PM Optimisation: Using PMO2000™ Reliability Software and Methodology
PM Optimisation: Using PMO2000™ Reliability Software and Methodology
PM OPTIMISATION
Using PMO2000™ Reliability
Software and Methodology
Information package
for organisations
with assets currently in use
1 Slough Road
Altona VIC 3018
INTRODUCTION............................................................................................................3
Not Done
Over the five years of development a
Not Done
PM
startling outcome of the initial
PM
to Do PM
Resources
found the following weaknesses in
to Do PM
Resources
1
In June 2000, State Government funding was removed from SIRF. Maintenance activities conducted by SIRF were adopted by
SIRFrt (refer to www.sirfrt.com.au) under government grants.
PMO2000™ from A to Z.
OVERVIEW
The PMO2000™ process has nine steps. These steps are listed below and discussed
in the following pages.
Step 1 Task Compilation
Step 2 Failure Mode Analysis
Step 3 Rationalisation and FMA Review
Step 4 Functional Analysis (Optional)
Step 5 Consequence Evaluation
Step 6 Maintenance Policy Determination
Step 7 Grouping and Review
Step 8 Approval and Implementation
Step 9 Living Program
PROJECT RANKING
It should be noted that a full PMO2000™ assignment, there needs to be some form of
criticality or system ranking process. This may be done by reviewing the equipment
hierarchy, and subdivide it into appropriate systems and/or equipment items for
analysis. Having performed this task, the criticality of each of the equipment
items/systems identified is assessed in terms of their contribution to the client
organisation’s strategic objectives. Higher criticality systems tend to be those that will
have an impact in the following ways:
♦ Have a high perceived risk in terms of achieving safety or environmental objectives,
♦ Have a significant impact on plant throughput, operating or maintenance costs, or
♦ Are consuming excessive labour to operate and maintain.
Having conducted the criticality assessment, this is used as the basis for assessing
which equipment items or systems should be analysed first, and the overall level of
rigour required for each analysis.
♦ Their likelihood is very low therefore the cost of a preventive or predictive task is
likely to be more than the cost of failure, or
♦ There is no technically feasible predictive or preventive maintenance task known to
manage them.
In the author’s experience, rigorous RCM analysis of equipment in accordance with the
standard shows that, on average, about 80% of failure modes result with the policy of
No Scheduled Maintenance.
This number rises with electronic equipment such as a PLC and falls with equipment
that has a high number of moving parts such as a conveyor
be listed against the one task. This significantly reduces the analysis time by reducing
the records that need to be dealt with. The concept can be best described by
reference to Tables 1 and 2.
It can be seen from Table 1 that providing vibration analysis was a technically feasible
and cost effective task to prevent all these failure modes from occurring unexpectedly,
PMO2000™ would consider the failure modes as a group.
Conversely at Table 2, RCM can be seen to have created a lengthy analysis process
compared with PMO2000™. Accepting that the resulting maintenance program will be
the same the route to this result covered four times the administration and probably
double the analysis time. Furthermore, with decomposed failure modes, there is
additional administrative effort required to roll them back up and link the four failure
modes to the one task.
3. Optional Functional Analysis
RCM begins with a complete functional analysis of the equipment whereas with PMO
the effort expended on functional analysis is discretionary. This is primarily because
consequence evaluation is performed at Question 5 of PMO2000™. As consequence
evaluation implicitly involves understanding what loss of function is incurred, additional
functional assessment is a duplication2 of effort.
Done properly, functional analysis consumes 30% of the total RCM analysis time and
is the lowest value adding activity of the process.
FLEXIBILITY COMPARISONS
FILTERING OF FAILURE MODES BY TRADE
RCM analysis cannot regulate or filter which failure modes are analysed at which time.
Therefore, RCM analysis requires the presence of all trades simultaneously. With
PMO2000™ it is possible to review the activities of a particular trade on a particular
piece of equipment or site. This is because PMO2000™ begins with maintenance
tasks that can be filtered by trade. This is particularly useful when the activities of one
trade are ineffective or inefficient and need to be reviewed in isolation from other
trades.
There have been highly successful PMO2000™ analyses performed exclusively on
either operator rounds, on instrumentation rounds, on lubrication rounds, on vibration
2
This point is also relevant where functions are hidden, as the loss of hidden functions will result in consequences that are
conditional on some other failure occurring.
BENEFITS OF SPEED
Experience in the US Nuclear Power Industry was that over a large number of
analyses, PMO2000™ was on average six times faster than RCM (Johnson, 1995).
PMO2000™ is considered to be a much faster approach than the approach taken by
Johnson.
The positive effect of deploying a process of maintenance analysis that is six times
faster than RCM for the same given outcome cannot be overstated. The benefits are
listed below:
♦ Resources to perform analysis are generally the most valuable and scarce on site.
The less resource intensive the program (for the same results) the less the
organisation will suffer from the loss of its most valuable people.
♦ Efficient analysis allows the organisation to be implementation intensive rather than
analysis intensive.
♦ Maintenance analysis is subject to diminishing returns. PMO2000™ is cost
effective on all items of the plant whereas it is difficult to justify RCM on any other
than critical assets because of the high fixed cost and the inflexibility of the process.
♦ Where the maintenance of failure modes that have safety or environmental
consequences is considered suspect, the use of PMO2000™ will allow these
issues to be dealt with much faster than by using RCM as they will be eradicated
plant wide six times faster.
