0% found this document useful (0 votes)
41 views37 pages

Degu Qun

This document contains a project summary including: 1. Location details and owners for a residential building project in Gondar, Ethiopia. 2. A breakdown of excavation and concrete work for the building's substructure including quantities for items like site clearance, bulk excavation, pit excavation, trench excavation and concrete footing pads. 3. Quantities for additional substructure works including fill material, carting away of excavated material, masonry work and ground beams. 4. Details of hard core and concrete works for individual building axes A1 through A6.

Uploaded by

amare addis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views37 pages

Degu Qun

This document contains a project summary including: 1. Location details and owners for a residential building project in Gondar, Ethiopia. 2. A breakdown of excavation and concrete work for the building's substructure including quantities for items like site clearance, bulk excavation, pit excavation, trench excavation and concrete footing pads. 3. Quantities for additional substructure works including fill material, carting away of excavated material, masonry work and ground beams. 4. Details of hard core and concrete works for individual building axes A1 through A6.

Uploaded by

amare addis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 37

Take of sheet

PROJEResidential Building
LOCAGONDAR
OWNETemesgen
CONSAbriham
CONTTENNA

T D Sq Descripition T D Sq Descripition
A. SUB STRUCTURE 2.0 Concrete work
1.0 EARTH WORK 1.3 2.01 Lean concrete
1.01 Site clerance 13 1.3
15.51 21.97 m2,lean concrete aunder footing pad 5cm thiknes
11.4 7.7
176.81 site clerance by adding 1m working space all side 2 0.5
14.01 1.02 Bulk excavation 7.7 m2 lean concrete under masonary work on axis 1&4 5cm thiknes
9.9 11.31
1 2 0.5
138.7 bulck excavation 100 cm from NGL by adding working space 25 cm 11.31 m2 lean concrete under masonary work on axis A&D
1.03 Pite excavation 19.01 total lean concrete under masonary wall
1.8 4.8
13 1.8 3.252
1.25 15.61 m2, C 5, lean concrete above hard core for A 1
52.65 m3 pit excavation from reduced level by adding 25cm working space for F 1 2.9
1.04 Trench excavation 3.252
7.7 9.43 m2 C 5, lean concrete above hard core for A 2
2 1 2.752
0.6 3.762
9.24 m3 trench excavation on axis 1 &4 ,depth 20 cm ,working space 25cm 10.35 m2, C 5, lean concrete above hard core for A 3
ADD 4.848
11.31
2 1 3.762
0.6 18 m2 C5 lean concrete above hard core for A 4
13.57 m3 trench excavation on axis A &D ,depth 20 cm ,working space 25cm 2.752
22.81 Total Trench excavation 4.396
1.05 fill from selected quary site 12.1 m2 ,C5 lean concrete above hard core for A 5
11.4 m3 fill around trench excavation 4.848
13 1.8 4.396
1.8 21.31 m2,C5 lean concrete above hard core for A 6
1.25 86.8 m2total lean concrete under ground slab
52.65 m3 pite excavtion 1.3 2.02 C25 ,Concrete Work
Ddt 13 1.3
1.3 0.35
13 1.3 7.69 m3 footing pad concrete work
0.35 1.25
7.69 m3, concrete work for footing pad 13 0.3
Ddt 0.2
0.3 0.98 m3 footing column concrete work
13 0.2 8.67 total concrete work for footing pad and footing column
0.85 12.51
0.66 m3, concrete work for footing column 2 0.35
44.3 m3, fill around footing pad& footing column 0.2
1.75 m3 concrete work for GB axis 1&D
194.4 m3 Total fill form selected quarry site 7.7
1.06 Cart Away 2 0.35
CA=BE+PE+TE 0.2
214.16 m3 1.08 m3 concrete work for GB axis 1&2
7.9
7.7 1.07 Masonry Work 0.35
2 0.5 0.2
0.6 0.55 m3 concrete work for GB axis 4
4.62 m3 masonry work on axis 1&4 depth 60cm 8.2 L=4.396+3.762=8.2
ADD 0.35
11.31 0.2
2 0.5 0.57 m3 concrete work for GB axis B
0.6 3.55
6.79 m3 masonry work on axis A&D depth 60cm 0.35
11.41 m3 Total masonry work 0.2
0.25 m3 concrete work for GB axis C
2.45 m3 total concrete work for GB

