0% found this document useful (0 votes)
25 views

PPM Gazipur

The document outlines a 28 task project schedule with details on task name, duration, start date, finish date and task dependencies. Key tasks include preliminary survey from 10/1/2020-10/4/2020, land acquisition from 10/4/2020-10/19/2020, clearing and grubbing from 10/19/2020-11/18/2020, final design from 11/23/2020-12/8/2020, RCC drain installation from 12/8/2020-4/27/2021, road construction from 3/28/2021-10/26/2021 including excavation, subgrade preparation, base preparation and paving. The schedule also lists resource requirements and rates for each task

Uploaded by

Mohammad Adnan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views

PPM Gazipur

The document outlines a 28 task project schedule with details on task name, duration, start date, finish date and task dependencies. Key tasks include preliminary survey from 10/1/2020-10/4/2020, land acquisition from 10/4/2020-10/19/2020, clearing and grubbing from 10/19/2020-11/18/2020, final design from 11/23/2020-12/8/2020, RCC drain installation from 12/8/2020-4/27/2021, road construction from 3/28/2021-10/26/2021 including excavation, subgrade preparation, base preparation and paving. The schedule also lists resource requirements and rates for each task

Uploaded by

Mohammad Adnan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 74

ID Task Name Duration Start Finish

1 Preliminary Survey 3 10/1/2020 10/4/2020


2 Mobilization & Site Prep 20
3 Land Acquisition 15 10/4/2020 10/19/2020
4 Clearing, Grubbing & Dismantling 30 10/19/2020 11/18/2020
5 Survey Inspection 5 11/18/2020 11/23/2020
6 Final Design, Drawing etc. 15 11/23/2020 12/8/2020
7 Bed Preparation for R.C.C Drain & Ducting 20 12/8/2020 12/28/2020
8 Sand Filling and Compaction for R.C.C Drain 20 12/28/2020 1/17/2021
9 C.C Casting for R.C.C Drain 10 1/17/2021 1/27/2021
10 Rebar Fabrication for Drain 15 1/27/2021 2/11/2021
11 Shuttering for Drain 15 2/11/2021 2/26/2021
12 Concreting 30 2/26/2021 3/28/2021
13 Curing 30 3/28/2021 4/27/2021
14 Ducting Works 40 4/27/2021 6/6/2021
15 Excavation & Backfilling for road 30 3/28/2021 4/27/2021
16 Subgrade Preparation 30 4/27/2021 5/27/2021
17 Improved Subgrade 8 4/27/2021 5/5/2021
18 Existing Road Dismantling 10 4/27/2021 5/7/2021
19 Sub Base Preparation 11 5/7/2021 5/18/2021
20 Base-2 Preparation 30 5/18/2021 6/17/2021
21 Rebar Fabrication for R.C.C Road 12 6/17/2021 6/29/2021
22 Casting of R.C.C Road 30 6/29/2021 7/29/2021
23 Base-1 Preparation 20 6/17/2021 7/7/2021
24 Prime Coat laying 16 7/7/2021 7/23/2021
25 Bitumen Binder Course prep 30 7/23/2021 8/22/2021
26 Bitumen Tack Coat 30 8/22/2021 9/21/2021
27 Bitumen Wearing Course Prep. 20 9/21/2021 10/11/2021
28 Road Marking & Other Finishing Works 15 10/11/2021 10/26/2021
Predecessors 1 Predecessors 2 Predecessors 3
0
1
1
2 3
4
2 3 5
6
7
8
9
10
11
12
13
12
15
15
12 15
18
19
20
21
20
23
24
25
26
27
Resource Names
Asst.Surveyor, Jeep Car, Survey Equipment, Surveyor
Container, Cook, Electrical Arrangement Work Team, Jeep Car, Laptop , Motor Bike, Printer Scanner Photocopier, Site En
Civil Engineer, Project Manager, Surveyor, Asst.Surveyor
Civil Engineer, Dozer, Excavator, Site Engineer, Surveyor, Dump Truck
Asst.Surveyor, Survey Equipment, Surveyor
Civil Engineer, Project Manager
Excavator, Hand Compactor, Soil Bed Preparation Team
Hand Compactor, Sand Work Team, Water Supply Line/Water Boucher
Concrete Work Team, Concrete Mix Design Team, Lab Technician
Reinforcement Work Team
Shutter Formwork
Concrete Mix Design Team, Lab Technician
Day Labour
Ducting Material Work Team
Excavator, Sand Work Team
Dump Truck, Excavator, Hand Compactor
Dump Truck, Hand Compactor, Lab Equipment, Lab Technician, Sand Work Team
Road Dismantling Team, Dump Truck
Brick Chips Work Team, Civil Engineer, Concrete Mix Design Team, Dump Truck, Lab Technician, Sand Work Team, Site
Dump Truck, Grader, Sand Work Team, Scrafier, Steel Drum Roller/Vibratory Roller, Stone Chips Work Team, Water Supp
Civil Engineer, Reinforcement Work Team, Site Engineer, Surveyor
Civil Engineer, Concrete Work Team, Lab Technician, Shutter Formwork
Dump Truck, Grader, Sand Work Team, Scrafier, Steel Drum Roller/Vibratory Roller, Stone Chips Work Team, Water Supp
Bitumen Work Team, Bitumen Sprayer, Sand Work Team
Asphalt Work Team, Rubber Tyre Roller, Steel Drum Roller/Vibratory Roller
Bitumen Work Team
Asphalt Work Team, Rubber Tyre Roller, Steel Drum Roller/Vibratory Roller
Thermoplast Machine, Footpath and Divider Team
Resource name Type Rate

