0% found this document useful (0 votes)
880 views

S-PCM Minutes of Meeting: Train 02

1. The minutes of meeting document the discussion of a scaffolding erection and dismantling activity taking place from February 28th to March 31st, 2018. 2. Safety precautions for the activity include wearing proper PPE, using fall protection such as full body harnesses and life lines, and establishing exclusion zones with barricades and signage. 3. The scaffolding dismantling and erection sequences are outlined step-by-step to ensure safety during the process.

Uploaded by

sudeesh kumar
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
880 views

S-PCM Minutes of Meeting: Train 02

1. The minutes of meeting document the discussion of a scaffolding erection and dismantling activity taking place from February 28th to March 31st, 2018. 2. Safety precautions for the activity include wearing proper PPE, using fall protection such as full body harnesses and life lines, and establishing exclusion zones with barricades and signage. 3. The scaffolding dismantling and erection sequences are outlined step-by-step to ensure safety during the process.

Uploaded by

sudeesh kumar
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Appendix: S-PCM Minutes of Meeting

S-PCM Minutes of Meeting Page: /

SUBJECT: DCBM: Scaffolding Erection and Dismantling Activity


DATE OF MEETING: 27/02/2018 JOB NO:
LOCATION: Train 02 REPORTED BY:
ATTENDENCE FROM SECL ATTENDENCE FROM SUBCONTRACTOR
Org. Job Title Name Signature Org. Job Title Name Signature
SECL DCBM
SECL DCBM
SECL DCBM
SECL

 The Head of the team responsible for construction work or the work supervisor is required to attend S-PCM or
the meeting needs to be held at site.
ITEM No DESCRIPTION OF DISCUSSION
1. Activity: Scaffolding erection and dismantling activity

2. Height/Length/Width: (H:3 to 6m)(W:3m) (L: 10m)


3. Weight:
4. Working Period:28/02/2018--------31/03/2018
5. Working Team: 1 job sv 1 HSE sv 1 watcher 9 worker total:12
6. Working Equipment’s: Hand tools, Pulley. Rope ,Clamps ,Boom truck, pickup

DETAIL DRAWING:

SAMSUNG ENGINEERING CO.LTD

Page: /
ITEM No DESCRIPTION OF DISCUSSION
7. Dismantling Work Sequence:
 Conduct to TBM before start the job.
 Arrange area for keeping removing scaffold materials.
 Before dismantling remove all unwanted materials from platform.
 Put red tag on the scaffold during dismantling.
 Fixing pulley on the steel structure use 16mm of rope.(if required)
 Install life line on the steel structure for 100% tie off.(if required)
 Dismantling should be start top to downward
 Remove handrail.
 Remove wood plank.
 Remove pipe and coupler
 Remove hanging pipe, coupler, and beam clump.
 Scaffolding dismantling step by step.
 Materials will be lower by PP rope and pulley to the ground level.
 During lowering materials fix it properly by using clamps &rope.

Item no Description of Discussion


09 Safety precaution:
 All person should be wear proper PPE at work site.
 Wear full body harness while working at height and 100% TIE OFF.
 Provide proper welfare facility for workforce, rest shelter, smoking
shelter.
 Provide first aid box, stretcher for the first aid facility.
 A trained watcher should be stand by with whistle safety vest and
green helmet.
 Ground level area should be double barricaded with signage.
 Full time job supervision by HSE supervisor and job supervisor.
 Use proper manual handling technique.
 All scaffold materials should be organized and barricaded well.
 All materials should be Shift from site to storage (ASAP).
 Use inspected tools and equipment.
 Unauthorized person not allowed in the work area.
 Provide competent person for this job.
 All work should training for work at height
 Unauthorized individual, will not be allowed to enter activity area.
 Emergency procedure should be in place.
 Use insulated tools and Tools arrestors
 SIMOPS are not allowed.
 Follow the emergency procedure.
 Do not do any horseplay at site. Eating, sleeping is prohibited at site.
 Keep regular supervision for all the time of the activity.
 Each time PTW and SPCM will be reconsidered for review as per
Situation.
 Full time first Aid and emergency response preparedness.
 Emergency access always should be clear.
 Ensure that the work area is maintained clean and tidy during work.

Item no Description of Discussion


08  Scaffold Erection Sequence:
 TBM before start the job.
 Start the job as per design.
 All scaffold material should be inspected.
 Inspect the ground condition. Use footings that are level, sound, rigid and
capable of supporting the load without settlement or displacement.
 Brace poles, legs, posts, frames, and uprights to prevent swaying and
displacement.
 Install life line (if required)
 Start scaffold erection by using sole plate and base jack.
 Put red tag on the scaffold.
 Start frame formulation and erection step by step.
 Fasten all couplers and/or connections securely before assembling the next
level.
 Provide pulley and 16mm of rope for lifting the scaffold materials.
 Provide materials bag for clumps and small wood plank to lifting upper level.
 Scaffold components should not intermix from different manufacturers, unless
you can do so while maintaining the scaffold’s structural integrity.
 The base jack should be tied around with pipe.
 Installing platform with fixing hand rail, mid rail wood plank.
 Install guys, ties, and braces according to the requirement of area.
 Once erected, provide toe boards on all railed sides to prevent falling object
hazards
 Position the first level of bracing as close to the base as possible
 Brace poles, legs, posts, frames, and uprights to prevent swaying and
displacement.
 Provide proper access by installing ladder.
 After complete the scaffold should be inspect by Samsung scaffold inspector.
 Put green tag after inspection.
 After finish the work all remaining materials should be remove from site and
area should be clean.

You might also like