♦ First line supervisors who invest in the program get rewarded with labour
productivity improvements six times greater. PMO2000™ targets a return on
analysis time of 5 to 1. That is for every man-hour invested in analysis, five man-
hours will be returned to the department every year. At this rate, line supervision is
prepared to invest their resources. At a rate six times less, they often become
uncooperative.
3
In fact what happens in reality is that RCM facilitators “Black Box” the item which is to say that RCM in its strict use can not cope
efficiently with analysis of such assets.
4
Readers interested in learning more about where these algorithms are flawed can contact the author.
Implementing PMO2000™
A full scale PMO2000™ implementation program generally starts with some
workshops or briefings introducing key decision-makers to the process. The objective
of these sessions is to lay the groundwork for ensuring successful implementation.
Prior to this however, most organisations choose to trial the PMO2000™ process on
one or more equipment items or systems. In this environment, the workshop is
strongly facilitator lead. Following the trial, the benefits, costs and implementation
issues are assessed, and a decision reached on whether, and how, to roll out
PMO2000™ on a wider scale within the organisation. Following a trial, the take up rate
has been 100%.
OPTION 1 - PMO2000™ CONSULTANT PROVIDES FULL TIME PROJECT MANAGEMENT, TRAINING AND FACILITATION
This approach is suitable for companies in the following situation:
Ø Limited internal management resources to drive the program,
Ø Poor asset management systems and documentation,
Ø Large opportunity to improve uptime and this opportunity translates to significant
increases in profitability.
Ø Moderate or poor record of implementing new systems and modern
management philosophies.
OPTION 2 - PMO2000™ CONSULTANT PROVIDES PART TIME TRAINING, WORKSHOP FACILITATION AND LIMITED PROJECT SUPPORT
This approach is suitable for companies in the following situation:
Ø Can dedicate one full time resource to the project.
Ø Good standard of asset management systems and procedures.
Ø Isolated areas of opportunity to improve and moderate impact on profitability.
Ø Good record of successfully implementing new systems and modern
management philosophies.
OPTION 3 - PMO2000™ CONSULTANT PROVIDES TRAINING ONLY
This approach is suitable for companies in the following situation:
Ø Can dedicate a team of specialist tradesmen and engineers to the project full
time. This usually applies to sites that have a full time reliability group or
section.
Ø Advanced asset management systems.
Ø Deriving profitability through advanced reliability engineering practices.
Ø "Implementing change" is a way of life.
KEY FEATURES
Key features of PMO2000™ are as follows:
Ø User interfaces are designed for use by shop floor personnel who may have limited
computer literacy.
Ø Task analysis can be completed in only one screen.
Ø Full implementation can be completed in three screens as follows:
Ø Analysis,
Ø Approval, and
Ø Implementation Verification.
Each screen can be password protected using an inbuilt security protocol.
Ø The software steps ensure consideration and consistency of the conditions to be
inspected, the limits of acceptability and the action to be taken if the limits are
exceeded.
Ø Both PM Optimisation and RCM methods are fully supported. Zero based Failure
Mode Effect and Criticality Analysis (FMECA) is a feature included for use in the
design of new equipment whether the design is a totally new concept or an upgrade
of a previous model. The software is therefore a living tool from the equipment
Copyright OMCS International Written by Steve Turner [email protected] Page 18
concept design to decommissioning.
Ø Maintenance analysis can be completed rapidly using single screen analysis or,
where required, rigorous analysis using cost benefit calculations. All analysis can
be fully costed and the returns calculated by in-built intelligent cost calculators.
Ø Cloning or duplication of maintenance analysis is fully supported by drag and drop
facility similar to the copy and paste function in Windows Explorer. This removes a
significant administrative burden where there are many items of identical plant or
where there is a need to apply unilateral maintenance policy to groups of common
components with like failure modes and similar failure consequences. This also
makes available features such as equipment and strategy libraries.
Ø Single tasks can be assigned to multiple hierarchical schedules such as monthly,
three monthly, six monthly and annually. The order that the task appears on each
schedule can be set for each schedule independently. There is therefore no need
to retype each task on each hierarchical servicing.
Ø The labour content for each schedule can be calculated by adding the content for
each individual task or by assigning a global labour content for the schedule as a
work package.
Ø All changes to the maintenance program are archived on final approval for
implementation. At any subsequent time, the rationale for changes to each task
can be easily viewed no matter how many changes are made to the same task.
Ø Work arising from the analysis (such as writing operating procedures or assessing
modifications) is allocated to people during the analysis via the software.
Management of this work can be controlled via the software.
Ø Following implementation approval the relevant maintenance schedules are
electronically and automatically updated. Maintenance schedules can be linked to
CMMS via Hyperlink functions.
Ø Whilst there are several inbuilt reports, the report writing functionality is limited only
by imagination as the database can be queried and reported on using MS Access,
Excel or other like tools.
Ø The system can be used and operated by many people at once using a centralised
database.
Power
Johnson L.P (1995) "Improving Equipment Reliability and Plant Efficiency through PM Optimisation at Kewaunee Nuclear
Power Plant" SMRP 3rd Annual Conference, Chicago Illinois.
Moubray J M (1997) “Reliability – centred Maintenance”. Butterworth - Heinemann, Oxford
Nowlan F S and Heap H (1978) “Reliability – centred Maintenance”. National Technical Information Service, US Department
of Commerce, Springfield, Virginia.
PMOptimisation web site at www.pmoptimisation.com