Widht/ Height/
Length
Sr. No. Item Description No. (m) Breadth Depth Quantity
(m) (m)
1 Earthwork in Excavation in
Foundation:
Footing (1m x 1m) 15 1.30 1.30 2.19 55.52 cu m
2 PCC in Foundation
L / W = 1.3 m H = 40 mm (0.040 m) 15 1.3 1.3 0.04 1.01 cu m
3 Footing
L / W = 1 m H = 150 mm (0.150 m) 15 1 1 0.15 2.25 cu m
4 RCC Column
Size = 230 mm x 230 mm 15 0.23 0.23 2.93 2.32 cu m
Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23 0.23 1.01 cu.m
Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23 0.23 0.31 cu.m
Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23 0.23 0.56 cu.m
Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23 0.23 0.60 cu.m
Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23 0.23 0.52 cu.m
Total 16.60 sq .m
H = 3.98
Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23 0.23 1.01 cu.m
Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23 0.23 0.31 cu.m
Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23 0.23 0.56 cu.m
Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23 0.23 0.60 cu.m
Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23 0.23 0.52 cu.m
Thickness = 150 mm
Deduction
Column (230 mm x 230 mm) 3 0.23 0.23 0.125 0.02 cu.m
H= 0.125 m
Beam
Beam - 1 (230 x 230 mm) L = 3.12 m 3 3.12 0.23 0.15 0.32 cu.m
Beam - 2 (230 x 230 mm) L = 3.80 m 3 3.8 0.23 0.15 0.39 cu.m
Beam - 3 (230 x 230 mm) L = 1.96 m 1 1.93 0.23 0.15 0.07 cu.m
Beam - 4 (230 x 230 mm) L = 3.52 m 1 3.52 0.23 0.15 0.12 cu.m
Beam - 5 (230 x 230 mm) L = 3.79 m 1 3.79 0.23 0.15 0.13 cu.m
Beam - 6 (230 x 230 mm) L = 3.28 m 1 3.28 0.23 0.15 0.11 cu.m
10 Earthfilling up to plinth
L = 13.26 m W = 7.16 m 1 13.26 7.16 0.934 88.68 cu.m
Deduction:
Beam and Wall
Beam - 1 (230 x 230 mm) L = 3.12 m 3 3.12 0.23 0.984 2.12 cu.m
Beam - 2 (230 x 230 mm) L = 3.80 m 3 3.8 0.23 0.984 2.58 cu.m
Beam - 3 (230 x 230 mm) L = 1.96 m 1 1.93 0.23 0.984 0.44 cu.m
Beam - 4 (230 x 230 mm) L = 3.52 m 1 3.52 0.23 0.984 0.80 cu.m
Beam - 5 (230 x 230 mm) L = 3.79 m 1 3.79 0.23 0.984 0.86 cu.m
Beam - 6 (230 x 230 mm) L = 3.28 m 1 3.28 0.23 0.984 0.74 cu.m
7.53 cu.m
Actal Earthwork =
88.68 - 7.53 = 81.14 m 81.14 cu.m
11 Brick Wall GL to PL
Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23 0.704 2.53 cu.m
Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23 0.704 3.08 cu.m
Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23 0.704 0.94 cu.m
Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23 0.704 1.71 cu.m
Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23 0.704 1.84 cu.m
Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23 0.704 1.59 cu.m
11.68 cu.m
L = 3.12 m, W = 0.23 m, H = 3m
Wall - 2
