100% found this document useful (1 vote)
1K views

Building Estimation Excel Sheet 3D Model 1

The document provides a quantity sheet listing materials needed to construct a building. It includes 12 items with specifications for earthwork excavation, concrete footing, columns, plinth beams, brickwork, slab, parapet wall, and totals. Quantities are provided for excavation of 40.5 cubic meters of earth. Concrete requirements include 3.74 cubic meters for columns and 3.6 cubic meters for plinth beams and slab. Brickwork needs total 53.27 cubic meters.

Uploaded by

nitin yadav
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
1K views

Building Estimation Excel Sheet 3D Model 1

The document provides a quantity sheet listing materials needed to construct a building. It includes 12 items with specifications for earthwork excavation, concrete footing, columns, plinth beams, brickwork, slab, parapet wall, and totals. Quantities are provided for excavation of 40.5 cubic meters of earth. Concrete requirements include 3.74 cubic meters for columns and 3.6 cubic meters for plinth beams and slab. Brickwork needs total 53.27 cubic meters.

Uploaded by

nitin yadav
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 15

QUANTITY SHEET

Widht/ Height/
Length
Sr. No. Item Description No. (m) Breadth Depth Quantity
(m) (m)

1 Earthwork in Excavation in
Foundation:
Footing (1m x 1m) 15 1.30 1.30 2.19 55.52 cu m

L \ W = 1 + 0.15 + 0.15 = 1.3


Depth From GL = 2.19 m

2 PCC in Foundation
L / W = 1.3 m H = 40 mm (0.040 m) 15 1.3 1.3 0.04 1.01 cu m

3 Footing
L / W = 1 m H = 150 mm (0.150 m) 15 1 1 0.15 2.25 cu m

4 RCC Column
Size = 230 mm x 230 mm 15 0.23 0.23 2.93 2.32 cu m

H = 2.93 m (up to Plinth)

5 RCC Beam at Ground Level


Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23 0.23 0.83 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23 0.23 1.01 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23 0.23 0.31 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23 0.23 0.56 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23 0.23 0.60 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23 0.23 0.52 cu.m

Total 3.82 cu.m

6 DPC at Plinth Level


Beam - 1 w = 0.23, L = 3.12 m 5 3.12 0.23 3.59 sq.m

Beam - 2 w = 0.23, L = 3.80 m 5 3.8 0.23 4.37 sq.m

Beam - 3 w = 0.23, L = 1.96 m 3 1.93 0.23 1.33 sq.m

Beam - 4 w = 0.23, L = 3.52 m 3 3.52 0.23 2.43 sq.m


Beam - 5 w = 0.23, L = 3.79 m 3 3.79 0.23 2.62 sq.m

Beam - 6 w = 0.23, L = 3.28 m 3 3.28 0.23 2.26 sq.m

Total 16.60 sq .m

7 RCC Column in Superstructure


Column (230 mm x 230 mm) 15 0.23 0.23 3.98 3.16 cu.m

H = 3.98

8 RCC Beam at Slab Level


Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23 0.23 0.83 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23 0.23 1.01 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23 0.23 0.31 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23 0.23 0.56 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23 0.23 0.60 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23 0.23 0.52 cu.m

Total 3.82 cu.m

9 RCC Slab (1:1.5:3)


L = 13.26 m, W = 7.16 m 1 13.26 7.16 0.125 11.87 cu.m

Thickness = 150 mm

Deduction
Column (230 mm x 230 mm) 3 0.23 0.23 0.125 0.02 cu.m

H= 0.125 m

Beam
Beam - 1 (230 x 230 mm) L = 3.12 m 3 3.12 0.23 0.15 0.32 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 3 3.8 0.23 0.15 0.39 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 1 1.93 0.23 0.15 0.07 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 1 3.52 0.23 0.15 0.12 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 1 3.79 0.23 0.15 0.13 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 1 3.28 0.23 0.15 0.11 cu.m

Total 1.15 cu.m

Total Deduction 1.17 cu.m


Slab Qty after Deduction = 10.70 cu.m

11.87 - 1.17 = 10.70 cu. m

10 Earthfilling up to plinth
L = 13.26 m W = 7.16 m 1 13.26 7.16 0.934 88.68 cu.m

Deduction:
Beam and Wall
Beam - 1 (230 x 230 mm) L = 3.12 m 3 3.12 0.23 0.984 2.12 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 3 3.8 0.23 0.984 2.58 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 1 1.93 0.23 0.984 0.44 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 1 3.52 0.23 0.984 0.80 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 1 3.79 0.23 0.984 0.86 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 1 3.28 0.23 0.984 0.74 cu.m

