Operational Safety Competencies For Aerodrome Operators
Operational Safety Competencies For Aerodrome Operators
Explanatory Note
Introduction
Purpose
Terminology
Application
i
10. Airfield Work in Progress
ii
Explanatory Note to this version
This advisory circular is a living document and will be revised at intervals to take
account of changes in regulations, feedback from industry, and recognised best
practices to facilitate the license holder to demonstrate compliance in terms of
manpower deployed for aerodrome operation.
iii
Introduction
Purpose
The aim of this document is to enable licensees to assess the level of operational
safety management competence existing within their respective airport organisations,
including any areas that are contracted out, and to ensure that they have the necessary
expertise at the appropriate level to formulate and implement systems to adequately
manage safety.
Therefore, it addresses tasks at the senior to supervisory level in two Chapters,
chapter 1 aimed at the senior management level and Chapter 2 at the line to supervisory
level. It does not cover tasks at the “operative” level. However, licensees are encouraged
to adapt and apply the material for this purpose; it is intended as a management tool to be
used by licensees and their airport managements for internal use, not only as a
mechanism to satisfy the safety regulator. It should be noted that most of the topic areas
covered by this document are subject to specific safety regulation by the DGCA, but
licensees may wish to extend the principle to other areas for their own managerial
purposes.
As recognized above, some tasks within the competences and some topic areas
may be ‘contracted out’ by the aerodrome licensee. Whilst day-to-day operational
management is the responsibility of such a contractor, the aerodrome licensee continues
to have overall accountability and responsibility for the safe integration of contracted
activities with the rest of the aerodrome operation. A licensee, therefore, needs to ensure
that competence and safety management requirements are included in contract
specifications and documents, including those relating to:
2
The maintenance of determined and declared staff/operative numbers;
Safety performance; and
Appropriate supervision, monitoring and follow-up.
This material:
1. Takes account of the need to accommodate a range of licensed aerodromes and
their varied scope of operations. Not all of the tasks listed will be appropriate or
necessary for all aerodromes, an issue of particular interest to the smaller
aerodromes. Not all of the areas of competence have to be vested in one person,
an issue of particular interest to the larger aerodromes.
2. Will assist the aerodrome licensee to:
(a) Identify the post/s and person/s that have accountabilities and/or
responsibility for a specific task, including project managers, shift
supervisors and those monitoring the safety performance of contracted-out
services;
(b) Be satisfied that persons within the management structure possess the
relevant operational safety competence, or identify gaps and, therefore,
training needs, that may exist in specific areas of competence;
(c) Develop job specifications, training programmes, recruitment and
succession planning; and
(d) Provide, for aerodrome licensing purposes, the safety assurance sought
by the DGCA on operational safety competence of the licensee’s
organisation.
Terminology
For ease of interpretation, several key terms used throughout this document are
defined as follows:
Background Knowledge – The collective body of information and skill sets, gained
through experience and training, that people need to have, if they are to perform their
roles competently. This includes memorised relevant facts, regulations, theories and
principles, and knowing where to find such data when it is not necessary to commit them
to memory.
Ensure – The dictionary meaning implies 100% guarantee, and this is the
objective. It may be argued that an interpretation may at times be like safety risks
being reduced to As Low As Reasonably Practicable (ALARP). However, that
cannot and must not be an excuse for not making all reasonable efforts to “ensure”
to the dictionary definition where possible.
3
Infrastructure project - A building or structure (defined as arrangement of parts).
This could be a new or upgrade of facilities, a replacement or refurbishment of an
existing facility or a major maintenance project that will cause operational
disruption over a significant period of time. Such projects will have different
significance in different contexts. For example, in terms of obstacle limitation
surfaces height will be the significant element, whereas for wildlife management
the significant element will be attractiveness to wildlife.
Named Person – A person, identified by name, who currently holds a specified post.
This applies equally to staff for functions that are outsourced; functions for which
the licensee remains accountable, in terms of aerodrome licence obligations.
Risk, specifically Safety Risk - A measure of the seriousness of, or “put a number”
on, the consequences of hazards, expressed in terms of predicted probability and
severity, of the consequences of a hazard ((ICAO 9859, edition 2).
Specified Post – A post within an aerodrome management structure, which has been
identified as having responsibility for the management of a specific safety related task.
Where more than 1 post has responsibility for the task then all the posts and post-
holders need to be identified and reviewed against the background knowledge.
