Protection Coordination Report: NTPC Limited
Protection Coordination Report: NTPC Limited
NTPC LIMITED
1 EXECUTIVE SUMMARY 3
2 Reference Documents 4
3 Single Line Diagram 5
4 Short Circuit Current Report 13
5 Load Flow Report 15
6 Setting Calculation for Transformers 21
7 Setting Data for ICOG Panel 22
8 Setting Data for LT Panels /MCC 24
9 Time Current Characterstics Curves 30
Executive Summary
Introduction
Project: PAKRI BARWADIH COAL MINING PROJECT
Client: NTPC LIMITED
Electrical Contractor: SIEMENS INDIA LTD, MUMBAI
Electrical Consultant: DEVELOPMENT CONSULTANTS PVT LTD
ElectricalDistribution System 33/6.6/0.415 kV Distribution system
Power System Data
Max Source Fault level (assumed) 1500 MVA sec at 33 kV
The short circuit currents at various busbars are calculated based on the above
assumptions. Calculated Short circuit currents are tabulated in the report and also
shown in the SLD.
Selectivity of relays and circuit breakers were worked out based on the cable size
and flow of short circuit currents.
Time current characterstic curves are generated for every path and verified .
Conclusion
Settings for each device,short circuit currents at every busbars,detailed
calculations for the settings are given in the following pages. No deviation is
observed and the interuupting capacities of the devices are above the calculated
short circuit currents .
Reference Documents STACKER
Sl No File name Document title Document ref
1 Stacker- Power-G71101-J0466-P0101_P2_25.04.18.pdf Power Cable schedule G71101-J0466-P0101
2 7010-602-PVE-P-857-R2.pdf SINGLE LINE DIAGRAM FOR STACKER G71101-J0466-S0101-R3
3 AS BUILD DRAWING-500.pdf GENERAL ARRANGEMENT OF 500 kVA GA-500-SC-18-316
DRY TYPE TRANSFORMER
4 2939-F104.pdf MCC ST 1 G71101-J0466-V1003
SIEMENS INDIA LTD
NTPC LIMITED
T2
7.5 MVA 12.5/16MVA
TH2 SS 6.6 kV
CB2
C:ICOG STACKER
N:ICOG
ICOG
SW1
CB:ICOG
CT:ICOG ±
R:ICOG
Cable T12 HV
TR12 HV
T12
0.5 MVA
T12 LV
Cable T12 LV
CT:PSS_IC2 R R:LTBD_IC
C:BS C:OC C:BOOM CONV C:BOC C:HRC1 C:HRC2 C:CLS1 C:CLS2 C:TD C:CRD
C:HT
N:BOOM OIL COOLER N:HYD R CLAMP1 N:HYD R CLAMP2 N:C LUB SYS 1 N:C LUB SYS 2 N:TRAVEL DRIVE N:CRD
N:HOOTER FOR ST N:BOOM SLEW N:OIL COOLER N:BOOM.CONVE
OIL COOLER BOOM.CONVE BOOM OIL COOLER HYD R CLAMP1 HYD R CLAMP2 C LUB SYS 1 C LUB SYS 2 TRAVEL DRIVE CRD
HOOTER FOR ST BOOM SLEW
AUX LTBD IC 0.37 kW 90 kW 2.2 kVA 1.5 kVA 1.5 kVA 0.75 kVA 0.75 kVA 150 kVA 3 kVA
0.37 kVA 15 kW
AUX LT BD
0.415 kV
SW:PWD1 SW:PWD2 SW:LT SW:CT SW:WS1 SW:WS2 SW:WS3 SW:UPSS1 SW:AC OPC SW:CT2 SW:AC EC1 SW:AC EC2
F:PWD1 F:PWD2 F:LT F:CT F:WS1 F:WS2 F:WS3 F:UPSS1 F:AC OPC F:CT2 F:AC EC1 F:AC EC2
C:PWD1 C:PWD2 C:WS1 C:WS2 C:WS3 C:UPSS1 C:AC OPC C:AC EC1 C:AC EC2
N:CONT.TR N:CONT.TR2
N:PWD SS1 N:PWD SS2 N:LIGHT.TR1
CONT.TR N:WS1 N:WS2 N:AC OP CABIN CONT.TR2 N:AC EL CABIN1 N:AC EL CABIN2
LIGHT.TR1 N:WS3 N:UPSS
3 kVA 3 kVA
10 kVA
PWD SS1 PWD SS2 WS1 WS2
11 kVA 11 kVA 47.25 kVA 47.25 kVA UPS1 AC OP CABIN AC EL CABIN1 AC EL CABIN2
WS3
47.25 kVA 5 kVA 1.7 kVA 1.7 kVA 1.7 kVA
RELAY COORDINATION ANALYSIS
This chapter covers the protection co-ordination of over current & earth fault elements for various protection devices
installed at various voltage levels starting from 33kV, 6.6kV & 0.415kV (PCC Incomers) in the plant.
