c3 PDF
c3 PDF
3.1 General
The Port Louis conurbation, is currently experiencing severe morning and afternoon
traffic congestion, estimated to cost the Mauritian economy around Rs 2 billion annually.
The Road Development Authority (RDA), Ministry of Public Infrastructure and Land
Transport of the Government of Mauritius is thus implementing a Road Decongestion
Programme, entailing the establishment of a network of roads, in order to alleviate the
severe traffic congestion being experienced along the Port Louis-Curepipe corridor and
around Port Louis itself.
The Government of Mauritius (GOM) has set a high priority for development of road
infrastructure to support the achieved and planned pace of economic growth. The main
focus is set on the National Road Decongestion Programme to provide an effective
approach of decongestion of the road network in Mauritius.
The whole extent of Port Louis to St Jean Road (A1) is heavily congested throughout the
day and traffic jam reach an unbearable level during peak hours. Severe traffic
congestion occurs along the M1 Motorway from Caudan waterfront through the M2
Motorway towards Quay D and Mer Rouge Roundabouts, especially during peak times.
Also, the traffic volume of the inner roads in Port Louis City has been largely exceeded
its capacity and acute traffic jams occur during business hours, especially in the vicinity
of Place d'Armes.
Therefore, in order to ease the traffic congestion, a re-design of the Pont Fer, Jumbo and
Dowlut Roundabouts as part of the Road Decongestion Programme (RDP) has been
prioritised.
The proposed project has been selected based on the recommendations of traffic
modelling performed by KEC whose parameters are considered to remain valid as well
as the following parameters:
Function
Cost
Constructability
Social Impact
Environmental Impact
Maintenance.
The project description, as given in this chapter, are extracts from the Front End
Engineering Design Report (FEED) prepared by KEC.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-1 May 2017
M191/GSJ/3.1
3.1 Project Description
All 3 roundabouts; Pont Fer, Jumbo and Dowlut, have 2 lanes in operation. The close
proximity between the roundabouts increases the traffic congestion from one intersection
to the other.
3.1.4 Operation of Pont Fer Roundabout
The Pont Fer Roundabout operates with 2 lanes. However, the single lane as an
independent road for Airport bound from Port Louis adds an additional lane to the part of
the roundabout. This results in a partial 3 lane operation, which then requires the
approaching traffic into the factory area to turn and cut across 3 lanes simultaneously.
This raises an alarm in the road safety and seeks an immediate remediation.
Construction of the Pont Fer viaduct which is shown schematically in Figure 3-1
Improvement of the Jumbo viaduct alignment on B63 road which is shown
schematically in Figure 3-2
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-2 May 2017
M191/GSJ/3.1
Improvement to the existing 3 legs intersection at Jumbo Roundabout as shown in
Figure 3-3
Improvement of the alignment of the ramp at Dowlut Roundabout as shown in
Figure 3-4
A new link road from, Swami Baktivedanta Road (Sodnac Link Road) B94 to
Phoenix-Beau Songes Road B130 as shown in Figure 3-3.
Figure 3-1: Proposed Pont Fer Viaduct Figure 3-2: Proposed Jumbo Viaduct
Figure 3-3: Proposed 3-leg Intersection at Figure 3-4: Alignment of Ramp at Dowlut
Jumbo Roundabout
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-3 May 2017
M191/GSJ/3.1
Overall, the project is as shown schematically Figure 3-5.
Through the proposed Road Decongestion Programme the RDA expects to meet,
amongst others, the following objectives:
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-4 May 2017
M191/GSJ/3.1
Improvement of entrance and exit for industrial area on Pont Fer Roundabout
Improvement of Pont Fer viaduct alignment on M1 Motorway
Improvement of the Jumbo viaduct alignment on B63 road
Change of the existing Jumbo Roundabout to 3 legs intersection
Improvement of alignment of the ramp at Dowlut Roundabout
Diversion and protection of all affected utility services, cables, etc.
Construction and installation of all required ancillary buildings, offices and road
furniture
Construction of additional lane at Pont Fer and extension of culvert at River Mesnil
will entail the following:
Temporary diversion of existing river flow to proceed with construction works
Realignment of existing river to original alignment.
The road design involves the following main fields, amongst others:
Geometric design
Pavement design
Bridge
Geotechnical engineering
Traffic analysis.
The following sections 3.4 to 3.7 have been extracted from the FEED Report produced
by KEC in association with Cheil Engineering Co. Ltd. and Kyongdong Engineering .Co
Ltd.
As a basic element of the road design, the road design standard should be based on
various factors: function of roads, traffic and site conditions, geological and geotechnical
conditions, social environmental and economic factors.
According to the design standard stipulated in the Contract Agreement between RDA
and KEC (signed on 25 Nov., 2016), all design fields will basically follow local standards
and AASHTO standards. The Consultant will comply with the followings as reference
standards in the order of priority listed below, unless otherwise specified.
Local standards
AASHTO Standard, 2011, AASHTO, USA(Design Standard for the Project)
Design Manual for Road and Bridges Volume 6, 2015, British Standard, UK
Road Design Standard, 2012, Ministry of Land, Infrastructure and Transport,
Republic of Korea
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-5 May 2017
M191/GSJ/3.1
South African Pavement Engineering Manual Second Edition, 2014, - The South
African National Road Agency
Southern African Transport and Communications Commission,1998, - The division
of Roads and Transport Technology.
According to the Road Traffic (Speed) Regulations 2011 of Mauritius, the roads in
Mauritius are classified into four categories: Motorway, A roads, B roads, and Un-rated
roads.
Regarding the road classification for the project, the RDA informed that all RDP projects
would normally consist of 'A Class' road. Based on this information, the project road
sections to be newly constructed are classified as 'A road' while current classifications
remain the same for the existing roads subject to upgrade. The road classifications for
each section of the Grade Separated Junction at Pont Fer-Jumbo-Dowlut (GSJ) are as
follows:
Table 3-1 below shows road classification according to the AASHTO Manual.
Local AASHTO
Project Road Standard,2011
Classification
The Road Traffic (Speed) Regulations 2011 provided by the RDA defines the maximum
speed ranges by road classification and vehicle type as follows:
Considering operating speed limit on the A1 road, the design speed of the A1-M1 Link
Road is decided as 60km/h. The adopted design speed of the existing roads to be
improved in the Grade Separated Junctions at Pont Fer / Jumbo / Dowlut Roundabouts
ranges from 60 km/h to 80 km/h as shown in Table 3-2. In the selection of design
speeds for existing road upgrades, the traffic and site conditions as well as function of
each road were taken into consideration.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-6 May 2017
M191/GSJ/3.1
Table 3-2 - Adopted Design Speeds of the Grade Separated Junctions
Design Speed
Component (km/h) Remark
M1 Motorway (Viaduct) 80
M1 Motorway (Frontage
40
Road)
Existing Road
A10 Road (Viaduct) 40 Upgrades
A10 Connector Road 30
B63 Road (Viaduct) 60
Note 1: For the design speed of a connector road, 50km/h is adopted for direct ramps
while 40km/h is adopted for loops in the FEED report.
3.4.3 Intersections
(a) Profiles
In the case of locating roundabouts on grades, grades steeper than 4 percent are not
recommended in the roundabouts (An Informational Guide by FHWA).
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-7 May 2017
M191/GSJ/3.1
3.4.4 Design Surveys
A topographical survey to determine the elevation along the road alignment and to
facilitate the production of accurate topographical maps
Soil investigations
An investigation of the natural and man-made drainage in order to determine the
direction of flow
An investigation of services and utilities in the area
Traffic surveys including traffic volume, OD (Origin & Destination) and Speed and
Delay studies
An economic analysis with vehicle operating costs
A road furniture study.
For the Front- End Engineering Design (FEED) stage, the topographical survey covers
the following:
For the Detailed Design stage, the topographical surveys covered the following:
a) Cross-section levelling at 25m intervals. Cross sections are to cover at least 50m
either side of proposed centre line or up to the land acquisition limit whichever is
greater;
b) Underground surveys and consultations with relative institutions regarding relocation
of existing utilities (both of underground and ground) and data acquisition.
The elements of the cross section of a road are, mainly, the carriageway, the shoulder,
and the median strip. The width of the lanes, which consists of the carriageway,
changes depending on the design speeds (road classifications) and significantly
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-8 May 2017
M191/GSJ/3.1
influences the traffic capacity. It would be rational to determine the road width based on
the design speed and the volume of the traffic. The condition of the existing roads and
the location conditions should also be taken into account.
The decisions on the cross section design elements were based on the existing roads
and rights-of-way, the existing developments as well as the AASHTO Design Standards
- A Policy on Geometric Design of Highways and Streets, 2011.
Width of lane
Width of shoulder
Median Strip
Sidewalks.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-9 May 2017
M191/GSJ/3.1
3.5.3 Shoulder Widths
Considering the road passes through an area which is heavily populated with obstacles
and in order to minimize any contacts with obstacles on right side of the roads, a
minimum width of shoulder ranging from 0.6m to 1.0m was applied required for the
minimum width of gutter. The outer shoulder widths ranging from 1.0m to 2.5m are to be
used for M, A, and B roads in consideration of the restrictive site conditions.
Median width is defined as the width between edges of the travelled way for the
roadways in opposing directions of travel, including the width of the right shoulders.
Most median widths are in the range from 1.2m to 24.0m according to AASHTO Design
Standard but median width can be limited in consideration of economic factors and the
features of the project site.
The median width of ranging from 2.0m to 3.0m will be reflected in consideration of a
restrictive site condition such as viaduct for the Grade Separated Junction at three
roundabouts. The median width of 3.0m will be applied for the A1-M1 Link Road, which
is the minimum width of a median strip for a road to install lighting poles and sign boards.
3.5.5 Sidewalks
Sidewalk widths in residential areas vary from 1.2m to 2.4m. Sidewalks less than 1.5m in
width require the addition of a passing section every 60m for accessibility.
KEC- CHEIL- Kyongdong set the cross section elements of the project based on the
review and the comparison of each design elements defined in the three design
standards as well as road measurements through the site surveys: AASHTO-2011
(U.S.), DMRB Vol.6- 2015 (UK), and RDS-2012 (Korea) standards refer.
Grade Separated Junctions comprise the M1, A10, B63 and B94 roads and their cross
section elements and typical cross sections are as follows:
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-10 May 2017
M191/GSJ/3.1
Table 3-3 - Typical Cross Section (M1) – Duel Carriageway with 3 to 4 Lanes in each Direction
Northbound Southbound
Paved Outer Paved Outer
Lane Median Lane
Shoulder Shoulder
The typical cross section for the M1 Motorway and the M1 Frontage Road is as
follows:
Table 3-4 - Typical Cross Section (M1) - Duel Carriageway with 2 Lanes in each Direction
Northbound Southbound
Paved Outer Paved Outer
Lane Median Lane
Shoulder Shoulder
1.0 m [email protected]=7.0 m 2.0 m 2@3. 5=7.0 m 1.0 m
Total Width : 18.0 m
Northbound Southbound
Paved Paved Paved Paved
Lane Lane
Outer Inner Inner Outer
1.0 m [email protected]=10.5 m 1.0 m 1.0 m 2@3. 5=7.0 1.0 m
Total Width : 21.5 m
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-11 May 2017
M191/GSJ/3.1
Figure 3-8: Typical Cross Section (M1 Motorway and M1 Frontage Roads)
Table 3-6 - Typical Cross Section (M1) - Duel Carriageway with 3 Lanes in each Direction
Northboun Southboun
Paved Outer d d Paved Outer
Lane Median Lane
Shoulder Shoulder
2.5 m [email protected]=10.5 m 2.0 m 3@3. 5=10.5 m 1.5 m
Total Width : 27.0 m
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-12 May 2017
M191/GSJ/3.1
(c) Typical Cross Section for Dowlut Ramp-1, 2 of A10 Road and A10 Connector Road
Table 3-7 - Typical Cross Section (A10) - One-way Ramp with 1 Lane
One Direction
Paved Outer Shoulder Lane Paved Inner Shoulder
1.5~5.8 m 3.5 m 1.5 m
Total Width : 6.5 m~10.8m
One Direction
Sidewalk Paved Outer Shoulder Lane Paved Inner Shoulder
1.5 m 1.0 m 3.5 m 1.0 m
Total Width : 7.0 m
Typical cross section for Dowlut Ramp-1 of A10 and A10 connector road is as follows:
Figure 3-10: Typical Cross Section (Dowlut Ramp-1of A10 and A10 Connector Road)
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-13 May 2017
M191/GSJ/3.1
(d) Typical Cross Section for Sayed Hossen B63 Road and B63 Frontage Road
Figure 3-12: Typical Cross Section for Sayed Hossen B63 Road and B63 Frontage Road
One Direction
Paved Outer Shoulder Lane Paved Inner Shoulder
1.0 m 2@3. 5=7.0 m 1.0 m
Total Width : 9.0
Table 3-10 - Typical Cross Section (B63 Frontage Road) - Duel Carriageway with 2 Lanes in Each
Direction
Northbound Southbound
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-14 May 2017
M191/GSJ/3.1
(e) Typical Cross Section for Sodnac Link Road
Table 3-11 - Typical Cross Section - Sodnac Link Road
Northbound Southbound
Table 3-12 - Typical Cross Section (B130) - Two-Way with 2 Lanes in Each Direction
Northbound Southbound
Paved Outer Paved Outer
Sidewalk Lane Median Lane Sidewalk
Shoulder Shoulder
1.5 m 1.0m [email protected]=6.5 m 1.7 m [email protected]=6.5 m 1.0 m 1.5m
Total Width : 19.7 m
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-15 May 2017
M191/GSJ/3.1
3.6 Pavement Design
The design manuals, standards and guidance documents that have been used in the
development of the pavement design are as follows:
a) AASHTO guide for the design of pavement structures (DOPS) 1986, 1993 and
supplementary guide to the design of pavement structures 1998
b) Guidelines for 1993 AASHTO Pavement Design Virginia Department of
Transportation 2003
c) Highways Capacity Manual (2000) National Research Council
d) Recalibration of the Asphalt Layer Coefficient, NCAT Final Report 09-03, 2009
e) Material Properties of the 2003 NCAT Test Track Structural Study, NCAT Report
06-01, 2006.
The primary function of a pavement is to provide a suitable running surface and remain
serviceable for the anticipated traffic expected over the design life. The overall traffic
loading is therefore a key element of the pavement design process.
The road and interchange pavement design is based on traffic forecasts for 20 years.
Traffic growth from 2020 to 2039 as the basic years were used for the pavement design
calculation.
The pavement structure is designed for a life of 20 years after the opening of the road
which is currently planned for 2019. The performance period is the length of time the
initial pavement should last before it requires major rehabilitation and therefore has
deteriorated from its initial serviceability level to its terminal serviceability level. No major
rehabilitation is planned prior to 2039. Therefore, the performance period is 20 years.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-16 May 2017
M191/GSJ/3.1
3.6.3 Grade Separated Junction Pavement Types
In this section, the four main types of pavement structures are described in the following
tables :
Table 3-13 - Pavement Layers for Port Louis to Pont Fer Roundabout Section
Thickness Total SN
Categories Description (mm) provided
(mm)
Table 3-14 - Pavement Layers for Pont Fer to Jumbo Roundabout (Type B)
Thickness Total SN
Categories Description (mm) provided
(mm)
Layer 1 HMA Surface Course 50
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-17 May 2017
M191/GSJ/3.1
3) Type C: Pont Fer to Dowlut Roundabout Section
3.7 Bridges
Three road bridges are planned over three roundabouts at the Grade Separated
Junctions.
The locations of bridges at the grade separated junctions are as shown in Figure 3-14
and the list of bridges is given in Table 3-17.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-18 May 2017
M191/GSJ/3.1
Figure 3-15: Location of Bridges at Grade Separated Junctions
The project area consists of three roundabouts at Pont Fer, Jumbo and Dowlut, in close
proximity from one another. They are surrounded by industrial, commercial and
residential areas, and their capacity has reached the saturation with heavy traffic flows
experienced especially during peak hours.
The Metro Express is planned to pass within a few meters of the Jumbo Roundabout.
The River Sèche and River Mesnil flow under the existing road at Pont Fer and Dowlut
Roundabouts. Utility lines such as communications, conduit tubes, water supply pipes
and sewage pipes are currently buried underground along the project roads.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-19 May 2017
M191/GSJ/3.1
Pont Fer Roundabout Existing Culvert
A total of five (5) boreholes investigations for the FEED phase were carried out at Grade
Separated Junctions. According to the results of the investigations, the composition of
strata is in order of silty clay/residual basalt, highly/completely weathered basalt and
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-20 May 2017
M191/GSJ/3.1
moderately/slightly weathered basalt. The bearing layer such as moderately/slightly
weathered basalt for the bridge foundation was encountered on the range of 19.0m to
21.0m in depth below the ground level. Considering the depth of bearing layer by boring
investigations, a type of pile foundation is adopted for the bridge at Grade Separated
Junctions.
The Consultant has looked for locally available construction materials and equipment
that can be used for the construction. As Mauritius is an island, the procurement of the
required construction materials and equipment becomes an important factor to consider
compared to other countries.
Firstly, the main materials for the construction of this project are concrete, reinforcing
bars, steel and prestressing steel. Steel bridges, which are light in weight and have high
tensile strength, are commonly used in urban areas because of the application of curved
alignments and having a superior and longer span.
Had there been steelworks and a steel structure manufacturing plant in Mauritius, then a
diverse type of steel bridge could have been adopted. Unfortunately, supply of
steelwork is scarce in Mauritius and imported steel from another country will add extra
transportation costs and increase construction period. Sand and aggregate, which are
the raw materials used to make concrete, are readily available and concrete is widely
manufactured in Mauritius. However, cement, reinforcing bars and prestressing steel
cables have to be imported.
As for construction equipment, scaffolding & stage, cranes, form traveler and climbing
form are expected in place. 200T Cranes are available locally, however, more than 300T
cranes must be imported. Climbing forms or slip forms, which are required for
construction of an extradosed bridge would be also expected to be imported. The
quality of shoring available in Mauritius is relatively poor.
The vertical clearance of overpasses and underpasses is decided based on the road
categories and discussion with the local authorities.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-21 May 2017
M191/GSJ/3.1
3.7.7 Pont Fer Viaduct: BR1
a) Site Conditions
The Pont Fer Roundabout is a three-leg interchange, which connects the M1 motorway
and B63 road, and the bridge planned at Pont Fer Roundabout will cross over the M1
motorway. The Pont Fer Roundabout has a complicated structure with a number of
access roads connecting the nearby industrial area as well as other inner roads, and
currently these suffer from heavy traffic flows throughout the day.
The main obstacles around Pont Fer Roundabout include the existing culvert and five
frontage roads including access roads. Also the Metro Express is planned to pass on
the left hand side of the project alignment.
The planned bridge is also surrounded by the Ministry of Education and Human
Resources and an industrial area.
The horizontal alignment within the bridge consists of a straight line with 186m from the
beginning of the bridge, and a clothoid of 103m. The last 26m of the bridge consists of a
curve radius of 560m. This is shown in Figures 3-18 and 3-19.
The proposed bridge is planned to cross over the box culvert at the start of the bridge,
and has the total length of approximately 300m with a 6.0m-7.0m height retaining wall.
The location of the bridge is surrounded by commercial / industrial areas, which are
connected by a number of access roads as well as the frontage road leading to the main
road. Owing to the fact that the bridge will be a good distance from the nearest
pedestrians, the height of the retaining wall is not expected to intimidate anyone’s
viewpoint. However, in case the height of the retaining wall is less than 5m, then the
space below and between the side spans of the bridge is reduced to less than 2m. This
makes it difficult to utilize the space under the bridge and is less effective in terms of
giving a sense of openness.
Following the determination of the total length of the bridge the next step is to determine
the span of bridge and the bridge type. This bridge needs at least a 40m span in order
to secure the required clearance for the intersection underneath. Considering
constructability, economic efficiency, aesthetics, maintenance management as well as
securing minimum 40m span length, the Consultant reviewed the three alternatives
below.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-22 May 2017
M191/GSJ/3.1
Figure 3-19: Plan of Pont Fer Viaduct: BR1
a) Site Conditions
The Phoenix shopping mall is situated in the vicinity of the start of the bridge, and
the Metro Express is planned to pass through the narrow area on the left hand side
of B63 Road, resulting in unavoidable conflicts with the project alignment.
The horizontal alignment within the bridge consists of straight line and a curve
radius of 500m. The bridge is situated at a gradient of (+)3.850%~ (-)6.150% on a
vertical curve. The road lanes consist of the total two lanes (one lane for each
direction) and the bridge width is 10m. This is shown in Figures 3-20 and 3-21.
