S-PCM Minutes of Meeting: Train 02
S-PCM Minutes of Meeting: Train 02
The Head of the team responsible for construction work or the work supervisor is required to attend S-PCM or
the meeting needs to be held at site.
ITEM No DESCRIPTION OF DISCUSSION
1. Activity: Scaffolding erection and dismantling activity
DETAIL DRAWING:
Page: /
ITEM No DESCRIPTION OF DISCUSSION
7. Dismantling Work Sequence:
Conduct to TBM before start the job.
Arrange area for keeping removing scaffold materials.
Before dismantling remove all unwanted materials from platform.
Put red tag on the scaffold during dismantling.
Fixing pulley on the steel structure use 16mm of rope.(if required)
Install life line on the steel structure for 100% tie off.(if required)
Dismantling should be start top to downward
Remove handrail.
Remove wood plank.
Remove pipe and coupler
Remove hanging pipe, coupler, and beam clump.
Scaffolding dismantling step by step.
Materials will be lower by PP rope and pulley to the ground level.
During lowering materials fix it properly by using clamps &rope.