Accountant Monthly
Asphalt Work Team Team
Asst.Surveyor Monthly
Bitumen Sprayer Daily
Bitumen Tanker Daily
Bitumen Work Team Team
Brick Chips Work Team Team
Civil Engineer Monthly
Concrete Mix Design Team Team
Concrete Work Team Team
Container Project
Cook Monthly
Day Labour Daily 350
Dozer Daily
Driver Monthly
Ducting Material Work Team Team
Dump Truck Project
Electrical Arrangement Work Team Team
Electrician Monthly
Excavator Project
Footpath and Divider Team Team
Grader Daily
Hand Compactor Project
Jeep Car Project
Lab Equipment Project
Lab Technician Monthly
Labour Foreman Daily
Laptop Project
Motor Bike Project
Moving Generator Project
Paver Daily
Payloader Project
Printer Scanner Photocopier Project
Project Coordinator Monthly
Project Manager Monthly
Pump/Mud Pump Project
Reinforcement Work Team Team
Road Dismantling Team Team
Road Mix design Work Team Team
Rubber Tyre Roller Daily
Sand Work Team Team
Scrafier Daily
Security Guard Monthly
Shutter Formwork Project
Site Engineer Monthly
Soil Bed Preparation Team Team
Steel Drum Roller/Vibratory Roller Daily
Stone Chips Work Team Team
Store Keeper Monthly
Sub-Contractor NA
Survey Equipment Project
Surveyor Monthly
Thermoplast Machine Daily
Vibrator Machine Project
Water Supply Line/Water Browser Daily
Nahid Monthly
Sl No. Task id Task name
1 1 Preliminary Survey
2 1 Preliminary Survey
3 1 Preliminary Survey
4 1 Preliminary Survey
5 2 Mobilization & Site Prep
6 2 Mobilization & Site Prep
7 2 Mobilization & Site Prep
8 2 Mobilization & Site Prep
9 2 Mobilization & Site Prep
10 2 Mobilization & Site Prep
11 2 Mobilization & Site Prep
12 2 Mobilization & Site Prep
13 3 Land Acquisition
14 3 Land Acquisition
15 3 Land Acquisition
16 3 Land Acquisition
17 4 Land Acquisition
18 4 Clearing, Grubbing & Dismantling
19 4 Clearing, Grubbing & Dismantling
20 4 Clearing, Grubbing & Dismantling
21 4 Clearing, Grubbing & Dismantling
22 4 Clearing, Grubbing & Dismantling
23 4 Clearing, Grubbing & Dismantling
24 5 Survey Inspection
25 5 Survey Inspection
26 5 Survey Inspection
27 6 Final Design, Drawing etc.
28 6 Final Design, Drawing etc.
29 7 Bed Preparation for R.C.C Drain & Ducting
30 7 Bed Preparation for R.C.C Drain & Ducting
31 7 Bed Preparation for R.C.C Drain & Ducting
32 8 Sand Filling and Compaction for R.C.C Drain
33 8 Sand Filling and Compaction for R.C.C Drain
34 8 Sand Filling and Compaction for R.C.C Drain
35 9 C.C Casting for R.C.C Drain
36 9 C.C Casting for R.C.C Drain
37 9 C.C Casting for R.C.C Drain
38 10 Rebar Fabrication for Drain
39 11 Shuttering for Drain
40 12 Concreting
41 12 Concreting
42 13 Curing
43 13 Curing
44 14 Ducting Works
45 15 Excavation & Backfilling for road
46 15 Excavation & Backfilling for road
47 16 Subgrade Preparation
48 16 Subgrade Preparation
49 16 Subgrade Preparation
50 17 Improved Subgrade
51 17 Improved Subgrade
52 17 Improved Subgrade
53 17 Improved Subgrade
54 17 Improved Subgrade
55 18 Existing Road Dismantling
56 18 Existing Road Dismantling
57 18 Existing Road Dismantling
58 19 Sub Base Preparation
59 19 Sub Base Preparation
60 19 Sub Base Preparation
61 19 Sub Base Preparation
62 19 Sub Base Preparation
63 19 Sub Base Preparation
64 19 Sub Base Preparation
65 19 Sub Base Preparation
66 20 Base-2 Preparation
67 20 Base-2 Preparation
68 20 Base-2 Preparation
69 20 Base-2 Preparation
70 20 Base-2 Preparation
71 20 Base-2 Preparation
72 20 Base-2 Preparation
73 21 Rebar Fabrication for R.C.C Road
74 21 Rebar Fabrication for R.C.C Road
75 21 Rebar Fabrication for R.C.C Road
76 21 Rebar Fabrication for R.C.C Road
77 22 Casting of R.C.C Road
78 22 Casting of R.C.C Road
79 22 Casting of R.C.C Road
80 22 Casting of R.C.C Road
81 23 Base-1 Preparation
82 23 Base-1 Preparation
83 23 Base-1 Preparation
84 23 Base-1 Preparation
85 23 Base-1 Preparation
86 23 Base-1 Preparation
87 23 Base-1 Preparation
88 24 Prime Coat laying
89 24 Prime Coat laying
90 24 Prime Coat laying
91 25 Bitumen Binder Course prep
92 25 Bitumen Binder Course prep
93 25 Bitumen Binder Course prep
94 25 Bitumen Binder Course prep
95 26 Bitumen Tack Coat
96 27 Bitumen Wearing Course Prep.
97 27 Bitumen Wearing Course Prep.
98 27 Bitumen Wearing Course Prep.
99 27 Bitumen Wearing Course Prep.
100 28 Road Marking & Other Finishing Works
101 28 Road Marking & Other Finishing Works
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
Resource name Utilization % Duration (Days)
Asst.Surveyor 100 3
Jeep Car 100 3
Survey Equipment 100 3
Surveyor 100 3
Container 100 20
Cook 100 20
Electrical Arrangement Work Team 100 20
Jeep Car 100 20
Laptop 100 20
Motor Bike 100 20
Printer Scanner Photocopier 100 20
Site Engineer 100 20
Civil Engineer 100 15
Project Manager 100 15
Surveyor 100 15
Asst.Surveyor 100 15
Survey Equipment 100 15
Civil Engineer 100 30
Dozer 100 30
Excavator 100 30
Site Engineer 100 30
Surveyor 100 30
Dump Truck 100 30
Asst.Surveyor 100 5
Survey Equipment 100 5
Surveyor 100 5
Civil Engineer 100 15
Project Manager 100 15
Excavator 100 20
Hand Compactor 100 20
Soil Bed Preparation Team 100 20
Hand Compactor 100 20
Sand Work Team 100 20
Water Supply Line/Water Boucher 100 20
Concrete Work Team 100 10
Concrete Mix Design Team 100 10
Lab Technician 100 10
Reinforcement Work Team 100 15
Shutter Formwork 100 15
Concrete Mix Design Team 100 30
Lab Technician 100 30
Day Labour 100 7
Day Labour 100 30
Ducting Material Work Team 100 40
Excavator 100 30
Sand Work Team 100 30
Dump Truck 100 30
Excavator 100 30
Hand Compactor 100 30
Dump Truck 100 8
Hand Compactor 100 8
Lab Equipment 100 8
Lab Technician 100 8
Sand Work Team 100 8
Road Dismantling Team 100 10
Excavator 100 10
Dump Truck 100 10
Brick Chips Work Team 100 11
Civil Engineer 100 11
Concrete Mix Design Team 100 11
Dump Truck 100 11
Lab Technician 100 11
Sand Work Team 100 11
Site Engineer 100 11
Steel Drum Roller/Vibratory Roller 100 11
Dump Truck 100 30
Grader 100 30
Sand Work Team 100 30
Scrafier 100 30
Steel Drum Roller/Vibratory Roller 100 30
Stone Chips Work Team 100 30
Water Supply Line/Water Boucher 100 30
Civil Engineer 100 12
Reinforcement Work Team 100 12
Site Engineer 100 12
Surveyor 100 12
Civil Engineer 100 30
Concrete Work Team 100 30
Lab Technician 100 30
Shutter Formwork 100 30
Dump Truck 100 20
Grader 100 20
Sand Work Team 100 20
Scrafier 100 20
Steel Drum Roller/Vibratory Roller 100 20
Stone Chips Work Team 100 20
Water Supply Line/Water Boucher 100 20
Bitumen Work Team 100 16
Bitumen Sprayer 100 16
Sand Work Team 100 16
Asphalt Work Team 100 30
Road Mix design Work Team 100 30
Rubber Tyre Roller 100 30
Steel Drum Roller/Vibratory Roller 100 30
Bitumen Work Team 100 30
Asphalt Work Team 100 20
Road Mix design Work Team 100 20
Rubber Tyre Roller 100 20
Steel Drum Roller/Vibratory Roller 100 20
Thermoplast Machine 100 15
Footpath and Divider Team 100 15
Resources
Asst.Surveyor
Asst.Surveyor, Jeep Car
Asst.Surveyor, Jeep Car, Survey Equipment
Asst.Surveyor, Jeep Car, Survey Equipment, Surveyor
Container
Container, Cook
Container, Cook, Electrical Arrangement Work Team
Container, Cook, Electrical Arrangement Work Team, Jeep Car
Container, Cook, Electrical Arrangement Work Team, Jeep Car, Laptop
Container, Cook, Electrical Arrangement Work Team, Jeep Car, Laptop , Motor Bike
Container, Cook, Electrical Arrangement Work Team, Jeep Car, Laptop , Motor Bike, Printer Scanner Photocopier
Container, Cook, Electrical Arrangement Work Team, Jeep Car, Laptop , Motor Bike, Printer Scanner Photocopier, Site En
Civil Engineer
Civil Engineer, Project Manager
Civil Engineer, Project Manager, Surveyor
Civil Engineer, Project Manager, Surveyor, Asst.Surveyor
Civil Engineer, Project Manager, Surveyor, Asst.Surveyor, Survey Equipment
Civil Engineer
Civil Engineer, Dozer
Civil Engineer, Dozer, Excavator
Civil Engineer, Dozer, Excavator, Site Engineer
Civil Engineer, Dozer, Excavator, Site Engineer, Surveyor
Civil Engineer, Dozer, Excavator, Site Engineer, Surveyor, Dump Truck
Asst.Surveyor
Asst.Surveyor, Survey Equipment
Asst.Surveyor, Survey Equipment, Surveyor
Civil Engineer
Civil Engineer, Project Manager
Excavator
Excavator, Hand Compactor
Excavator, Hand Compactor, Soil Bed Preparation Team
Hand Compactor
Hand Compactor, Sand Work Team
Hand Compactor, Sand Work Team, Water Supply Line/Water Boucher
Concrete Work Team
Concrete Work Team, Concrete Mix Design Team
Concrete Work Team, Concrete Mix Design Team, Lab Technician
Reinforcement Work Team
Shutter Formwork
Concrete Mix Design Team
Concrete Mix Design Team, Lab Technician
Day Labour
Day Labour
Ducting Material Work Team
Excavator
Excavator, Sand Work Team
Dump Truck
Dump Truck, Excavator
Dump Truck, Excavator, Hand Compactor
Dump Truck
Dump Truck, Hand Compactor
Dump Truck, Hand Compactor, Lab Equipment
Dump Truck, Hand Compactor, Lab Equipment, Lab Technician
Dump Truck, Hand Compactor, Lab Equipment, Lab Technician, Sand Work Team
Road Dismantling Team
Road Dismantling Team, Excavator
Road Dismantling Team, Dump Truck
Brick Chips Work Team
Brick Chips Work Team, Civil Engineer
Brick Chips Work Team, Civil Engineer, Concrete Mix Design Team
Brick Chips Work Team, Civil Engineer, Concrete Mix Design Team, Dump Truck
Brick Chips Work Team, Civil Engineer, Concrete Mix Design Team, Dump Truck, Lab Technician
Brick Chips Work Team, Civil Engineer, Concrete Mix Design Team, Dump Truck, Lab Technician, Sand Work Team
Brick Chips Work Team, Civil Engineer, Concrete Mix Design Team, Dump Truck, Lab Technician, Sand Work Team, Site
Brick Chips Work Team, Civil Engineer, Concrete Mix Design Team, Dump Truck, Lab Technician, Sand Work Team, Site
Dump Truck
Dump Truck, Grader
Dump Truck, Grader, Sand Work Team
Dump Truck, Grader, Sand Work Team, Scrafier
Dump Truck, Grader, Sand Work Team, Scrafier, Steel Drum Roller/Vibratory Roller
Dump Truck, Grader, Sand Work Team, Scrafier, Steel Drum Roller/Vibratory Roller, Stone Chips Work Team
Dump Truck, Grader, Sand Work Team, Scrafier, Steel Drum Roller/Vibratory Roller, Stone Chips Work Team, Water Supp
Civil Engineer
Civil Engineer, Reinforcement Work Team
Civil Engineer, Reinforcement Work Team, Site Engineer
Civil Engineer, Reinforcement Work Team, Site Engineer, Surveyor
Civil Engineer
Civil Engineer, Concrete Work Team
Civil Engineer, Concrete Work Team, Lab Technician
Civil Engineer, Concrete Work Team, Lab Technician, Shutter Formwork
Dump Truck
Dump Truck, Grader
Dump Truck, Grader, Sand Work Team
Dump Truck, Grader, Sand Work Team, Scrafier
Dump Truck, Grader, Sand Work Team, Scrafier, Steel Drum Roller/Vibratory Roller
Dump Truck, Grader, Sand Work Team, Scrafier, Steel Drum Roller/Vibratory Roller, Stone Chips Work Team
Dump Truck, Grader, Sand Work Team, Scrafier, Steel Drum Roller/Vibratory Roller, Stone Chips Work Team, Water Supp
Bitumen Work Team
Bitumen Work Team, Bitumen Sprayer
Bitumen Work Team, Bitumen Sprayer, Sand Work Team
Asphalt Work Team
Asphalt Work Team, Road Mix design Work Team
Asphalt Work Team, Rubber Tyre Roller
Asphalt Work Team, Rubber Tyre Roller, Steel Drum Roller/Vibratory Roller
Bitumen Work Team
Asphalt Work Team
Asphalt Work Team, Road Mix design Work Team
Asphalt Work Team, Rubber Tyre Roller
Asphalt Work Team, Rubber Tyre Roller, Steel Drum Roller/Vibratory Roller
Thermoplast Machine
Thermoplast Machine, Footpath and Divider Team
bratory Roller
###
###
###
###
Project Start Date 10/1/2020 10/26/2021

