Structural Analysis & Design: Structural Report On Dang Project
Structural Analysis & Design: Structural Report On Dang Project
OF
GHORAHI, DANG
July, 2016
Page | 0
Structural report on Dang Project
1. PROJECT DETAILS………………………………………………………. 3 - 4
1.1 Salient features of the project
2. STRUCTURE FEATURES………………………………………………….5-
2.1 Building foundation
2.2 Framing description
5. LOADS………………………………………………………………………… 7 - 10
5.1 Dead loads
5.2 Imposed or live loads
5.3 Earthquake loads
5.4 Load combinations
6.1 Method
6.2 Conditions
7. MEMBER DESIGN………………………………………………………………24 - 68
Page | 1
Structural report on Dang Project
7.4 Foundation design
Page | 2
Structural report on Dang Project
1. PROJECT DETAILS
The building is multipurpose convention hall. The plinth area of the building is 1631.28
sqm. The building is a four storey building on strip and isolated footing foundation.
The columns are 500x500 except the two columns in stage which are 600x600 and
columns those supporting balcony beams are 750x750. The roof above the Audience hall
is metal truss tied with secondary trusses. The roofing is uPVC sheet.
B Soil investigation
Soil investigation report Yes
Allowable bearing capacity 120kN/m2
Liquefaction system Please refer the soil test report
Page | 3
Structural report on Dang Project
Soil type = II
Damping = 0.5%
Seismic response acceleration coefficient = 2.5
2. STRUCTURAL FEATURES
Page | 4
Structural report on Dang Project
Basically most of the footings for the building are isolated footing and are rigidly
connected with foundation beams of size 300x550. The continuous strip footing is
provided along the concrete wall with the width of footing 2.0 m. The depth of
foundation is 2.0m from the original ground level. The thickness of footing is
750mm.Below the mat concrete of the footing, there is a layer of 150mm th. Stone dust
and aggregate with well compaction.
2.2Framing description
All the main beams at floor level are of size 400x550 mm d secondary beams are of sizes
300x450mm. The stage beam at the level +10400 is 500x900. The cantilever beams for
balcony slab at level +7300 are 450x750
location/orientation:
All the internal beams are concentric with the columns i.e. the center line of beams
match with t the to column centre line. The beams at the periphery are flushed with
column outer face. It I s to be noted that the side surface of beams may be matched
with surfaces of column, walls/ partitions by additional concrete as required in
architectural drawings.
2.2.1 Columns
All the columns are square shape in various sizes. The size is varies from 500x500 to
750x750. The buttresses column and column below the audience floor slab is of size
350x350. The secondary columns as vertical tie for clad wall in building four corners are
of size 200x230mm.
2.2.2 Slab
Concrete slab 150mm thick is provided at the floor level. For staircase cover, similar
thickness of concrete slab is provided.
2.2.3 Staircase
There are two concrete e staircases. One is doglegged stair and other is open well
staircase. The dogged staircase is located south west whereas s the open well staircase I
located at north east corner. Besides RC staircase, there is a metal stair case in the
North West corner to serve as emergency stair.
Page | 5
Structural report on Dang Project
4 IS 875 (Part 3): Code of Practice for Design Loads (other than
1987 Earthquake) for Buildings
5 SP 34: 1987 Handbook on Concrete Reinforcement and Detailing
6 IS 13920: 1993 Ductile detailing of reinforced concrete structures
subjected to seismic
7 IS 1893: 2002 Criteria for Earthquake Resistant Design of structures
8 IS 1786: 1985 Specification for high strength deformed steel bars and
wires for concrete
9 SP 16 : 1980 Design Aids for Reinforced Concrete to IS 456 : 1978
10
4.1 Concrete
All concrete structures ( substructures as well as super structure) are designed for
concrete grade M25 to IS 456:2000
Unless noted otherwise concrete is to be normal weight with a typical dry density of
2400 kg/m3
Page | 6
Structural report on Dang Project
5.0 LOADS
W = seismic Wight of the building equal to the total dead load plus appropriate
amounts of specified imposed load
Where :
I = Importance factor depending upon the functional use of the structures , characterized
by hazardous consequences of its failure, post earthquake functional needs
historical value of economic importance as given in table 6 IS 1893 part 2 : 2002
Page | 7
Structural report on Dang Project
R= Response reduction factor depending on the perceived seismic damage performance
of the structure, characterized by ductile or brittle deformations.
Sa/g = Average response acceleration coefficient for rock or soil sites as be given in fig.
below and table 3 IS 1893 (part 20-2002) based on approximate natural periods and
damping g of the structure.
