Implementation of Critical Path Method in Project Planning and Scheduling
Implementation of Critical Path Method in Project Planning and Scheduling
S Atin1*, R Lubis1
1
Informatics Engineering , Faculty Of Engineering and Computer Science,
Universitas Komputer Indonesia, Indonesia.
Email: [email protected]
Abstract. Scheduling in a project is a tool to determine the activities needed to complete a project
in a certain order and time frame, in which every activity must be carried out so that the project
is completed on time at an economical cost. The purpose of this study is to find out the critical
path in project implementation and find out which projects are postponed and which cannot be
delayed in their completion which can affect the entire project work process so that the project
can be completed on time. The method used in this study is the Critical Path Method (CPM),
which is a network method that has a series of activity components with the longest total amount
of time and shows the fastest time period of completion. The results of this study indicate that
the use of CPMs is able to get the longest total amount of time with the fastest project completion
period, project scheduling and project critical paths can be seen more clearly so that the project
can be completed on time.
1. Introduction
The project is a combination of several resources (labor, budget, equipment, facilities, support services)
in one organization to achieve the stated objectives [1]. Planning is an activity carried out in the project
to anticipate existing tasks and conditions by setting goals and objectives to be achieved and determining
implementing policies, programs to be carried out, schedule and time of implementation,
implementation procedures and administrative and operational as well as budget and source power [2].
Project scheduling is an activity carried out to determine the duration of project activities that must be
completed, raw materials, labor and the time needed by each activity [2]. To make planning and
scheduling projects can use several methods, one of which is the Critical Path Method (CPM) [3]. CPM
is an integrated network consisting of a series of activities with one another intended to obtain maximum
work efficiency [3]. In determining the total time, the CPM project is simpler, it is obtained by summing
the duration of each activity and taking the last / greatest finish time. The path where delays may not
occur in each project activity is called the critical path [3]. CPM is more used than other traditional
methods. CPM concentrates on the most important tasks the project can be confirmed on time and in
line with the predetermined schedule [4][5].
Some previous studies using CPM were studies carried out by the 1950 DuPont Company and
Remington Rand Corporation, CPMs used to manage power plants and construction could save the
company one million dollars in the first year of use [5]. In 2013 Putra proved that scheduling time using
CPM proved to be very helpful in time and cost efficiency [6]. Another study conducted by Hamzah et
al. In 2013 [7] proved that CPM networks help in time and cost efficiency. As well as a study conducted
by Ezekiel, et al. [8] stated that CPM is suitable for scheduling, formulating, and managing various
Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence. Any further distribution
of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.
Published under licence by IOP Publishing Ltd 1
INCITEST 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 662 (2019) 022031 doi:10.1088/1757-899X/662/2/022031
activities in all construction work, because it provides a schedule built on experience, and observations
that have been made.
The purpose of this study is to find a project critical path that can be used to find out the longest time
the project is completed, as well as the project leader's guidance to determine which jobs can be delayed
and which jobs cannot be delayed. In this study, researchers used CPM to design and schedule projects
so that a critical path in construction projects was obtained, namely the construction of government
buildings. By using the CPM time of project execution and the critical path of the project can be known
so that the project can be completed on time.
2. Methodology
The research methodology used in this research is descriptive methodology. Descriptive methodology
is a research methodology that is used to make descriptions, drawings or paintings systematically,
factually and actually about the facts, the characteristics and relationships between the phenomena
investigated. The methodology of this research begins with a review of CPM literature studies together
with secondary data collection and determining the logical relationship between jobs. Then calculate the
project's forward time value, then calculate the project backward time. After the forward time and
backward time, the next step is to calculate the total float and determine the critical path and the last one
produces the design guide and project scheduling.
2
INCITEST 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 662 (2019) 022031 doi:10.1088/1757-899X/662/2/022031
The first step to find a critical path is to calculate the forward time, namely the fastest time of a project
can be completed using the formula EF (i-j) = ES (i-j) + D (i-j) [10], then the forward time value is
obtained as in Table 2.
3
INCITEST 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 662 (2019) 022031 doi:10.1088/1757-899X/662/2/022031
Total float is the amount of time allowed for an activity to be delayed, without knowing the overall
project schedule. To calculate the total float in this study using the formula TF = LS - ES. The results
of the total float calculation can be seen in Table 4.
Based on the calculations in table 4, it can be concluded that the initial total project work is 48 weeks,
and the work in the critical path can be determined by looking at the results of Total Float (TF), TF = 0,
from the results the critical path is obtained at work I- II-V-IX-XV-XVIII. The results of analysis of
project critical work can be seen in table 5 while the project network can be seen in Figure 1.
4
INCITEST 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 662 (2019) 022031 doi:10.1088/1757-899X/662/2/022031
4. Conclusion
The conclusion in this study is that the critical path on the project can be used to determine the longest
time that shows the project completion period. In addition, the critical path can be a reference for project
leaders in the project that work on the critical path must be timely in order for the project to finished on
time.
5. Acknowledgments
The researcher thanked to The Directorate of Research and Community Service Institution (LPPM)
Universitas Komputer Indonesia for funding this research using the internal research scheme in 2018,
and the xyz company for data contributions for this study.
References
[1] Atin, S., Harihayati, T. and Widianti, U.D., 2018, August. “Utilization of function point method
for measuring software project complexity”. In IOP Conference Series: Materials Science and
Engineering (Vol. 407, No. 1, p. 012086). IOP Publishing.
[2] Heryanto. I, Triwibowo.T, (2016) “Manajemen Proyek Berbasis Teknologi Informasi”,
Informatika Bandung, Revisi Kedua.
[3] John. M. Nocolas, 2004, “Project management for Business and Engineering”: Principles and
Parctice 2nd ed. Burlington : Elsevier Inc, 2004.
[4] James E. Kelley, Jr.F And Margon R. Walker.1959, “Critical Path Planning And Scheduling”,
Proceedings Of the Eastern Joint Computer Conference.
[5] Rogelio, A., Spring 2010, “Analysis Of Project Planning Using CPM And Pert”, In Pathial
Fulfillment Of Math 4395-Senior Project, Departhment Of Computer And Mathematical
Science.
5
INCITEST 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 662 (2019) 022031 doi:10.1088/1757-899X/662/2/022031
[6] Putra, A.E., 2013, “Analisis Pengendalian Waktu Dan Biaya Dengan Metode Crash Program
(Studi Kasus: Pembangunan Bali Adat Belalawan, Tesis Fakultas Teknik Sipil, Program
Magister Teknik Sipil Universitas Islam Indonesia.
[7] Sugiyarto, Qomariyah. S., Hamzah. F., 2013, “ Analisis Network Planning dengan CPM (Critical
Path Method) Dalam Rangka Efisiensi Waktu dan Biaya Proyek”, ISSN 2354-8630, e-Jurnal
Matriks Teknik Sipil Vol.1 no.4/Desember 2013/408
[8] Ezekiel R. M. Iwawo, Jermias Tjakra, & Pingkan A.K. Pratasis, 2016, Penerapan Metode CPM
Pada Proyek Konstruksi ( Studi Kasus Pembangunan Gedung Baru Kompleks Eben Haezer
Manado). Jurnal Sipil Statistik, 4 (9) : 551-558.
[9] Holliday, I., 2002, Building E-Government In East And Southeast Asia: Regional Rhetoric And
National (in) Action. Public Administration & Development, 22 (4), 323-335.
[10] Hartono. I., 1995, Manajemen Proyek : Dari Konseptual Sampai Operasional
[11] Taylor. B. W., 2011. Introduction To Management Science.