Application
4
The tasks listed in the areas of competence, appropriate to a particular
aerodrome, are those that should be vested in a particular “specified post or posts” and
“named person or persons” occupying that post/posts, and annotated in the document
against each relevant task.
Furthermore, it is expected that the ‘named person or persons’ for each task will
have knowledge and understanding of the aerodrome management’s policies and
systems, appropriate to the task expected of them.
This circular is issued with the aim to guide aerodrome operators to appoint
persons for key positions with adequate knowledge and experience in the relevant field.
Although not being applied now, depending on the experience gained in future with
application of this circular, prior approval of licensing authority may be made mandatory
before appointment of such persons.
The DGCA, in partnership with industry, will review and amend this material in the
light of usage and experience.
Sd/-
(J.S. Rawat)
Joint Director General
for Director General of Civil Aviation
New Delhi
8th March 2011
5
Chapter 1 Areas of Competence at senior level above line management,
including corporate level when there is an element of
accountability in provision and service that may have an
impact on securing safety of aircraft using the airport
Specified N a m e d
Tasks
Post(s) Person(s)
Ensure a thorough understanding throughout the
organisation of:
The Licensees’ accountability and responsibilities in
securing and managing safety at the airport.
The DGCA’s statutory duties in licensing and safety
oversight of Indian aerodromes.
Ensure that aerodrome licensing and license renewal
requirements are met, and that the aerodrome operates in
accordance with licence conditions and statutory
requirements, including those related to non-compliances,
exemptions and airport infrastructure projects.
Ensure an understanding by the aerodrome management
of the legal requirement for, and status of the Aerodrome
Manual.
Ensure that the necessary steps are taken for the
aerodrome and its airspace to be safe for aircraft during
operational hours. This includes:
Using appropriate management tools, the
determination and provision of the necessary level of
managerial and operative staff, i.e. staff numbers, as well
as the combination of qualifications, experience and skill-
sets of those staff, for both initial licensing and continuing
operations.
Ensuring that the aircraft accepted by the airport are
appropriate to the airport reference codes, movement
area geometry and infrastructure.
Ensuring exemptions to licensing requirements are
kept under review as part of planned and significant
changes to aerodrome infrastructure, traffic levels or
aircraft types.
The Chief executive, all senior management and line management staff must
have training on the legal framework for aerodrome licensing, and collective
background knowledge must include the following, at the appropriate level:
[Chapter-1] Page 1
CAR Series B, Part IV Exemption Procedure for Noncompliance at
Aerodromes
CAR Series F, Part I Requirement for Issue of an Aerodrome License
CAR Series X, Part II Aeronautical Information Services
CAR Series X, Part III Aeronautical Charts
Wildlife Control at Aerodromes
Dangerous Goods Regulations (as they apply to aerodromes)
Notice to Airmen (NOTAM)
The ICAO Convention, Annexes 4, 11 (as it applies to aerodrome ground
operations), 14, 15, 16, 17 and 18 to the Convention.
ICAO Annex 9 (only for international airport)
ICAO Manuals - 9774 Certification of Aerodromes, and 9859 Safety
Management Manual;
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-1] Page 2
2. M a n a g e m e n t C o m p e t e n c e - Senior Operations Management
This is the competence for the overall management of the operational function.
This includes the meeting of licence obligations, and thus extends beyond the purely
operational area; for example ensuring adequate financial budget allowance for
necessary recruitment, training and equipment procurement. Therefore, these tasks
usually require authority across the whole of the line level, in which case the post
should have that necessary and more senior authority within the organisational
structure of the airport.
Tasks Specified N a m e d
Post(s) Person(s)
To effectively and efficiently lead, direct and manage the
management function, understanding, accepting and being
appropriately involved in areas of personal accountability.
To set and approve the organisation’s operational and safety
policies/objectives, ensuring that associated accountabilities
and responsibilities are detailed and recorded, and are in line
with the declared safety policies and objectives.
To ensure that:
Non-compliances for which there are temporary
exemptions granted by the DGCA are regularly
reviewed and the reasons for seeking such
exemptions are removed/corrected in order to meet
the requirements of the action plan agreed with the
DGCA, and to avoid licensing action being taken if the
action plan requirements are not met.