Z = 0.36
Soil type = II
Response
reduction
actor = 5
Ta = 0.075*h 0.75
Page | 8
Structural report on Dang Project
Where :
The design base shear ( Vb) computed in CL.7.5.3 shall be distributed along the
height of the building as per the following expression
Qi = Wi*HI/∑WiHi
Where
N = number of storey in the building is the number of levels at which the masses are
located
NOTE: in calculating the seismic weight of the floors, the full dead load at each storey is
considered while the imposed load is considered as per the following criteria (IS 1893;
2002 table 8)
For design of concrete elements the default load combination ( DCIN 1 To DCON 14)
defined by the computer software for concrete design is followed as pert he Indian
standard IS 456:2002
Where
DL = Dead load
Page | 9
Structural report on Dang Project
Load Specified
Combo Name
No. DL LL EQx EQy
LC1 DCON 1 1 1 0 0
LC2 DCON2 1.5 1.5
LC3 DCON3 1.5 0 1.5 0.0
LC4 DCON4 1.5 0 -1.5 0.0
LC5 DCON5 1.5 0 0 1.5
LC6 DCON6 1.5 0 0 -1.5
LC7 DCON7 0.9 0 0 0
LC8 DCON8 0.9 0 0 0
LC9 DCON9 0.9 0 0 1.5
LC10 DCON10 0.9 0 0 -1.5
LC11 DCON11 1.2 1.2 1.2 0
LC12 DCON12 1.2 1.2 -1.2 0
LC13 DCON13 1. 1.2 0 1.2
2
LC14 DCON14 1.2 1.2 0 -1.2
If
imposed load > 3kN/m2 consider only 50% of imposed load
6.1 Method
All the structural elements of reinforced concrete are designed to Limit State method
Program used SAP200 version 16 is used for thaliana static analysis and design of three
dimensional structural models in computer. In which the spatial distribution of the
mass and stiffness of the structure is adequate for the calculation of the significant
features of structures
6.2 Conditions
Page | 10
Structural report on Dang Project
Since all the columns are rigidly connected to the foundation we can assume that there
would be no any deflection or rotation of these columns at base. Hence the supporting
conditions for column are fixed.
Similarly at the level where the RC slab panels are rigidly connected to the beams we
assume that there should b e equal displacement i.e. the concrete floor acts as rigid floor
diaphragm
The input data for the design of structure generally includes the dead load except the
self weight of structure presented in the model. The imposed lade the lateral loads the
wind load and other special loads (for example loads due to thermal effects)
Page | 11
Structural report on Dang Project
Floor beam
Page | 12
Structural report on Dang Project
Page | 13
Structural report on Dang Project
Dead load are calculated on the basis of unit weight of the specified construction
materials in accordance with IS 875
Live load
The live load for the building has been adopted as given in IS 875 – Part VI section I
loads for assembly buildings
5 Balconies 4
6 Dressing rooms 3
7 Cinema slab 4
Reductions in live load as given in the code has been applied for the design of column
and footings
Page | 14
Structural report on Dang Project
SAP2000 version 16 automatically incorporates all the required calculations for lateral
loads as per the IS 1893:2002 based on the input data we provide. The required
parameter for lateral loads calculations has already mentioned in 6.3
User provides seismic zone coefficient and desired seismic load command
Programme calculates Vb from the above equations W is obtained from the weight
data provided by the user.
The total lateral seismic load ( base shear ) is then distributed by the programme
among different levels of the structure as per the IS 1893 (part I) :2002 procedures
Page | 15
Structural report on Dang Project
displacement, bending moment shear stress etc.) some of the output information as
obtained from SAP12000 after analyzing the structure is shown below.
Page | 16
Structural report on Dang Project
Page | 17
Structural report on Dang Project
Page | 18
Structural report on Dang Project
Page | 19
Structural report on Dang Project
Support reaction
Page | 20
S.N. Story Load Gri FZ FZ (Un-
1 BASE DCON A1 (Factored)
1845.82 Factored)
1,230.55
2 2
BASEStructural
DCON report
B1 on Dang Project
3091.64 2,061.09
3 BASE DCON2 C1 2806.10 1,870.73
4 BASE DCON D1 2456.34 1,637.56
2
5 BASE DCON E1 2373.28 1,582.19
2
6 BASE DCON F1 578.35
2
385.57
Page | 22
Structural report on Dang Project
Deflection of the building:
Ground
floor lvl
+0.00
The permissible storey drift as per the code IS 1893-2002 is 0.004 times the storey
height in the elastic range. In our case the maximum drift is 0.0021 <<<< 14.8
The behavior of a two way slab is very complex and being highly indeterminate. Its
analysis is made using approximate theory which yields a satisfactory result for design
purposes. Detail design of the slab is done for each slab panel and result has been
tabulated for sake f convince.
