Progress Measurement System PMS PDF

This document outlines the progress measurement procedure for engineering, procurement, construction and commissioning phases of a project. It defines responsibilities and the method for measuring physical progress. Progress will be measured based on completion of deliverables, issues, and approvals. The project is broken into work packages that are assigned weight factors to calculate overall progress percentages at each phase. Milestones will be set upfront for measuring progress of each activity.

Uploaded by

Mohamed Atef
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
655 views

Progress Measurement System PMS PDF

This document outlines the progress measurement procedure for engineering, procurement, construction and commissioning phases of a project. It defines responsibilities and the method for measuring physical progress. Progress will be measured based on completion of deliverables, issues, and approvals. The project is broken into work packages that are assigned weight factors to calculate overall progress percentages at each phase. Milestones will be set upfront for measuring progress of each activity.

Uploaded by

Mohamed Atef
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Document Title: Progress Measurement Procedure

Document Number: 8903-00-PL-PCJ-007-7 Page 3 of 9

Table of Contents

1. Purpose ............................................................................................................................................ 4

2. Scope ................................................................................................................................................ 4

3. Definitions and Abbreviations....................................................................................................... 4

4. Responsibilities ............................................................................................................................... 4

5. Method of Physical Progress Measurement ................................................................................. 5


5.1 Engineering ............................................................................................................................. 5
5.2 Procurement ............................................................................................................................ 8
5.3 Construction ............................................................................................................................ 9
5.4 Commissioning, Start-Up & Performance Test ...................................................................... 9
Document Title: Progress Measurement Procedure

Document Number: 8903-00-PL-PCJ-007-7 Page 4 of 9

1. Purpose
This procedure defines the physical progress measurement and progress calculation
method for the PROJECT.

2. Scope
This progress measurement procedure, describes the physical progress calculation
throughout engineering, procurement, construction and commissioning

3. Definitions and Abbreviations


Owner
MC
Licensor
Contractor

4. Responsibilities
Planning and Project Control Department is responsible for preparing and issuing the
Progress Measurement Procedure for approval at the beginning of the PROJECT and
shall be responsible for executing the requirements of this procedure.
Document Title: Progress Measurement Procedure

Document Number: 8903-00-PL-PCJ-007-7 Page 5 of 9

5. Method of Physical Progress Measurement

The project divided into four (4) phases for measuring the project progress and a weight
percentage assigned to each part in proportion to the contract amount.
The four phases are as follow:
- Engineering
- Procurement
- Construction
- Commissioning
A detail breakdown of all work activities (Work Breakdown Structure – WBS (code: 8903-00-
PL-WBS-001)) with its weight factor shall be prepared. The breakdown shall be used for the
assessment of the project progress after the OWNER / MC’s review and approval. The
progress percentage of each activity in the lowest level of WBS shall be summarized by its
weight factor and generate the progress percentage in the higher level of the WBS.
The physical progress measurement milestones for assessment of all activities separately in
engineering, procurement, construction and commissioning phase shall be developed at
the start of the project and submitted to the OWNER / MC for approval.

5.1 . Engineering

For the engineering phase of the project, the physical progress measurement criteria shall be
based on the actual deliverables issued for OWNER / MC approval and the already
approved deliverables and non-deliverables. Such List shall be defined for each discipline
in early stage of project. Work steps for measuring the physical progress of engineering
deliverables will be done according to following table :
Document Title: Progress Measurement Procedure

Document Number: 8903-00-PL-PCJ-007-7 Page 6 of 9

a) IFA
First Issue: 65%
Second Issue: 15%
Final Issue: 20%

b) IFR
First Issue: 60%
Second Issue: 20%
Final Issue: 20%

c) IFI
First Issue: 60%
Second Issue: 20%
Final Issue: 20%

 Level 5th of WBS should be considered as deliverables. In case of any change in the list
of deliverables, Weight Factor for added documents should be considered as Zero and for
deleted documents, 100% progress should be consider

Note: Weights of not issued documents which will be deleted from project MDR shall be divided
between other not issued documents in same category equally
Document Title: Progress Measurement Procedure

Document Number: 8903-00-PL-PCJ-007-7 Page 7 of 9

Sample:

Step of Issued FINAL STATUS


FIRST SECOND Or higher.. FINAL
IFQ IFP IFD IFC
IFI 60% 20% 20%
Process Design for doc witch final status is IFD
x for doc witch final status is IFD the step will be passed x
Calculations the step will be passed
x
if any x x x
for doc witch final status is IFC
x
if any x x x
for doc witch final status is IFP
60% 20%
IFR 20%
PURPOSE OF ISSUE

Owner comment IFQ IFP IFD IFC


First issue
implementation
x
Equipment anchor loads x for doc witch final status is IFD the step will be passed x
by second issue
Plan drawing of rack x x
x x
piping by second issue for doc witch final status is IFC
x x
MR for steel structure x x
by second issue for doc witch final status is IFP
x x
TBA for steel structure x x
by second issue for doc witch final status is IFP
65% 15%
IFA First issue Owner approval
20% IFQ IFP IFD IFC

Project procedure x x for doc witch final status is IFD the step will be passed x
x
Plot plan x x x
for doc witch final status is IFC
x
MR for M List x x x
for doc witch final status is IFP
TBA for M List x x for doc witch final status is IFD the step will be passed x
Document Title: Progress Measurement Procedure

Document Number: 8903-00-PL-PCJ-007-7 Page 8 of 9

5.2 . Procurement

The equipment and material control log shall be prepared. In which every equipment /
material, with their associated weight value shall be shown. The weight factor shall be
established based on the price breakdown of all equipment and bulk material of this project.
The specific tasks in sequence of work steps related to each equipment, are utilized as the
physical progress measurement milestones which shall show the steps of progression to
complete a procurement activity. The procurement physical progress achieved shall be
ascertained from the approved weighting factors as below:

Procurement:

Pre Order: 10%


• MR 20%
• TBA 50%
• Contract / PO 30%
Note: Contract/PO means PO shall be countersigned between purchaser and seller.

Work steps for measuring the physical progress of MR and TBA will be done as
per table of article 5.1 above.

Post Order: 90%


• Manufacturing & inspection 90%
Vendor’s approved progress shall be applied.

• Transportation & Delivery to Site: 10%


Delivery to Port of Departure (FOB) 20%
Delivery to Port of Destination (CFR) 40%
Custom Clearance 30%
Transportation & Delivery at Site 10%

Note: for domestic equipment 100% progress will be achieved after delivery of the goods to the
site.
Document Title: Progress Measurement Procedure

Document Number: 8903-00-PL-PCJ-007-7 Page 9 of 9

5.3 . Construction
For the construction phase of the project, the physical progress measurement criteria shall
be derived from quantities or volumes completed versus quantities or volumes required
refer to 3rd clause of CONTRACT. The estimation of quantities shall be extracted and
shown.
Construction physical progress achieved shall be derived from the approved weighting
factors established for incremental steps required to complete all types of field construction
activities per discipline which will be finalized later. In fact, these steps are used for
assessment of the progress for the construction activities as the physical progress
measurement milestones.

5.4 . Commissioning, Start-Up & Performance Test

For the Commissioning, Start-Up & Performance Test phase of the project, the physical
progress measurement criteria shall be ascertained from the approved weighting factors as
below:

Commissioning 50%
- Completion of Compressors Test 50%
- Completion of Integral Functional Test of the Plant 50%

Start-Up 25%

Performance Test 25%