Labor Production Rates: Concrete Works
Labor Production Rates: Concrete Works
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
CONCRETE WORKS Carpenter Steel Fixer Con Mason Helper
b Concrete m 3
20 2 3
2 PCC below slab on grade
a Formwork m2 25 1 1
b Concrete m 3
40 2 3
3 Column footings / Pile Caps
a Formwork m2 30 2 2
b Reinforcement (fabrication & fix) kg 170 1
c Concrete m 3
55 2 2
4 Strip footings
a Formwork m2 25 2 2
a Formwork m2 25 2 1
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m3 20 1 2
6 Tie Beams
a Formwork m2 30 2 1
7 Slab on grade
a Formwork & Joints m2 of slab 200 2 1
b Mesh Reinforcement m 2
300 2
8 Retaining Walls
a Formwork m2 30 3 1
c Concrete m3 18 1 2
d De-Shuttering m 2
9 Shear Walls
a Formwork m2
b Reinforcement (fabrication & fix) kg
c Concrete m3
d De-Shuttering m2
c Concrete m3 9 1 2
d De-Shuttering m 2
Page 1 of 5
LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
CONCRETE WORKS Carpenter Steel Fixer Con Mason Helper
11 Beams
a Formwork m2 20 2 2
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m3 15 1 2
d De-Shuttering m 2
12 Slabs (Solid)
a Formwork m2 15 1 1
b Reinforcement (fabrication & fix) kg 200 1
c Concrete m 3
75 3 3
d De-Shuttering m2
13 Slabs (Hourdy)
a Formwork m2
b Reinforcement (fabrication & fix) kg
c Concrete m3
d De-Shuttering m2
14 Parapets
a Formwork m2 20 2 2
b Reinforcement (fabrication & fix) kg 175 1
c Concrete m 3
12 1 1
15 Cantilevers
a Formwork m2 12 1 1
a Formwork m2 15 1 1
b Reinforcement (fabrication & fix) kg 170 1
c Concrete m3 20 1 1
17 Ramps
a Formwork m2
b Reinforcement (fabrication & fix) kg
c Concrete m3
18 Lintels
a Formwork m2 8 1 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m 3
5 1 1
Page 2 of 5
LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
BLOCK WORK Block Mason Helper
Sub-Structure - Solid Blocks
1 200 mm Blockwork m2 12 1 1
Super-Structure (upto 3m height) - Solid Blocks
1 100 mm Blockwork with pointing m2 15 1 2
1 Cover Block m2 9 1 1
2 Cutting & Chasing m 2
Page 3 of 5
LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
TILING WORK Tiler Helper
1 Ceramic Floor Tiles m2 20 1 1
9 Terrazzo Tiles m2 20 1 1
10 Terrazzo Skirting LM 40 1 1
11 Terrazzo Treads & Risers LM 30 1 1
2 Ceiling Tiles m2 60 1 1
3 Gypsum Ceiling & Cornish (i/c Suspension System) m 2
2.5 1 1
4 Dry wall partition m 2
20 1 1
Page 4 of 5
LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
WOOD WORKS Joiner Helper
1 Wooden frames fixing for openings upto 5 m 2 nos 8 2 1
7 Handrail LM