8.16 11,3 Laying of 25mm th. Mosaic flooring, 20mm th. C/ P in 1:2 and on th top of that 6mm th. White cement
and marble ( in 1:1) coat, complete with polishing. For 1.00 sqm Sqm 3506.73
8.17 11, 5 Paving 25mm th. Oiled terrazo tiles on 1:2 Surkhi mortar complete
with 1:1 cement sand pointing. For 1.0 Sqm Sqm 2179.99
8.18 11, 7 Laying of procelain glaxed tiles on 1:4 cement sand
mortar. For 1.0 sqm sqm 2753.98
8.19 11, 6 Laying of 25mm th. 450*450mm Marble on 20mmth. 1:4 surkhi mortar,
complete with polishing. For 1.00 sqm Sqm 4510.50
Filling work including watering and compaction.For 1cum:
8.20 11,19,ka With sand cum 3360.83
8.21 11,19,kha With 15 -150 mm broken bricks cum 8673.50
9 CEMENT PLASTERING
12.5 mm thick Cement Sand plaster For 1 sqm
9.01 12 , 1 ka In 1:2 cement sand mortar Sqm 436.52
9.02 12 ,1 Kha In 1:3 cement sand morter Sqm 382.40
9.03 12 ,1 Ga In 1:4 cement sand mortar Sqm 369.25
9.04 12,1,gha In 1:6 cement sand mortar Sqm 340.42
20 mm thick cement sand plaster For 1 sqm
9.05 12 ,4 ka In 1:3 cement sand morter Sqm 506.28
9.06 12 ,4 Kha In 1:4 cement sand mortar Sqm 482.13
9.07 12,4,ga In 1:6 cement sand mortar Sqm 437.30
9.08 12,5 25mm th. Mud plaster.For 1 sqm: Sqm 381.94
9.09 12, 6 12.5mm th. Mud plaster.For 1 sqm: Sqm 294.53
9.10 Flush pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 252.48
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 232.77
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 222.39
9.11 Flush ruled pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 292.08
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 272.37
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 261.99
9.12 Flush ruled pointing work on boulder stone masonry wall.
14,2, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 325.77
14,2, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 287.98
14,2, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 268.83
9.13 14,3 Flush ruled pointing work with 1:3 c/ m on ashler
stone masonry wall. For 1.0 sqm Sqm 172.38
10 PAINTING WORK
10.01 13 ,11 Three coats chapra resin polishing.For 1sqm Sqm 163.31