Page | 23
Structural report on Dang Project
BM x or y = ax/y *W*Lx 2
Where
ax & ay are coefficient given in table 26
Moment calculation
DL+LL = 9.75kN/m2
IS 456:2000
Annex D The factored load =1.5*9.75 = 14.63kN/m2
clause D
1.1 Mx (edge) = ax ( edge) *W* Lx2
Page | 24
Structural report on Dang Project
= 0.037*14.63*3.752
= 7.61 kNm
= √7.61*106/0.138*25*1000
BM = 0.87*fy*Ast*( d-fy*Ast/fck*b)
= 48019.65Ast -5.99Ast 2
Page | 25
Structural report on Dang Project
= 48019.65Ast -5.99Ast 2
Ast = 121.60mm2
Provided 10mm dia. Bars @ 150c/c
= 48019.65Ast -5.99Ast 2
= 48019.65Ast -5.99Ast 2
Ast = 121.60mm2
Provided 10mm dia. Bars @ 150c/c
Therefore it is OK
Page | 26
Structural report on Dang Project
Page | 27
Structural report on Dang Project
Effective depth of beam should lies within the range such that: L / 15 deff < L / 12
= 350mm 230mm
Page | 28
Structural report on Dang Project
Width ‘b’ / Depth ‘D’ =1/2
DESIGN OF BEAM
Design value:
1 MU ( - ve) = 177.84 KN-m
VU = 104.49 KN
Clear cover (C) = 25 mm
Assumed dia. of bar () = 20mm
Now, the effective depth deff = 550 – 25 – 20/2 =
515 mm
Ultimate moment of resistance
MU,lim = 0.36 fck b xm ( d – 0.42 xm)
= 0.36254000.48515(515 –
0.420.48515)
Page | 29
Structural report on Dang Project
A st ×100
b×D = (1902) X 100)/400 x 515 = 0.92%
4% Hence OK.
Check for shear reinforcement
Maximum shear occurs at the face of the support.
VU = 104.49 KN
VU
Nominal shear stress, v = b×d = (104.49 x 1000)/
400X515 = 0.51 N/mm2
A st ×100
% of tension steel = b×d = 0.92 %
From IS: 456-2000, Table - 19
IS: 456- Shear strength for M25 concrete, c = 0.63 N/mm2
2000, > v
Clause Hence nominal shear reinforcement is enough
26.5.1.5 Sv 515 mm
Page | 30
Structural report on Dang Project
Design value:
MU ( - ve) = 791.00 KN-m
VU = 286.00 KN
Clear cover (C) = 25 mm
Assumed dia. of bar () = 20mm
Now, the effective depth deff = 900 – 25 – 25/2 =
862.50mm
Breadth provided b = 500mm
Ultimate moment of resistance
MU,lim = 0.36 fck b xm ( d – 0.42 xm)
= 0.36254000.48862.50(862.50
– 0.420.48862.50)
= 1282.90 KN-m > MU
1
Therefore, the section can be designed as single reinforced
section.
Calculation of reinforcement
Page | 31
Structural report on Dang Project
A st ×100
b×D = (3483) X 100)/500 x862.50 = 0.81%
4% Hence OK.
Check for shear reinforcement
Maximum shear occurs at the face of the support.
