Base Shear Check
Base Shear Check
75
When h = 12.34 m ( h in meters excludes basement storeys)
T= 0.49 sec (for RC MRF building)
T= 0.53 sec (for RC-Steel Composite MRF bui
T= 0.56 sec (for Steel MRF building)
Sa/g = 2.0251275 Medium Soil
2. Time period for MRF buildings with RC structural walls: T= 0.075h 0.75 /√Aw >= 0.09h/√d
When h = 12.34 m Awi = Effective c/s area of wall I in first storeybof building, in s
Awi = 2.804 sqm Lwi = Length of structural wall I in first storey in the considere
Lwi = 14.02 m d = base dimension of the building at plinth lvl along consid
d= 17.07 m Nw = number of walls in the considred direction
Nw = 2 Lw/h shall not exceed 0.9.
T= 0.29 sec
3. All other buildings: Time period for MRF with brick infill panel: T= 0.09h/√d
When h = 17.1 m
d= 11.60 m
T= 0.45 sec
Soft Soil
Medium Soil
2.625 2.530
1.022 1.021
1. Time period for bare MRF buildings without any masonry infills: T= 0.075h 0.75
When h = 27.2 m ( h in meters excludes basement storeys)
T= 0.89 sec (for RC MRF building)
T= 1.01 sec (for Steel MRF building)
Sa/g = 1.119469 Medium Soil
2. All other buildings: Time period for MRF with brick infill panel: T= 0.09h/√d
When h = 16.09 m
d= 24.42 m
T= 0.29 sec