Activities Report: Activity ID Activity Name Activity Status Original Duration Early Start Early Finish Longest Path

This document contains a project schedule for the construction of a 2-storey building in Islamabad. It lists over 60 activities in chronological order from start of project to finish of earthworks. The activities include contract agreement, site surveys, excavation, foundation work, walls, floors, and columns. All activities currently have a status of "Not Started" and are planned to take place between August 28, 2020 and December 23, 2020 over a total duration of 96 days.

Uploaded by

sameer khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views

Activities Report: Activity ID Activity Name Activity Status Original Duration Early Start Early Finish Longest Path

This document contains a project schedule for the construction of a 2-storey building in Islamabad. It lists over 60 activities in chronological order from start of project to finish of earthworks. The activities include contract agreement, site surveys, excavation, foundation work, walls, floors, and columns. All activities currently have a status of "Not Started" and are planned to take place between August 28, 2020 and December 23, 2020 over a total duration of 96 days.

Uploaded by

sameer khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Constuction of 2 Storey Building in Islamabad 01-Sep-20 20:30

Activities Report

Activity ID Activity Name Activity Status Original Duration Early Start Early Finish Longest Path

A1000 Start of Project Not Started 0d 28-Aug-20 Yes


A1010 Contract Agreement Not Started 1d 28-Aug-20 29-Aug-20 Yes
A1020 Mobilization of temporary facilities Not Started 14d 29-Aug-20 15-Sep-20 Yes

A1030 Initial Survey Not Started 1d 24-Sep-20 24-Sep-20 Yes


A1040 Site Clearance Not Started 5d 25-Sep-20 01-Oct-20 Yes
A1050 Final Survey Not Started 1d 01-Oct-20 02-Oct-20 Yes
A1060 Start of earthworks Not Started 0d 02-Oct-20 Yes
A1070 Excavation layout Not Started 1d 02-Oct-20 03-Oct-20 Yes
A1080 Excavation of Foundation Not Started 3d 03-Oct-20 07-Oct-20 Yes
A1090 Termite Proofing Not Started 1d 07-Oct-20 08-Oct-20 Yes
A1100 Backfilling Not Started 10d 10-Dec-20 23-Dec-20 Yes
A1110 Finish of Earthwork Not Started 0d 23-Dec-20 Yes
A1120 Start of Foundation Not Started 0d 08-Oct-20 Yes
Structureworks
A1130 Layout of PCC Not Started 1d 08-Oct-20 09-Oct-20 Yes
A1140 PCC under footings Not Started 5d 09-Oct-20 15-Oct-20 Yes
A1150 Column Footings Not Started 20d 15-Oct-20 09-Nov-20 Yes
A1160 Wall Footings Not Started 15d 15-Oct-20 03-Nov-20 No
A1170 Columns upto plinth Not Started 5d 06-Nov-20 12-Nov-20 Yes
A1180 Plinth Beams Not Started 15d 12-Nov-20 01-Dec-20 Yes
A1190 External & Internal water proofing Not Started 5d 01-Dec-20 07-Dec-20 Yes
A1200 Horizontal DPC Not Started 3d 07-Dec-20 10-Dec-20 Yes
A1210 Finish of foundation Not Started 0d 10-Dec-20 Yes
structureworks
A1220 Walls Not Started 5d 28-Aug-20 03-Sep-20 No
A1230 PCC Floor layout Not Started 5d 28-Aug-20 03-Sep-20 No
A1240 PCC Floor Pouring Not Started 5d 28-Aug-20 03-Sep-20 No

© Oracle Corporation Page 1 of 2


Constuction of 2 Storey Building in Islamabad 01-Sep-20 20:30

Activities Report

Activity ID Activity Name Activity Status Original Duration Early Start Early Finish Longest Path

A1250 Columns till first floor Not Started 5d 28-Aug-20 03-Sep-20 No


A1260 Slab construction Not Started 5d 28-Aug-20 03-Sep-20 No

Total 96d 28-Aug-20 23-Dec-20