Non-compliances for which there are permanent
exemptions granted by the DGCA are regularly
reviewed to ensure that mitigating measures are still
valid, and that every opportunity is taken to
remove/correct the non-compliance.
Ensure that:
Once the necessary number, qualifications,
experience and skill-set requirements of operational
and supporting staff establishment have been
determined, this is not allowed to decline unless there
is an understandable and valid case made and signed
off by senior management, e.g. in the event of
curtailment of services or reductions in operational
areas (in which case the DGCA are to be advised).
Any holder of a safety-critical post at line or specialist
level, e.g. that responsible for day-to-day operations,
or the Safety Manager is not replaced without the new
appointee being given the appropriate familiarisation
training, and the DGCA being consulted prior to the
appointee taking up the post. If the provision of
familiarisation training is not practicable beforehand,
then as soon as possible, and only after the
“Accountable Executive” being satisfied that safety
policies or objectives will not be compromised, usually
[Chapter-1] Page 3
by the provision of a safety, assurance and being
demonstrated to the DGCA.
Should there be retention difficulties and a service has
to be out-sourced that:
- At least the same mix of numbers,
qualifications, experience, and skill-set
requirements are provided prior to any change
and that any new staff/operatives are not
allowed to operate until they have successfully
undertaken the necessary familiarisation/
induction training and have demonstrated
competence to the Licensee’s satisfaction.
- Through adequate contract specifications that
for outsourced safety-critical functions:
o The licensee retains control of the
operation of the facility, as required for
licensing requirements and conditions to
be met.
o The safety-performance of that function
and the interfaces with other functional
areas will not be compromised by being
out-sourced.
**To ensure that the organisation, using appropriate
management systems and functions, such as task analysis,
recruitment, training, has and maintains organisational
competence necessary to satisfy:
the organisations safety policies and objectives;
its stakeholders, including users; and
national regulations and requirements, to the satisfaction of
the DGCA.
[Chapter-1] Page 4
For outsourcing, the necessary knowledge in relation to ensuring
appropriate contract specification for safety assurance requirements,
including:
o SMS obligations;
o safety performance and monitoring requirements;
o timely corrective action planning and implementation where
indicated by safety management processes; and
o Timely and adequate communication of safety critical information,
particularly reports/evidence of safety performance being
compromised.
DGCA Rules
[Chapter-1] Page 5
3. Aerodrome Safety Management System
Tasks Specified N a m e d
Post(s) Person(s)
Ensure the promulgation to appropriate parties, and
declaration in appropriate documents the post and name of the
Accountable Executive (who ICAO and the DGCA expect to be
at the most senior, i.e. Airport Director level).
**Initiate the planning for the development of a safety
management system (SMS) for the control of safety risks.
Ensure that there is direction and guidance for the
development of the SMS, and that the organisation
provides the necessary financial, human and training
resource, as part of its commitment and support.
Ensure that the necessary processes are being planned as
part of the SMS, including change management and safety
risk assessment, as well as those aimed at developing a just
and positive safety culture, particularly in the area of desired
behaviour standards – see competences 3a and 3b.
Ensure the establishment and maintenance of the internal
Safety Groups established by the SMS.
Establish, maintain and monitor the output of an airport
Safety Committee, representing the licensee, users and
contractors.
[Chapter-1] Page 6
- safety risk management
- change management
- data collection, storage setting and measuring safety
performance metrics
- inspection and auditing accident/incident reporting and
investigation
- communicating aerodrome safety rules, regulations and
information
- safety performance monitoring, measurement and follow-up, using
safety auditing, studies, reviews and surveys
- co-ordination and control of airside activities
Aerodrome Emergency Plan
Human factors principles
Knowledge of aerodrome operations, including a basic understanding of
aircraft operations, sufficient to be able to identify and understand
potential hazards
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-1] Page 7
3a. Safety Risk Management as an element of an Aerodrome Safety
Management System
Tasks Specified N a m e d
Post(s) Person(s)
To ensure that the process for safety risk management is
applied throughout the organisation, including:
Identifying and analysing hazards, including
those from unplanned change and day-to-day
operations, as well as planned change;
Risk assessment, applying the senior
management approved thresholds for risk
acceptance and tolerability;
Selecting appropriate risk control/mitigation
measures, including the elimination of
intolerable risks;
Reviewing the continued validity of the control
measures against safety performance metrics;
and
Reviewing the hazard log for continued
relevance of specific hazards.
