressure Shaft-One, progress. Draft tube erection and EOT crane Erection &
3.80m dia & 358m Load testing completed.
length
Penstock- 3 Nos., 2.20
m dia & 34m, 42m, 48m
long.
P. House-Surface
Turbine-Vertical Francis
TRT- Open Channel,
650m length
Cost : Original : 666.47
Latest:1694.00(PL-2018)
Contractors
Civil : L&T
HM : General
Mechanical Works
E&M : Voith
31 Maheshwar, M. P. Civil & HM Works: - Completion of R&R
SMHPCL All major civil works completed. All 27 nos radial gates works and E&M
30 12 96/ 29.9.2006 2001-02 commissioned. works.
(FC) 2021-22 Unit Erection: - Works held up due to
10x40= 400 MW Unit-10: Initial spinning achieved on 14.10.2011. Fund constraints with
Broad Features: (Subject to Unit-9 & 8: Ready for spinning. developer.
Dam-35m High, re-start of Unit-7: Guide apparatus trial assembly in progress. - Sub-Judice in NCLT.
concrete gravity works) Unit-6: Erection of turbine embedded parts & foundation
P.Shaft-10x7.82m x parts completed.
52m Unit-5 to 1: Erection of units is in initial stages.
P.House - Surface Works suspended since Nov-11 due to cash flow
Turbine- Kaplan problem with developer.
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
Cost: A high level committee under the chairmanship of
Original: 1569.27 Additional Chief Secretary(Finance) GoMP, was formed on
Latest: 8121.00 16th Oct, 2014 to find ways to complete the project. The
Contractors committee has submitted its report on 2.5.2015. The
Civil & HM : Sew committee has recommended three scenarios for
E&M : BHEL commissioning the Maheshwar Project. Under the first
scenario, another attempt to complete the project with the
present private developer has been envisaged. Timeline
for first Scenario has elapsed (2nd August 2015) without
the promoter complying with its requirements. As per
second scenario, Lenders as Govt. Companies (PFC as
lead lender) have acquired majority equity i.e. 51% in the
SMHPCL w.e.f. 1st June, 2016. National Company Law
Tribunal (NCLT), Ahmedabad inter-alia declaring
shareholding of lenders bad in law. Against the adverse
order of NCLT, appeal has been filed in National Company
Law Appellate Tribunal (NCLAT), New Delhi. NCLAT
passed the order on 12-03-2018 against the share holding
of lenders. NCLAT in the order also mentioned that Central
Govt. may also as a part of investigation, direct, at the cost
of the company, forensic audit of the company under
supervision of the official of CAG at least since 2005 if not
earlier. PFC has filed an application in NCLT Ahmedabad
on 16th February 2018 to start Corporate Insolvency
Resolution Professional (CIRP) under Insolvency and
Bankruptcy Code(IBC). The way forward is now dependent
on the outcome of the petition filed by PFC in NCLAT
seeking resolution under IBC and also on the forensic audit
by CAG.

32 Rangit-IV Sikkim Dam & Intake works: Excavation 409184 / 492775 cum Financial crunch with
Jal Power corp. Ltd. completed and concreting 61045 cum out of 173229 cum the developer.
06.07.2007 2011-12 completed. Excavation of road diversion tunnel has been Work held up since
3x40= 120 MW 2022-23 completed. Oct, 2013 due to fund
Broad Features: (Subject to HRT: Excavation in progress and 3794 m out of 6488 m constraints.
Dam: Concrte 44m high re-start of completed.
.HRT : D- 6.4m L- works) Surge Shaft: Excavation has been completed & In the latest Joint
6.5km concreting yet to start. Lenders Forum meet
Power House : Surface Pressure Shaft: Excavation of Horizontal Pressure Shaft held in PFC on 5th April,
Turbine: Francis completed. Vertical Pressure Shaft 60.5 m out of 84.7m 18, Lenders decided to
Cost: Original:726.17 completed. file application in
Latest : 1692.60 Power House: Excavation in Power House completed. NCLAT and the same
Contractors Concreting 8565 cum out of 19900 cum completed. has been filed on 24th
Civil : Coastal Desilting chamber: Excavation 2143 m out of 3360 m April, 18. Now nos. of
HM : Texmacho completed. hearing by NCLAT has
E&M : Andritz been fixed so far
without outcome till
date.