###
Week Required 0 55.71

1
2
3
1 Preliminary Survey 10/1/2020 10/4/2020 1
2 Mobilization & Site Prep
3 Land Acquisition 10/4/2020 10/19/2020 1 1
4 Clearing, Grubbing & Dismantling 10/19/2020 11/18/2020 1
5 Survey Inspection 11/18/2020 11/23/2020
6 Final Design, Drawing etc. 11/23/2020 12/8/2020
7 Bed Preparation for R.C.C Drain & Ducting 12/8/2020 12/28/2020
8 Sand Filling and Compaction for R.C.C Drain 12/28/2020 1/17/2021
9 C.C Casting for R.C.C Drain 1/17/2021 1/27/2021
10 Rebar Fabrication for Drain 1/27/2021 2/11/2021
11 Shuttering for Drain 2/11/2021 2/26/2021
12 Concreting 2/26/2021 3/28/2021
13 Curing 3/28/2021 4/27/2021
14 Ducting Works 4/27/2021 6/6/2021
15 Excavation & Backfilling for road 3/28/2021 4/27/2021
16 Subgrade Preparation 4/27/2021 5/27/2021
17 Improved Subgrade 4/27/2021 5/5/2021
18 Existing Road Dismantling 4/27/2021 5/7/2021
19 Sub Base Preparation 5/7/2021 5/18/2021
20 Base-2 Preparation 5/18/2021 6/17/2021
21 Rebar Fabrication for R.C.C Road 6/17/2021 6/29/2021
22 Casting of R.C.C Road 6/29/2021 7/29/2021
23 Base-1 Preparation 6/17/2021 7/7/2021
24 Prime Coat laying 7/7/2021 7/23/2021
25 Bitumen Binder Course prep 7/23/2021 8/22/2021
26 Bitumen Tack Coat 8/22/2021 9/21/2021
27 Bitumen Wearing Course Prep. 9/21/2021 10/11/2021
28 28 Road Marking & Other Finishing Works 10/11/2021 10/26/2021
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
4 ###
5 ###

1 1 1
6 ###

1
7 ###
8 ###

1 1
9 ###
### ###
### ###

1 1 1
### ###
### ###
### ###

1 1 1
### ###

1
### ###
### ###
### ###

1 1 1
### ###
### ###

1 1 1
### ###
### ###
### ###
### ###

1 1 1 1
### ###
### ###
### ###
### ###

1 1 1 1
1 1 1 1
### ###

1
### ###

1 1
### ###

1
### ###
### ###
1 1 1 1 1

### ###
1 1 1 1 1 1

### ###
### ###
1 1 1 1 1 ### ###
1 1 ### ###

1 1 1
### ###
### ###
### ###
1 1 1 ### ###
1 1 1 1 1

### ###
### ###
### ###
1 1 1 1

### ###
### ###
### ###
### ###
1 1 1 1

### ###
1

### ###
### ###

1 1
### ###
### ###

1 1
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
Quantity

Sum of Quantity
Sub Item
0.18mm thick polythene sheet
18/20/22 BWG MS Sheet/plate
1st Class Brick
1st Class Brick Chips (20mm down graded)
1st Class Picked Brick Chips (20mm down graded)
1st Class/ Picked Brick chips (40mm down graded)
300mmx300mmx25mm high load bearing parking Tiles
75mm PVC Pipe -2.9mm to 3.4mm wall thick
AC Paver
All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc. ( +22.00 % on Subtotal-A )
Asphalt Plant
Bitumen [Grade 60/70]
Bitumen [Grade 80/100]
Bitumen [Grade 80/100]
Diesel
Electrode
Empty Gunny Bag
Fire wood
Foreman
Geo Textile (Grade-I-DF-20-1.5mm thick)
GI Wire (22 BWG)
H. C. of Thermoplastic Appilicator Machine
H.C. of 3 Wheel Static Road roller (8-10 ton)
H.C. of Backhoe End Loader (6 tons)
H.C. of Casing
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)
H.C. of Distributor
H.C. of Driving Equipment
H.C. of Dump Truck/ Tripping Trucks
H.C. of Excavator (Medium Size)
H.C. of Flat Body Truck (3 tons)
H.C. of Grinding Machine
H.C. of Mixing Machine for Aggregate
H.C. of Motor Graders (14 tons)
H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)
H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost
H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories
H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (3-5 tons)
H.C. of Vibratory Road Roller (8-10 ton)
H.C. of Water Pump
H.C. of Water Tanker (Towed by Tractor)
H.C. of Water Tanker (Truck Mounted)
H.C. of Welding Machine
Head Mason
Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/Operator
Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/Operator
Hire and running charges of Batching and Mixing Plant @ 20 cum/hour
Hire and running charges of Concrete Pump (30 & 45 cum capacity)
Hire and running charges of Concrete Vibrator
Kerosene
Lubricant
M.S. Ribbed/ Deformed Bar (Grade 400)
Manufacturing and supplying CC blocks (3.09.5.2)
Manufacturing and supplying CC blocks (3.09.5.3)
Mason
MS Angle 25mmx25mmx3mm
MS Angle, Flat bar, Z bar
Operator
Ordinary Labour
Plumber/ Electric Mistry/ Painter
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)
Re-bar Fabricator
Reflectorising Glass Beads
Royalty of Earth
Royalty of Earth (Within Municipal Area)
Sand (FM - 0.5)
Sand (FM - 0.8)
Sand (FM - 1.2)
Sand (FM - 1.5)
Sand (FM - 1.8)
Sand (FM - 2.5)
Sardar
Skilled Labour
Stackyard Rent
Stone Chips (12mm down graded) [LAA≤25]
Stone Chips (12mm down graded) [LAA≤30]
Stone Chips (12mm down graded) [LAA≤35]
Stone Chips (16mm down graded) [LAA≤35]
Stone Chips (20mm down graded) [LAA≤35]
Stone Chips (25mm down graded) [LAA≤35]
Stone Chips (25mm down graded)[LAA≤30]
Stone Chips (38mm down graded) [LAA≤35]
Stone Chips (6mm down graded) [LAA≤35]
Stone Dust (2.38mm down)
Stone Shingles (20mm down graded)
Synthetic Enamel Paint
Synthetic enamel paint primer/ sealer
Thermoplastic Compound
Turf
uuPVC Pipe 50mm dia of 2.5mm to 3.0mm wall thick
Water reducing chemical admixture : Type-A
Welder
(blank)

Grand Total
(All)