[Chapter-1] Page 8
- change management
- data collection, storage setting and measuring safety
performance metrics
- inspection and auditing accident/incident reporting and
investigation
- communicating aerodrome safety rules, regulations and
information
- safety performance monitoring, measurement and follow-up, using
safety auditing, studies, reviews and surveys
- co-ordination and control of airside activities
- Aerodrome Emergency Plan
- Knowledge of aerodrome operations, including a basic
understanding of aircraft operations, sufficient to be able to
appreciate and understand potential hazards
- Any other CAR/ Directions issued in the subject matter from time to
time
[Chapter-1] Page 9
3b. Change Management as an element of an A e r o d r o m e Safety
Management System
[Chapter-1] Page 10
- data collection, storage setting and measuring safety
performance metrics
- inspection and auditing accident/incident reporting and
investigation
- communicating aerodrome safety rules, regulations and
information
- safety performance monitoring, measurement and follow-
up, using safety auditing, studies, reviews and surveys
- co-ordination and control of airside activities
[Chapter-1] Page 11
Chapter 2 Areas of competence at line management, project managers,
and middle/supervisory levels, where appropriate, including
shift managers and those responsible for outsourcing and
supervising contractors for safety-critical services
The line and other appropriate level management staff must have training on
the legal framework for aerodrome licensing, and background knowledge must include
the following at the appropriate level:
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 2
5. M a n a g e m e n t C o m p e t e n c e – L i n e l e v e l Management
This is the competence for the line management of the operational function.
This includes the meeting of licence obligations, and extends beyond the purely
operational area; for example ensuring liaison and coordination between line
functions.
[Chapter-2] Page 3
Background knowledge must include:
[Chapter-2] Page 4
6. Aerodrome Safety Management System, including Safety Risk
Assessment and Change Management
Tasks Specified Named
Post(s) Person(s)
**Plan the development of a safety
management system (SMS) for the control of
safety risks, formulation of an Implementation
Plan (IP), phased as necessary, and the
production and review of an SMS Manual. At
the appropriate time in planning ensure that
the resources for the following facilities and
processes are known to senior management
in a timely way:
Hazard identification and safety
risk management, including:
- hazards from unplanned
change and day-to-day
operations, as well as from
planned change; and
- the setting of thresholds
for risk acceptability and
tolerability, and the
application of these within
the relevant processes.
Change management, including
reviewing its operation; and the
preparation of safety assurances
for senior management approval
and sign off, before offering them
to the DGCA.
An occurrence reporting system.
The establishment of a database,
data analysis, exchange and
usage for data driven safety
assurance.
Safety performance monitoring
and measurement.
The establishment of safety
promotion programmes and
procedures, including those for:
the determination of the SMS
training need and an SMS
training programme; and
the identification and
promulgation of safety
information such as that to
explain safety
actions/interventions to staff, as
well as external communications
of safety critical material, such
[Chapter-2] Page 5
as a “Hot Spot” chart and details
of exemptions for the AIP.
In implementing the SMS, and its processes,
direct, guide and report on its progress,
applying all of the SMS processes as
required, and monitoring their effectiveness in
practice.
Document the SMS outputs
Coordinate the Aerodrome Emergency Plan
Serve the internal Safety Groups established by
the SMS
Oversee the workings and monitor the output of
the airport Safety Committee, representing the
licensee, users and contractors
Implement the process for the training and
development of internal and external staff
involved in SMS, including safety risk
management
The Senior Managers, the Safety Manager, Safety Group members and staff
responsible for safety management should be selected with particular reference to
training, experience and knowledge on Safety Management Systems. Background
knowledge must include that from the following, appropriate to the individual tasks:
[Chapter-2] Page 6
- safety performance monitoring, measurement and follow-up, using
safety auditing, studies, reviews and surveys
- co-ordination and control of airside activities
Aerodrome Emergency Plan
Project management principles
Human factors principles
Knowledge of aerodrome operations, including a basic understanding of
aircraft operations, sufficient to be able to identify and understand
potential hazards
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 7
7. Management and Operation of the Airport Operations Control Centre
(AOCC)
Tasks Specified N a m e d
Post(s) Person(s)
Plan for, design, provide, test and verify all the necessary
back-ups and contingency planning for all possible failure
modes of the AOCC systems, including power sources,
taking account of the need for rapid switch over in aircraft
safety-critical areas.
Formulate and implement “failure mode” exercises of the
AOCC’s safety-critical functionality on a regular basis.
Ensure that:
The technical equipment and operating
systems are correctly specified against the
operational objectives, and that they have
been tested and verified as “fit for purpose”.
AOCC staff members are trained, initially
and on a recurrent basis, in the areas they
interface with, as well as their own functional
area. This to include “failure mode”
operations in the safety-critical areas, and
how to report, record and follow-up on
observed safety-related occurrences.
AOCC staff are aware of:
- The need for timely action in safety-
critical areas.
- The authorities and powers that can
be applied, and where to go if further
authority is required.
The AOCC operating rules, aeronautical
data used by aircraft and reference criteria,
including that loaded into the AOCC data
bank are valid and verified.
That the AOCC SOPs related to aircraft
safety are in-line with company policy on
occurrence and non-adherence reporting,
expected behaviour norms and safety
culture development, as detailed in the SMS
Manual and other documentation. Examples
of such SOPs are those for:
- Monitoring airside operations, to
include watching for failures or
outages of safety-critical airside
systems, and potentially hazardous
situations, for example a fuel
bowser’s exit route being blocked
while refueling on an aircraft stand.
- The timely reporting, recording and
follow-up of safety-related
occurrences and observations of non-
compliance.
[Chapter-2] Page 8
Aerodrome operator’s staff responsible for planning, design, operation,
monitoring and maintenance of the AOCC must be trained on all AOCC functional and
interface areas that relate to aircraft safety. Background knowledge must include that
from the following, again appropriate to the individual tasks:
CAR Series B, Part I Aerodrome Design and Operations, and Part III
Heliports
CAR Series B, Part IV Exemption Procedure for Noncompliance at
Aerodromes
CAR Series F, Part I Requirement for Issue of an Aerodrome License
CAR Series X, Part II Aeronautical Information Services
CAR Series X, Part III Aeronautical Charts
Wildlife Control at Aerodromes
Dangerous Goods Regulations (as they apply to aerodromes)
Aeronautical Information Service (AIS), NOTAMs, Aeronautical
Information Regulation and Control (AIRAC) cycles
Aeronautical Information Publication India
Maps and charts
Notice to Airmen (NOTAM)
Surface Movement Guidance Control System (SMGCS)
Company SMS, including processes/procedures for:
- occurrence reporting, investigation and follow-up
- safety risk management
- change management
- data collection, storage setting and measuring safety
performance metrics
- inspection and auditing accident/incident reporting and
investigation
- communicating aerodrome safety rules, regulations and
information
- safety performance monitoring, measurement and follow-up, using
safety auditing, studies, reviews and surveys
- LVPs
- Works-in Progress (WIP)
- co-ordination and control of airside activities
- disabled aircraft recovery
Wildlife Management
Airside Vehicle Operations
Apron management and operations, including refueling practices
Aerodrome Emergency Plan
Human factors principles
Knowledge of aerodrome operations, including a basic understanding of
aircraft operations, sufficient to be able to identify and understand
potential hazards
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 9
8. Aerodrome Physical Characteristics- Movement Area Status and Condition
Tasks Specified N a m e d
Post(s) Person(s)
Ensure that the paved areas, runway strips, clear and
graded areas and RESAs continue to meet licensing
i thatt aerodrome is clear of obstructions, debris and
Ensure
spoil.
Determine and instigate repair programmes process for
aerodrome pavements and surfaces.
Ensure that the design and layout of the apron and
manoeuvring area remains adequate for the safety of
intended operations, bearing in mind the need to review
when there is a change in the operation.
Ensure that there adequate provision for aerodrome
drainage is maintained, particularly of the runway and
ti
Ensure that appropriate separation distances are
maintained between runways, taxiways and aprons.
Review, calculate and promulgate declared runway
distances for obstacle restricted operations.
Ensure that there is an effective mechanism for
appropriate feed-back from runway and apron safety
teams.