7.53 cu.m

Actal Earthwork =
88.68 - 7.53 = 81.14 m 81.14 cu.m

11 Brick Wall GL to PL
Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23 0.704 2.53 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23 0.704 3.08 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23 0.704 0.94 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23 0.704 1.71 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23 0.704 1.84 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23 0.704 1.59 cu.m

11.68 cu.m

11 Brick Work in Superstructure

Wall - 1 6 3.12 0.23 2.85 12.27 cu.m

L = 3.12 m, W = 0.23 m, H = 3m
Wall - 2
L = 3.80 m, W = 0.23 m, H = 3m 4 3.8 0.23 2.85 9.96 cu.m

Wall - 4
L = 1.96 m, W = 0.23 m, H = 3m 2 1.96 0.23 2.85 2.57 cu.m

Wall - 4
L = 3.52 m, W = 0.23 m, H = 3m 3 3.52 0.23 2.85 6.92 cu.m

Wall - 5
L = 3.79 m, W = 0.23 m, H = 3m 3 3.79 0.23 2.85 7.45 cu.m

Wall - 6
L = 3.28 m, W = 0.23 m, H = 3m 3 3.28 0.23 2.85 6.45 cu.m

Wall - 7
L = 3.12 m, W = 0.23 m, H = 3m 3 3.12 0.23 2.85 6.14 cu.m

Extra Wall
L = 2.29 m, W = 0.23 m, H = 3m 1 2.29 0.23 2.85 1.50 cu.m

53.27 cu.m

Deduction of Door & Window:


Door :
D = (1.2 x 2.1 m) 2 1.2 0.23 2.1 1.16 cu.m

L = 1.2 m,W = 0.23 m, H = 2.1 m


D2 = (1.0 x 2.1 m) 2 1 0.23 2.1 0.97 cu.m

L = 1.0 m,W = 0.23 m, H = 2.1 m


D3 = (0.82 x 2.1 m) 3 0.82 0.23 2.1 1.19 cu.m

L = 0.82 m,W = 0.23 m, H = 2.1 m

Window:
W1 = ( 1.5 x 1.05 m) 1 1.5 0.23 1.05 0.36 cu.m

L = 1.5 m, W = 0.23 m, H = 1.05 m

Ventilation 2 0.6 0.6 0.23 0.17 cu.m

L = 0.60 m, W = 0.23, H = 0.60

Parking Opening 1 3.17 0.23 2.85 2.08 cu.m

L = 3.17 W = 0.23 H= 3
Total 5.92 cu.m

Actual Qty= 52.27 - 5.92 = 49.87 cu. m 47.35 cu.m


13 Parapet Wall
Long wall, L = 13.72 m, W =0.15 2 13.72 0.15 0.98 4.03 cu.m

Height = 0.90 m

Short Wall, L = 7.62 m, W = 0.15 2 7.62 0.15 0.98 2.24 cu.m

Height = 0.90
Total 6.27 cu.m

Deduction:
Column:
L = 0.23 W= 0.15 m, H = 0.98 m 15 0.23 0.15 0.9 0.47 cu.m

Atual Brick work = 6.27 - 0.47 = 5.81m 5.81 cu.m


To unprotect sheet ang Get passwork , Please Pay 300 rs
to Mobile Number 8905904345 by google pay
any other app and Msg I have paid 3D Estimation Excel Shee
password.
Building Estimation
QUANTITY SHEET
Widht/ Height/
Sr. No. Item Description No. Length Breadth Depth Quantity
(m) (m) (m)

1 Earthwork in Excavation in
Foundation:
Footing (1m x 1m) 12 1.50 1.50 1.50 40.50 cu m

Depth From GL = 1.5 m


2
Footing (1m x 1m) 12 1.3 1.3 0.1 2.03 cu m
Thickness = 0.10

3 Column(300mm x 300mm)
Base(1m x 1m) 12 1.00 1.00 0.15 1.80 cu m
Thickness = 0.15
Stem(0.30 x0.30)
height= 1.25+0.55 = 1.80 m 12 0.30 0.30 1.80 1.94 cu m
Total 3.74 cu m

