Ganjeena Lectures-Ar
Ganjeena Lectures-Ar
By;
Fall - 2020
Methods of Construction and Estimating
Each project has many phases to be complete:
Planning
designing
Budgeting
Tendering
Contracting
Implementing
Supervising
Following up
Evaluating
Planning: To plan for the required projects according to the demand of the
nationality depending on the strategically plan prepared previously. The
planner should take in consideration the government policy situation, the
availability or the capability of finance, the exact necessary for the project
and the capability of implementation.
Contracting: will take place when the previous steps were finished, this will
be through an agreement between the government or the owner of the
project and the implementer. The agreement should mention for the total
budget, the duration of the project, the mechanism of payments and other
criteria's such as the delay penalty.
Supervising and following up: the project during the implementation will
be supervised by expert group and at the same time it will be followed up
by another group. This to:
1. Insure the specifications required or agreed on in the agreement.
2. Discuss the means for implementing the ITEMs.
3. Control the level of implemented works.
4.Solve the unexpected problems closely.
5. Forward the payments.
6. Receive the implemented hidden ITEMs.
Engineering Design
Engineering design for any project should consist the following after taking
in consideration the identified finance, economic, availability of crude
materials and the capability of the implementers:
Project schedule plan is the main plan included in any Project Management
Plan. Project schedule is responsible for bringing project time, cost and
quality under control. Project schedule links resources ,
tasks and time line together. Once a Project Manager has list of resources,
work breakdown structure (WBS) and effort estimates, he is good to go for
planning project schedule. Schedule network analysis helps Project
Manager to prevent undesirable risks involved in the project. Two main
types of networks are followed:
AOA Diagram: Activity on arrow diagram (arrow diagraming), and
AON Diagram: Activity on node diagram (precedence diagram).
Event: A work has time during within the project. Event could be the
time at which an activity is completed.
Dummy Activity: An artificial activity with zero time duration that only
shows a precedence relationship among activities.
Activity description
Duration of activity
Node Number
k
k
c or d
j
a j
Early Start (ES): Earliest possible point in time on which a task can start.
Early Finish (EF): Earliest possible point in time on which a task can finish.
Late Start (ES): Latest possible point in time on which a task can start.
Late Finish (EF): Latest possible point in time on which a task can finish.
NOTE:
- Critical path has zero or negative Total Float. A project can have
several critical paths.
- Early Start and early finish dates are calculated by means of
Forward Pass and Late Start and Late Finish dates are calculated by
means of Backward Pass.
- Many Tasks have some amount of buffer added to them referred as
Slack Time or Float.
Float time: Is the amount of time a task can slip before it delays project
schedule. There are two common types of floats:
Free Float: Amount of time a single task can be delayed without delaying
the early start of any successor (follow) task.
Total Float: Amount of time a single task can be delayed without delaying
project completion. Mathematically:
7 day
Window frame
Installing 3 day
3
( AOA ) diagram, CP (critical path) = 22 days
Example:
Task Pred. Dur. Task Pred. Dur.
a -- 4 g c,d 1
b -- 3 h e 4
c a 3 i f 5
d a 2 j e,g 6
e b 6 k h,i 1
f b 4
Draw AOA and AON networks
c5
2
a d4 g6
j
b e h
k
f i
Activity Precd. Act. Dur. (week) Activity Precd. Act. Dur. (week)
a -- 3 f c,e 2
b a 3 g b 2
c a 4 h b,d 2
d a 5 i b,d 4
e b 3 j f,g,h 3
To have the proper use for the resources, we should consider for the
following:
1. Turbulent uses of resources in duration and number will cost more.
2. Not insure to get the proper quality and number of resources at the time
implementer needed.
3. As a physiological mater, the labors need a time to understand the site
and provide the best product. New labors are not preferred.
4. Labors worked for time in any project will be in knowledge about the site
details and equipment movements, this will lead to limiting the self and
equipment safety.
Activity Precd. Act. Dur. (week) Activity Precd. Act. Dur. (week)
a -- 3 f c,e 2
b a 3 g b 2
c a 4 h b,d 2
d a 5 i b,d 4
e b 3 j f,g,h 3
PERT Method:
P: Program E: Evaluation
R: Review T: Technique
Activity )a) time )m) time )b) time )T) time Variance
A 2 6 5 61.3 0.25
B 6 4 5 6 0.11
C 2 6 3 6166 4144
D 4 5 7 5.16 0.25
E 3 7 8 7 0.11
F 2 6 5 61.3 0.25
Variance = ((b-a)/6)2
Act. Dur. S(w) Star. Finish. Cost Act. Fb. Mar. Apr. May June
(W) Date Date ($) Wt.
A
B
C
D
E
F
G
H
I
J
K
% Plan
% Actu
±%
TIME GRID (BAR CHARD) SCHEDUAL
Act. Dur. S(w) Star. Finish. Cost Act. Fb Mar. Apr. May June
(W) Date Date ($) Wt.%
.
15/2/ 15/3/
A 4 1 2014 2014 1000 1
15/2/20 8/3/
B 3 0 14 2014 2000 2
16/3/ 5/4/
C 3 1 2014 2014 5000 5
16/3/ 29/3/
D 2 2 2014 2014 10000 10
9/3/ 19/4/
E 6 0 2014 2014 20000 20
9/3/ 5/4/
F 4 2 2014 2014 25000 25
6/4/ 12/4/
G 1 1 2014 2014 10000 10
20/4/ 17/5/
H 4 1 2014 2014 7000 7
6/4/ 8/5/
I 5 2 2014 2014 5000 5
20/4/ 31/5/
J 6 0 2014 2014 10000 10
18/5/ 24/5/
K 1 1 2014 2014 5000 5
% Plan
% Actu
±% 100
TIME GRID (BAR CHARD) SCHEDUAL
Act. Dur. S(w) Star. Finish. Cost Act. Fb Mar. Apr. May Jun
(W) Date Date ($) Wt.%
. e
15/2/ 15/3/
A 4 1 2014 2014 1000 1
15/2/20 8/3/
B 3 0 14 2014 2000 2
16/3/ 5/4/
C 3 1 2014 2014 5000 5
16/3/ 29/3/
D 2 2 2014 2014 10000 10
9/3/ 19/4/
E 6 0 2014 2014 20000 20
9/3/ 5/4/
F 4 2 2014 2014 25000 25
6/4/ 12/4/
G 1 1 2014 2014 10000 10
20/4/ 17/5/
H 4 1 2014 2014 7000 7
6/4/ 8/5/
I 5 2 2014 2014 5000 5
20/4/ 31/5/
J 6 0 2014 2014 10000 10
18/5/ 24/5/
K 1 1 2014 2014 5000 5
0 1 2 6 1 2 4 5 7 7 8 8 9 9 1
% Plan . . . . 5 7 3 9 4 8 2 7 1 3 0
6 5 5 0 . . . . . . . . . . 0
6 9 8 9 1 3 6 0 4 9 3 8 5 .
1 4 7 5 5 0
% Actu
±% 100
TIME GRID (BAR CHARD) SCHEDUAL
Act. Dur. S(w) Star. Finish. Cost Act. Fb Mar. Apr. May Jun
(W) Date Date ($) Wt.%
. e
15/2/ 15/3/
A 4 1 2014 2014 1000 1
15/2/20 8/3/
B 3 0 14 2014 2000 2
16/3/ 5/4/
C 3 1 2014 2014 5000 5
16/3/ 29/3/
D 2 2 2014 2014 10000 10
9/3/ 19/4/
E 6 0 2014 2014 20000 20
9/3/ 5/4/
F 4 2 2014 2014 25000 25
6/4/ 12/4/
G 1 1 2014 2014 10000 10
20/4/ 17/5/
H 4 1 2014 2014 7000 7
6/4/ 8/5/
I 5 2 2014 2014 5000 5
20/4/ 31/5/
J 6 0 2014 2014 10000 10
18/5/ 24/5/
K 1 1 2014 2014 5000 5
0 1 2 6 1 2 4 5 7 7 8 8 9 9 1
. . . . 5 7 3 9 4 8 2 7 1 3 0
% Plan 6 5 5 0 . . . . . . . . . . 0
6 9 8 9 1 3 6 0 4 9 3 8 5 .
1 4 76 7 5 8 5 0
1 3 4 8 9
8 8 8 1
4 1 8 7 3 3
% Actu 1 2 3
. . .
.
9
4
.
7
.
.
2
.
0
0
9 8 7 5 0
5 5 5
+ + + + + + + + + + + + +
. . . 8 1 2 2 1 1 5 5 5 8
±% 100 3
4
4
1
5 .
8
5
.
1
.
5
.
4
.
3
.
.
1
.
3
.
7
.
2
9 6 6 4 7
6
S – Curve Diagram:
S - Curve Chart
100
90
80
Implementation %
70
60
50
40
30 Actual curve
20 plan curve
10
0 1; 1
0,66
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Time ( Duration) in weeks
HOME WORK NO (3)
Draw the Bar Chart and the S – Curve for the example in HW-2?
TIME GRID (BAR CHARD) SCHEDUAL
Act. Dur. S(w) Star. Finish. Cost Act. Fb Mar. Apr. May Jun
(W) Date Date ($) Wt.%
. e
15/2/ 15/3/
A 4 1 2014 2014 1000 1
15/2/20 8/3/
B 3 0 14 2014 2000 2
16/3/ 5/4/
C 3 1 2014 2014 5000 5
16/3/ 29/3/
D 2 2 2014 2014 10000 10
9/3/ 19/4/
E 6 0 2014 2014 20000 20
9/3/ 5/4/
F 4 2 2014 2014 25000 25
6/4/ 12/4/
G 1 1 2014 2014 10000 10
20/4/ 17/5/
H 4 1 2014 2014 7000 7
6/4/ 8/5/
I 5 2 2014 2014 5000 5
20/4/ 31/5/
J 6 0 2014 2014 10000 10
18/5/ 24/5/
K 1 1 2014 2014 5000 5
0 1 2 6 1 2 4 5 7 7 8 8 9 9 1
. . . . 5 7 3 9 4 8 2 7 1 3 0
% Plan 6 5 5 0 . . . . . . . . . . 0
6 9 8 9 1 3 6 0 4 9 3 8 5 .
