Pile Boring Analysis PDF

The document provides cost estimates for bored cast-in-situ reinforced concrete piles. It includes costs for: 1) Materials like concrete and bentonite required for the piles. 2) Machinery hire charges for the hydraulic piling rig, crane, pumps, and vehicles for transporting material. 3) Labour costs for supervisors and workers. 4) Overhead charges of 8% on material and labour costs. 5) Contractor's profit of 10% on total of material, labour, and overhead costs. The total estimated cost per meter of pile is provided.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
382 views

Pile Boring Analysis PDF

The document provides cost estimates for bored cast-in-situ reinforced concrete piles. It includes costs for: 1) Materials like concrete and bentonite required for the piles. 2) Machinery hire charges for the hydraulic piling rig, crane, pumps, and vehicles for transporting material. 3) Labour costs for supervisors and workers. 4) Overhead charges of 8% on material and labour costs. 5) Contractor's profit of 10% on total of material, labour, and overhead costs. The total estimated cost per meter of pile is provided.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

12.25 1100 & Bored cast-in-situ M35 grade R.C.C.

Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 5755.15 58529.88

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 3065.22 18391.32
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 200.00 100.00
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.50 452.17 226.09
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 506.09 253.05
bore hole
Bentonite kg 385.00 2.69 1035.65
c) Labour
Mate/Supervisor day 0.18 233.50 42.03
Mazdoor day 4.50 213.50 960.75
d) O h d charges
Overhead h @ 8 % on (b+
(b+c)) 1680 71
1680.71
e) Contractor's profit @ 10 % on (b+c+d) 2268.96
Cost for 9 m = a+b+c+d+d+e 83488.42
Rate per metre (a+b+c+d+e)/9 9276.49
Add for labour welfare cess @1% 92.76
Total cost 9369.25