Telecom Tower Construction ZTL

This document outlines the tasks, durations, dependencies, and timeline for a telecom tower construction project. The project includes tasks for site acquisition, design, procurement, construction of the tower and foundation, equipment installation, and fence installation over a period of 61 days from November 18, 2020 to February 10, 2021. Key milestones include the project start, various construction phases, equipment delivery and installation, and final project completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
249 views

Telecom Tower Construction ZTL

This document outlines the tasks, durations, dependencies, and timeline for a telecom tower construction project. The project includes tasks for site acquisition, design, procurement, construction of the tower and foundation, equipment installation, and fence installation over a period of 61 days from November 18, 2020 to February 10, 2021. Key milestones include the project start, various construction phases, equipment delivery and installation, and final project completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID Task Name Duration Start Finish Predecessors Successors

01 Nov '20 15 Nov '20 29 Nov '20 13 Dec '20 27 Dec '20 10 Jan '21 24 Jan '21 07 Feb '21
S W S T M F T S W S T M F T S W S T M F T S W S T
1 General 61 days? 18 Nov '20 10 Feb '21
These durations
2 Milestones 61 days? 18 Nov '20 10 Feb '21 shall be zero
3 Project Start 1 day? 18 Nov '20 18 Nov '20 6
4 Project Finish 1 day? 10 Feb '21 10 Feb '21 54
5 Site Acquisition 11 days? 19 Nov '20 03 Dec '20
6 Site Hunting 3 days 19 Nov '20 23 Nov '20 3 7
7 Document submission to CDC 7 days 24 Nov '20 02 Dec '20 6 8
8 BP approval 1 day? 03 Dec '20 03 Dec '20 7 10
9 Design 7 days 04 Dec '20 14 Dec '20
10 Soil Test 4 days 04 Dec '20 09 Dec '20 8 11
11 Detail Design Drawing 3 days 10 Dec '20 14 Dec '20 10 13
12 Procurement 20 days? 15 Dec '20 11 Jan '21
13 Telecom Tower Construction 1 day? 15 Dec '20 15 Dec '20 11 14
14 Tower Materials, Fence & 2 days 16 Dec '20 17 Dec '20 13 17
Please assign the
15 Construction materials
Tower,Fence Order
& Grounding and
Material 2 days 08 Jan '21 11 Jan '21 32 36
proper duration
16 delivery
CW Construction 25 days? 18 Dec '20 21 Jan '21 for these
17 Site Kick Off Meeting 1 day? 18 Dec '20 18 Dec '20 14 18
18 Site Clearing 1 day? 21 Dec '20 21 Dec '20 17 19
19 Site barrier and HSSE preparation 1 day? 22 Dec '20 22 Dec '20 18 20,24
20 Excavation 1 day? 23 Dec '20 23 Dec '20 19 21
21 Hardcore and sand filling 1 day? 24 Dec '20 24 Dec '20 20 22
22 Lean Concrete 1 day? 25 Dec '20 25 Dec '20 21 25 Fabrication shall
23 Footing 8 days? 23 Dec '20 01 Jan '21 be linked with
24
installation
Rebar fabrication 2 days 23 Dec '20 24 Dec '20 19 29,40
25 Rebar Installation 2 days 28 Dec '20 29 Dec '20 22 26
26 Formwork installation 1 day? 30 Dec '20 30 Dec '20 25 27
27 Casting 2 days 31 Dec '20 01 Jan '21 26 30
28 Column 17 days? 25 Dec '20 18 Jan '21
29 Rebar fabrication 1 day? 25 Dec '20 25 Dec '20 24
30 Rebar and bolt &nut Installation 2 days 04 Jan '21 05 Jan '21 27 31
31 Formwork installation 1 day? 06 Jan '21 06 Jan '21 30 32
32 Casting 1 day? 07 Jan '21 07 Jan '21 31 33,15 Materials
33 setting time 7 days 08 Jan '21 18 Jan '21 32 34 checking shall be
34 Backfilling 3 days 19 Jan '21 21 Jan '21 33 37 linked with
35 Tower Installation 14 days? 12 Jan '21 29 Jan '21 installation
36 Tower materials checking 1 day? 12 Jan '21 12 Jan '21 15
37 Tower Installation 4 days 22 Jan '21 27 Jan '21 34 38
38 Tower checking 2 days 28 Jan '21 29 Jan '21 37 41
39 Equitment & DG pad 29 days? 25 Dec '20 03 Feb '21
40 Rebar fabrication 1 day? 25 Dec '20 25 Dec '20 24 51
41 Rebar Installation 1 day? 01 Feb '21 01 Feb '21 38 42
42 Formwork installation 1 day? 02 Feb '21 02 Feb '21 41 43
Task Project Summary Manual Task Start-only Deadline

Project: Telecom Tower constru Split Inactive Task Duration-only Finish-only Progress

Date: 20 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Name Duration Start Finish Predecessors Successors
01 Nov '20 15 Nov '20 29 Nov '20 13 Dec '20 27 Dec '20 10 Jan '21 24 Jan '21 07 Feb '21
S W S T M F T S W S T M F T S W S T M F T S W S T
43 Casting 1 day? 03 Feb '21 03 Feb '21 42 45,50
44 Power 2 days? 04 Feb '21 05 Feb '21
45 Equitment & DG delivery 1 day? 04 Feb '21 04 Feb '21 43 46
46 Equitment & DG installation 1 day? 05 Feb '21 05 Feb '21 45 48
47 Fence & Grounding Installation 32 days? 28 Dec '20 09 Feb '21
48 Grounding Installation 1 day? 08 Feb '21 08 Feb '21 46
49 Fence foundation 31 days? 28 Dec '20 08 Feb '21
50 Excavation 1 day? 04 Feb '21 04 Feb '21 43 52
51 Rebar fabrication 1 day? 28 Dec '20 28 Dec '20 40
52 Rebar installation 1 day? 05 Feb '21 05 Feb '21 50 53
53 Concrete casting 1 day? 08 Feb '21 08 Feb '21 52 54
54 Fence Installation 1 day? 09 Feb '21 09 Feb '21 53 4

Task Project Summary Manual Task Start-only Deadline

Project: Telecom Tower constru Split Inactive Task Duration-only Finish-only Progress

Date: 20 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone