Rate Analysis-Norms

1. The document provides rates per unit for various construction works such as site clearance, earthwork, stone work, brick work, and cement concrete work based on the Construction Norms 2041. 2. Rates are provided for tasks like felling trees, digging tree roots, surface dressing work, excavation work, stone masonry work, dry stone masonry work, brick work, and cement concrete work in foundations and walls. 3. The rates vary based on the type and size of the work, with higher rates for works involving harder materials like stone, excavation of harder soils, and construction of walls of greater heights.

Uploaded by

Gajendra Joshi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
710 views

Rate Analysis-Norms

1. The document provides rates per unit for various construction works such as site clearance, earthwork, stone work, brick work, and cement concrete work based on the Construction Norms 2041. 2. Rates are provided for tasks like felling trees, digging tree roots, surface dressing work, excavation work, stone masonry work, dry stone masonry work, brick work, and cement concrete work in foundations and walls. 3. The rates vary based on the type and size of the work, with higher rates for works involving harder materials like stone, excavation of harder soils, and construction of walls of greater heights.

Uploaded by

Gajendra Joshi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

SUMMARY OF RATE

Amanat Rate of F.Y. 2075/076 For Different Project without Road


Rate Analysis base on "Construction Norm's 2041" Page 1 of 7
Norms Rate per Unit
SN No. Description Unit Rs Remarks
1 SITE CLEARANCE
Felling of trees including cutting branches, sawing and carrying up to 15m away
from the site. For Each
1.01 1,1,ka Girth of tree 12 - 30cm Each 85.80
1.02 1,1,kha Girth of tree 31 - 60cm Each 257.40
1.03 1,1,ga Girth of tree 61 - 90cm Each 646.80
1.04 1,1,gha Girth of tree 91 - 120cm Each 646.80
1.05 1,1,ng Girth of tree 121 - 180cm Each 2640.00
1.06 1,1,cha Girth of tree 181 - 240cm Each 2640.00
1.07 1,1,chha Girth of tree 241 - 300cm Each 6864.00
1.08 1,1,ja Girth of tree over 301cm Each 27502.20
Tree root digging, lifting it and carrying up to 15m away from the site. For Each
1.09 1,2,ka Girth of tree 12 - 30cm Each 264.00
1.10 1,2,kha Girth of tree 31 - 60cm Each 349.80
1.11 1,2,ga Girth of tree 61 - 90cm Each 1663.20
1.12 1,2,gha Girth of tree 91 - 120cm Each 1663.20
1.13 1,2,ng Girth of tree 121 - 180cm Each 7920.00
1.14 1,2,cha Girth of tree 181 - 240cm Each 7920.00
1.15 1,2,chha Girth of tree 241 - 300cm Each 19536.00
1.16 1,6 Bamboo cutting,root digging,removel of bamboo from site (Dug-pit
dimension to be measured).For 1m3 cum 1848.00
1.17 1,7 Surface dressing work,cutting and filling earthwork,including levelling
ground surface(service road etc.). For 1m 2 sqm 6.60
1.18 1 ,8 Excavation 15-20 cm of the top soil including disposal
out side of the construction site. For 1 m2 sqm 105.60
2 EARTHWORK
Earthwork in excavation including a lead of 10m and a lift of 1.5m in:
2.01 2,1 Soft Clay : For 1 cum cum 475.86
2.02 2,2 Hard clay mixed boulder less than 30cm size :.For 1cum cum 543.84
2.03 2 ,10 Soft Rock : For 1 cum cum 1699.50
2.04 2 ,4 Medium Rock without blasting : For 1 cum cum 2039.40
2.05 2 ,6ka Hard Rock without chiselling : For 1 cum cum 3399.00
Earthwork in filling including watering & ramming every 20cm th. Layers For 1cum :
2.06 2 ,25ka With Ordinary Soil cum 339.90
Earthwork in filling including ramming every 15cm th. Layers (without watering )For 1cum :
2.07 2 ,25kha With Ordinary Soil cum 169.95
Turfing work Including cutting, hauling for 10m and watering For 1sqm :
2.08 2 , 40 Turfing work cum 33.99
3 STONE WORK
Stone (rubble) masonry work up to 5 m ht. Of wall including collection of stones,
preparation of mortar and a lead of 10 m. For 1 cum :
3.01 6,1,ka,2 In 1:4 Cement Sand Mortar cum 10470.29
3.02 6,1ka,3 In 1:6 Cement Sand Mortar cum 9448.03