L = 3.80 m, W = 0.23 m, H = 3m 4 3.8 0.23 2.85 9.96 cu.m
Wall - 4
L = 1.96 m, W = 0.23 m, H = 3m 2 1.96 0.23 2.85 2.57 cu.m
Wall - 4
L = 3.52 m, W = 0.23 m, H = 3m 3 3.52 0.23 2.85 6.92 cu.m
Wall - 5
L = 3.79 m, W = 0.23 m, H = 3m 3 3.79 0.23 2.85 7.45 cu.m
Wall - 6
L = 3.28 m, W = 0.23 m, H = 3m 3 3.28 0.23 2.85 6.45 cu.m
Wall - 7
L = 3.12 m, W = 0.23 m, H = 3m 3 3.12 0.23 2.85 6.14 cu.m
Extra Wall
L = 2.29 m, W = 0.23 m, H = 3m 1 2.29 0.23 2.85 1.50 cu.m
53.27 cu.m
Window:
W1 = ( 1.5 x 1.05 m) 1 1.5 0.23 1.05 0.36 cu.m
L = 3.17 W = 0.23 H= 3
Total 5.92 cu.m
Height = 0.90 m
Height = 0.90
Total 6.27 cu.m
Deduction:
Column:
L = 0.23 W= 0.15 m, H = 0.98 m 15 0.23 0.15 0.9 0.47 cu.m
1 Earthwork in Excavation in
Foundation:
Footing (1m x 1m) 12 1.50 1.50 1.50 40.50 cu m
3 Column(300mm x 300mm)
Base(1m x 1m) 12 1.00 1.00 0.15 1.80 cu m
Thickness = 0.15
Stem(0.30 x0.30)
height= 1.25+0.55 = 1.80 m 12 0.30 0.30 1.80 1.94 cu m
Total 3.74 cu m
4 Plinth Beam
Beam (300 mm x 300 mm)
Beam - 1 (3m length) 4 3.00 0.30 0.30 1.08 cu m
Beam - 2 (4m length) 7 4.00 0.30 0.30 2.52 cu m
Beam - 3 (3.4m length) 3 3.40 0.30 0.30 0.92 cu m
Beam - 4 (2.3m length) 3 2.30 0.30 0.30 0.62 cu m
Total 5.14 cu m
Bath / WC Wall:
W1, L = 1.5 m , B= 0.10 m 1 1.50 0.10 3.00 0.45 cu m
W2, L=0.8 m, B= 0.10 m(2.3-1.5) 1 0.80 0.10 3.00 0.24 cu m
Total 51.72 cu m
Deduction:
Door:
D(1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
D1(1.00 X 2.10 m) 1 1.00 0.30 2.10 0.63 cu m
D2(0.75 X 2.10 m) 2 0.75 0.30 2.10 0.95 cu m
MS (1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
Windows:
W(2.00 X 1.20 m) 1 2.00 0.30 1.20 0.72 cu m
W1(1.50 X 1.20 m) 3 1.50 0.30 1.20 1.62 cu m
W2(1.20 X 1.00 m) 2 1.20 0.30 1.00 0.72 cu m
W3(1.20 X 1.20 m) 2 1.20 0.30 1.20 0.86 cu m
Ventilation:
V(0.90 x 0.60 m) 1 0.90 0.30 0.60 0.16 cu m
V1 (0.60 x 0.60 m) 1 0.60 0.30 0.60 0.11 cu m
Cupboard:
CB(1.50 x 1.80 m) 1 1.50 0.15 1.80 0.41 cu m
CB1 (1.20 x 1.80 m) 1 1.2 0.15 1.80 0.32 cu m
Open:
O (1.20 x 2.10) 2 1.20 0.30 2.10 1.51 cu m
Total 9.52 cu m
Lintel:
Door:
D(1.20 X 2.10 m)(L= 1.20+0.15+0.15) 1 1.50 0.30 0.15 0.07 cu m
D1(1.00 X 2.10 m) 1 1.30 0.30 0.15 0.06 cu m
D2(0.75 X 2.10 m) 2 1.05 0.30 0.15 0.09 cu m
MS (1.20 X 2.10 m) 1 1.50 0.30 0.15 0.07 cu m
Windows:
W(2.00 X 1.20 m) 1 2.30 0.30 0.15 0.10 cu m
W1(1.50 X 1.20 m) 3 1.80 0.30 0.15 0.24 cu m
W2(1.20 X 1.00 m) 2 1.50 0.30 0.15 0.14 cu m
W3(1.20 X 1.20 m) 2 1.50 0.30 0.15 0.14 cu m
Ventilation:
V(0.90 x 0.60 m) 1 1.20 0.30 0.15 0.05 cu m
V1 (0.60 x 0.60 m) 1 0.90 0.30 0.15 0.04 cu m
Open:
O (1.20 x 2.10) 2 1.50 0.30 0.15 0.14 cu m
Total 1.13 cu m
8 Slab
L = 7.9 m
B = 10.9 m
H = 0.10 1 7.90 10.90 0.10 8.61 cu m
150 mm
150 mm