Weekly Work Progress Report For PAL-Zone
Weekly Work Progress Report For PAL-Zone
Company
Total
Building Project Cost
Project Name Project Code area Start date Finish date
Type (Lakh)
(sft)
Single-storied
Spice Shed -01 RCC building
P PAL 42,000 200.50 15/10/020
Floor casting
P Spice Shed -01 Paint work
PAL 47,500 61.75 25/11/020
Floor Paint work
P Paint Work
Retort Bldg Roof NAL 11,200 19.89 20/10/020 05/11/020
top Paint work
P RCC Road RCC Road
casting work
PAL 7000 33.22 12/10/020 30/12/020
P M.Oil M/C base NAL RCC Foundation 200 5.24 24/09/020 25/10/020
Single-storied
RCC building
P Coconut shed NAL 7560 57.45 01/10/020 30/12/020
extension
PAL-02
Dist. Loading Single-storied
unloading point RCC building
with canopy PAL-2 3520 56.35 11/08/202 30/10/020
work.
Parking area with RCC drain and
drain work double
PAL-2 interlock block 10050 56.35 25/10/020 30/11/020
PDC Shahjadpur(PRAN-Depot)
P Chattle feed mill Single-storied
Shed RCC building
PDL 4,900 26/08/020 30/11/020
Up coming Project(PRAN-Depot)
Develomnent
P Main Gate PAL work
OHWT shifting Develomnent
PAL work
Spice shed
internal all works PAL
Expeller & Ghani
M/C base NAL
Main gate
finished PAL-2
RCC road
PAL-2
M. oil bldg-2 PAL-2
AHU shed on the
Noodles roof top PAL
Printing M/C Ishwardi
AL-Zone
work
Construction Status Remarks
progress
Need materials
Existing all pit increase up to floor & floor filling 5%
ongoing Need to remove
obstacle materials &
pipe line
As discousion with GM sir it will start later.
Depot)
Footing, s/column, g/b floor sand filling & macadam
filling done, anchore bolt fitting done & casting also
done. And floor ready for casting.. Truss work pending 35%
due to contractor select.
Materials pending
All civil work done, floor chipping work done for tiles
work, tiles work ongoing, drain work ongoing. 65%
-Depot)
Need drawing, BOQ &
Financial approval.
T/Tank=03#
(10000ltr+10000ltr+50
00ltr=25000ltr)
Need working drawing
Approval donr but working drawing not finnal final,
Need BOQ & financial
Drawing ok approval.
Materials PR done.
Need layout &
finnancial approval.
Need drawing
BOQ ongoing
Need Drawing