All the above in the context of aircraft operations and runway and apron safety,
including:
[Chapter-2] Page 10
The purpose of SMGCS and provision of the level appropriate to airport
traffic density, visibility condition and aerodrome layout category
The relationship between the reference code (ARC) and aerodrome
physical characteristics
The relevance of runway width and slope, as well as length, and (all
movement area) surface condition and its monitoring and maintenance
The relevance of runway strip and RESA
The function of stopway and clearway
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 11
9. Surface Movement and Guidance System (SMGCS), Visual Aids for
Approaches and Electrical Systems
[Chapter-2] Page 12
10. Aerodrome Works in Progress (W.I.P)
Tasks Specified N a m e d
Post(s) Person(s)
Undertake appropriate safety and resource
assessments, at the level for the scope and complexity
of the work and in accordance with the company SMS
processes, including change control, in order to ensure
Monitor and maintain aerodrome status systems and
Equipment according to laid down procedures.
Promulgate to all appropriate stakeholders, and record
information about the W.I.P, the aerodrome status and
condition.
Inspect and monitor the W.I.P work in progress.
Ensure that adequate systems, procedures and
resources are in place for the planning, co-ordination,
control and oversight of work in progress, taking account
of human factor principles throughout the process.
Ensure that contingency plans are drawn up to manage
breakdowns in operating systems.
Revise declared runway distances and other aerodrome
operational limitations, as appropriate.
Ensure that airside safety briefings are provided for
external contractors and work areas are controlled to
maintain safe operations.
Ensure compliance with the SMS requirements and
SOPs when returning an operational area to service.
The staff responsible for the planning and execution of works that affect the
aerodrome movement area and obstacle limitation surfaces must have training on
aerodrome works in progress. Background knowledge must include that from the
following, again appropriate to the individual tasks:
[Chapter-2] Page 13
Implications of work permits, contractors briefings, NOTAMs, Air Traffic
Information Service (ATIS), operational safety notices, organisational
safety policy for outside works
Inspection, recording, reporting and other documentation systems
National legislation related to standard safety and working practices
LVOs
National Aviation Security Programme
Regulatory and organisational inspection/audit systems
Regulatory and organisational standards and objectives
Standard aircraft operation procedures
Standard engineering practices and procedures, work methods and
temporary repair options
Work access and provision of Rescue and Fire Fighting Service (RFFS)
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 14
11. Aerodrome Zoning/ Safeguarding- Obstacle and Wildlife Habitat Control
Aspects on and Around Aerodromes
The staff responsible for preparing obstacle limitation charts (ICAO Charts),
inspection of obstacle limitation surfaces, initiating surveys, conducting safety risk
assessment and wildlife management must be trained on Aerodrome Zoning/Land-
use/Safeguarding. Background knowledge must include that from the following, again
appropriate to the individual tasks:
[Chapter-2] Page 15
ICAO Document 9859 Safety Management Manual
Safety management systems for on-aerodrome developments, including
principles and methods of risk assessment
Knowledge of survey requirements
Knowledge of aerodrome operations, including a basic understanding of
aircraft operations, sufficient to be able to identify and understand the
effect of obstacles on aircraft take-off performance and landing criteria
(possible operational restrictions).
Topographical, aviation and planning maps and charts
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 16
12. Apron Management and Operations
[Chapter-2] Page 18
13. Airside Vehicle Operations
Tasks Specified N a m e d
Post(s) Person(s)
Establish and monitor systems for the issue of any Airside
Driving and Equipment/Vehicle Operating permit.
Ensure that processes and procedures for the provision and
auditing of driver training, initial and recurrent, and vehicle
maintenance programmes are implemented and maintained
to established standards.
Ensure that airside vehicle accidents and incidents are
recorded, investigated and closed by appropriate action,
and ensure a system is established for the reporting of
vehicle faults, documented according to laid down
procedures.
Ensure that vehicles are operated in accordance with
standard operating procedures and with regard to aircraft,
other Airside users, traffic rules, signs and markings.
Ensure that audits are undertaken to ensure compliance
with procedures and practices which contribute to the
Safety of airside traffic operations.
Ensure that the Aerodrome Safety Committee/ Board
consider and review all the above requirements.
[Chapter-2] Page 19
Rules of the Air relevant to ground movement
Standards for vehicle maintenance and operation
Systems for road signs, markings and lights, and for traffic control,
speed limits and parking, particularly in relation to runway incursion
prevention and apron management
[Chapter-2] Page 20
14. Runway Surface Friction
Specified N a m e d
Tasks Post(s) Person(s)
Ensure that runway surface friction measurement
conforms to organisational, national and ICAO
standards, taking account of prevailing weather
diti that dessential
Ensure t d equipment for runway friction
measurement and reporting is provided.