4 Plinth Beam
Beam (300 mm x 300 mm)
Beam - 1 (3m length) 4 3.00 0.30 0.30 1.08 cu m
Beam - 2 (4m length) 7 4.00 0.30 0.30 2.52 cu m
Beam - 3 (3.4m length) 3 3.40 0.30 0.30 0.92 cu m
Beam - 4 (2.3m length) 3 2.30 0.30 0.30 0.62 cu m
Total 5.14 cu m

5 Earth Filling in Plinth


Bed Room (3m x 4m) 1 3.00 4.00 0.45 5.40 cu m
Kitchen + Dining (4m x 4m) 1 4.00 4.00 0.45 7.20 cu m
Drawing (4m x 6m) 1 4.00 6.00 0.45 10.80 cu m
Bath/ W.C. (3m x 2.3m) 1 3.00 2.30 0.45 3.11 cu m
Varandah (3m x 3.4m) 1 3.00 3.40 0.45 4.59 cu m
Total 31.10 cu m

6 Damp Proof Course(DPC)


57.9 - ((0.3/2)*8)
56.7 1 56.70 0.30 17.01 sq. m
7 Brick Work in Super Structure
57.9 - ((0.3/2)*8)
56.7 1 56.70 0.30 3.00 51.03 cu m

Bath / WC Wall:
W1, L = 1.5 m , B= 0.10 m 1 1.50 0.10 3.00 0.45 cu m
W2, L=0.8 m, B= 0.10 m(2.3-1.5) 1 0.80 0.10 3.00 0.24 cu m
Total 51.72 cu m
Deduction:
Door:
D(1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
D1(1.00 X 2.10 m) 1 1.00 0.30 2.10 0.63 cu m
D2(0.75 X 2.10 m) 2 0.75 0.30 2.10 0.95 cu m
MS (1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
Windows:
W(2.00 X 1.20 m) 1 2.00 0.30 1.20 0.72 cu m
W1(1.50 X 1.20 m) 3 1.50 0.30 1.20 1.62 cu m
W2(1.20 X 1.00 m) 2 1.20 0.30 1.00 0.72 cu m
W3(1.20 X 1.20 m) 2 1.20 0.30 1.20 0.86 cu m
Ventilation:
V(0.90 x 0.60 m) 1 0.90 0.30 0.60 0.16 cu m
V1 (0.60 x 0.60 m) 1 0.60 0.30 0.60 0.11 cu m
Cupboard:
CB(1.50 x 1.80 m) 1 1.50 0.15 1.80 0.41 cu m
CB1 (1.20 x 1.80 m) 1 1.2 0.15 1.80 0.32 cu m
Open:
O (1.20 x 2.10) 2 1.20 0.30 2.10 1.51 cu m
Total 9.52 cu m
Lintel:
Door:
D(1.20 X 2.10 m)(L= 1.20+0.15+0.15) 1 1.50 0.30 0.15 0.07 cu m
D1(1.00 X 2.10 m) 1 1.30 0.30 0.15 0.06 cu m
D2(0.75 X 2.10 m) 2 1.05 0.30 0.15 0.09 cu m
MS (1.20 X 2.10 m) 1 1.50 0.30 0.15 0.07 cu m
Windows:
W(2.00 X 1.20 m) 1 2.30 0.30 0.15 0.10 cu m
W1(1.50 X 1.20 m) 3 1.80 0.30 0.15 0.24 cu m
W2(1.20 X 1.00 m) 2 1.50 0.30 0.15 0.14 cu m
W3(1.20 X 1.20 m) 2 1.50 0.30 0.15 0.14 cu m
Ventilation:
V(0.90 x 0.60 m) 1 1.20 0.30 0.15 0.05 cu m
V1 (0.60 x 0.60 m) 1 0.90 0.30 0.15 0.04 cu m
Open:
O (1.20 x 2.10) 2 1.50 0.30 0.15 0.14 cu m
Total 1.13 cu m

Total Brickwork after deduction Total 41.06 cu m

Beam (300 mm x 300 mm)


Beam - 1 (3m length) 4 3.00 0.30 0.23 0.83 cu m
Beam - 2 (4m length) 7 4.00 0.30 0.23 1.93 cu m
Beam - 3 (3.4m length) 3 3.40 0.30 0.23 0.70 cu m
Beam - 4 (2.3m length) 3 2.30 0.30 0.23 0.48 cu m
Total 3.94 cu m

8 Slab
L = 7.9 m
B = 10.9 m
H = 0.10 1 7.90 10.90 0.10 8.61 cu m
150 mm