Unit Type Total


m2 27543.9
kg 252.8
each 590804.8
m3 4201.0
m3 4714.1
m3 4609.8
sqm 7200.7
m 644.4
day 86.3
ls 643.2
day 86.3
kg 145148.4
kg 9712.1
kg 9591.2
liter 40860.8
pkt 5.8
each 1074.0
kg 15739.5
day 112.0
m2 3988.4
kg 11706.5
day 42.4
day 41.6
day 34.2
day 12.5
day 526.9
day 7.2
day 12.5
day 404.4
day 57.5
day 810.7
day 7.6
day 34.7
day 17.4
day 86.3
day 82.5
day 12.5
day 86.3
day 770.3
day 71.3
day 71.3
day 17.4
day 7.6
day 2666.1
day 265.6
day 106.9
day 34.2
day 34.2
day 742.9
liter 4795.6
liter 2539.7
kg 1194058.9
each 7950.0
each 4918.0
day 8196.1
kg 371.5
kg 16375.4
day 65.1
day 66388.1
day 265.6
bag 87870.1
day 3511.9
kg 370.6
m3 1671.9
m3 50666.1
m3 2590.0
m3 14622.9
m3 964.7
m3 326.8
m3 1228.7
m3 3586.3
day 180.9
day 18343.1
m3 8683.3
cum 642.7
m3 1348.9
cum 2763.0
cum 408.1
cum 4174.0
cum 283.2
cum 2025.4
cum 1144.2
cum 493.0
cum 323.1
m3 737.5
liter 295.1
liter 221.3
kg 7412.3
m2 2985.6
m 643.2
liter 8317.8
day 10.2
0 0.0
(blank)
2420561.2
Sl No Per Tender Sl No Per LGED Unit Type Quantity
1 6.01.18 LS
2 4.01.05.02 LS
3 LS
4 LS
5 LS
6 LS
7 LS
8 2.01.1 SQM 12786.8
8 2.01.1 SQM 12786.8
9 3.10.01.2 SQM 8204
9 3.10.01.2 SQM 8204
9 3.10.01.2 SQM 8204
9 3.10.01.2 SQM 8204
9 3.10.01.2 SQM 8204
9 3.10.01.2 SQM 8204
10 3.01.4.3 SQM 21591.5
10 3.01.4.3 SQM 21591.5
10 3.01.4.3 SQM 21591.5
10 3.01.4.3 SQM 21591.5
10 3.01.4.3 SQM 21591.5
10 3.01.4.3 SQM 21591.5
10 3.01.4.3 SQM 21591.5
11 4.05.01.01.01 CUM 2975
11 4.05.01.01.01 CUM 2975
12 3.02.1.2 CUM 9978.801
12 3.02.1.2 CUM 9978.801
12 3.02.1.2 CUM 9978.801
12 3.02.1.2 CUM 9978.801
12 3.02.1.2 CUM 9978.801
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
13 3.03.4.1 CUM 5397.876
14 3.04.3.2 M 1966
14 3.04.3.2 M 1966
14 3.04.3.2 M 1966
14 3.04.3.2 M 1966
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
15 3.05.7.2 CUM 6285.5
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
16 3.05.8.2 CUM 2397.8
17 3.06.1.2 SQM 11989
17 3.06.1.2 SQM 11989
17 3.06.1.2 SQM 11989
17 3.06.1.2 SQM 11989
17 3.06.1.2 SQM 11989
17 3.06.1.2 SQM 11989
17 3.06.1.2 SQM 11989
17 3.06.1.2 SQM 11989
17 3.06.1.2 SQM 11989
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
18 3.06.8.1 CUM 839.23
19 3.06.2.4 SQM 11989
19 3.06.2.4 SQM 11989
19 3.06.2.4 SQM 11989
19 3.06.2.4 SQM 11989
19 3.06.2.4 SQM 11989
19 3.06.2.4 SQM 11989
19 3.06.2.4 SQM 11989
19 3.06.2.4 SQM 11989
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
20 3.06.7.2 CUM 599.45
21 3.08.4.1 SQM 1717.5
21 3.08.4.1 SQM 1717.5
21 3.08.4.1 SQM 1717.5
21 3.08.4.1 SQM 1717.5
22 3.07.1 SQM 18217.5
22 3.07.1 SQM 18217.5
23 5.03.05.01 CUM 313.244
23 5.03.05.01 CUM 313.244
23 5.03.05.01 CUM 313.244
23 5.03.05.01 CUM 313.244
23 5.03.05.01 CUM 313.244
23 5.03.05.01 CUM 313.244
23 5.03.05.01 CUM 313.244
23 5.03.05.01 CUM 313.244
23 5.03.05.01 CUM 313.244
24 4.06.05.02 CUM 1256.252
24 4.06.05.02 CUM 1256.252
24 4.06.05.02 CUM 1256.252
24 4.06.05.02 CUM 1256.252
24 4.06.05.02 CUM 1256.252
24 4.06.05.02 CUM 1256.252
24 4.06.05.02 CUM 1256.252
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
25 3.07.3.2 CUM 4125
26 4.11.01.02 KG 377105.1
26 4.11.01.02 KG 377105.1
26 4.11.01.02 KG 377105.1
26 4.11.01.02 KG 377105.1
26 4.11.01.02 KG 377105.1
27 3.09.6.2 M 4918
27 3.09.6.2 M 4918
27 3.09.6.2 M 4918
27 3.09.6.2 M 4918
28 2.02.3.06 CUM 40532.89
28 2.02.3.06 CUM 40532.89
28 2.02.3.06 CUM 40532.89
28 2.02.3.06 CUM 40532.89
28 2.02.3.06 CUM 40532.89
28 2.02.3.06 CUM 40532.89
28 2.02.3.06 CUM 40532.89
29 3.11.13 M 50
30 2.06.1 SQM 2985.6
30 2.06.1 SQM 2985.6
31 3.11.11.1 SQM 3727.5
31 3.11.11.1 SQM 3727.5
31 3.11.11.1 SQM 3727.5
32 6.06.01.04 EACH 39406
32 6.06.01.04 EACH 39406
32 6.06.01.04 EACH 39406
32 6.06.01.04 EACH 39406
32 6.06.01.04 EACH 39406
32 6.06.01.04 EACH 39406
32 6.06.01.04 EACH 39406
33 6.06.06 CUM 551.684
33 6.06.06 CUM 551.684
33 6.06.06 CUM 551.684
34 5.16.10.01 SQM 2459
34 5.16.10.01 SQM 2459
34 5.16.10.01 SQM 2459
34 5.16.10.01 SQM 2459
35 3.12.08 SQM 1482.45
35 3.12.08 SQM 1482.45
35 3.12.08 SQM 1482.45
35 3.12.08 SQM 1482.45
35 3.12.08 SQM 1482.45
35 3.12.08 SQM 1482.45
36 3.12.01.1 EACH 4
37 3.12.03 SQM 25.383
37 3.12.03 SQM 25.383
37 3.12.03 SQM 25.383
37 3.12.03 SQM 25.383
37 3.12.03 SQM 25.383
37 3.12.03 SQM 25.383
37 3.12.03 SQM 25.383
37 3.12.03 SQM 25.383
37 3.12.03 SQM 25.383
38 3.12.01.2 EACH 1
39 6.13.06.1 M 1331
39 6.13.06.1 M 1331
39 6.13.06.1 M 1331
39 6.13.06.1 M 1331
39 6.13.06.1 M 1331
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
40 4.09.02.01 CUM 25
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
41 4.09.02.02.01 CUM 39.752
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
42 4.09.02.03.01 CUM 22.6
43 3.09.6.1 M 3000
43 3.09.6.1 M 3000
43 3.09.6.1 M 3000
43 3.09.6.1 M 3000
44 2.02.2.1 CUM 1492.8
44 2.02.2.1 CUM 1492.8
44 2.02.2.1 CUM 1492.8
45 4.05.01.01.01 CUM 17532.48
45 4.05.01.01.01 CUM 17532.48
45 4.05.01.01.01 CUM 17532.48
45 4.05.01.01.01 CUM 17532.48
45 4.05.01.01.01 CUM 17532.48
45 4.05.01.01.01 CUM 17532.48
45 4.05.01.01.01 CUM 17532.48
46 3.02.1.1 CUM 1398.96
46 3.02.1.1 CUM 1398.96
46 3.02.1.1 CUM 1398.96
46 3.02.1.1 CUM 1398.96
46 3.02.1.1 CUM 1398.96
47 3.07.1 SQM 9326.4
47 3.07.1 SQM 9326.4
48 5.03.05.01 CUM 699.479
48 5.03.05.01 CUM 699.479
48 5.03.05.01 CUM 699.479
48 5.03.05.01 CUM 699.479
48 5.03.05.01 CUM 699.479
48 5.03.05.01 CUM 699.479
48 5.03.05.01 CUM 699.479
48 5.03.05.01 CUM 699.479
48 5.03.05.01 CUM 699.479
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
49 4.09.02.01 CUM 1865.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
50 4.09.02.02.01 CUM 3056.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
51 4.09.02.03.01 CUM 1865.28
52 4.11.01.02 KG 793540.9
52 4.11.01.02 KG 793540.9
52 4.11.01.02 KG 793540.9
52 4.11.01.02 KG 793540.9
52 4.11.01.02 KG 793540.9
53 7.08.01.02 M 643.2
53 7.08.01.02 M 643.2
54 4.13.04 EACH 1074
54 4.13.04 EACH 1074
54 4.13.04 EACH 1074
54 4.13.04 EACH 1074
54 4.13.04 EACH 1074
55 2.01.02 EACH 418
55 2.01.02 EACH 418
55 2.01.02 EACH 418
55 2.01.02 EACH 418
55 2.01.02 EACH 418
55 2.01.02 EACH 418
55 2.01.02 EACH 418
55 2.01.02 EACH 418
55 2.01.02 EACH 418
55 2.01.02 EACH 418
55 2.01.02 EACH 418
56 3.09.7.1 EACH 8577
56 3.09.7.1 EACH 8577
56 3.09.7.1 EACH 8577
56 3.09.7.1 EACH 8577
56 3.09.7.1 EACH 8577
56 3.09.7.1 EACH 8577
56 3.09.7.1 EACH 8577
56 3.09.7.1 EACH 8577
56 3.09.7.1 EACH 8577
57 5.21.05.05 SQM 7200.7
57 5.21.05.05 SQM 7200.7
57 5.21.05.05 SQM 7200.7
57 5.21.05.05 SQM 7200.7
57 5.21.05.05 SQM 7200.7
57 5.21.05.05 SQM 7200.7
57 5.21.05.05 SQM 7200.7
58 5.06.05 KG 16054.27
59 3.09.5.3 EACH 3216
59 3.09.5.3 EACH 3216
59 3.09.5.3 EACH 3216
59 3.09.5.3 EACH 3216
59 3.09.5.3 EACH 3216
59 3.09.5.3 EACH 3216
59 3.09.5.3 EACH 3216
59 3.09.5.3 EACH 3216
60 3.09.9 CUM 111.501
60 3.09.9 CUM 111.501
60 3.09.9 CUM 111.501
60 3.09.9 CUM 111.501
60 3.09.9 CUM 111.501
60 3.09.9 CUM 111.501
61 4.05.03
Sub Item Unit Type

Sardar day
Ordinary Labour day
Skilled Labour day
Ordinary Labour day
H.C. of Excavator (Medium Size) day
H.C. of 3 Wheel Static Road roller (8-10 ton) day
Diesel liter
Lubricant liter
Mason day
Ordinary Labour day
H.C. of Water Tanker (Towed by Tractor) day
H.C. of Water Pump day
H.C. of 3 Wheel Static Road roller (8-10 ton) day
Diesel liter
Lubricant liter
Mason day
Ordinary Labour day
Sand (FM - 0.8) m3
Ordinary Labour day
H.C. of Vibratory Road Roller (8-10 ton) day
Diesel liter
Lubricant liter
1st Class/ Picked Brick chips (40mm down graded) m3
1st Class Brick Chips (20mm down graded) m3
Sand (FM - 0.8) m3
Ordinary Labour day
Skilled Labour day
Mason day
Diesel liter
Lubricant liter
H.C. of Vibratory Road Roller (8-10 ton) day
H.C. of Water Tanker (Towed by Tractor) day
H.C. of Water Pump day
1st Class Brick each
Sand (FM - 0.5) m3
Mason day
Ordinary Labour day
1st Class/ Picked Brick chips (40mm down graded) m3
1st Class Picked Brick Chips (20mm down graded) m3
Sand (FM - 0.5) m3
Ordinary Labour day
Skilled Labour day
Head Mason day
H.C. of Mixing Machine for Aggregate day
H.C. of Dump Truck/ Tripping Trucks day
H.C. of Motor Graders (14 tons) day
H.C. of Vibratory Road Roller (8-10 ton) day
H.C. of Water Tanker (Truck Mounted) day
Stackyard Rent m3
Diesel liter
Lubricant liter
Stone Chips (38mm down graded) [LAA≤35] cum
Stone Chips (20mm down graded) [LAA≤35] cum
Stone Chips (12mm down graded) [LAA≤35] cum
Sand (FM - 0.8) m3
Ordinary Labour day
Skilled Labour day
Head Mason day
H.C. of Mixing Machine for Aggregate day
H.C. of Dump Truck/ Tripping Trucks day
H.C. of Motor Graders (14 tons) day
H.C. of Vibratory Road Roller (8-10 ton) day
H.C. of Water Tanker (Truck Mounted) day
Stackyard Rent m3
Diesel liter
Lubricant liter
Bitumen [Grade 80/100] kg
Fire wood kg
Kerosene liter
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Distributor day
Diesel liter
Lubricant liter
Stone Chips (16mm down graded) [LAA≤35] cum
Stone Chips (12mm down graded) [LAA≤35] cum
Stone Chips (6mm down graded) [LAA≤35] cum
Stone Dust (2.38mm down) cum
Bitumen [Grade 60/70] kg
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons) day
H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (3-5 tons) day
Diesel liter
Lubricant liter
Foreman day
Asphalt Plant day
AC Paver day
H.C. of Dump Truck/ Tripping Trucks day
Stone Chips (25mm down graded) [LAA≤35] cum
Bitumen [Grade 80/100] kg
Fire wood kg
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Distributor day
Diesel liter
Lubricant liter
Stone Chips (16mm down graded) [LAA≤35] cum
Stone Chips (12mm down graded) [LAA≤35] cum
Stone Chips (6mm down graded) [LAA≤35] cum
Stone Dust (2.38mm down) cum
Bitumen [Grade 60/70] kg
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons) day
H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (3-5 tons) day
Diesel liter
Lubricant liter
Foreman day
Asphalt Plant day
AC Paver day
H.C. of Dump Truck/ Tripping Trucks day
1st Class Brick each
Sand (FM - 0.5) m3
Mason day
Ordinary Labour day
0.18mm thick polythene sheet m2
Ordinary Labour day
1st Class Brick Chips (20mm down graded) m3
Sand (FM - 1.2) m3
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
1st Class Brick each
Sand (FM - 1.2) m3
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
Stone Chips (25mm down graded)[LAA≤30] cum
Stone Chips (12mm down graded) [LAA≤30] m3
Sand (FM - 2.5) m3
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
Hire and running charges of Batching and Mixing Plant @ 20 cum/hour day
Hire and running charges of Concrete Vibrator day
H.C. of Backhoe End Loader (6 tons) day
Hire and running charges of Concrete Pump (30 & 45 cum capacity) day
H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost day
Diesel liter
M.S. Ribbed/ Deformed Bar (Grade 400) kg
GI Wire (22 BWG) kg
Re-bar Fabricator day
Skilled Labour day
Ordinary Labour day
Manufacturing and supplying CC blocks (3.09.5.3) each
Sand (FM - 0.5) m3
Mason day
Ordinary Labour day
Royalty of Earth (Within Municipal Area) m3
Ordinary Labour day
Sardar day
H.C. of Flat Body Truck (3 tons) day
Diesel liter
Lubricant liter
H.C. of Vibratory Road Roller (8-10 ton) day
0
Turf m2
Ordinary Labour day
Geo Textile (Grade-I-DF-20-1.5mm thick) m2
Skilled Labour day
Ordinary Labour day
Stone Shingles (20mm down graded) m3
Sand (FM - 1.5) m3
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Mason day
Skilled Labour day
Ordinary Labour day
Synthetic Enamel Paint liter
Synthetic enamel paint primer/ sealer liter
Plumber/ Electric Mistry/ Painter day
Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/Operator day
Thermoplastic Compound kg
Reflectorising Glass Beads kg
H. C. of Thermoplastic Appilicator Machine day
Foreman day
Skilled Labour day
Ordinary Labour day
0
18/20/22 BWG MS Sheet/plate kg
MS Angle 25mmx25mmx3mm kg
Electrode pkt
Foreman day
Welder day
Skilled Labour day
Ordinary Labour day
H.C. of Welding Machine day
H.C. of Grinding Machine day
0
Sand (FM - 2.5) m3
Bitumen [Grade 80/100] kg
Fire wood kg
Skilled Labour day
Ordinary Labour day
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Stone Chips (20mm down graded) [LAA≤35] cum
Stone Chips (12mm down graded) [LAA≤25] cum
Sand (FM - 2.5) m3
Sand (FM - 1.8) m3
Water reducing chemical admixture : Type-A liter
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Stone Chips (20mm down graded) [LAA≤35] cum
Stone Chips (12mm down graded) [LAA≤35] cum
Sand (FM - 2.5) m3
Sand (FM - 1.8) m3
Water reducing chemical admixture : Type-A liter
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Stone Chips (20mm down graded) [LAA≤35] cum
Stone Chips (12mm down graded) [LAA≤35] cum
Sand (FM - 2.5) m3
Sand (FM - 1.8) m3
Water reducing chemical admixture : Type-A liter
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
Manufacturing and supplying CC blocks (3.09.5.2) each
Sand (FM - 0.5) m3
Mason day
Ordinary Labour day
Royalty of Earth m3
Sardar day
Ordinary Labour day
Skilled Labour day
Ordinary Labour day
Operator day
Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/Operator day
H.C. of Excavator (Medium Size) day
Diesel liter
Lubricant liter
Sand (FM - 0.5) m3
Ordinary Labour day
H.C. of Vibratory Road Roller (8-10 ton) day
Diesel liter
Lubricant liter
0.18mm thick polythene sheet m2
Ordinary Labour day
1st Class Brick Chips (20mm down graded) m3
Sand (FM - 1.2) m3
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Stone Chips (20mm down graded) [LAA≤35] cum
Stone Chips (12mm down graded) [LAA≤25] cum
Sand (FM - 2.5) m3
Sand (FM - 1.8) m3
Water reducing chemical admixture : Type-A liter
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Stone Chips (20mm down graded) [LAA≤35] cum
Stone Chips (12mm down graded) [LAA≤35] cum
Sand (FM - 2.5) m3
Sand (FM - 1.8) m3
Water reducing chemical admixture : Type-A liter
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Stone Chips (20mm down graded) [LAA≤35] cum
Stone Chips (12mm down graded) [LAA≤35] cum
Sand (FM - 2.5) m3
Sand (FM - 1.8) m3
Water reducing chemical admixture : Type-A liter
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
M.S. Ribbed/ Deformed Bar (Grade 400) kg
GI Wire (22 BWG) kg
Re-bar Fabricator day
Skilled Labour day
Ordinary Labour day
uuPVC Pipe 50mm dia of 2.5mm to 3.0mm wall thick m
remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc. ( +22.00 % on Subtotal-A
ls )
1st Class Brick Chips (20mm down graded) m3
75mm PVC Pipe -2.9mm to 3.4mm wall thick m
Sand (FM - 0.8) m3
Empty Gunny Bag each
Skilled Labour day
Stone Shingles (20mm down graded) m3
Sand (FM - 2.5) m3
H.C. of Casing day
H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories day
H.C. of Driving Equipment day
Operator day
Foreman day
Skilled Labour day
Ordinary Labour day
Diesel liter
Lubricant liter
Stone Chips (38mm down graded) [LAA≤35] cum
Stone Chips (16mm down graded) [LAA≤35] cum
Sand (FM - 1.8) m3
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
300mmx300mmx25mm high load bearing parking Tiles sqm
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Sand (FM - 1.2) m3
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
MS Angle, Flat bar, Z bar kg
Stone Shingles (20mm down graded) m3
Sand (FM - 1.5) m3
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Mason day
Skilled Labour day
Ordinary Labour day
H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum) day
Hire and running charges of Concrete Vibrator day
Sand (FM - 1.2) m3
Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) bag
Head Mason day
Mason day
Skilled Labour day
Ordinary Labour day
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Quantity Rate Total Sub Item Quantity

13 800 10229 Sardar 0.001


256 370 94622 Ordinary Labour 0.02
45 450 20305 Skilled Labour 0.0055
230 370 84993 Ordinary Labour 0.028
5 8880 43711 H.C. of Excavator (Medium Size) 0.0006
5 3500 17228 H.C. of 3 Wheel Static Road roller (8-10 ton) 0.0006
123 68 8368 Diesel 0.015
8 220 1805 Lubricant 0.001
432 550 237507 Mason 0.02
4750 370 1757548 Ordinary Labour 0.22
17 1500 25910 H.C. of Water Tanker (Towed by Tractor) 0.0008
17 500 8637 H.C. of Water Pump 0.0008
37 3500 128469 H.C. of 3 Wheel Static Road roller (8-10 ton) 0.0017
356 68 24226 Diesel 0.0165
35 220 7600 Lubricant 0.0016
74 550 40906 Mason 0.025
893 370 330225 Ordinary Labour 0.3
11476 480 5508298 Sand (FM - 0.8) 1.15
998 370 369216 Ordinary Labour 0.1
80 3000 239491 H.C. of Vibratory Road Roller (8-10 ton) 0.008
399 68 27142 Diesel 0.04
35 220 7684 Lubricant 0.0035
1781 2786 4962699 1st Class/ Picked Brick chips (40mm down graded) 0.33
3239 2940 9521853 1st Class Brick Chips (20mm down graded) 0.6
2159 480 1036392 Sand (FM - 0.8) 0.4
2699 370 998607 Ordinary Labour 0.5
1188 450 534390 Skilled Labour 0.22
54 550 29688 Mason 0.01
648 68 44047 Diesel 0.12
54 220 11875 Lubricant 0.01
54 3000 161936 H.C. of Vibratory Road Roller (8-10 ton) 0.01
54 1500 80968 H.C. of Water Tanker (Towed by Tractor) 0.01
54 500 26989 H.C. of Water Pump 0.01
27524 9 247716 1st Class Brick 14
10 420 4129 Sand (FM - 0.5) 0.005
8 550 4325 Mason 0.004
59 370 21823 Ordinary Labour 0.03
2828 2786 7880131 1st Class/ Picked Brick chips (40mm down graded) 0.45
4714 2940 13859528 1st Class Picked Brick Chips (20mm down graded) 0.75
943 420 395987 Sand (FM - 0.5) 0.15
1886 370 697691 Ordinary Labour 0.3
1257 450 565695 Skilled Labour 0.2
31 650 20428 Head Mason 0.005
25 8000 201136 H.C. of Mixing Machine for Aggregate 0.004
189 4500 848543 H.C. of Dump Truck/ Tripping Trucks 0.03
13 6000 75426 H.C. of Motor Graders (14 tons) 0.002
189 3000 565695 H.C. of Vibratory Road Roller (8-10 ton) 0.03
13 2500 31428 H.C. of Water Tanker (Truck Mounted) 0.002
6286 6 40730 Stackyard Rent 1
5028 68 341931 Diesel 0.8
377 220 82969 Lubricant 0.06
1079 4850 5233199 Stone Chips (38mm down graded) [LAA≤35] 0.45
599 4930 2955289 Stone Chips (20mm down graded) [LAA≤35] 0.25
575 4320 2486039 Stone Chips (12mm down graded) [LAA≤35] 0.24
959 480 460378 Sand (FM - 0.8) 0.4
719 370 266156 Ordinary Labour 0.3
480 450 215802 Skilled Labour 0.2
12 650 7793 Head Mason 0.005
10 8000 76730 H.C. of Mixing Machine for Aggregate 0.004
72 4500 323703 H.C. of Dump Truck/ Tripping Trucks 0.03
5 6000 28774 H.C. of Motor Graders (14 tons) 0.002
72 3000 215802 H.C. of Vibratory Road Roller (8-10 ton) 0.03
5 2500 11989 H.C. of Water Tanker (Truck Mounted) 0.002
2398 6 15538 Stackyard Rent 1
1918 68 130440 Diesel 0.8
144 220 31651 Lubricant 0.06
9591 66 633019 Bitumen [Grade 80/100] 0.8
7673 8 61384 Fire wood 0.64
4796 72 345283 Kerosene 0.4
1 750 899 Mason 0.0001
12 650 7793 Skilled Labour 0.001
72 370 26616 Ordinary Labour 0.006
4 3750 13488 H.C. of Distributor 0.0003
30 68 2038 Diesel 0.0025
4 220 791 Lubricant 0.0003
170 4720 802136 Stone Chips (16mm down graded) [LAA≤35] 0.2025
283 4320 1223597 Stone Chips (12mm down graded) [LAA≤35] 0.3375
283 3690 1045156 Stone Chips (6mm down graded) [LAA≤35] 0.3375
113 1500 169944 Stone Dust (2.38mm down) 0.135
77243 51 3939379 Bitumen [Grade 60/70] 92.04
134 550 73852 Mason 0.16
210 450 94413 Skilled Labour 0.25
336 370 124206 Ordinary Labour 0.4
50 3000 151061 H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons 0.06
50 3000 151061 H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compacto 0.06
4616 68 313872 Diesel 5.5
504 220 110778 Lubricant 0.6
34 800 26855 Foreman 0.04
50 10000 503538 Asphalt Plant 0.06
50 6000 302123 AC Paver 0.06
84 4500 377654 H.C. of Dump Truck/ Tripping Trucks 0.1
283 4920 1393541 Stone Chips (25mm down graded) [LAA≤35] 0.3375
8992 49 440596 Bitumen [Grade 80/100] 0.75
7193 8 55749 Fire wood 0.6
12 550 6594 Mason 0.001
24 450 10790 Skilled Labour 0.002
60 370 22180 Ordinary Labour 0.005
4 3750 13488 H.C. of Distributor 0.0003
36 68 2446 Diesel 0.003
4 220 791 Lubricant 0.0003
210 4720 990291 Stone Chips (16mm down graded) [LAA≤35] 0.35
210 4320 906368 Stone Chips (12mm down graded) [LAA≤35] 0.35
210 3690 774190 Stone Chips (6mm down graded) [LAA≤35] 0.35
210 1500 314711 Stone Dust (2.38mm down) 0.35
67906 51 3463190 Bitumen [Grade 60/70] 113.28
96 550 52752 Mason 0.16
150 450 67438 Skilled Labour 0.25
240 370 88719 Ordinary Labour 0.4
36 3000 107901 H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons 0.06
36 3000 107901 H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compacto 0.06
3297 68 224194 Diesel 5.5
360 220 79127 Lubricant 0.6
24 800 19182 Foreman 0.04
36 10000 359670 Asphalt Plant 0.06
36 6000 215802 AC Paver 0.06
60 4500 269753 H.C. of Dump Truck/ Tripping Trucks 0.1
53243 9 479183 1st Class Brick 31
21 420 8656 Sand (FM - 0.5) 0.012
17 550 9446 Mason 0.01
86 370 31774 Ordinary Labour 0.05
18218 12 224257 0.18mm thick polythene sheet 1
18 370 6740 Ordinary Labour 0.001
269 2940 792006 1st Class Brick Chips (20mm down graded) 0.86
135 584 78662 Sand (FM - 1.2) 0.43
1896 430 815443 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 6.054
25 650 16289 Head Mason 0.08
132 550 72359 Mason 0.42
235 450 105720 Skilled Labour 0.75
564 370 208621 Ordinary Labour 1.8
19 1200 22554 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.06
19 400 7518 Hire and running charges of Concrete Vibrator 0.06
2663 430 1145199 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 2.12
510038 9 4590345 1st Class Brick 406
377 584 220095 Sand (FM - 1.2) 0.3
75 650 48994 Head Mason 0.06
879 550 483657 Mason 0.7
879 450 395719 Skilled Labour 0.7
1256 370 464813 Ordinary Labour 1
2025 5220 10572458 Stone Chips (25mm down graded)[LAA≤30] 0.491
1349 4470 6029471 Stone Chips (12mm down graded) [LAA≤30] 0.327
1770 1500 2654438 Sand (FM - 2.5) 0.429
31750 430 13652554 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 7.697
330 650 214500 Head Mason 0.08
1444 550 794063 Mason 0.35
1650 450 742500 Skilled Labour 0.4
6188 370 2289375 Ordinary Labour 1.5
34 23000 787463 Hire and running charges of Batching and Mixing Plant 0.0083
248 400 99000 Hire and running charges of Concrete Vibrator 0.06
34 6000 205425 H.C. of Backhoe End Loader (6 tons) 0.0083
34 5000 171188 Hire and running charges of Concrete Pump (30 & 45 cum 0.0083
83 10000 825000 H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel 0.02
2888 68 196350 Diesel 0.7
384647 58 22309536 M.S. Ribbed/ Deformed Bar (Grade 400) 1.02
3771 90 339395 GI Wire (22 BWG) 0.01
1131 570 644850 Re-bar Fabricator 0.003
943 450 424243 Skilled Labour 0.0025
2828 370 1046467 Ordinary Labour 0.0075
4918 408 2007528 Manufacturing and supplying CC blocks (3.09.5.3) 1
5 420 2066 Sand (FM - 0.5) 0.001
15 550 8115 Mason 0.003
1475 370 545898 Ordinary Labour 0.3
50666 50 2533305 Royalty of Earth (Within Municipal Area) 1.25
12971 370 4799094 Ordinary Labour 0.32
162 800 129705 Sardar 0.004
811 2000 1621315 H.C. of Flat Body Truck (3 tons) 0.02
14187 68 964683 Diesel 0.35
811 220 178345 Lubricant 0.02
365 3000 1094388 H.C. of Vibratory Road Roller (8-10 ton) 0.009
0 0 0
2986 5 14928 Turf 1
134 370 49710 Ordinary Labour 0.045
3988 60 239306 Geo Textile (Grade-I-DF-20-1.5mm thick) 1.07
112 450 50321 Skilled Labour 0.03
373 370 137918 Ordinary Labour 0.1
473 3500 1655052 Stone Shingles (20mm down graded) 0.012
236 795 187967 Sand (FM - 1.5) 0.006
2246 430 965841 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 0.057
39 550 21673 Mason 0.001
394 450 177327 Skilled Labour 0.01
946 370 349925 Ordinary Labour 0.024
32 1200 37830 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.0008
11 550 6069 Mason 0.02
166 450 74477 Skilled Labour 0.3
717 370 265360 Ordinary Labour 1.3
295 260 76721 Synthetic Enamel Paint 0.12
221 206 45590 Synthetic enamel paint primer/ sealer 0.09
266 680 180589 Plumber/ Electric Mistry/ Painter 0.108
266 470 124819 Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/Op 0.108