Prepared by Checked by Approved by


SUMMARY OF RATE
Amanat Rate of F.Y. 2075/076 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041" Page 2 of 7
Norms Rate per Unit
SN No. Description Unit Rs Remarks
3.03 6 ,2.1 Dry Stone Masonry SITE CLEARANCE cum 3668.67
3.04 6 ,2.2 Mud Mortar Stone Masonry cum 3967.07

Stone (rubble) masonry work 5 to 10 m ht. Of wall including collection of stones,


preparation of mortar and a lead of 10 m.For 1 cum :
3.05 6,1,ka,2 In 1:4 Cement Sand Mortar cum 11242.49
3.06 6,1,ka,3 In 1:6 Cement Sand Mortar cum 10220.23
3.07 6 ,2.2 Mud Mortar Stone Masonry cum 4739.27
Stone (rubble) masonry work in arch or in sloping plane including collection of stones,
preparation of mortar and a lead of 30 m. For 1cum:
3.08 6,3,2 In 1:4 Cement Sand Mortar cum 11229.29
3.09 6,3,3 In 1:6 Cement Sand Mortar cum 10207.03
3.10 6,3,4 Stone (rubble) masonry work in (1:2) lime sand mortar For 1cum: cum 10516.57
Stone (One side dressed) masonry work including collection of stones, preparation of
mortar and a lead of 30m. For 1cum:
3.11 6,3,5 In 1:6 Cement Sand Mortar cum 13689.13
Stone (Three side dressed) masonry work including collection of stones, preparation
of mortar and a lead of 30m. For 1cum:
3.12 6,3,5 In 1:6 Cement Sand Mortar cum 20533.33
Stone (Five side dressed) masonry work including collection of stones, preparation of
mortar and a lead of 30m. For 1cum:
3.13 6,3,5 In 1:6 Cement Sand Mortar cum 30090.13
4 BRICK WORK
Brick work including collection of brick, preparation of mortar and transportation of
materials upto 30 m lead. For 1 cum :
Machine made brick ( size 224*108*57 mm) in :
4.01 5,1,ka,2 Cement mortar 1:4 cum 23147.78
4.02 5,1,ka,4 Cement mortar 1:6 cum 22615.29
Chimney made brick( size 224*108*57 mm) in:
4.03 5,1,kha,2 Cement mortar 1:4 cum 21369.88
4.04 5,1,kha,3 Cement mortar 1:6 cum 20812.69
4.05 5,1,kha,6 Mud mortar cum 17964.60
Extra work for scaffolding for 1cum
4.06 5,2,ka For ground floor cum 135.96
4.07 5,2,kha For above one floor cum 475.86
5 CEMENT CONCRETE WORK
Cement Ccncrete work in foundation,wall includingcollection of materials and a lead
of 30 m. For 1 cum
5.01 7 ,2 Ga With P.C.C ( 1:3:6 ) cum 11438.01
5.02 7 ,2 Gha With P.C.C. ( 1:2:4 ) cum 13299.44
5.03 With P.C.C. ( 1:1.5:3 ) cum 14892.34