0 1 5 1
8 4
1 7 3 5 56 7 58 8 9 01
. . . . 2 1 4 0 8 6 1 5 0 0
% Actu 6 3
2
3 9 . 8 . . . . . . . 0
6 2 3 6 6 3 6 5 4 1 8 5
- - - - - 2- - - - - - - - - 0
0 . . 0 6 1 2 2 2 9 6 6 6 3
±% 100 .
0
3
9
5 .
7
.
9
4
.
5
.
5
.
3
.
.
9
.
5
.
2
5 4 5 3 3 4
S - Curve Chart
100
90
80
Implementation %
70
60
50
40 Actual Curve
30
Plan Curve
20
10
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Time ( Duration ) in weeks
LECTURE NO. 5:
1- Land Surveying:
The soil type has a major role on the construction buildings in:
Selecting the foundation type and size.
The size of excavation.
The soil surface treatment beneath the building.
The way to resist or solve the negative problems from the soil.
3- Concreting:
The difference between all kinds of concretes are in the rate of consisting materials
and their types, concretes can be arranged in situ manually or by local small mixtures
or can be provided by central mixing plants. The main property of concretes is
workable in fresh condition and has high resistance (very hard) in hard condition.
Concrete is a Time – Temperature dependent material.
Concrete is consisting from cement plus one or more of the following materials:
Cement + Water slur uses for bonding
Cement + Water + Sand Mortar uses for bonding
Cement + Water + Sand + Gravel Conc. Mix. uses for structures.
Cement +Water +Sand +Gravel +Steel R. Forced Conc. Mix.
Cement + with one or all the above + Additive Improved Conc. Mix.
Concretes can be lay manually or mechanically on the ground, in the holes excavated
and in forms prepared from wood, steel or other kinds of materials.
Sometimes, and according to the type of concrete or the work requirements
concretes are installed by spraying (in plastering works) and injection (in tunnel
works).
4- Wall Building:
Walls are different in their duties and kind of materials consisting, regarding the duties
we have:
1. Bearing walls.
2. Partition walls.
3. Fence walls.
4. Retaining walls.
5. Isolating walls.
6. Others.
5- Finishing Works:
It consists all the complementary works which giving the final shaping to the buildings
like:
1. Gypsum plastering.
2. Cement plastering.
3. Wall ceramic or mar bell tiles.
4. Ground furnishing tiles (mar bell, porcelain, granite, mosaic, ceramic…1etc1)1
5. Axed rock covering.
6. Painting (for inside and outside walls, for windows and doors, ……etc1)1
7. Doors and windows installation.
8. Guard rails and grills installations.
9. Others.
6- Layout and Gardening Works:
Depending on the area and the size of the layout area, it can be includes many type of
works, like:
1. Walk ways.
2. Garages (parking).
3. Fence.
4. Service buildings (reception, generator room, pump room, stores …1 Etc1)1
5. Gardens.
6. Service trenches for electrical and sanitary facilities.
7. Lighting poles.
8. Storage water tanks.
For steps (1, 2 and 3) above the work includes preparation for the beneath soil and
compaction according to the specifications required.
Steel bars:
Two kinds of steel were used, smooth or deformed. Now a
days deformed type mostly used because of:
1. Has strong bond with concrete.
2. Easier for using.
Steel bars should be clean during the use and not oiled. It
can be fixed in its correct location by:
1. Steel wires.
2. Wilding.
When steel bars are continued through a line an over lab is
required at least (50 Diameter of steel).
Table show the X-Area and Wt./m.l. for each steel bar
Sr. no. Diameter X- Area mm2 Weight Kg/m.l.
mm inch
1 10 3/8 79 0.62
2 12 1/2 113 0.89
3 16 5/8 201 1.58
4 18 6/8 255 2.00
5 22 7/8 380 3.00
6 25 1 491 3.85
7 28 1 1/8 616 4.85
8 32 1 1/4 805 6.31
9 36 1 3/8 1018 8.00
10 38 1 1/2 1134 8.90
11 40 1 5/8 1257 9.86
Note: Weight (Kg/m.l.) = 0.00618 D2(mm)
SOIL STATEMENT:
There are many types of soil and it was differ from location
to another and from place to place, for this reason it is
necessary to study the soil case by case for identifying the
foundation type and size. Soils bearing capacity starts at
(0.25 Kg/cm2) in bad soils and ending at (40 Kg/cm2) in very
good rocky soils.
Bill of Quantity (BOQ) Table or Schedule: