03B. Pre-Mobilisation Checklist For Civil & Distribution
03B. Pre-Mobilisation Checklist For Civil & Distribution
KEC/IMS/EHS/07/F/03B
Pre-Mobilization Checklist Issue no. 2 Rev. no. 0
Civil & Distribution
Issue date 08.12.2018 Rev. date
Date of Inspection :
Name of Project & Location :
Project Manager /Construction Manager:
Regional EHS Manager / Engineer / Officer :
S. No. Items Check point Y N NS Remark
Is there any overhead line in Material storage area/Work Area etc. If
yes;
The risk shall be identified by goal posts Installed or other measures
to be taken like barriers etc.)
Is there proper approach road at site for material handling.
Is there any waterlogging at site
Storage and Are there any provisions for proper electrical connection
1 work Area Is there provision for drinking water at site
Are all hazardous materials kept within a locked storage area, and
warning signs or boards barricading arrangement shall be done as per
requirement
Are there any other materials need to be stored in designated storage
areas as agreed with the Site Management
Are ground conditions levelled for material movement and storage
Are there PPEs Identified as per HIRA risk assessment
Safety Helmet Safety Shoes
Personal
Full body harness Lifeline Rope Reflective Jacket
2 Protective
Goggles Other..................
Equipment
Is list of Tools & Tackles like slings / hooks / D-shackles with relevant
& valid certificates and identification marking color coding available
EHS
8 Compliance Is there any list of construction equipment with valid vehicle
documents & copy of valid driving licenses of driver
Are all cranes/ hydras with relevant & valid certificates & copy of valid
driving licenses of driver
Is there toilet facility in store area
Are there any loss on environment while establishment of store like
cut of tree and other nature.
Welfare and Are all washing facilities, accommodation for taking meals and other
9 Environment ancillary welfare accommodation are provided and maintained
Ensure that no smoking site and smoking, except within designated
smoking areas, is strictly prohibited.
Is there hazardous waste collection/storage point identified
Do all drivers wear PPE – High visibility clothing worn by all on site
Ensure no live wires or pipe line below or above the area where
excavation is going to take place unless we have mitigations
procedures
Are there portable ladders available at store for foundation and other
work.
Is there arrangement done like DG Set / Additional batteries/ torches
Preliminary / for emergency/ Area lighting
12 Enabling work
Is there barricading tape / chain available
Local Issues Are there any local issues to be taken into account if any and are
14 and ROW control measures taken to deal with it
Are there procedures, policies and responsibilities towards site by
15 Housekeeping
the sub contractor.
Any other
16 Other
Any other
Deviation In case of deviation, please request for approval and only PCH/ RM/ Head of EHS Civil can approve the deviation with other
contingency measures
Deviation Approved by
(PCH/ Country Head ) (RM-EHS) / T&D Corporate EHS
Y - Yes, N - No, NS - Not Satisfactory