Protection coordination has been reviewed to achieve sensitivity, speed, selectivity and reliability to isolate faults from the
rest of the healthy system and minimize the plant loss due to the faults under all foreseen system operation conditions.
Relay characteristics has been selected to give optimal performance in terms of sensitivity and rapidity of fault clearance.
This has resulted in the use of inverse time schemes supplemented by instantaneous/definite time schemes for phase over
current protection and earth fault protection of solidly earthed systems; and definite time schemes for earth fault
protection of resistance earthed systems.
Over-currents in a power distribution system can occur as a result of both normal (motor starting, transformer inrush, etc.)
and abnormal (ground fault, line-to-line fault, etc.) conditions. In either case,the basic purpose of current-sensing
protective devices is to detect the abnormal over-current with proper coordination, to operate selectively and to protect
equipment properly by minimizing the outage of the remainder of the system.
Relay operating characteristics and their setting must be carefully coordinated in order to achieve selectivity. The aim of
selectivity is to switch off only the faulty component and to leave the rest of the power system in service in order to
minimize supply interruptions and to ensure stability. Protection should be as sensitive as possible to detect faults at the
lowest possible current level of both phase and ground faults. However, it should remain stable under all permissible load,
overload and through-fault conditions.
Primary Protection: The protective system, which is normally expected to operate in response to a fault in the protected
zone.
Back-Up Protection: A protective system intended to supplement the main protection in case the later should be
ineffective, or to deal with faults in those parts of the power system that are not readily included in the operating zones of
the main protection.
The setting of the existing relays is proposed by modeling the network from 33kV to 0.4 kV along with all phase fault and
earth fault protection relays in ETAP 19.1 Software.
b. The impedance in ohms, percent or per unit of all power transformers, rotating machines if any and feeder circuits.
c. The maximum and minimum values of short circuit currents that are expected to flow through each protective device.
The maximum and minimum short circuit level has been calculated depending upon number of sources in service.
There are two basic adjustable settings on all inverse time relays; one is the current setting usually known as the Plug
Setting Multiplier (PSM) and the other is Time Multiplier Setting (TMS).
𝑻𝑶𝑷
𝑻𝑴𝑺 =
𝑻𝑴
Where,
TOP = the required time of operation
TM = The time operation at TMS =1.0 for maximum fault current
(b) The grading time comprises of the following component times as recommended in Ref. 3:
2. CONSIDERATIONS
1. Grid 3Ph & 1Ph fault level is considered as (1500MVA) at 33kV level.
2. MV Connection has 1x 7.5MVA, 33/6.6kV, 8%Z, dnY transformer. 1x12.5/16MVA,33/6.6kV,10%Z,Dyn11
3. 0.2s Is considered as the minimum time of operation at the PCC incomers assuming this as maximum time required to
clear the fault for the downstream network.
4. The circuit breakers installed at 0.415kV PCC Incomers have no releases.
Their settings should be correctly implemented as per the directions provided in relay coordination
setting sheet.
10 times the transformer full load current (to account for the inrush current)
1.3 times the through fault current reflected on the primary (MV) side, for a fault on the LV sideof the transformer
Whenever there is a fault on LV side, when the fault current magnitude is such that the time ofoperation on primary side is
more due to IDMT characteristics under such scenario, an additionaDMT characteristics is to be provided. Pickup is
adjusted as follows.
Pickup: DMT pickup current of LV side x Transformation ratio x Factor (1.3)
TMS: Time is adjusted by providing the coordination time interval as per Table 8-1.
In all the cases, the earth fault coordination is achieved considering the DMT characteristics only.
The pickup is provided as 100% of Ir. and Time is set to instantaneous.
3.4. MV feeders
Here the IDMT pickup is set considering the summation of rated current of all the individual transformer or motor feeders
under that substation. Characteristics curve and TMS is selected in such a way that, the highest rated motor under that
substation should starts with its starting current flow for its time required to its rated speed.
DMT pickup is set by coordinating it with the highest instantaneous pickup on T/r primary side or Motor feeders under that
plant. Normally Ipickup = Highest instantaneous/DMT pickup x 1.1 to 1.2
E/F DMT pickup is set by coordinating it with the highest instantaneous pickup on T/r primary side or Motor feeders under
that plant. Normally Ipickup = Highest instantaneous/DMT pickup x 1.1 to 1.5.
SHORT CIRCUIT ANALYSIS
Short Circuit Analysis performed to check the adequacy of existing switchgears and recommendations are given if any switchgears violating the rated
breaking capacity. Short circuanalysis shall be performed based on IEC 60909-2001 method. Grid fault level for 3 Ph is considered 1500 MVAsec for 33kV
source
Short circuit model has been developed for both the three-phase & single phase short circuit analysis.The three-phase & single phase short circuit study has
been conducted for various network operatin scenarios specified in Table The model considers positive, negative and zero sequenceparameters.
1. VOLTAGE FACTORS
The “equivalent source” technique adopted in IEC 60909-2001 recommends applying a voltage factoC (Cmax or Cmin) to the pre-fault nominal system
voltage, in order to obtain the voltage magnitude othe equivalent source at the fault location. Table 1 shows c-factors for various voltage levels. Theare
important in distinguishing between maximum and minimum short-circuit currents and arintroduced in order to account for pre-fault system loading, off-
nominal transformer taps etc.
NTPC LIMITED
AUX LT BD 0.415 13.723 22.435 12.039 12.577 20.561 12.577 12.577 11.814 19.314 11.814 11.814 13.892 22.711 13.892 13.892
LT SWBD STACKER 0.415 14.140 23.646 12.039 12.812 21.424 12.812 12.812 12.153 20.323 12.153 12.153 14.335 23.972 14.335 14.335
N:ICOG 6.600 7.744 18.425 7.625 7.817 18.598 7.817 7.817 6.703 15.947 6.703 6.703 7.850 18.675 7.850 7.850
T12 LV 0.415 15.516 26.524 13.414 15.285 26.129 15.285 15.285 13.347 22.816 13.347 13.347 15.728 26.886 15.728 15.728
TH2 SS 6.600 7.860 19.931 7.743 7.991 20.263 7.991 7.991 6.803 17.251 6.803 6.803 7.936 20.123 7.936 7.936
All fault currents are in rms kA. Current ip is calculated using Method C.
* LLG fault current is the larger of the two faulted line currents.
SIEMENS INDIA LTD
NTPC LIMITED
* Indicates operating load of a bus exceeds the bus critical limit ( 110.0% of the Continuous Ampere rating).
# Indicates operating load of a bus exceeds the bus marginal limit (100.0% of the Continuous Ampere rating).
Project: ETAP Page: 2
Transformer
CKT / Branch Busway / Cable & Reactor
Loading (input) Loading (output)
Ampacity Loading Capability
ID Type (Amp) Amp % (kVA) kVA % kVA %
Vd
From-To Bus Flow To-From Bus Flow Losses % Bus Voltage
% Drop
C:AC EC1 1.6 0.0 -1.6 0.0 0.0 0.0 101.4 101.3 0.05
C:AC EC2 1.6 0.0 -1.6 0.0 0.0 0.0 101.4 101.3 0.05
C:AC OPC 1.6 0.0 -1.6 0.0 0.0 0.0 101.4 101.1 0.22
C:AUX LT BD -174.2 -0.1 174.6 0.3 0.4 0.2 101.4 101.6 0.23
C:PWD1 10.1 0.0 -9.9 0.0 0.3 0.0 101.4 98.8 2.61
C:PWD2 10.1 0.0 -9.9 0.0 0.3 0.0 101.4 98.8 2.61
C:UPSS1 4.7 0.0 -4.7 0.0 0.0 0.0 101.4 101.2 0.15
C:WS1 48.2 0.0 -47.9 0.0 0.3 0.0 101.4 100.6 0.72
C:WS2 48.2 0.0 -47.9 0.0 0.3 0.0 101.4 100.6 0.72
C:WS3 48.1 0.0 -47.6 0.0 0.5 0.0 101.4 100.4 1.00
C:BS 14.7 6.3 -14.6 -6.3 0.1 0.0 101.2 100.6 0.63
C:OC 0.4 0.2 -0.4 -0.2 0.0 0.0 101.2 101.1 0.09
C:CLS1 0.7 0.0 -0.7 0.0 0.0 0.0 101.2 101.0 0.17
C:CLS2 0.7 0.0 -0.7 0.0 0.0 0.0 101.2 101.0 0.17
C:HRC1 1.5 0.0 -1.5 0.0 0.0 0.0 101.2 101.0 0.23
C:HRC2 1.5 0.0 -1.5 0.0 0.0 0.0 101.2 101.0 0.27
C:CRD 3.0 0.0 -3.0 0.0 0.0 0.0 101.2 100.8 0.38
C:HT 0.4 0.0 -0.4 0.0 0.0 0.0 101.2 101.1 0.10
C:TD 148.7 0.3 -147.9 0.0 0.8 0.3 101.2 100.7 0.54
Cable T12 LV -261.5 -44.8 262.4 45.2 0.9 0.4 101.2 101.6 0.37
C:BOC 2.2 0.0 -2.2 0.0 0.0 0.0 101.2 100.7 0.56
C:BOOM CONV 87.8 38.0 -87.3 -37.9 0.5 0.1 101.2 100.7 0.52
C:ICOG STACKER -447.4 -61.0 447.6 60.9 0.1 -0.1 104.4 104.4 0.03
Cable T12 HV 447.4 61.0 -447.4 -61.0 0.0 0.0 104.4 104.4 0.01
T12 -437.0 -45.5 447.4 61.0 10.4 15.6 101.6 104.4 2.81
15.1 18.7
Project: ETAP Page: 4
% Alert Settings
Critical Marginal
Loading
Bus 110.0 100.0
Bus Voltage
OverVoltage 110.0 105.0
Generator Excitation
OverExcited (Q Max.) 100.0 95.0
Marginal Report
kW kvar kVA % PF
Number of Iterations: 3
Setting Calculation for Power Transformer STACKER
Transformer capacity PT 500 kVA
Primary Voltage Vp 6.6 kV
Secondary Voltage Vs 0.433 kV
Transformer HV side CT details CTHV 60/1
Turns Ratio CTR1 60
Transformer LV side CT details CTLV 800/1
Turns Ratio 800
Percentage Impedance of Transformer Z 5.00%
Fault Current at 6.6 kV Bus 6703 A
Fault current at 0.415 kV Bus as per report 12153.00 A
Transformer Full Load HV side Primary Current at 0% tapping Ipfl 500/ (1.732 X6.6) Amps
Transformer Full Load HV side Primary Current at -0% tapping 43.74 Amps
NTPC LIMITED
NTPC LIMITED
V kn 284.30 volts
10% Percent setting
Required Loop Resistance value
Rs=Vs/Is
Is=10 % 10
Is= 0.1 Amps 0.1 Amps
Vs= 142.15 volts
Rs= 1421.50 ohms
Relay VA burden= VA 1
Relay resistance= VA/Is2 100 ohms
Rstab=Rs-Relay resistance 1321.50 Ohms
rounded off to 1320 ohms
SIEMENS INDIA LTD
NTPC LIMITED
500 500
300 300
100 100
50 50
30 30
10 10
R:ICOG - P
5 5
Seconds
Seconds
OC1
3 3
R:LTBD_IC - P
OC1
1 1
.5 .5
.3 .3
.1 .1
.05 .05
.03 .03
.01 .01
.5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K
Amps N:ICOG (Nom. kV=6.6, Plot Ref. kV=6.6) ETAP Star 18.0.0C
STACKER
500 500
300 300
100 100
50 50
30 30
10 10
R:ICOG - N
5 5
Seconds
Seconds
OC1
3 R:LTBD_IC - N 3
OC1
1 1
.5 .5
.3 .3
.1 .1
.05 .05
.03 .03
.01 .01
.5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K
Amps N:ICOG (Nom. kV=6.6, Plot Ref. kV=6.6) ETAP Star 18.0.0C
STACKER