Creating Task With Predecessors
Creating Task With Predecessors
As you can see in that previous figure, task #1 (research models online) starts
before task #2 (test drive cars at various dealers). You represent this by typing the
number 1 in line 2's predecessor column. The graphical chart on the right is called
a Gantt chart. The Gantt chart shows how Microsoft Project is automatically
calculating when one task should start and the other should finish.
This task-linking feature alone is what makes Microsoft Project so compelling to
project managers.
The project options dialog with the show project summary task option selected.
From now on, when you create a project, the project summary task will
display (task zero).
Activity: Verify you are ready to create a
project
At this point, you should be looking at an empty project plan. Follow these steps
to make sure Microsoft Project is ready, so you can create a project:
1. The blank project should be open as shown in the following figure (the
project name might be different for you).
Click the Task tab and then click the Gantt chart icon.
Verify you can view the project summary task.
Verify all new tasks are auto scheduled by viewing the status bar at the
bottom-left side of the application window.
Now your project plan should look something like the figure below:
Your project plan after entering durations.
Link all the tasks so Microsoft Project can calculate the start and finish date for your project .
As you type predecessors, Microsoft Project automatically fills in
the successor column. If you want to see the successors column, follow these
steps:
1. Right-click the heading of the start column.
2. A menu appears. Select Insert Column.
3. A list of available fields appears. Type the word Successor and then press
the Enter key on your keyboard.
Your final project should look like the figure below: