0% found this document useful (0 votes)
448 views

Pre-Cast Concrete Panel Check List

This document is a checklist for inspecting pre-cast concrete panels. It contains over 30 individual inspection criteria across various stages of the pre-cast concrete panel process from setup of formwork and reinforcement to pouring, finishing, and curing of the concrete. However, based on the scores recorded, none of the inspection criteria on the checklist were actually completed, as every item is marked as 0%.

Uploaded by

Alberto SORO
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
448 views

Pre-Cast Concrete Panel Check List

This document is a checklist for inspecting pre-cast concrete panels. It contains over 30 individual inspection criteria across various stages of the pre-cast concrete panel process from setup of formwork and reinforcement to pouring, finishing, and curing of the concrete. However, based on the scores recorded, none of the inspection criteria on the checklist were actually completed, as every item is marked as 0%.

Uploaded by

Alberto SORO
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Powered by iAuditor

Pre-cast Concrete Panel check list


Pre-cast Concrete Panel check list Incomplete

Score 0% Failed items 0 Actions 0

Audit Title

Document No. 000001

Client / Site

Conducted on

Prepared by GUEYESSONGUILE ABDOULAYE


ALBERT SORO

Location

Personnel

Private & Confidential 1/4


Powered by iAuditor

Audit 0%
Audit- 0%

Precast panel Set Up 0%


Precast panel Set
- 0%
Up
Panel Number

Form work and Bond Breaker 0%


Form work and Bond Breaker
- 0%
Check Width height diagonal

Check form work is bolted securely

Check for service penatrations

Check any required fillets have been fixed into position

Check bond breaker has been applied and dry before placing reo bar

Reinforcing Steel 0%
Reinforcing Steel
- 0%
Check size and position of perimeter and intermediate reinforcing bar

Check mesh Tie wire and bar chairs

Cast In plates 0%
Cast In plates
- 0%
Check cast in plates. Far Face (flush or recessed)

Check cast in plates. Near Face. ( flush or recessed)

Check bottom ferrule size and correct position

Ferrule Quantity and Position 0%


Ferrule Quantity and Position
- 0%
Check slab ferrules. FarFace

Check slab ferrules. Near Face

Props and Lifters 0%


Props and Lifters
- 0%
Check prop ferrules. Near Face

Check prop ferrules. Far Face

Check position of Near Face lifters

Check position of Far Face lifters

Check position of Top Edge lifters

Private & Confidential 2/4


Powered by iAuditor

Subcontractors signature

Engineer inspection 0%
Engineer inspection
- 0%
Engineer to provide approval to pour panel
Photos
site inspection

Site Manager signiture

Pre- Pour of Concrete 0%


Pre- Pour of Concrete
- 0%
Check all concrete tools are available

Check concrete crew is adequate to carry out the pour

Check troweling machine is serviced ( fuel and oil) and starts correctly

Check vibrator is serviced ( fuel and oil) and starts correctly

Check backup machines are available

Order concrete pump ( panels above six high)

Order concrete. Confirm correct Concrete strength and confirm Slump


note order concrete with a higher slump if a wetter mix is required. No
water is to be added on site

Check site is clear for concrete truck and pump

Check all site services under ground and above ground are protected from
trucks and machinery

Site manager signiture

Pour Concrete 0%
Pour Concrete
- 0%
Check concrete is vibrated

Check that feast in plates - ferrules- and lifters are secure and haven't
moved

Check panel for flatness

Check all Near Face ferrules have been positioned

Check alcohol has been sprayed onto panel to control drying

Check panel is troweled to a flat hard smooth finish

Check curing oil has been Applied

Private & Confidential 3/4


Powered by iAuditor

Strip Formwork 0%
Strip Formwork
- 0%
Remove formwork
check for defects

Check all cast in plates ferrules and lifters are still correct

Panel defects 0%
Panel defects
- 0%
List defects

Method of rectification

Time frame to rectify panel

Site Manager