Pre-Cast Concrete Panel Check List
Pre-Cast Concrete Panel Check List
Audit Title
Client / Site
Conducted on
Location
Personnel
Audit 0%
Audit- 0%
Check bond breaker has been applied and dry before placing reo bar
Reinforcing Steel 0%
Reinforcing Steel
- 0%
Check size and position of perimeter and intermediate reinforcing bar
Cast In plates 0%
Cast In plates
- 0%
Check cast in plates. Far Face (flush or recessed)
Subcontractors signature
Engineer inspection 0%
Engineer inspection
- 0%
Engineer to provide approval to pour panel
Photos
site inspection
Check troweling machine is serviced ( fuel and oil) and starts correctly
Check all site services under ground and above ground are protected from
trucks and machinery
Pour Concrete 0%
Pour Concrete
- 0%
Check concrete is vibrated
Check that feast in plates - ferrules- and lifters are secure and haven't
moved
Strip Formwork 0%
Strip Formwork
- 0%
Remove formwork
check for defects
Check all cast in plates ferrules and lifters are still correct
Panel defects 0%
Panel defects
- 0%
List defects
Method of rectification
Site Manager
Sub Contractor