7412 121 899847 Thermoplastic Compound 5
371 121 44992 Reflectorising Glass Beads 0.25
42 2000 84796 H. C. of Thermoplastic Appilicator Machine 0.0286
42 800 33918 Foreman 0.0286
85 450 38092 Skilled Labour 0.0571
169 370 62694 Ordinary Labour 0.1143
0 0 0
253 70 17697 18/20/22 BWG MS Sheet/plate 9.96
372 58 21547 MS Angle 25mmx25mmx3mm 14.636
6 810 4729 Electrode 0.23
2 800 1625 Foreman 0.08
10 680 6904 Welder 0.4
4 450 1713 Skilled Labour 0.15
15 370 5635 Ordinary Labour 0.6
8 500 3807 H.C. of Welding Machine 0.3
8 100 761 H.C. of Grinding Machine 0.3
0 0 0
1 1500 1997 Sand (FM - 2.5) 0.001
720 49 35297 Bitumen [Grade 80/100] 0.5412
873 8 6767 Fire wood 0.656
33 450 14734 Skilled Labour 0.0246
65 370 24230 Ordinary Labour 0.0492
151 430 65038 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 6.05
13 4930 64090 Stone Chips (20mm down graded) [LAA≤35] 0.52
9 4640 39440 Stone Chips (12mm down graded) [LAA≤25] 0.34
6 1500 9675 Sand (FM - 2.5) 0.258
4 970 4171 Sand (FM - 1.8) 0.172
30 130 3933 Water reducing chemical admixture : Type-A 1.21
2 650 1300 Head Mason 0.08
11 550 5775 Mason 0.42
19 450 8438 Skilled Labour 0.75
50 370 18500 Ordinary Labour 2
2 1200 1800 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.06
2 400 600 Hire and running charges of Concrete Vibrator 0.06
240 430 103415 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 6.05
21 4930 101908 Stone Chips (20mm down graded) [LAA≤35] 0.52
14 4320 58388 Stone Chips (12mm down graded) [LAA≤35] 0.34
10 1500 15384 Sand (FM - 2.5) 0.258
7 970 6632 Sand (FM - 1.8) 0.172
48 130 6253 Water reducing chemical admixture : Type-A 1.21
3 650 2067 Head Mason 0.08
17 550 9183 Mason 0.42
30 450 13416 Skilled Labour 0.75
80 370 29416 Ordinary Labour 2
2 1200 2862 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.06
2 400 954 Hire and running charges of Concrete Vibrator 0.06
137 430 58794 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 6.05
12 4930 57937 Stone Chips (20mm down graded) [LAA≤35] 0.52
8 4320 33195 Stone Chips (12mm down graded) [LAA≤35] 0.34
6 1500 8746 Sand (FM - 2.5) 0.258
4 970 3771 Sand (FM - 1.8) 0.172
27 130 3555 Water reducing chemical admixture : Type-A 1.21
2 650 1175 Head Mason 0.08
9 550 5221 Mason 0.42
17 450 7628 Skilled Labour 0.75
45 370 16724 Ordinary Labour 2
1 1200 1627 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.06
1 400 542 Hire and running charges of Concrete Vibrator 0.06
7950 58 457364 Manufacturing and supplying CC blocks Size 375mmx1 2.65
3 420 1260 Sand (FM - 0.5) 0.001
30 550 16500 Mason 0.01
300 370 111000 Ordinary Labour 0.1
1672 25 41798 Royalty of Earth 1.12
6 800 4777 Sardar 0.004
522 370 193318 Ordinary Labour 0.35
53 450 23669 Skilled Labour 0.003
319 370 118064 Ordinary Labour 0.0182
53 570 29981 Operator 0.003
107 470 50266 Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/Op 0.0061
53 8880 467065 H.C. of Excavator (Medium Size) 0.003
6482 68 440760 Diesel 0.3697
191 220 42043 Lubricant 0.0109
1609 420 675698 Sand (FM - 0.5) 1.15
140 370 51762 Ordinary Labour 0.1
11 3000 33575 H.C. of Vibratory Road Roller (8-10 ton) 0.008
56 68 3805 Diesel 0.04
5 220 1077 Lubricant 0.0035
9326 12 114808 0.18mm thick polythene sheet 1
9 370 3451 Ordinary Labour 0.001
602 2940 1768563 1st Class Brick Chips (20mm down graded) 0.86
301 584 175653 Sand (FM - 1.2) 0.43
4235 430 1820898 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 6.054
56 650 36373 Head Mason 0.08
294 550 161580 Mason 0.42
525 450 236074 Skilled Labour 0.75
1259 370 465853 Ordinary Labour 1.8
42 1200 50362 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.06
42 400 16787 Hire and running charges of Concrete Vibrator 0.06
11285 430 4852526 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 6.05
970 4930 4781832 Stone Chips (20mm down graded) [LAA≤35] 0.52
634 4640 2942666 Stone Chips (12mm down graded) [LAA≤25] 0.34
481 1500 721863 Sand (FM - 2.5) 0.258
321 970 311203 Sand (FM - 1.8) 0.172
2257 130 293409 Water reducing chemical admixture : Type-A 1.21
149 650 96995 Head Mason 0.08
783 550 430880 Mason 0.42
1399 450 629532 Skilled Labour 0.75
3731 370 1380307 Ordinary Labour 2
112 1200 134300 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.06
112 400 44767 Hire and running charges of Concrete Vibrator 0.06
18490 430 7950912 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 6.05
1589 4930 7835079 Stone Chips (20mm down graded) [LAA≤35] 0.52
1039 4320 4489064 Stone Chips (12mm down graded) [LAA≤35] 0.34
789 1500 1182780 Sand (FM - 2.5) 0.258
526 970 509910 Sand (FM - 1.8) 0.172
3698 130 480753 Water reducing chemical admixture : Type-A 1.21
245 650 158927 Head Mason 0.08
1284 550 706001 Mason 0.42
2292 450 1031495 Skilled Labour 0.75
6113 370 2261647 Ordinary Labour 2
183 1200 220052 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.06
183 400 73351 Hire and running charges of Concrete Vibrator 0.06
11285 430 4852526 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 6.05
970 4930 4781832 Stone Chips (20mm down graded) [LAA≤35] 0.52
634 4320 2739723 Stone Chips (12mm down graded) [LAA≤35] 0.34
481 1500 721863 Sand (FM - 2.5) 0.258
321 970 311203 Sand (FM - 1.8) 0.172
2257 130 293409 Water reducing chemical admixture : Type-A 1.21
149 650 96995 Head Mason 0.08
783 550 430880 Mason 0.42
1399 450 629532 Skilled Labour 0.75
3731 370 1380307 Ordinary Labour 2
112 1200 134300 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.06
112 400 44767 Hire and running charges of Concrete Vibrator 0.06
809412 58 46945881 M.S. Ribbed/ Deformed Bar (Grade 400) 1.02
7935 90 714187 GI Wire (22 BWG) 0.01
2381 570 1356955 Re-bar Fabricator 0.003
1984 450 892734 Skilled Labour 0.0025
5952 370 2202076 Ordinary Labour 0.0075
643 93 59818 uuPVC Pipe 50mm dia of 2.5mm to 3.0mm wall thick 1
643 20 13160 All remaining cost like Labour,Tee, elbow, bend, socket, 1
91 2940 268393 1st Class Brick Chips (20mm down graded) 0.085
644 165 106326 75mm PVC Pipe -2.9mm to 3.4mm wall thick 0.6
29 480 13919 Sand (FM - 0.8) 0.027
1074 30 32220 Empty Gunny Bag 1
107 450 48330 Skilled Labour 0.1
84 3500 292600 Stone Shingles (20mm down graded) 0.2
42 1500 62700 Sand (FM - 2.5) 0.1
13 260 3260 H.C. of Casing 0.03
13 3000 37620 H.C. of Tripod and Mechanical Winch Machine complete w 0.03
13 350 4389 H.C. of Driving Equipment 0.03
13 570 7148 Operator 0.03
10 800 8026 Foreman 0.024
40 450 18058 Skilled Labour 0.096
35 370 12991 Ordinary Labour 0.084
798 68 54233 Diesel 1.908
10 220 2198 Lubricant 0.0239
65 4850 316148 Stone Chips (38mm down graded) [LAA≤35] 0.0076
28 4720 133595 Stone Chips (16mm down graded) [LAA≤35] 0.0033
46 970 44926 Sand (FM - 1.8) 0.0054
656 430 282140 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 0.0765
9 550 4717 Mason 0.001
52 450 23544 Skilled Labour 0.0061
196 370 72356 Ordinary Labour 0.0228
8 1200 9263 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.0009
8 400 3088 Hire and running charges of Concrete Vibrator 0.0009
7201 452 3254716 300mmx300mmx25mm high load bearing parking Tiles 1
1944 430 836001 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 0.27
144 584 84104 Sand (FM - 1.2) 0.02
1584 650 1029700 Head Mason 0.22
1584 550 871285 Mason 0.22
2376 450 1069304 Skilled Labour 0.33
2376 370 879205 Ordinary Labour 0.33
16375 59 966146 MS Angle, Flat bar, Z bar 1.02
181 3500 633713 Stone Shingles (20mm down graded) 0.0563
90 795 71844 Sand (FM - 1.5) 0.0281
851 430 365910 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 0.2646
16 550 8844 Mason 0.005
96 450 43416 Skilled Labour 0.03
362 370 133866 Ordinary Labour 0.1125
14 1200 17366 H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 c 0.0045
14 400 5789 Hire and running charges of Concrete Vibrator 0.0045
8 584 4897 Sand (FM - 1.2) 0.0752
39 430 16963 Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 0.3538
2 650 1450 Head Mason 0.02
28 550 15331 Mason 0.25
89 450 40140 Skilled Labour 0.8
167 370 61883 Ordinary Labour 1.5
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Unit Type Rate Total

