Macro Air Sabs Methodology - Sept 2016
Macro Air Sabs Methodology - Sept 2016
METHODOLOGY
MACRO AIR SABS WALL COMPOSITION
Expanded Adhesive Macro Air Sabs
Foam (Hither or Fisher)
EPS Boards (Saebi Alternative Building
(Expandable Polystyrine) Systems):
This is composite building
system with EPS and Macro
Air Sabs structural coatings
consisting of MAS Premix,
Sand, MAS additives and
Interior Finished water as the main
(By Others) component.
Mas Coating
(Glass Fiber Reinforced
Concrete)
MACROAIR SABS WALL SYSTEM.
METHODOLOGY
Scope of Works Outline
Hauling works
Eps Installation
MEPFS Installation
Mas Coating – Masonry Works
Sealant Application
HAULING WORKS
Hauling Works
Horizontal Hauling
Level Bar
Ladder
EPS installation
2. Materials
PU Foam as per
approved
Eps Installation
Line &Grade
2) Leave Out
1) Direct Coating
• 2 Options for MAS Coating : Coating of wall surface leaving
Cutting of coated Walls suing out the MEPFS area.Then, Rough
Thermo Foam Cutter (By MEPFS). ins of MEPFS piping, followed by
1) Direct Coating - Immediate Then, rough ins of MEPFS piping, testing prior to finishing coat or
coating of entire surface w/o followed by testing prior to restoration of wall using mortar
finishing coat
MEPFS embeddments filling ( optional only )
Mix the water and MAS Add the the glass fiber into the
Additives using Shear Mixer Mixing with set of MAS
mixture Premix and Sand
for 1 minute
MAS Coating - Masonry
MAS Coating Application
Start MAS Application
from the bottom to top Door Lintel and Door Install nylon string for
portion of the EPS wall for Stiffiner Area will be reference of the final Macro Air Sabs Wall
the initial coating (scracth First Mas Coated for coating thickness Finishes
coat) Allignment Purposes.
SEALANT
APPLICATION
Sealant Application
Sealant Application