Prepared by Checked by Approved by


SUMMARY OF RATE
Amanat Rate of F.Y. 2075/076 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041" Page 3 of 7
Norms Rate per Unit
SN No. Description Unit Rs Remarks
SITEstructure,
Cement Concrete work in supper CLEARANCE
deck slab,beams including collection of
materials and a lead of 30 m. For 1 cum
5.04 7,4,ka With P.C.C. ( 1:2:4 ) cum 15081.44
5.05 7,4,kha With P.C.C. ( 1:1.5:3 ) cum 16674.34
5.06 7,4,ga With P.C.C. ( 1:1:2 ) cum 20895.83
6 IRON WORK
6.01 7 ,5 Reinforcement bar cutting, binding, placing in position according to drawing & binding
for RCCwork including a lead of 30m. For 1kg. kg 124.18
6.02 M/S angle including making hole, cutting in required
length and shape. Per 1 kg kg 143.90
7 FORM WORK
7.01 8 ,2 Ka Preparation of formwork including selection,collection of materials cutting, nailing, fixing in
position, removel & disposal etc. as per drawing and a lead of 30 m.
For floor & slab. For 1 SQM : Sqm 737.50
7,02 Formwork for Ferrocement :For 1 SQM Sqm 349.11
Formwork for Column including nailing, fixing in position,removing and a lead of
30 m. For 1sqm :
7.03 8,3,ka Perimeter of column 0 - 2 m Sqm 1139.70
Form work for structural beam including selection, fixing,nailing,oiling,removel and
disposal with a lead of 30 m.For 1sqm :
7.04 8,4,ka Height of beam upto 0.30 m Sqm 1189.60
8 FLOORING
8.01 Preparation of Concrete-floor in 1:2:4, complete with cement punning. For 1.0 Sqm
11, ka a. 25 mm (1") Thick Sqm 476.34
11, kha b. 38 mm (11 / 2") Thick Sqm 652.01
11, ga c. 50 mm (2") Thick Sqm 802.94
11, gha d. 75 mm (3") Thick Sqm 1099.44
8.02 11 ,20 3 mm th.cement Punning in For 1 SQM Sqm 272.57
8.03 11 ,16 Stone Soling with sand For 1cum cum 6412.58
8.04 11 ,16 Dry stone soling For 1 cum cum 4658.67
8.05 11,15,ka Brick soling with sand - On Flat For 1sqm Sqm 1368.55
8.06 Brick soling without sand - On Flat For 1sqm Sqm 1294.44
8.07 11,15,kha Brick soling with sand - On Edge For 1 sqm Sqm 2594.14
8.08 Brick soling without sand - On Edge For 1 sqm Sqm 2418.75
8.09 11,8,ka Paving of 50 mm thick flagstone in (1:4) C/M : For 1sqm Sqm 1552.33
8.10 11, 9 Paving of 37.5 mm thick flagstone in (1:4) C/M : For 1sqm Sqm 1485.60
8.11 11, 10 Paving of 25 mm thick flagstone in (1:4) C/M : For 1sqm sqm 1365.62
8.12 11, 12 Paving brick, flat on cement sand mortar, complete with
1:2 cement sand pointing. For 1.0 Sqm Sqm 1858.55
8.13 11, 13 Paving brick, on - edge on 1:6 C / M, complete with
1:2 cement sand pointing. For 1.0 Sqm Sqm 2684.08
8.14 11, 21 Planking work of 25mm th. Local salwood planks on 600*600mm
frame of 50mm*75mm Local salwood. For 1.0 sqm Sqm 6661.94

Prepared by Checked by Approved by


SUMMARY OF RATE
Amanat Rate of F.Y. 2075/076 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041" Page 4 of 7
Norms Rate per Unit
SN No. Description Unit Rs Remarks
8.15 11, 21 SITE
Planking work of 25mm th. Local CLEARANCE
soft wood planks on 600*600mm
frame of 50mm*75mm Local salwood. For 1.0 sqm Sqm 2464.81

8.16 11,3 Laying of 25mm th. Mosaic flooring, 20mm th. C/ P in 1:2 and on th top of that 6mm th. White cement
and marble ( in 1:1) coat, complete with polishing. For 1.00 sqm Sqm 3506.73
8.17 11, 5 Paving 25mm th. Oiled terrazo tiles on 1:2 Surkhi mortar complete
with 1:1 cement sand pointing. For 1.0 Sqm Sqm 2179.99
8.18 11, 7 Laying of procelain glaxed tiles on 1:4 cement sand
mortar. For 1.0 sqm sqm 2753.98
8.19 11, 6 Laying of 25mm th. 450*450mm Marble on 20mmth. 1:4 surkhi mortar,
complete with polishing. For 1.00 sqm Sqm 4510.50
Filling work including watering and compaction.For 1cum:
8.20 11,19,ka With sand cum 3360.83
8.21 11,19,kha With 15 -150 mm broken bricks cum 8673.50
9 CEMENT PLASTERING
12.5 mm thick Cement Sand plaster For 1 sqm
9.01 12 , 1 ka In 1:2 cement sand mortar Sqm 436.52
9.02 12 ,1 Kha In 1:3 cement sand morter Sqm 382.40
9.03 12 ,1 Ga In 1:4 cement sand mortar Sqm 369.25
9.04 12,1,gha In 1:6 cement sand mortar Sqm 340.42
20 mm thick cement sand plaster For 1 sqm
9.05 12 ,4 ka In 1:3 cement sand morter Sqm 506.28
9.06 12 ,4 Kha In 1:4 cement sand mortar Sqm 482.13
9.07 12,4,ga In 1:6 cement sand mortar Sqm 437.30
9.08 12,5 25mm th. Mud plaster.For 1 sqm: Sqm 381.94
9.09 12, 6 12.5mm th. Mud plaster.For 1 sqm: Sqm 294.53
9.10 Flush pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 252.48
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 232.77
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 222.39
9.11 Flush ruled pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 292.08
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 272.37
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 261.99
9.12 Flush ruled pointing work on boulder stone masonry wall.
14,2, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 325.77
14,2, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 287.98
14,2, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 268.83
9.13 14,3 Flush ruled pointing work with 1:3 c/ m on ashler
stone masonry wall. For 1.0 sqm Sqm 172.38
10 PAINTING WORK
10.01 13 ,11 Three coats chapra resin polishing.For 1sqm Sqm 163.31

Prepared by Checked by Approved by


SUMMARY OF RATE
Amanat Rate of F.Y. 2075/076 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041" Page 5 of 7
Norms Rate per Unit
SN No. Description Unit Rs Remarks
10.02 Distempering painting SITE CLEARANCE
13,3, ka a. Lining. For 1 sqm Sqm 52.32 For rate to
estimate
13,3, kha b. First one coat. For 1 sqm Sqm 49.65 add a, b &
13,3, ga c. 2nd coat and additional coats. For 1 sqm Sqm 42.51 c
10.03 13,6 Applying 1 coat lining and 2 coats of aluminum
paint. For 1.00sqm Sqm 275.69
10.04 13,5ka-ga 1Coat primer & 2 Coat enamel paint. For 1sqm Sqm 298.23
10.05 13,5ka-ga
1Coat primer & 2 Coat weather coat(exterior)emulsion paint. For 1sqm sqm 311.41
10.06 1 Coat primer & 2 Coat emulsion paint.(Interior) For 1sqm sqm 292.43
11 7 line hori. and 2 line diago. barbed wire fencing on m/s angle
(50*50*6mm),at a spacing 2m c/c.For 1m Rm 467.83
12 ROOFING WORK
White CGI sheet roofing including collection of materials.
12.01 9 ,1 For 1 SQM (CGI sheet 24 SWG): Sqm 1930.18
12.02 9 ,1 For 1 SQM (CGI sheet 26 SWG): Sqm 1618.15
12.03 9 ,1 For 1 SQM (CGI sheet 28 SWG): Sqm 1309.26
Color CGI sheet roofing including collection of materials.
12.04 9 ,1 For 1 SQM (CGI sheet 24 SWG): sqm 2335.52
12.05 9 ,1 For 1 SQM (CGI sheet 26 SWG): sqm 2023.49
12.06 9 ,1 For 1 SQM (CGI sheet 28 SWG): sqm 806.57
12.07 9 ,2 White GI Plain sheet ridge fixing 24 SWG. For 1 M m 776.28
12.08 9 ,2 White GI Plain sheet ridge fixing 26 SWG. For 1 M m 730.58
12.09 9 ,2 White GI Plain sheet ridge fixing 28 SWG. For 1 M m 671.52
12.10 9 ,2 Color GI Plain sheet ridge fixing 24 SWG. For 1 M m 877.66
12.11 9 ,2 Color GI Plain sheet ridge fixing 26 SWG. For 1 M m 780.36
12.12 9 ,2 Color GI Plain sheet ridge fixing 28 SWG. For 1 M m 716.39
12.13 9,5 Slate roofing . For 1Sqm Sqm 2340.83
12.14 9,9,kha Thatch roofing.For 1sqm: Sqm 4372.96
12.15 9,6 Clay tiles (Chimney made) roofing. For 1sqm : Sqm 477.50
12.16 9,7 Clay tile as ridge (Chimney made) plate fixing. For 1m: m 404.10
13 WOOD WORK
13.01 10 ,1 a.Local salwood work for frames including fixing.For 1 cum cum 193446.88
10 ,1 b.Local soft wood work for frames.For 1 cum cum 83783.21
13.02 10 ,2 38mm th. wood frame for panelled door shutter. For 1 no
(shutter size -1.07*1.982 = 2.12sqm)
a.With Local salwood Sqm 11271.89
10,2 b.With Local softwood Sqm 7321.74
13.03 10 ,3 38*75mm size wood frame using 3mm plain glass for glazed shutter. For 1no.(shutter
size - 1.892*1.22 = 2.23sqm)
a.With Local salwood Sqm 8108.68
10 ,3 b.With Local softwood Sqm 5918.09