VU = 286.00kn
VU
Nominal shear stress, v = b×d = (286.00x 1000)/
500X862.50 = 0.664 N/mm2
IS: 456- A st ×100
2000, Table b×d
% of tension steel = = 0.81 %
-19
From IS: 456-2000, Table - 19
Shear strength for M25 concrete, c = 0.61 N/mm2
< v
IS: 456- As per
2000, c, max = 2.8 N/mm2
Clause c, max v < c
26.5.1.5 Hence shear reinforcement must be designed for shear value
(v - c) b d
Sv = 0.87*4*62*415*862.5/(0.81-0.61)*500*862.50 = 895mm
4 As per IS: 456-2000, Clause 26.5.1.5
Sv 862.50mm
<0.75 d = 0.75 862.50 = 646.88 mm
100 mm
Check for ductility
Maximum spacing of vertical stirrup at the support
SV, max = 0.25 d = 0.25 862.50
= 215.62 mm C/C
Therefore, provide 4- legged 10mm vertical stirrup @ 125
mm C/C throughout
Page | 32
Structural report on Dang Project
Pt = 1.60%
Pt/fck = 1.60/25 = 0.064
Uni-axial moment capacity of the section about the X-X axis &
y-y axis
Pu/fck*b*d = 366000/25*750*750
= 0.026
Mu/fck*b*d2 = 0.115
Mux1 = 0.115*25*7503
Calculation of Pz
Page | 33
Structural report on Dang Project
= 0.45*25*553500 +0.75*415*9000
= 9028.13kN
Calculation of Pu/Puz
Pu/Puz = 366000/9028130
= 0.0405
an = 2/3 { 1+2.5*P/Pz}
= 0.67*(1+2.5*0.0405)
= 0.74
Criteria to be satisfied
= 0.47<1
Page | 34
Structural report on Dang Project
Shear stress = d* tc
Where
d = 1+(3*Pu/Ag*fck)
Pu = axial compression in N
Ag = gross cross section of concrete
fck = characteristic compressive strengthof concrete
d = 1+(3*Pu/Ag*fck)
IS 456:2000
clause = 1 + ( 3* 366000/750*750 *25)
40.2.2 = 1.07
Column is designed in biaxial bending. The value of moment and axial force is taken
from the model analysis.
Page | 35
Structural report on Dang Project
Factored moment acting parallel to the larger dimension Mux = 423.45kNm
Pt = 3.57%
Pt/fck = 3.5725 = 0.143
Uni-axial moment capacity of the section about the X-X axis &
y-y axis
Pu/fck*b*d = 3018.73*1000/25*600*600
= 0.335
Mu/fck*b*d2 = 0.19
Mux1 = 0.19*25*6003
Calculation of Pz
= 0.45*25*347148 +0.75*415*12852
= 7905.60kN
Calculation of Pu/Puz
Pu/Puz = 3018.73/7905.60
= 0.38
Page | 36
Structural report on Dang Project
an = 2/3 { 1+2.5*P/Pz}
= 0.67*(1+2.5*0.38)
= 1.31
Criteria to be satisfied
= 0.389<1
Shear stress = d* tc
Where
d = 1+(3*Pu/Ag*fck)
Pu = axial compression in N
Ag = gross cross section of concrete
fck = characteristic compressive strengthof concrete
d = 1+(3*Pu/Ag*fck)
IS 456:2000
Page | 37
Structural report on Dang Project
Page | 38
Structural report on Dang Project
Page | 39
Structural report on Dang Project
I6
Page | 40
Structural report on Dang Project
IS 456:2000
table 19 = 2577.98 ( 4.20-0.75)/2*2577.98 + 700*4.22
= 2577.98* 3.45/17503.96
= 0.508m
BM = 146.14*4.2 *{(4.2-0.75)0.5}2
= 146.14*4.2*1.7252
= 1826.40 kn-m
= 397mm
Page | 41
Structural report on Dang Project
Page | 42
Structural report on Dang Project
= 1936.86* 3.30/13981.72
= 0.457m
Page | 43
Structural report on Dang Project
BM = 134.13*3.8 *{(3.8-0.50)0.5}2
= 146.14*4.2*1.7252
= 1387.64 kN-m
= 326mm
Page | 44
Structural report on Dang Project
The wall is reinforced with vertical bars of 12mm dia @ 140c/c in both faces. The
horizontal reinforcement is 10mm dia. @ 175c/c.
Page | 45
Structural report on Dang Project
Stair width = 3300
Tread =300
Riser = 155
Page | 46
Structural report on Dang Project
= 1.5(25*0.25*1.126 +1.94+1.2+3.0)
= 19.77 kN/m2
Ra = 64.60kN Rb =71.26kN
X = 64.60/23.51 = 2.75m
The maximum BM = 64.60*2.75 -23.51*1.611*1.94 –
29.655*1.139*1.139*0.5
= 177.65 – 73.48 -19.24
= 84.93 kN-m
Page | 47
Structural report on Dang Project
= 128.11mm
The overall depth D = 128.11+20+8 = 156mm
Provide overall depth 185mm
Calculation of reinforcement
dmin. =l/26*mf
= 5057/26* mf
Page | 48
Structural report on Dang Project
152N/mm2
Design of staircase
Tread =300
Riser = 150
Page | 49
Structural report on Dang Project
= 1.5(25*0.18*1.12 +1.875+1.2+5.0)
Page | 50
Structural report on Dang Project
= 19.67 kN/m2
Ra = 111.61kN Rb =104.79kN
X = 111.61/38.52 = 2.90m
The maximum BM = 111.61*2.90 -38.52*0.553*2.62 –
47.214*2.10*1.603 – 38.52*0.247*0.247*0.5
= 323.67 – 55.81 -158.94-1.17
= 108.75 kN-m
= 128.13mm
The overall depth D = 128.13+20+8 = 156mm
Provide overall depth 200mm
Calculation of reinforcement
Page | 51
Structural report on Dang Project
dmin. =l/26*mf
= 5083/26* mf
Steel truss
Page | 52
Structural report on Dang Project
The analysis of roof truss consist of determination of loads and reactions as well as
determination of the internal forces in the member of roof trusses. The analysis and
design of steel truss is carried out by SAP 2000 version 16. The spacing between the
truss is 3.125m & 2.5m c/c the length of the truss is 22.50m. the ridge height of the truss
is 2.80m. The elevation of the truss is trapezoidal shape . The truss end height in either
side is 750mm. The main truss is connected by secondary trusses of different height in
lateral direction. The secondary trusses are parallel trusses made of hollow circular
pipes.
Dead load
The dead load on roof trusses include self weight of trusses, roof coverings, purlins,
false ceiling, wind bracing etc. Usually the dead load on the roof truss is expressed as
the load per unit area in kN/m2
= 99.914 kN
Live load
Page | 53
Structural report on Dang Project
= 94.218kN
Wind load
K3 = topography factor = 1 for slope ø <30 and 1 to 1.36 for upward slope for ø > 3 0
K1 = 1.08
K3 = 1.0
= 47.207 m/sec
= 1337.1 N/m2
Page | 54
Structural report on Dang Project
Lee ward Cpe = -0.84 = - 1378.42 = 848.26
= 193.840 kN
Page | 55
Structural report on Dang Project
7.8.2 Design of roof purlins
Wind load
Load combination
IS 800-2007
Considering the purlin to be continuous the design
maximum moments are
Page | 56
Structural report on Dang Project
W = W*L/1668
= 0.509*3125/1668 = 0.95cm3 < provided
Minimum dimension fro grade St 210 as pert heIS
IS 800:2007 800:2007
L/70 = 3125/70 = 44.64mm < provided
Checking deflection
L = 3125mm
E = 2.1*10 5 N/mm4
I = 67.63 cm4
W = Dead load + 0.5 live load = 509.93 + 0.5*753.71 =
886.78N/m
= 0.013*2.70*1010/142.02*109
IS 800-2007
table 2 clause = 2.47mm < 20.84mm
3.7.2 & 3.7.4
The provided roof purlin 75x75x2.8 SHS is adequate ,
hence safe in deflection
The limiting width to thickness ratio
D/t < 88 ε2
88 ε2 = 88 *( √250/210)2 = 88*1.19 = 104.72
Page | 57
Structural report on Dang Project
Page | 58
Structural report on Dang Project
Compression = - 276.69kN
Tension = 108.74kN
Page | 59
Structural report on Dang Project
T d,g = Ag ( fy/gmo)
= 88*1.19 = 104.72
D/t = 165.10/4.8 = 34.39mm < 104.72
Compression = - 121.39kN
Tension = 53.37kN
Page | 60
Structural report on Dang Project
Length of the member L = 1.125m
T d,g = Ag ( fy/gmo)
Page | 61
Structural report on Dang Project
= 88*1.19 = 104.72
D/t = 165.10/4.8 = 34.39mm < 104.72
Page | 62
Structural report on Dang Project
T d,g = Ag ( fy/gmo)
Page | 63
Structural report on Dang Project
= 88*1.19 = 104.72
D/t = 114.30/4.5 = 25.4mm < 104.72
Page | 64
Structural report on Dang Project
= 184.8-(184.8-183.4)/20*1.10
= 184.72 N/mm2
= 88*1.19 = 104.72
D/t = 114.30/4.5 = 25.4mm < 104.72
The downward factored reaction due to wind load = 1.5( 99.914 +94.218) = 291.20 kN
Page | 65
Structural report on Dang Project
Consider the bearing stress of MS plate is 4Mpa
Tp = √18900*6/189
= 24.49mm
An = tu*gmo/0.9fu
149.43*103*1.1/0.9*310 = 589.15mm2
L = 149.43*103*0.6/ 4*3.14*16
356.92mm
Page | 66
Structural report on Dang Project
Lets provide the length of anchor bolt 450mm in U shaped
Page | 67