The length of the bridge at the Jumbo intersection is planned in such a way that
there is sufficient clearance under the bridge for passing vehicles to secure the sight
distance at the start of the bridge and also for providing enough room for a bus
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-23 May 2017
M191/GSJ/3.1
station (H=2.5m) at the end of the bridge. In this case, the retaining wall with height
of around 7.0m seems to be a little high. However, as both sides of the bridge are
surrounded by two lane roads and inner roads providing enough spatial margin, a
sense of intimidation from the high wall is expected to be low. The Consultant has
decided that the optimal length of the bridge should be 180m in consideration of
economic efficiency and constructability.
A minimum 45m span is required to secure clearance under the bridge even though
the piers are planned to be installed on the traffic island in the middle of the
interchange. In consideration of economic efficiency, constructability and
maintenance, the Consultant reviewed three alternatives.
The Consultant proposes PSC Ι Girder as Alternative 1. The thick depth of girder
gives poor aesthetics compared to other alternatives. However, the girder can be
manufactured at the time of construction of the substructure and placed using a
crane The construction period is therefore shortened and construction becomes
easier with the merit of economic efficiency and maintenance.
The Dowlut Roundabout, which connects the M1 motorway and the A10 road, is planned to
change to a grade separated interchange. The planned bridge crossing over M1 motorway
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-24 May 2017
M191/GSJ/3.1
is planned on the proposed ramp road. The alignment of the ramp has a small curve radius
of 41m and widening of the road width that is required to secure the sight distance of
drivers, is a crucial point for bridge plan.
In the vicinity of the Dowlut Roundabout, the Mesnil river intersects with the road at two
locations resulting in another constraint to bridge design. As part of a graded separated
junction type, overpass and underpass proposals can be considered. For urban areas, an
underpass is generally preferred as this gives better aesthetics. However, due to the
location of the river at the Dowlut Roundabout, an underpass is not feasible.
The horizontal alignment consists of a curve radius of 41m. The bridge is situated in the
gradient of (+)9.990% ~ (-)3.647% at vertical curve. The road lanes consist of the total one
lane for one direction and the bridge width is variable with the range of from 11.7 to 15.2m.
This is shown in Figures 3-22 and 3-23.
The proposed bridge intersected with M1 motorway, which has the width of 18.0m, and the
intersecting angle between the two roads is 35 degrees. The width of the proposed bridge
varies between 20.4m and 12.5m. Therefore, minimum bridge length of 25m is required.
At start and end points of the bridge, an 8m height retaining wall is planned. The large
height of the retaining wall is unavoidable as the curve radius on the horizontal alignment is
already too small for installation of a bridge. Based on this, the Consultant has decided that
the optimal bridge length over the M1 motorway to be approximately 30m.
The location of the bridge has a very small curve radius of 41m. The intersecting angle of
35 degrees is too small as an acute angle of bridge, and the super elevation being 8% is
too high. Also, the vertical alignment has reached almost the maximum value of 10%. This
acts as a big constraint for deciding appropriate bridge type. Considering this constraint, the
Consultant reviewed two alternatives.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-25 May 2017
M191/GSJ/3.1
Figure 3-23: Plan of Dowlut Ramp Bridge: BR3
In consideration of the bearing capacity and the settlement of the foundation against the
load from the superstructure, the drilled pile, which is to be socketed in the layer of
moderately to slightly weathered basalt, is planned to have the length of 2.5 times the
diameter of the pile. The minimum thickness of the layer from the bottom of the pile is
planned to have a length of 2.0 times the diameter of the pile. From these requirements,
the bearing layer thickness should be over 4.5 times the diameter of the pile.
Based on the fact that moderately to slightly weathered basalt and completely weathered
basalt are altered and considering minimum bearing layer thickness, an 800mm
diameter drilled pile is applied for foundations.
The proposed stormwater drainage scheme for discharge of runoff is as shown in the
Figure 3-25.
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-26 May 2017
M191/GSJ/3.1
Figure 3-25: Drainage Scheme for GSJ Pont Fer-Jumbo-Dowlut
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-27 May 2017
M191/GSJ/3.1
3.7.12 Construction Methodology for the River Diversion Scheme
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-28 May 2017
M191/GSJ/3.1
Figure 3-29: Stage 4 Construction of Box Culverts
EIA GSJ at Pont Fer / Jumbo / Dowlut Roundabouts 3-29 May 2017
M191/GSJ/3.1