Prepared by Checked by Approved by


SUMMARY OF RATE
Amanat Rate of F.Y. 2075/076 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041" Page 6 of 7
Norms Rate per Unit
SN No. Description Unit Rs Remarks
13.04 10 ,3 SITE4mm
38*75mm size wood frame using CLEARANCE
plain glass for glazed shutter. For 1no.(shutter
size - 1.892*1.22 = 2.23sqm)
a.With Local salwood Sqm 8168.81
10 ,3 b.With Local softwood Sqm 5978.22
13.05 10 ,9 38mm wood frame using 26 SWG Plain GI sheet on both side. For 1 no.(shutter size -
1.092*2.058 = 2.247sqm)
a.With Local salwood sqm 6403.43
10,9 b.With Local softwood sqm 4868.30
13.06 10 ,10 38mm wood frame using 24 SWG GI wire mesh mosquito proof shutter .For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 4531.47
10 ,10 b.With Local softwood Sqm 3377.91
13.07 10,7 38mm wood frame using 3mm plywood both side for flush shutter. For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 6624.76
b.With Local softwood Sqm 5089.63
13.08 38mm wood frame using 3mm plywood one side for flush shutter .For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 5625.58
b.With Local softwood Sqm 4090.45
13.09 10,7 38mm wood frame using 6mm plywood both side for flush shutter. For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 7326.50
b.With Local softwood Sqm 5791.37
13.10 38mm wood frame using 6mm plywood one side for flush shutter .For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 5976.45
b.With Local softwood Sqm 4441.32
13.11 Fixing glass of different thichness in window frame including fixing of wooden listis.
For 1sqm with :
10,11,ka a.3 mm thick glass Sqm 866.18
b 4 mm thick glass Sqm 989.77
13.12 10 ,17 Wood work for beam and joist including fixing .For 1cum
a.With Local salwood cum 167180.05
b.With Local softwood cum 62501.09
13.13 10,18 a.Local salwood work for truss fixing.For 1M3 cum 189933.80
b.Local soft wood work for truss fixing.For 1M3 cum 85254.84
13.14 10 ,19 a.Local salwood work for 25mm th. Eaves board including fitting.
For 1SQM Sqm 4098.30
10 ,19 b.Local hardwood work for 25mm th. Eaves board including fitting.
For 1SQM Sqm 1356.71

Prepared by Checked by Approved by


SUMMARY OF RATE
Amanat Rate of F.Y. 2075/076 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041" Page 7 of 7
Norms Rate per Unit
SN No. Description Unit Rs Remarks

13.15 10,14,ka SITE


0.61*0.915m size wooden frame CLEARANCE
(wood size 38*75mm) work for partation using 3mm
plywood both side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2803.77
b. With Local soft wood Sqm 1823.35
13.16 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 3mm
plywood one side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2321.29
b. With Local softwood Sqm 1340.87
13.17 10,14,ka 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 6mm
plywood both side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 3518.36
b. With Local soft wood Sqm 2537.95
13.18 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 6mm
plywood one side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2678.59
b. With Local softwood Sqm 1698.17
13.19 10,16,ka 0.60*0.90m size wooden frame (wood size50*75mm)using 3mm plywood for different
type false ceilings( ceilings size=9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2841.64
b. With Local soft wood Sqm 1581.11
13.20 10,16,ka 0.60*0.90m size wooden frame (wood size50*75mm)using 6mm plywood for different
type false ceilings( ceilings size=9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 3198.94
b. With Local soft wood Sqm 1938.41
14 DEMOLIITIONS AND REPAIR WORK
14.01 19-1 Demolishing mud mortar masonry and disposing the
materials to a distance of 10m. For 1cum: cum 699.60
14.02 19-2 Demolishing cement or lime surkhi mortar masonry and disposing
the materials to a distance of 10m.For 1cum : cum 1399.20
14.03 19 - 3 Demolishing RCC or RBC work and disposing
materials to a distance of 10m. For 1cum : cum 7260.00
14.04 19 - 4 Demolishing PCC or lime surkhi concrete and disposing
the materials to a distance of 10m.For 1cum : cum 2640.00
14.05 19 - 5 Demolishing cement or lime surkhi plaster and disposing
the materials to a distance of 10m.For 1cum : cum 71.28
14.06 19 -6 Demolishing tiled roof and stacking the tiles, wood etc.
properly at a distance of 10m. For 1cum : cum 106.92
END