Make adequate provision for the storage, calibration and
care of runway surface friction measurement and
reporting equipment.
Monitor runway surface friction measurement and
reporting to ensure equipment is used according to
established procedures.
Ensure that staff are trained in the use of runway
surface friction measurement, and analysing and
reporting results
Establish a system for the recording and retrieval of
runway surface friction data.
Ensure that there are procedures for the analysis and
interpretation of data collected by runway surface
friction measurement.
Take account of the effect of work-in-progress on
runway surface friction and ensure that the necessary
procedures and promulgation action is taken.
Staff responsible for carrying out technical inspection of the runway must have training
on Runway Surface Friction Characteristics. Background knowledge must include
that from the following, again appropriate to the individual tasks:
[Chapter-2] Page 21
15. Runway Contamination
[Chapter-2] Page 22
Obtaining information on weather conditions and trends, interpretation of
meteorological data
Procedures relating to night and low visibility operations
Runway surface construction and friction characteristics
Types of surface deposits, significant changes in runway conditions, the
effect of painted surfaces on friction
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 23
16. Wild Life Hazard Control
Tasks Specified N a m e d
Post(s) Person(s)
Establish a wildlife hazard control plan, including habitat
management, and assess relevant areas for wildlife
hazards using all available information sources.
Communicate information about wildlife strike hazards to
all relevant parties.
Initiate and review appropriate wildlife dispersal action
according to local circumstances and aerodrome
characteristics.
Keep appropriate records in relation to wildlife hazard,
strikes and dispersal.
Ensure that:
training and development for internal and
external staff is given in the use of wildlife
hazard control measures; and
sufficient trained and competent staff and
well maintained equipment resource is
always made available.
Ensure that wildlife control process, including that out-
sourced meets the contract specifications and is
effective, in accordance with safety performance metrics.
[Chapter-2] Page 24
17. Aeronautical Information System
[Chapter-2] Page 25
18. Low Visibility and Night Operations
The staff responsible for carrying out Visual Assessment of Lights (VAL) and
Runway Visibility Range (RVR) measurements must be trained on Low Visibility and
Night Operations. Background knowledge must include that from the following, again
appropriate to the individual tasks:
[Chapter-2] Page 26
Weather trends in relation to LVOs
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 27
19. Fire and Rescue Operations
The staff responsible for ensuring availability of all equipment including the requisite
amount of extinguishing agents, to achieve the rated category of the RFFS must be
trained on Fire and Rescue Operations. Background knowledge must include that
from the following, again appropriate to the individual tasks:
[Chapter-2] Page 28
- Equipment testing
[Chapter-2] Page 29
- Handling dangerous cargo
- LVOs
- Medical services
- Medical standards
- Response times
- Staffing levels, rosters etc
[Chapter-2] Page 30
20. Handling of Fuel and Hazardous Materials
Tasks Specified N a m e d
Post(s) Person(s)
Ensure that there is a system to verify that areas and
zones for storage of hazardous materials are adequately
maintained so as to reduce hazards to aircraft, staff and
vehicles.
Ensure that operations involving the receipt and storage
of fuel, and the fuelling of aircraft are monitored, to
ensure that they take place according to regulations and
procedures.
Ensure that:
there is an adequate system for the
inspection of fuel facilities, its transport,
storage and dispensing, including the
sampling, testing and recording of fuel
quality; and
records are kept of all fuelling operations,
including receipt and use of fuel
Deal with hazardous material incidents (i.e. fuel spillage
etc.) and report to the concern agency, if appropriate.
Ensure that adequate fire hazard protection is taken
during handling of hazardous materials.
Ensure that an adequate system exists for the inspection
of facilities used to transport, store and load into the
aircraft the hazardous materials to ensure it is maintained
to appropriate standards.
Ensure that training to internal and external staff is given
in the handling of hazardous materials.