33 Bhasmey Sikkim Project is in initial stage of construction. River diversion - Slow progress of works
Gati Infrastructure achieved. - Works stalled since
2x25.5= 51 MW 2012-13 Barrage: 61555cum/194600cum excavation completed. Sept., 2016 due to
Broad Features : 2022-23 HRT: 1670m/4460m excavation completed. paucity of funds.
Dam-33.2m High, (Subject to PH: 136105 cum/185937cum excavation completed.
Symmetrical gravity re-start of
HRT-5.3m dia &5.132 works) Surge Shaft : 8567cum / 22000cum Surface excavation
km length , Circular. completed.
Surge Shaft- 89.8m
Hight & 14m dia.
P.House-Outdoor
Turbine-VF
TRT-2 Nos, L- 50m
Swityard-132/11 KV
Cost :Original : 408.50
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
Latest : 690.30
Contractors
Civil : Simplex
E&M : Voith
34 Rangit-II Sikkim EPC contract awarded to M/s Coastal in February, 2012. Works are stalled due to
Sikkim Hydro Power Diversion Tunnel: River diversion through diversion non releasing of funds by
Limited 2015-16 tunnel has been achieved. lenders because of
10.02.2010 2021-22 Dam : Excavation 53100cum out of 85000cum completed. Power evacuation and
2x33= 66 MW (Subject to HRT: Excavation 623m out of 4745m completed. land acquisition issues.
Broad Features : re-start of Surge Shaft: Excavation completed. Concreting 37/1667 Works restarted. A
Dam-47m High, works) cum done. meeting with financers
Concrete Gravity Pressure shaft: Excavation of pressure shaft I - 25m out were held on 23.09.2016
HRT-3.9m dia &4.745 of 128m and pressure shaft II - 154m out of 377m for release of funds. The
km length , completed developer was asked to
Surge Shaft- 65.5m Power House: Excavation of surface power house is submit certain document
High & 10m dia. being taken up. for release of funds.
Underground Pressure Works are stalled since
Shaft : 1.7 m dia & 2.5 December, 2017 due to
km length. funds constraints with
P.House-Outdoor developer.
Turbine- Pelton Vertical
Swityard- GIS,
132/11KV
Cost : Original : 496.44
Latest : 496.44
Contractors
Civil & HM : Coastal
E&M : Gammon
35 Rongnichu Sikkim The civil works have been re-awarded to M/s Moshvaraya - Land acquisition.
Madhya Bharat Power Infrastructure Ltd. and E&M works to M/s Litosroj Power, - Poor geology.
Corporation Ltd. 2014-15 Slovania & CG Electric system, Hungary.
01.10.2008 2020-21 Barrage: Excavation completed & 71255 out of 71670 cum
2x48= 96 MW concreting completed.
Cost : Original : 491.32 HRT: Excavation completed and concreting 5050cum out
Latest : 1187.00 of 14115.56cum completed.
Contractors Surge shaft: Excavation completed.
Civil & HM : Sew Pressure Shaft: 97% Civil works LHPS & 48% Civil works
E&M : Voith of VPS completed.
Power House: Excavation completed. 15482cum out of
24644 cum Concreting has been completed.
E&M works: EOT Crane works completed
36 Panan Sikkim Civil works awarded on 22.02.2014. Infrastructural works -Works stalled for want
Himagiri Hydro Energy and geological investigations are in progress. of NoC from NWLB
Pvt. Ltd. 2018-19
07.03.2011 2023-24 Starting of civil construction works was earlier held up for
4x75= 300 MW (Subject to want of the National Board of Wild Life (NBWL) clearance.
Broad Features : re- start of NBWL clearance obtained in December, 2015. However,
Dam-115m from works) there is a case challenging the Eco-Sensitive zone
deepest foundation notification of MoEF & Climate Change in NGT. The case
level is disposed on 21.8.2017. The developer applied for
Desilting Chambers : issuance of clearance from Forest, Environment & Wild
Underground, 2 Life Management Dept., Govt. of Sikkim.
Size (14Lx22Wx2.5H)
HRT- modified horse
shoe, 6 m dia & 9549m
length ,
Surge Shaft- 102 m
High & 15m dia.
Pressure Shaft : 2/4,
3.4/2.4m dia,
707.4 m-Height
P.House-Surface
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
Turbine-Vertical Francis
Cost : Original: 1833.05
Latest :2516.00
Contractors
Civil : Essar

Grand Total : 36 nos. – 12,034.5 MW