Report On The Work Performed by Maintenance Labors: Division:-Mannar Month of Reporting
Report On The Work Performed by Maintenance Labors: Division:-Mannar Month of Reporting
Labour Performance
No
of
Place of work
No Name of ML Days Work output with location
performed
wor
ked
1 T.Thayalan Thiruketheswaram 2 Soil lab, Palavai tank Boundary and Thepaikulam
cleaning and maintenance work –(2 days.)
Koorai 18 Main Canal Clearing (Manual)– 2335m2 (9days)
Main Canal Clearing (Machinery)– 3710m2
(8days)
Rain (1day)
2 K.Pratheeba Office 19 Office work, Store maintenance work. (19days)
3 S.Thayananthakuma Thiruketheswaram 21 Removing dry leaves and weeding in soil lab inner
r and outer boundary-(21days)
4 R.Bernad Kurai 3 Weeding in Tank Bund (Manual)– 252m2 (1 day)
Weeding in Tank Bund (Machinery)– 948m2 (2
days)
Mullikulam 13 Bund Clearing – 3541.64m2 (7days)
Main Canal Clearing (Manual)– 4260m2 (6days)
Periyamadhu 2 Works in Pallamadu Office –(1 day)
Painting Water level Scale–(1 day)
5 A.S.M Harries Koorai 20 Weeding in Tank Bund (Manual)– 252m2 (1 day)
Weeding in Main canal (Manual) – 2238m2 (9day)
Weeding in Main canal (Machinery) – 3640m2
(8day)
Rain (2day)
No. of
Achieved Cumulative labour days Output/
Annual need under Output/ L
Description output in output spent for L.Day
this division per no
this month this month Achieved
Achievement
Bund clearing 541925 m2 13470 64 210.47 *1
Spill way clearing 166140 m 2
1660 5 332.00 *1
Main Canal
162414 m2 2430 10 243.00 *1
clearing
Weedin Bund 15211.50 59 281.69
g Main 22518.00 65 346.43
Pathinium
Clearing
Spill Tail clearing
Greasing of 17 sluice Gates, 24
Structures Turnouts, 12 Gated _ _ _ _
Regulators
Anticorrosive and
painting of others 17 sluice Gates, 24
Turnouts, 12 Gated _ _ _ _
Regulators, 07 planks
Prepared By: ………..………… Checked By:……………….
Mr.M.Vinoj, Mr.V.Joy Christy Peries,
DO Draughtsman
Submitted By …………………………
Eng.R.Tharakan,
Irrigation Engineer,
Mannar Division.