0% found this document useful (0 votes)
275 views

Inspection Test Plan: Fabrication and Instalation of Piping

This document outlines the inspection test plan for the fabrication and installation of piping. It details the quality control activities, characteristics to be verified, controlling documents, acceptance standards, verification documents, and responsibilities for inspection at each stage including engineering, material handling, shop fabrication, welding, NDT testing, mechanical completion, blasting and painting, shipping, and site installation. Key stages include material verification against test certificates and drawings, fit-up and welding inspections against approved procedures and standards, NDT testing such as radiography, and stage-wise inspection during installation. Responsible parties include the design engineer, project manager, QA/QC personnel, fabrication and painting supervisors. The objective is to ensure all work conforms to contractual

Uploaded by

Rejoy baby
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
275 views

Inspection Test Plan: Fabrication and Instalation of Piping

This document outlines the inspection test plan for the fabrication and installation of piping. It details the quality control activities, characteristics to be verified, controlling documents, acceptance standards, verification documents, and responsibilities for inspection at each stage including engineering, material handling, shop fabrication, welding, NDT testing, mechanical completion, blasting and painting, shipping, and site installation. Key stages include material verification against test certificates and drawings, fit-up and welding inspections against approved procedures and standards, NDT testing such as radiography, and stage-wise inspection during installation. Responsible parties include the design engineer, project manager, QA/QC personnel, fabrication and painting supervisors. The objective is to ensure all work conforms to contractual

Uploaded by

Rejoy baby
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 3

INSPECTION TEST PLAN Contract No:

DANEM ENGINEERING WORKS WLL. FABRICATION AND INSTALATION OF PIPING QCP NO: Rev:0

CLIENT:

Verifying
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Documents/Reports Responsible Person Remarks
DANEM QVC

1.0 Engineering Approved Drawings Site Contractual Documents Relevent Contractual Documents Drawing Calculations Design Engg: H H
survey Standards Relevent Standards Requirements Project Manager

Preliminary activities
drawing approval technical Approved Drawings Approved Drawings Approved letter of
2.0
documents to start of Specifications - Specifications signature on Project Manager H H
documents
manufacture

Drawing, Material Test certificates QA/QC ,


3.0 Material Certificate ,Grade &Heat Store record MTC ,Drawing Material inspection
Fab:SUPVR
H w
Number report

Clearly identified ,Segregated


3.1 Material storage to prevent MTC , Store Record Identification as per MTC - Store Keeper , H R
SUPVR
damage&contamination

4.0
Shop Fabrication prior to Dimensions, Heat Number Approved Drawings Approved Drawings Inspection Report QA/QC , H R
cutting of pipe ,Grade, Size&Specs Fab:SUPVR

Approved WPS,Check weld Fit Approved Drawings Accordance with QA/QC ,


4.1 Fit-Up approved and project Inspection Report H R
up as per WPS spec Fab:SUPVR

5.0 Welding Monitoring Welding control procedure Electrode baking/Holding/Issue MFRS Recommendations Records QA/QC , Store S S
Records Keeper

5.1 Welding ApprovedWPS /PQR,Welders WPS /PQR,Welders certificate ASME SEC-IX ASMEB31.3 Weld /NDT summary QA/QC H R
certificate &drawings report

100% Visual inspection on


5.2 Visual Inspection completed weld Approved Drawings Weld map ASMEB31.3 &drawings Inspection Report QA/QC H R

Radiogrphy on completed Weld map/ Records / Asper Scope ASME.SEC V,NDT


6.0 NDT welds of Work and Approved Drawings Procedure &Project Test Reports QA/QC H R
Specification

1 of 3
INSPECTION TEST PLAN Contract No:

DANEM ENGINEERING WORKS WLL. FABRICATION AND INSTALATION OF PIPING QCP NO: Rev:0

CLIENT:

Verifying
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Documents/Reports Responsible Person Remarks
DANEM QVC

Mechanical Completion Shop Activities have to App. Drawing Project QA/QC


7.0 completed prior to shipping Weld Map Records QC Documents H R
(Shop Fabrication) to site Specification FAB. SUPVR.

As per approved
Surface preparation and Painting procedure and Project Blasting & painting QA/QC
8.0 Blasting&Painting drawings and Project Report. PAINTING. SUPVR
H R
painting Spec.
Spec.

8.0 Shipping

Final Review
8.1 Shipping to Site ( Document &Reports ) Delivery Note Relevant Document Delivery Note FAB.SUPVR. H S
Approval Identification Mark

9.0 Site Installation

Accordance with
Fit-Up Approved WPS,Check weld Fit Approved Drawings approved and project Inspection Report QA/QC , H R
9.1
up asper WPS spec Fab:SUPVR

Welding Approved ASME SEC-IX ASMEB31.3 Weld /NDT summary


9.2
WPS /PQR,Welders certificate WPS /PQR,Welders certificate &drawings report QA/QC H R

As per approved
Stage wise Inspection
9.3 Stage wise Inspection As per approved drawings drawings and Project Inspection Report QA/QC H R
during Installation.
Spec.

As per approved
Alignment Check of all
9.4 Alignment As per approved drawings drawings and Project Inspection Report QA/QC H R
Flanges
Spec.

As per approved
Orientation check of all
9.5 Orientation As per approved drawings drawings and Project Inspection Report QA/QC H R
Flanges.
Spec.

2 of 3
INSPECTION TEST PLAN Contract No:

DANEM ENGINEERING WORKS WLL. FABRICATION AND INSTALATION OF PIPING QCP NO: Rev:0

CLIENT:

Verifying
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Documents/Reports Responsible Person Remarks
DANEM QVC

As per approved
Alignment Check of all
9.6 Alignment As per approved drawings drawings and Project Inspection Report QA/QC H R
valves
Spec.

As per approved
Orientation check of all
9.7 Orientation As per approved drawings drawings and Project Inspection Report QA/QC H R
valves
Spec.

As per approved
9.8 Overall dimension Overall dimension check As per approved drawings drawings and Project Inspection Report QA/QC H R
Spec.

Visual Inspection 100% Visual inspection on Approved Drawings Weld map ASMEB31.3 &drawings Inspection Report QA/QC H R
9.9
completed weld

Radiogrphy on completed Weld map Records / Asper Scope ASME.SEC V,NDT


9.10 NDT welds of Work and Approved Drawings Procedure &Project Test Reports QA/QC H R
Specification

Weld map /Records / Asper Scope App. Drawing Project


10 Hydro Test Hydro Test of Piping of Work and Approved Drawings Specification Test Report QA/QC H W

Mechanical Completion Activities have to be Weld Map and Records App. Drawing Project QC Documents QA/QC H H
11
completed Specification FAB. SUPVR.

Quality Dossier Contractual Requirements Documents and Reports Quality Inspection Test QC Dossier QA/QC Engineer H H
12
Plan Clients Requirements

Legends: H: Hold point I:Inspection R:Review W:Witness S: Surveillance

3 of 3