0% found this document useful (0 votes)
71 views3 pages

Detail of Packages Reviewed: S.No. CRS Document No

This document provides a summary of engineering documents that have been reviewed for a construction project. It includes 10 entries with information on the document number, type of structure or component, sub-discipline, reviewer, and date of review. The documents cover a range of structures for a rail project including station entrance canopies, handrails, foundation slabs, and tunnel framing.

Uploaded by

Sanjoy Sanyal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views3 pages

Detail of Packages Reviewed: S.No. CRS Document No

This document provides a summary of engineering documents that have been reviewed for a construction project. It includes 10 entries with information on the document number, type of structure or component, sub-discipline, reviewer, and date of review. The documents cover a range of structures for a rail project including station entrance canopies, handrails, foundation slabs, and tunnel framing.

Uploaded by

Sanjoy Sanyal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

D

S.No. CRS Document No

1 M-RMT-2B4DS0-CBEC-TRV-015525 M-BMM-2B4DS0-CBEC-ECA-000002

2 NA M-BRA-000DS0-CAST-ECA-000001

3 NA M-BRA-000DS0-CAST-ECA-000002

4 NA M-BRA-000DS0-CAST-ECA-000003

M-BMM-2F1AS0-CBEC-ECA-
5 NA
000005_00B
M-BMM-2F1AS0-CBEC-EDR-
6 NA
009515_000
M-BMM-2F1AS0-CBEC-EDR-
7 NA
009518_000
M-BMM-200AS0-FAB-EDR-
8 NA
100003_00D

9 NA M-BCW-200000-CBST-ECA-000002

10 NA M-BQL-200000-CA00-ECA-000002
Detail of Packages Reviewed
Mail No. Title
Structural Calculation for Aluminum Perforated Panels
M-BAC-WTRAN-185596
Entrance canopy- 2B4- DUG Canopies
Calculation Report for stainless steel floor mounted handrail
M-BAC-WTRAN-186652
type 2B
Calculation Report for stainless steel floor mounted handrail
M-BAC-WTRAN-186652
type GR - 3A & 3B
Calculation Report for stainless steel floor mounted handrail
M-BAC-WTRAN-186652
type GR - 4

M-BAC-WTRAN-182662 At-Grade Stn. 2F1 Calculation Suken Nuts

M-BAC-WTRAN-182662 LINE 2 - STATION 2F1 CANOPY NUT LOCKING SYSTEM

M-BAC-WTRAN-182662 LINE 2 - STATION 2F1 CANOPY NUT LOCKING SYSTEM

Line2- At Grade Station CANOPY SUNKEN NUT


M-BAC-WTRAN-182662
FABRICATION DETAIL
Design of Precast Cover Slab and Lifting Eye at Shallow and
M-BAC-TRANSMIT-147518
At Grade Stations

M-BAC-WTRAN-185136 Structural Calculations for TOR Framing


Sub-Discipline Type ICE reviewer Reviewed

CB00 DUG Sanjoy Sanyal 11/9/2020

CB00 DUG Sanjoy Sanyal 11/9/2020

CB00 DUG Sanjoy Sanyal 11/9/2020

CB00 DUG Sanjoy Sanyal 11/9/2020

CB00 At Grade Station Sanjoy Sanyal 11/10/2020

CB00 At Grade Station Sanjoy Sanyal 11/10/2020

CB00 At Grade Station Sanjoy Sanyal 11/10/2020

CB00 At Grade Station Sanjoy Sanyal 11/10/2020

CB00 At Grade Station Sanjoy Sanyal 11/26/2020

CB00 Line 2 Sanjoy Sanyal 11/26/2020