Turbine Performance Test Procedure
Turbine Performance Test Procedure
The purpose of this procedure is to provide guidelines and detail information related to implementation
of a Steam Turbine performance Test at TEL site. The Steam Turbine performance monitoring regime is
implemented to achieve following objectives:
Scope:
Boiler performance test will be conducted on half yearly basis in order to:
Reference Standards:
Responsibility:
Process Engineer: Initiate the test and conduct it successfully. Generate recommendation and follow up
with them.
E&I Manager: Ensure the availability of Test instruments and Calibration of installed instruments.
Mechanical Manager: Ensure the availability of mechanical machines and mechanical integrity of the
system
Test Procedure:
The parties to any test under this Code shall reach definite agreement on the specific objective of the
test and method of operation. This agreement shall reflect the intent of any applicable contract or
specification. Any specified or contract operating conditions or specified performance pertinent to the
objective of the test shall be ascertained. Unless the alternative test procedures are specified, full-scale
test procedures shall be used. Omissions or ambiguities about any of the conditions must be eliminated
or their values or intent agreed upon before the test is started. The cycle arrangement, operating
conditions, and testing procedures shall be established during the agreement on test methods.
Test Boundary:
1. Isolation points:
The accuracy of the test results depends on the isolation of the system. Extraneous flows should be
isolated, if possible, to eliminate errors. Extraneous flows for equipment that is included in the contract
cycle should be isolated only with mutual agreement by the parties. If there is any doubt about the
ability to isolate extraneous flows during the test, preparations shall be made prior to the test to
measure the flows. Following interconnection to be isolated from Turbine cycle before the
commencement of test.
2. Data Acquisition:
An important part of Performance Test includes the method of data acquisition. Data acquisition can be
both manual of automatic via Distributed Control System (DCS), online or periodic. At TEL, data will be
acquired online via DCS, in case of any limitation in online data collection, data shall be collected on
Performance Test input data sheet.
3. Test Instrumentation:
All performance tests require instrumentation of appropriate accuracy and repeatability to provide test
measurements necessary to determine Total plant and equipment efficiencies.
Performance is not measured directly, parameters like pressure, temperature, flow, differential
pressure, current and voltage are measured and the required results are computed using these
parameters. Performance. This is why Calibration regime of instruments required for Performance
testing shall be defined and implemented.
excitation and auxiliary power services (switchboard type) 0.25% accuracy class
3.2 Calibration:
All measuring instruments shall be accurate and reliable and calibrated as required in ASME PTC-6.
Frequency of instruments calibration shall be defined according to the type and usage of instruments.
Consideration shall be given to the environment in which the calibration takes place. Even under
laboratory conditions, the quantity being measured and instruments obtaining the measured value can
be influenced by vibration, magnetic fields, ambient temperature, changes in local acceleration due to
gravity, fluctuation, instability of the voltage source, and other variables.
The calibration report should include the identification of the calibration equipment and instruments, a
description of the calibration process, a statement of uncertainty of the measuring standard, and a
tabulation of the recorded calibration data. The report should be signed by a responsible representative
of the calibration laboratory.
Where appropriate, calibration shall be performed with test instruments installed in place for the test,
and all calibrations shall be available prior to the test. In-place calibration of station instrumentation is
necessary when secondary flow measurements are made by a permanently installed flow element for
which calibration is required or where station instruments and a computer are used for test data
acquisition.
4. Stabilization criteria
Preparatory to any test run, the turbine and all associated equipment shall be operated for a sufficient
time to attain steady-state condition. Appropriate means shall be employed for securing constant load.
This may be accomplished by blocking the means of Load limiter application.
5. Operating Conditions:
Every effort shall be made to run the tests under specified operating conditions, or as close to specified
operating conditions as possible in order to avoid the application of corrections to test results, or
minimize the magnitude of the corrections. In addition, variations in any condition that may influence
the results of the test shall be made as nearly constant as practicable before the test begins and so
maintained throughout the test. Steam generator and turbine controls shall be fine-tuned prior to the
test to minimize deviation of variables.
6. Deviations
Deviations of variables in excess of the limits prescribed in below table, may occur during a test run. If
such deviations are observed during the test run, the cause shall be eliminated and the test continued, if
possible, until all variables are within the specified limits for the planned duration of the test run. If the
cause of the deviations cannot be eliminated during the test run, or if deviations are discovered during
computation of results from a completed test run, that run shall be rejected in whole, or in part, and
repeated as necessary after the cause of the deviations has been eliminated, except in the case of initial
steam pressure and initial and reheat steam temperature. If the initial steam pressure, initial steam
temperature, or reheat steam temperature exceed the maximum permissible deviation indicated in
below table, the correction factors for these variables must be calculated for the specific cycle being
considered and used in place of the standard steam conditions corrections normally provided with the
turbine. Any rejected portions of the test run shall not be used in computing the overall averages.
A test shall be consisted of at least more than one Run, where Run is a complete set of reading, it is
recommend to take three set of reading in order to improve the quality of data. Efficiency Calculations
shall be done on the average data of all the runs. The data taken during the test shall be reviewed and
rejected in parts or in whole if not in compliance with the constancy of test and under the permissible
range of parameters.
9. Efficiency Calculation:
Step by step calculation of test results from the reduced data including detail calculation for Feed water
flow, Main steam flow, Extraction steam flows, thermal efficiencies of HP, IP and LP turbines, Turbine
cycle efficiency and cycle heat rate or any or any specific disposition set as the objective of test shall be
done.
Further, a detail discussion shall be set forth for onward discussion of test results and generate
recommendation.
Correction factors shall be applied on the test results in order to account for the parameters other than
the design values. The typical correction factors curves shall be given by the OEM. Typically, depending
upon the conditions, following correction factors are applied to the test results:
1. Final feed water temperature
2. Main steam temperature
3. Main steam pressure
4. Turbine Exhaust pressure
5. Turbine Speed
Appendix 1: