4-Quantity Calculations
4-Quantity Calculations
4
BUILDING QUANTITY CALCULATIONS
Building Quantities Calculations
Solution
Example 2 :
Calculate the quantity of the excavation for the wall shown
in figure .
Solution :
Example 3 :
For the room shown in the following plan Calculate
the quantities of the following items:
1- Excavation of the foundations
2- Broken stone under footings
3- Reinforced concrete 1:2:4 for the footings
4- Building walls using solid concrete blocks 15x20x40 cm
under D.P.C,
5- Building walls using cavity concrete blocks 20x20x40 cm
above D.P.C.
6- plain concrete 1:2:4 for D.P.C.
0.80
Solution :
1. Excavation
2. Broken stone
3. Reinforced concrete ( footing )
L = 18.8𝑚
𝐵 = 0.6𝑚
𝐻 = 0.4𝑚
𝑉 = 𝐿 × 𝐵 × 𝐻 → 𝑉 = 18.8 × 0.6 × 0.4 = 4.512𝑚3
𝐿 = 5 + 2 × 0.8 = 6.6𝑚
𝐵 = 4 + 2 × 0.8 = 5.6𝑚
𝐻 = 0.15𝑚
𝑉 = 6.6 × 5.6 × 0.15 = 5.544𝑚3
Measuring table
Description Unite No. Length Width Height Quantity
m m m
Excavation of 𝑚3 1 18.8 0.6 0.8 9.024
footing
Broken stone 𝑚2 1 18.8 0.6 0.1 11.28