[Chapter-2] Page 31
Methods of dealing with a fuel spillage
Methods of quality control after discharge, settling, testing
Need for clear exit paths for fuel vehicles
Precautions to be taken against fire risk
Procedures for product release for delivery into operating storage or into
aircraft fuelling equipment
Receipt procedure
Re-fuelling procedures, including those to be taken when passengers
remain on board
Storage conditions and testing requirements to keep equipment in good
working order
Storage procedures
Vehicle and hydrant operation
Dangerous goods safety regulations
Dangerous goods handling, storage and aircraft loading requirements
Dangerous goods training requirements
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 32
21. Aerodrome Emergency Plan and Procedures
The staff responsible for establishing the aerodrome emergency plan and
procedures and execution of established procedures must be trained in Aerodrome
Emergency Plan and Procedures. Background knowledge must include that from the
following, again appropriate to the individual tasks:
[Chapter-2] Page 33
22. Airport Security Provisions (*)
The staff responsible for establishing the airport security programme and
monitoring its implementation must be trained in airport security programme and
procedures. Background knowledge must include that from the following, again
appropriate to the individual tasks:
[Chapter-2] Page 34
Any other Directions issued in the subject matter from time to time by
BCAS
(*) This chapter has been included on the request of aerodrome operators with
the aim to provide information based on the general practices in security related
matters to be established at an aerodrome. However, BCAS directives, shall prevail if
differ from these guidelines.
[Chapter-2] Page 35
23. Cargo Operations
The staff responsible for Cargo Operations and its monitoring must be trained
in the specific areas for cargo operations, including the handling of dangerous goods.
Background knowledge must include that from the following, again appropriate to the
individual tasks:
[Chapter-2] Page 36
CAR Series B, Part I Aerodrome Design and Operations
CAR Series F, Part I Requirement for Issue of an Aerodrome License
Aerodrome layout in relation to the location of essential equipment for
LVPs
Vehicle and airside operations in LVPs
Dangerous goods safety regulations
Dangerous goods handling, storage and aircraft loading requirements
Dangerous goods training requirements
National Aviation Security Programme
National Aviation Security Training requirements
National and Airport Security Committee procedures and organisation
Aviation security Directions and security Circulars
Hi-jack procedures, bomb warnings and suspect baggage/parcels, etc
Methods of control of access to restricted zones and other sensitive areas
Regulatory authority requirements for the treatment of aircraft,
passengers and baggage to and from sensitive areas
Requirements for the recruitment and training of security staff
Guarding aircraft
Standards and testing procedures for security equipment
Standards required and other methods of screening passengers and their
baggage
Suspect baggage/risk assessments and procedures
Telephone techniques for handling security and bomb warnings
CCTV surveillance
Any other CAR/ Directions issued in the subject matter from time to time
[Chapter-2] Page 37
Chapter 3 This chapter has been developed to provide guidance to licensees
to plan the organizational structure for operation and maintenance
of airport. The typical organogram for organizational structure of
any aerodrome is included in this chapter.
The structure of the organogram and person engaged for the operation of
aerodrome may vary based on the size of the aerodrome and its operational
requirement but the main essence should remain as shown below to demonstrate the
hierarchy of delegated authority to the key persons for management and operations of
aerodrome.
The Accountable Executive and Safety Managers are considered key persons
from aerodrome licensing point of view and continued operation of the aerodrome. The
details of responsibility and functions for these officials are defined in ICAO Safety
Management Manual (Doc 9859). The licensee may also ensure that these persons are
having adequate knowledge and experience for carrying out functions assigned to
them.
The person named in para 6.1 of CAR Section 4 Series F Part 1 may also be
Chief Executive Officer who is termed as Accountable Executive for the purpose of
licensing. However, person named in-charge for day to day operations as per para 6.2
of CAR Section 4 Series F Part 1 (i.e. COO/Airport Director/controller etc.) is required to
be suitably qualified for the purpose and should have adequate experience in the field
of aerodrome operations and management. He is required to be conversant with his
role in handling aerodrome emergency procedures and is competent to handle such
situations before taking over the charge. It will also be his responsibility to ensure that
any changes in the named officials reporting to him directly are conversant in their job
profile indicated in the Aerodrome Manual. The Safety Manager is required to report to
the Accountable Executive.
All aerodrome operators shall prepare their organograms, include the same in
Part 5 of Aerodrome Manual. Any changes in the named persons holding positions in
the organograms are required to be incorporated in the Aerodrome Manual as per the
prevailing procedures.
[Chapter-3] Page 1
TYPICAL LAYOUT OF AN AIRPORT MANAGEMENT
ORGANOGRAM
Accountable Executive
(Chief Executive Officer/
Chief Operating Officer/
Airport Director etc.)
Safety Manager
-x-x-
[Chapter-3] Page 2