day 800 0.8


day 370 7.4
day 450 2.48
day 370 10.36
day 8880 5.33
day 3500 2.1
liter 68 1.02
liter 220 0.22
day 550 11
day 370 81.4
day 1500 1.25
day 500 0.42
day 3500 5.78
liter 68 1.12
liter 220 0.35
day 550 13.75
day 370 111
m3 480 552
day 370 37
day 3000 24
liter 68 2.72
liter 220 0.77
m3 2786 919.38
m3 2940 1764
m3 480 192
day 370 185
day 450 99
day 550 5.5
liter 68 8.16
liter 220 2.2
day 3000 30
day 1500 15
day 500 5
each 9 126
m3 420 2.1
day 550 2.2
day 370 11.1
m3 2786 1253.7
m3 2940 2205
m3 420 63
day 370 111
day 450 90
day 650 3.25
day 8000 32
day 4500 135
day 6000 12
day 3000 90
day 2500 5
m3 6.48 6.48
liter 68 54.4
liter 220 13.2
cum 4850 2182.5
cum 4930 1232.5
cum 4320 1036.8
m3 480 192
day 370 111
day 450 90
day 650 3.25
day 8000 32
day 4500 135
day 6000 12
day 3000 90
day 2500 5
m3 6.48 6.48
liter 68 54.4
liter 220 13.2
kg 66 52.8
kg 8 5.12
liter 72 28.8
day 750 0.08
day 650 0.65
day 370 3.3
day 3750 1.01
liter 68 0.17
liter 220 0.06
cum 4720 955.8
cum 4320 1458
cum 3690 1245.38
cum 1500 202.5
kg 51 4694.04
day 550 88
day 450 112.5
day 370 148
day 3000 180
day 3000 180
liter 68 374
liter 220 132
day 800 32
day 10000 600
day 6000 360
day 4500 450
cum 4920 1660.5
kg 49 36.75
kg 7.75 4.65
day 550 0.55
day 450 0.9
day 370 1.85
day 3750 1.13
liter 68 0.2
liter 220 0.07
cum 4720 1652
cum 4320 1512
cum 3690 1291.5
cum 1500 525
kg 51 5777.28
day 550 88
day 450 112.5
day 370 148
day 3000 180
day 3000 180
liter 68 374
liter 220 132
day 800 32
day 10000 600
day 6000 360
day 4500 450
each 9 279
m3 420 5.04
day 550 5.5
day 370 18.5
m2 12.31 12.31
day 370 0.37
m3 2940 2528.4
m3 584 251.12
bag 430 2603.22
day 650 52
day 550 231
day 450 337.5
day 370 666
day 1200 72
day 400 24
bag 430 911.6
each 9 3654
m3 584 175.2
day 650 39
day 550 385
day 450 315
day 370 370
cum 5220 2563.02
m3 4470 1461.69
m3 1500 643.5
bag 430 3309.71
day 650 52
day 550 192.5
day 450 180
day 370 555
day 23000 190.9
day 400 24
day 6000 49.8
day 5000 41.5
day 10000 200
liter 68 47.6
kg 58 59.16
kg 90 0.9
day 570 1.71
day 450 1.13
day 370 2.78
each 408.2 408.2
m3 420 0.42
day 550 1.65
day 370 111
m3 50 62.5
day 370 118.4
day 800 3.2
day 2000 40
liter 68 23.8
liter 220 4.4
day 3000 27

m2 5 5
day 370 16.65
m2 60 64.2
day 450 13.5
day 370 37
m3 3500 42
m3 795 4.77
bag 430 24.51
day 550 0.55
day 450 4.5
day 370 8.88
day 1200 0.96
day 550 11
day 450 135
day 370 481
liter 260 31.2
liter 206 18.54
day 680 73.44
day 470 50.76
kg 121.4 607
kg 121.4 30.35
day 2000 57.2
day 800 22.88
day 450 25.7
day 370 42.29

kg 70 697.2
kg 58 848.89
pkt 810 186.3
day 800 64
day 680 272
day 450 67.5
day 370 222
day 500 150
day 100 30

m3 1500 1.5
kg 49 26.52
kg 7.75 5.08
day 450 11.07
day 370 18.2
bag 430 2601.5
cum 4930 2563.6
cum 4640 1577.6
m3 1500 387
m3 970 166.84
liter 130 157.3
day 650 52
day 550 231
day 450 337.5
day 370 740
day 1200 72
day 400 24
bag 430 2601.5
cum 4930 2563.6
cum 4320 1468.8
m3 1500 387
m3 970 166.84
liter 130 157.3
day 650 52
day 550 231
day 450 337.5
day 370 740
day 1200 72
day 400 24
bag 430 2601.5
cum 4930 2563.6
cum 4320 1468.8
m3 1500 387
m3 970 166.84
liter 130 157.3
day 650 52
day 550 231
day 450 337.5
day 370 740
day 1200 72
day 400 24
each 57.53 152.45
m3 420 0.42
day 550 5.5
day 370 37
m3 25 28
day 800 3.2
day 370 129.5
day 450 1.35
day 370 6.73
day 570 1.71
day 470 2.87
day 8880 26.64
liter 68 25.14
liter 220 2.4
m3 420 483
day 370 37
day 3000 24
liter 68 2.72
liter 220 0.77
m2 12.31 12.31
day 370 0.37
m3 2940 2528.4
m3 584 251.12
bag 430 2603.22
day 650 52
day 550 231
day 450 337.5
day 370 666
day 1200 72
day 400 24
bag 430 2601.5
cum 4930 2563.6
cum 4640 1577.6
m3 1500 387
m3 970 166.84
liter 130 157.3
day 650 52
day 550 231
day 450 337.5
day 370 740
day 1200 72
day 400 24
bag 430 2601.5
cum 4930 2563.6
cum 4320 1468.8
m3 1500 387
m3 970 166.84
liter 130 157.3
day 650 52
day 550 231
day 450 337.5
day 370 740
day 1200 72
day 400 24
bag 430 2601.5
cum 4930 2563.6
cum 4320 1468.8
m3 1500 387
m3 970 166.84
liter 130 157.3
day 650 52
day 550 231
day 450 337.5
day 370 740
day 1200 72
day 400 24
kg 58 59.16
kg 90 0.9
day 570 1.71
day 450 1.13
day 370 2.78
m 93 93
ls 20.46 20.46
m3 2940 249.9
m 165 99
m3 480 12.96
each 30 30
day 450 45
m3 3500 700
m3 1500 150
day 260 7.8
day 3000 90
day 350 10.5
day 570 17.1
day 800 19.2
day 450 43.2
day 370 31.08
liter 68 129.74
liter 220 5.26
cum 4850 36.86
cum 4720 15.58
m3 970 5.24
bag 430 32.9
day 550 0.55
day 450 2.75
day 370 8.44
day 1200 1.08
day 400 0.36
sqm 452 452
bag 430 116.1
m3 584 11.68
day 650 143
day 550 121
day 450 148.5
day 370 122.1
kg 59 60.18
m3 3500 197.05
m3 795 22.34
bag 430 113.78
day 550 2.75
day 450 13.5
day 370 41.63
day 1200 5.4
day 400 1.8
m3 584 43.92
bag 430 152.13
day 650 13
day 550 137.5
day 450 360
day 370 555

You might also like