Project Title: Production of Sodium Hydroxide From Brine Electrolysis Using Membrane Cell
The document outlines a 16 week working schedule for a student group project on producing sodium hydroxide from brine electrolysis using a membrane cell. It assigns tasks such as introducing caustic soda properties, collecting data on production processes and materials, and completing material and energy balances to specific weeks.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
32 views
Project Title: Production of Sodium Hydroxide From Brine Electrolysis Using Membrane Cell
The document outlines a 16 week working schedule for a student group project on producing sodium hydroxide from brine electrolysis using a membrane cell. It assigns tasks such as introducing caustic soda properties, collecting data on production processes and materials, and completing material and energy balances to specific weeks.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2
Project Title
Production of Sodium Hydroxide from Brine Electrolysis
using Membrane Cell
Working schedule for final year design project
Supervisor: Dr. Sadiq Hussain Meeting with supervisor: Tuesday Group Leader: Hira Fatima Group Members: 1. Hira Fatima 2K17-CHE-03 2. Hasnain Sandhu 2K17-CHE-14 3. Afaq Izhar 2K17-CHE-37 4. Najaf Zaidi 2K17-CHE-43
Topic allotted on 29 September 2020. Wednesday
Total 16 weeks Working Schedule: Week No. Date Task Assigned Week 3 01-10-2020 Discussion with supervisor Sir Sadiq Hussain Work assigned and outline of chapter 1 Week 4: 06-10-2020 Introduction of caustic soda Historical Background Physical and chemical properties of caustic soda Week 5 13-10-2020 Raw Material Resources Raw Materials for production of Caustic soda Social Benefits Week 6 20-10-2020 Collect Data of Market Survey Local Survey on Production & Consumption of Caustic soda Capacity Selection Week 7 27-10-2020 Collect Data of Chapter 2 Process Selection
Week 8 03-11-2020 Different processes for Production of Caustic Soda
Mid Term Examination Week 9 17-11-2020 Comparison with other technologies and processes
Week 10 24-11-2020 Process Description
Process Flow Diagram Week 11 01-12-2020 Industrial Visit Week 12 08-12-2020 Understanding of Material Balance Week 13 15-12-2020 Material Balance Week 14 22-12-2020 Understanding of Energy Balance