Page 1
Take of sheet

4.8 2.9
3.252 3.252
0.1 9.43 m2 hard core for A 2
1.56 m3, C25,Ground Slab concrete work for A1 2.752
2.9 3.762
3.252 10.35 m2, hard core for A 3
0.1 4.848
0.94 m3, C25, G S concrete work for A 2 3.762
2.752 18.24 m2 hard core for A 4
3.762
0.1
1.04 m3 ,C25, G S concrete work for A 3 2.752
4.396
4.848 12.1 m2 hard core for A 5
3.762 4.848
0.1 4.396
1.82 m , C25, G S concrete work for A 4
3
21.31 m2 hard core for A 6
2.752 87.04 m2 Total hard core
4.396 2.05 Expanision joint 8 mm thiknes b/n grade beam and GF slab
0.1 14.6 m, for A 1
1.21 m ,C25,G S concrete work for A 5
3
12.4 m, for A 2
4.848 14.1 m, for A 3
4.396 17.5 m, for A 4
0.1 14.9 m,for A 5
2.13 m3,C25, G S concrete work for A 6 18.9 m, for A 6
8.7 m3 total concret work for G slab 92.4 m, total length of expanision joint
2.03 Formwork B. SUPER STRACTRUE
13 5.2 L=4(1.3)=5.2 1.01 C25, Concret Work
0.35 2.7
23.66 formork for footing pad 13 0.3
0.85 0.2
13 1 w=2(0.20+290.3)=1 2.11 m3 concrete work for GF elivation column
11.05 m2 formwork for footing column 8.3 L=5+3.1+0.2
34.71 m2 taotal form work for footing pad and f column 4 0.2
12.51 0.15
2 0.35 1 m3 , concrete work FFB aixs 1,2,3&4
8.76 m2, external formwork for GB axis 1&D 11.61 L= 4.696+4.026+3.452-0.6
2 11.51 2 0.2
0.35 0.15
8.06 m2, internal formwork for GB axis 1&D 0.7 m3 concret work FFB aixs A&D
8.1 8.358 L=4.696+4.062-0.4
2 0.35
5.67 m2 external form work for GB axies 1&4 0.2
7.7 L=4.8+1.9=7.7 0.15
4 0.35 0.25 m3 ,concrete work FFB axis B
3.252 L=3.452-0.2
10.78 m2 internal form work for GB axies 1,2&3 0.2
7.6 L=2.752+4.848=7.6 0.15
0.35 0.1 m3, concrete work FFB axis C
2.66 m2 internal form work for GB axies 4 8.3 L=5+3.1+0.2
7.4 L=4.8+2.9-0.3=7.4 12.51 w=4.696+4.026+3.452+0.3
0.35 0.15
2.59 m2 internal form work for GB axies 2 15.57 m3 concrete work FF slab
2 8.4 L=3.762+4.396+02=8.4 2.05 m3Total concrete work for FF beam
0.35 0.023 0.3 0.5*0.3*0.15=0.0225
5.88 m2 internal form work for GB axies B 9 1 0.15
2 3.4 L=3.152+0.2=3.4 0.2
0.35 ADD
3.1
2.38 m2 internal form work for GB axies C 1 sofite concrete work
46.78 m ,Total Gb formwork
2
0.15 ###
2.04 Hard core 0.47 3.1
4.8
3.252
15.61 m2, hard core for Area 1
1
2.7

Page 2
Take of sheet

0.67 m3, stair case concrete work for frist flight 3.29 total concrete work for RB
5.2
2 0.67 3.45
1.34 m3 stair case concrete work for two flight 0.1
1.79 m3 concrete work for roof solid slab
1.34 m3total concrete work for stair case
1 1.02 FORM WORK
2.1 13 2.7
0.15 1
0.32 m3 concrete work for landing 35.1 m2 form work for GF elivation column
2.7 1
5 0.3 10 0.15
0.2 1.5 m2 riser form work
0.81 m3 concrete work for FF columnn C1&C4 2 3.1
2.7 L=3-03=2.7 0.15
7 0.3 0.93 m2 side form work
0.2 1
1.13 m3 concrete work for FF C3 3.1
2.7 3.1 m2, stire case sofite form work
0.2 2.1
0.2 1
0.11 m concrete work for C2 at section c-c
3
2.1 m2 landing form work
1.7 L=8-6.3 7.63 m2 total form work for frist flight
0.3
0.2 2 13.16 26.32 m2stair case form work for two flight
0.1 m3 concrete work for c1 above top beam 2.8
1.7 5 1.1
0.2 15.4 m2 form work for FF elivation column C1&C4
0.2 2.8
0.07 m3 concrete work for C2 above top baeam 0.9
2.52 m2 form work for FF elivation column C 2
4 0.3 2.775
0.2 1.1
0.24 m concrete work for C4 above top beam
3
3.05 m2form work for elivation column C3 section C-C
2.46 m3 Total concret work for FF elivation column 1.7
7.985 1.1
0.2 1.87 m2 form work for elivation column C1
0.2 1.7
0.32 m3 RB 1 concrete work 0.9
12.51 1.53 m2 form work for elivation column C2
2 0.2 1.44
0.2 1
1 m3,RB 2 concrete work 1.44 m2 form work for elivatin column C4
3.452 25.81 m2 Total elivation column form work for FF
2 0.2 12.51
0.2 2 0.3
0.28 m3,RB 3 concrete work 7.51 m2 external form work for FF B axis 1& D
2.752 11.51
2 0.2 2 0.15
0.2 3.45 m2 internal form work for FFB axis 1&D
0.22 m3 RB 4 concrete work
7.9 11.31
3 0.2 2 0.2
0.2 4.52 m2 sofite form work for FFB axis 1&D
0.95 m3 RB 5 concrete work 8.3
2.9 2 0.3
0.2 4.98 m2 external form work for FFB axis 1&4
0.2 7.7
0.12 m3 RB 6 concrete work 4 0.15
4.848 4.62 m2 internal form work for FFB axis 1&4
0.2 3 7.7
0.2 0.2
0.19 m3 RB 7 concrete 4.62 m2 sofite form work for FFB axis 1&4
5.348 7.7
0.2 2 0.15
0.2 2.31 m2 internal form work FFB axis 2
0.21 m3 RB 8 concrete work

Page 3
Take of sheet

7.7 11.6
0.2 7.9
1.54 m2 soite form work FFB axis 2 91.64 For FF slab
8.7
2 0.15 1.03 HCB WORK
2.61 m internal form work FFB axis B
2
front elivation HCB
8.7 8.1
0.2 4.3
1.74 m2 sofite form work FFB axis B 34.83 m2
3.55 Ddt πr2/2=3.07m2
2 0.15 r=1.4
1.07 m2 internal form work FFB axis C
3.55
0.2 1.2
0.71 m2 sofite form work FFB axis C
39.68 m2Total form work for FFB 2.8
7.9 6.43 m 2
2.8*1.2=3.36m2
0.2
1.58 m2sofit formwork for RB I Ddt
7.7 πr2/2=2.45m2
0.6 r=1.25
4.62 m side form work for RB 1
2

2 12.51
0.3
7.51 m2external form work for RB 2
2 11.9 1.45
0.2
4.76 m2,sofite form work for RB 2
2 11.9 2.5
0.2 6.07 2.5*1.45=3.62m2
4.76 m2,internal formwork for RB 2 Ddt
2 3.452 r=0.4
0.2 3πr2/2=0.754m2
1.38 m2,sofite form work for RB 3 1
2 3.452
0.6 21.33 m2 HCB Work for front elevation G 0
4.14 m2, side form work for RB 3 5.1
2 2.752 ADD
0.2 4.25 0.5*2.4*4.25=5.12m2
1.1 m2,sofit form work for RB 4 1.7 ###
2.752 7.23
2 0.6 Ddt
3.3 m2,side form work for RB4 2.28
3 7.9 2
0.2 4.56
4.74 m2,sofite form worrk for RB5 1.7
3 7.9
0.6
14.22 m2,side form work for RB 5 4.25
2.9 7.77 m2 HCB work fronte elivation for G 1
0.2 5.2
0.58 m2,sofite form worrk for RB6 2
2.9 10.4 m2 HCB work fronte elivation for G 1
2 0.3
1.74 m2,side form work for RB 6 39.5 m2 Total HCB work for front lelivation both G 0&G1
4.848 12.5
0.2 6.47
0.97 m , sofit form work for RB 7
2

4.848 80.88 m2 HCB work for left lelivation


0.3 ADD
1.45 m2,side form work for RB 7 1.83
3.75
5.348 6.86 m2 HCBwork for left lelivation
0.2 Ddt
1.07 m2,sofit form work for RB8 3.18
2 5.348 2.7
0.3 8.59 m2 area of oppning b/n axis 2 and 3
3.21 m2,side form work for RB8
61.13 m2Total RB form work

Page 4
Take of sheet

Ddt Internal HCB work for G0


4.9 3.25
3.15 2.7
15.44 m2 of oppning on stair case 8.78 m2 ,internal HCB work on axis C for G 0 ,thiknes 20 cm
Ddt 3.55
1.5 2.7
1.01 9.59 m2,internal HCB work on axis B for G 0 ,thiknes 20 cm
1.52 m2 area of windwo 4.06
Ddt 2.7
1.5 10.96 m2 internal HCB work b/n axis 2&axis 3 ,thiknes 20 cm
0.61 3.3
0.92 m2 area of windwo 2.7
Ddt 8.91 m2,internal HCBwork b/n axis 1& axis 2 ,thiknes 15 cm
2.5 1
3 1 7.5 m2area of opning 2.7
Ddt 2.7 m2,internal HCB work b/n axis 3 &4, thiknes 20cm
3 0.39 1.17 m2 area of curve opning 1.06
52.6 m2Total HCB work for left side elevation both G 0&G1 2.7
8 2.86 m2, internal HCBwork b/n axis 2&3 ,thiknes 20cm
5.2 2.5
41.6 m2 area b/n axis wall b/n axis A& C 2.7
ADD 6.75 m2,internal HCB work on axis 2,thiknes 15 cm
6 0.4
3.1 2.7
18.6 m2 area b/n axis wall b/n axis D& C 1.08 m2 ,internal HCB work b/n axis 1&2,thiknes 20 cm
Det 1.43
2.7 2.7
2 0.9 3.86 m2,internal HCB work b/n axis 1&2 thikns 15
4.86 m2 area of Door b/n axis D& A 0.55
Ddt 2.7
1.8 1.49 m2 ,internal HCB work b/n axis 1&2,thiknes 15cm
1.5 Internal HCB work for G1
2.7 m2 area of windwo b/n axis D& C 3.77
Ddt 2.7
2 10.18 m2internal HCB work on axis B,thiknes15cm
2.9 4.46
5.8 m2 area of windwo b/n axis D& C 2.7
46.84 m2 Total HCB work for rear elivatio both G0 &G1 12.04 m 2internal HCB work on axis C,thiknes 20cm
6.25 2.75
11.31 70.69 m2 area of wall b/n axis 1 and 4 2.7
ADD 7.43 m2internal HCB work on axis 2, thiknes 15
0.5*1.45*11.3 8.19 m2 area of wall b/n axis 1 and 4 2.1
ADD 2.7
2.12 5.67 m 2 intrenal HCB work on axis 3, thiknes 15cm
3.45 2.1
7.31 m2 area of wall b/n axis 1 and 2 2.7
ADD 5.67 m 2 intenal HCB work b/n axis 2&3, thiknes 15cm
0.5 2.9
8.87 2.7
4.44 m2 area of wall b/n axis 2 and 4 7.83 m2 internal HCB work b/n axis2&3,thiknes 20
ADD 2.9
0.5*1.05*7.25 2.7
3.81 m2 area of wall b/n axis 2 and 4 7.83 m2 internal HCB work b/n axis2&3,thiknes 15
Ddt 1
2.2 2.7
1 2.7 m2 internal HCB work b/n axis 3&4,thiknes 20
2.2 m2 area of opnning b/n axis 3 and 4 4.35
Ddt 2.7
0.77 11.75 m2 internal HCB work b/n axis 3&4,thiknes 15
3.05 58.54 m2total internal HCB WORK with 20 cm thiknes
2.35 m area of windwo b/n axis 1 and 4 69.54 m2total internal HCB WORK with 15 cm thiknes
Ddt 128.08 m2,Net internal HCB work for both G0 &G1
3.14*0.5*0.5/2 0.39 m2 area opnning of b/n axis 3 and 4 228.19 m2 total HCB work for External wall with 20 cm thiknes
Ddt
3.14*0.4*0.4/2 0.25 m2 area of windwo b/n axis 3and 4

89.25 m2 total HCB work for right side elivation both G0 &G1

Page 5
Take of sheet

1.04 Roof Covering and Truss Member L2=1.2/cos15=1.2


roof covering is corrugated iron sheet G-30 it 's thiknes 0.315m y2=0.16+sin15*1.2=0.5
d2=√1.2 +0.5 =1.3 2 2

L3=1.2/cos15=1.2
L9 y3=0.5+sin15*1.2=0.8
d3=√1.2 +0.8 =1.4 2 2

L8 L4=1.2/cos15=1.2
y4=0.8+sin15*1.2=1.1
L7 d4=√1.2 +1.1 =1.6 2 2

y7 d7 y8 d8 y9 d9 vertical truss=y1+y2+y3+y4=0.16+0.5+0.8+1.1=2.56m
L5 y6 d6 1 diagonal truss=d1+d2+d3+d4=1.2+1.3+1.4+1.6=5.5m
L4 y5 d5 7 2.56 17.92 m vertical truss
L3 y4 d4 7 5.5 38.5 m diagonal truss
L2 y2 d2 y3 d3 7 5.4 37.8 horizontal truss
L1 y1 d1 102.05 m total amount of truss
0.6 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 15.96 m ,metal sheet gutter
11.01 3 6 18 m,pvc down pipe 100mm diam
tanθ= 1.3/11.61=0.11 2 6.17 12.34 m ,pvc down pipe 100mm diam
θ=6.4º 1 8 8 m,pvc down pipe 100mm diam
L1=0.6/cos6.4=0.61 38.34 m,
y1=0.6*sin6.4=0.06 13 18.41 239.33 m Eucalyptes rafter
d1=1.2=√1.2 +0.06 =0.072
2 2

L2=1.2/cos6.4=1.21 18 9.2 165.6 m,Eucalptes zigba 5*7 purlin


y2=y1+sin6.4*1.2=0.19 9.11
d2=√1.22+0.192=1.2 5.1
L3=1.2/cos6.4=1.2 46.461 m2
y3=y2+sin6.4=0.19+sin6.4=0.3 11.91
d3=√1.22+0.32=1.24 4.1
L4=1.2/cos6.4=1.21 48.831 m2
y4=0.3+sin6.4*1.21=0.43 95.292 m2,total area of roof
d4=√1.22+0.432=1.3 3.33 Celing work
L5= 1.2/cos6.4=1.2 4.7
y5=1.2sin6.4+0.43=0.56 15.651 m2 area above stair case
d5=√1.22+0.562=1.33 2.86
L6=1.2/cos6.4=1.21 1.85
y6=1.21*sin6.4+0.56=0.69 5.291 m2 area of correder
d6=√1.22+0.692=1.4 3 m2,area of verenda
L7=1.2/cos6.4=1.21 7.1 m2,bath room
y7=1.2*sin6.4+0.69=0.8 9.8 m2 area ofchildren bead room
d7=√1.22+0.82=1.4 3.8 m2,area of dressing room
L8=1.2/cos6.4=1.2 5 m2,area of toilet
y8=1.2*sin6.4+0.8=0.9 15.4 m2,bead room
d8=√1.22+0.92=1.5 17.3 m2,area of master bead room
L9=1.2/cos6.4=1.21 7 m2,area of verenda
y9=1.2*sin6.4+0.9=1.03 89.342 m2 total area of celing
d9=√1.22+1.032=1.6 1.05 Metal work
vrtical truss=y1+y2+y3+y4+y5+y6+y7+y8+y9=0.06+0.19+0.3+0.43+0.56+0.69+0.8+0.9+1.03=4.96m
diygonal truss=d1+d2+d3+d4+d5+d6+d7+d8+d9=0.072+1.2+1.24+1.3+1.33+1.4+1.4+1.5+1.6=11.042m 3 2.7 H=2.7
3 4.96 14.88 m ,vertical truss 0.9 W=0.9
3 11.042 33.13 m, diagonal truss 7.29 m2 Door (D1)
3 11.4 34.2 m horizontal truss 2 H= 2
0.9 W= 0.9
1.8 m2 wooden Door(D2)
L4 2 2 H= 2
1.3 0.85 W= 0.85
L3 3.4 m2 wooden Door (D3)
3 2 H= 2
L2 Y2 d2 y3 d3 y4 d4 0.7 W= 0.7
4.2 m 2
woodn Door(D4)
L1 y1 d1 4.9 H= 4.9
0.6 1.2 1.2 1.2 1.2 2.1 W= 2.1
tanθ=1.3/4.8=15º 10.29 m2 Windwo(W1)
L1=0.6/cos15=0.62 2.51 H= 2.51
y1=0.62*sin15=0.16 3.9 W= 3.9
d1=√1.2 +0.16 =1.2
2 2
9.79 m2 Windwo(W2)

Page 6
Take of sheet

1.06 FINISING WORK


2.51 H= 2.51 Plastering Work
1.7 W= 1.7 2 39.5 79 m2,plastering work for front elivation both G0&G1
4.267 m , Windwo (W3)
2
2 52.6 105.2 m ,plastering work for left side elivation both G0&G1
2

1.8 H= 1.8 2 46.84 93.68 m2,plastering work for rear side elivation both G0&G1
1.5 W= 1.5 2 89.25 178.5 m2 Plstering work for right side elivation both G0&G1
2.7 m , Windwo (W4)
2
456.38 m2 Total plastering work for all external wall
1.5 H=1.5 a) plastering work for column
1.01 W=1.01 13 0.6
1.52 m2 , Windwo(W5) 2.7
0.61 H=1.5 21.06 m2,plastering work for G0 column
1.5 W=0.61 12 0.6
0.92 m2, Windwo(W6) 2.7
2 H=2 19.44 m2,plastering work for G1 column
2.5 W=2.5 0.4
5 m2, Winwo(W7) 2.7
0.77 H=0.77 1.08 m2,plastering work for G1 column 2
0.61 W=0.61 0.6
0.47 m2, Windwo(W8) 1.32
2.28 H=2 0.79 m2,plastering work for C1 above top beam
2 W=2.28 0.4
4.56 m2, Windwo(W9) 1.48
2 H=2 0.59 m2, plastering work for C2 above top beam
2.9 W=2.9 4 0.6
5.8 m2, Windwo (W10) 1.52
1.3 H=2 3.65 m2 plastering work for C4 above top beam
2 W=1.3
2.6 m2, Windwo (11) 46.61 m2, Total plastering work for G0 &G1 Column
Door Glazing b) Plastering work for G1 Beam
3 1.4 0.3
0.4 8.3
1.68 m2 , for D 1 2.49 m2, external plastering work FFB axis 1
Window glazing 0.15
9 1.6 H=1.6 7.9
0.15 W=0.15 1.19 m2, internal plastering work FFB axis 1
2.16 m2, for W1 0.5
4 2.4 H=2.4 7.9
0.85 W=0.85 3.95 m2, plastering work FFB axis 2
8.16 m2 for W2 1
2.4 H=2.4 7.9
1.55 W=1.55 7.9 m2,plastering work FFB axis 3 and 7
3.72 m2 for W3 2 12.51
4 1.35 H=0.75 0.3
0.75 W=1.35 7.51 m2, external plastering work FFB axis A& D
4.05 m2, for W4 0.15
0.9 H=1.3 2 12.11
1.3 W=0.9 3.63 m2,internal plastering work FFB axis A&D
1.17 m2, for W5 0.5
1.3 H=1.3 8.62
0.5 W=0.5 4.31 m2 ,plastering work FFB axis B
0.65 m2 for W6 0.5
3 1.95 H=1.95 3.15
0.75 W=0.75 1.58 m2,plastering work FFB axis C
4.39 m2, for W7
0.7 H=0.7 32.56 m2,Tota l plastering work FFB
0.5 W=0.5 c) Plastering work for RB
0.35 m2, for W8 8.62
3 1.9 H= 1.9 1
0.7 W=0.7 8.62 m2 plastering work RB 1
3.99 m , for W9
2
2 12.51
3 1.95 H=1.95 0.6
0.9 W=0.9 15.01 m2,plastering work RB 2
5.27 m2 for W10 2 3.75
3 2.35 H=2.35 0.8
0.35 W=0.35 6 m2,plastering work RB 3
2.47 m2 for W11

Page 7
Take of sheet

2 3.2 e) Electrical cable for Soket outlet and lighting line


0.8 112 m,Supply and fix copper cable of 3×2.5mm2 for Socket outlet line.
5.12 m2,plastering work RB 4 112 m,conduit
3 8.3 174 m,Supply and fix copper cable of 2×1.5mm2 for lightin line.
0.6 174 m, condiut
14.94 m ,plastering work RB 5
2
9.55 m,Supply and fix copper cable 3×4 mm2 for water heater & stove line
4.25 1.08 Suantory Installation and joints
0.6 a) From riser water supplay diagram
2.55 m , plastering work RB6
2
16.85 16.85 m length φ 20 mm pvc cold water supplay pip line
5.3 7.9 7.9 m length φ 25 mm pvc cold water supplay pip line
0.6 8 m length φ32mm pvc cold water supplay line
3.18 m2, plastering work RB7 12 pcs elbow 90 joints ɸ20mm
8.3 3 pcs elbow 90 joints ɸ25mm
0.8 5 pcs T-joints ɸ20mm
6.64 m2,plastering work RB 8 2 pcs T-joints ɸ25mm
62.06 m2, total plastering work for RB b) From wast water diagram
2 128.08 256.16 m2, Partition wall plastering work both G0&G1 21 m length φ100mm pvc waste pipe
2 89.342 178.684 m2 slab plastering 14.6 m length φ50mm pvc waste pipe
1032.45 m2, Net plastring work 0.8 m length φ80mm pvc floor deraineg pipe
painting 1 pcs Y-joints of ɸ100mm
1032.45 m2 Total painting work 8 PCS Y-joints of ɸ50mm
Floor Finishing 1 pcs elbow 45 joints ɸ50mm
1 70.4 70.4 m2 ,GFF ceramic tile 3 pcs elbow 90 joints ɸ100mm
1 22.6 22.6 m2 GFF checkened tile on parking c) Water colest(WC)
1 92.9 92.9 m2 GF cement screed 3 pcs,fix water closet of wash down action,floor mounted,
1 42.5 42.5 m2 ,FF P.V.C tile closed cuopled with plastic cover.
1 37.68 37.68 m2,FF Ceramic tile d) Shower unit
1 3 3 m2,FF Terrazo tile 1 pcs,fix shower plate of approved quality complite with
0.15 H= 0.15 insallation of valves size 800*800 stall typ
2 1 W=1 1 pcs, fix shower plate of approved quality complite with
0.3 m2, marble finishing for riser instalation of valve bath corner
2 1 L=1 3 lavonteries vanity type
0.303 W.=0.303 1.09 Site Work
0.61 m2, marble finishing for trade 3 4.8
2.1 L=2.1 0.6
1 W=1 8.64 m2, HCB work for manhole
2
2.1 m ,marble finishing for landing 3
1 86.19 86.19 m2,FF cement screed 2 0.6
126.7 m, skerting 5mm thiknes and hight 100mm from floor finsh both G0 &G1 3.6 m2
1.07 Electrical Installation add
1 PCS Surface Mounted Distribution Board 2 1.6
7 PCS wall Mounted Sub-Distribution Board 0.6
a) Soket out let 1.92
16 PCS Single Outlet socket 5.52 m2, HCB work for septick tank
3 PCS double oute let socket 1 8.64 8.64 m2plastering work for manhol
2 pcs Heater Outlet 1 5.52 5.52 m2 plastering work for septink tank
1 pcs Stove outelet
b) Telhpon and TV out let
5 PCS Telehpone outlet
4 pcs TV OUTLET
2 PCS Heater Outlet
c) Switch
7 PCS Single pole switch
5 PCS Double pole switch
14 PCS Single Tow way switch
3 PCS Double tow way switch
2 PCS Trible tow way switch
d) Lithing
12 PCS Celing maounted lighting fixture
8 PCS Wall mounted lighting fixture
7 PCS Reccssed mounted lighting fixture
1 PCS Double fluorescente fixture
3 PCS quadrable fluorescent fixture
2 PCS Chandeleire

Page 8
Take of sheet

Page 9
Take of sheet

Page 10
Take of sheet

πr2/2=3.07m2

Page 11
project : Residential Building construction
location: GONDAR
owner: Temesgen
consultant:Abriham
contractor:TENAA
Reinforced bar schduling

n
tio
r

ar
e
tu

l
ap
ca

.b
.e
rc

n
.
no

no
no
Lo

sh

Le
st

φ
Sub Structure Reinfocement bar
1 pad footing 12 1.7 13
2 column F/colu 16 2.44 13
3 stirrup F/colu 8 0.9 13
4 G/B axi1,2,3&4 14 8.85 4
5 G/B axis A&D 14 7.459 2
6 G/B axis B 14 9.558 1
7 G/B axis C 14 4.302 1

8 stirrup GB axis1,3, 8 1 2
9" axis 4 " 8 1 1
10 " axis 2 " 8 1 1
11 " axis A&D " 8 1 2
12 " axis B " 8 1 1
13 " axis C " 8 1 1
14 G/slab reinb/n axis1&2 and axis A& C 8 3.25 1
15 " b/n axis1&2 and axis A& C 8 4.8 1
16 " b/naxis 1&2 and axis C&D 8 3.25 1
17 " b/naxis 1&2 and axis C&D 8 2.9 1
18 " b/n axis2&3and axis A&B 8 3.862 1
19 " b/n axis2&3and axis A&B 8 2.552 1
20 " b/n axis 2&3 and axis B&D 8 3.862 1
21 " b/n axis 2&3 and axis B&D 8 4.898 1
22 " b/n axis 3&4 and axis A&B 8 4.496 1
23 " b/n axis 3&4 and axis A&B 8 2.552 1
24 " b/n axis 3&4 and axisB&D 8 4.496 1
25 " b/n axis 3&4 and axisB&D 8 4.898 1
TOTAL LENGTH(M)
UNIT WEIGHT(KG/M)
TOTAL UNITE WEIGHT (KG)

Super Structure Reinfrcement Bar


26 column ground floor coloumn 16 3.64 13
27 stirrup ground floor coloumn 8 0.9 13
28 beam FFB axis 1,2,3&4 16 8.75 4
29 beam FFBaxis A&D 16 7.409 2
30 Beam FFB axis B 16 9.458 1
31 Beam FFB axis C 16 4.202 1

32 stirrup FFB axis 1,3&4 8 0.9 3


33 stirrup FFB axis 2 " 8 0.9 1
34 stirrup FFB axis A&D " 8 0.9 2
35 stirrup FFB axis B " 8 0.9 1
36 stirrup FFB axis C " 8 0.9 1
37 FF Slab b/n axis 1,2 & A,C 8 6.092 1
38 ff slab " 8 8.55 1
39 ff slab " 8 3.502 1
40 FF Slab b/naxis 2,3& A,B 8 5.682 1
41 FF Slab " 8 4.321 1
42 FF Slab b/n axis 2,3& A,B on axis 3 10 2.851 1
43 " b/n axis 2,3 & A,B on axis B 10 2.7 1
44 " b/n axis 3,4& A,B 8 6.601 1
45 " " 8 4.321 1
46 " b/n axis 1,2 &C,D 8 5.25 1
47 " b/n axis 1,3 & C& D 8 9.359 1
48 " b/n axis 1,2 &C,D on axis 2 10 2.5 1
49 " b/n axis 2,3 & B,D 8 7.023 1
50 " b/n axis 3,4& B,D 8 6.601 1
51 " " 8 7.023 1
52 " b/n axis 3,4 & B&D on axis3 10 2.851 1
53 roof beam RB 1 14 9.868 1
54 " RB 2 14 13.32 2
55 " RB 3 14 4.002 2
56 " RB 4 14 3.452 2
57 " RB 5 14 8.55 3
58 " RB 6 14 4.549 1
59 " RB 7 14 5.598 1
60 " RB 8 14 5.598 1

61 stirrup RB 1 8 0.7 1
62 stirrup RB 2 " 8 0.7 2
63 " RB3 " 8 0.7 2
64 " RB 4 " 8 0.7 2
65 " RB 5 " 8 0.7 3
67 " RB 6 " 8 0.7 1
68 " RB 7 " 8 0.7 1
69 " RB 8 " 8 0.7 1
column ff elevation c1 16 5.355 1
" ff elvation c2 16 5.557 1
" ff elvation c4 16 5.615 4
stirrup ff levation c1 8 0.9 1
" ff elvation c2 " 8 0.9 1
" ff elvation c4 " 8 0.9 4
" ff elevation c3 " 8 0.7 7
stair case 1st &2nd flght 12 6.45 2
" " 12 3.15 2
" " 14 3.14 2
" " 12 2.34 2
" " 14 2.475 2
" " 8 2.1 1
" " 8 1 2
" " 10 2.1 1
" " 10 1 2
" 10 1 2
" " 10 1 2
" " 10 0.45 18
TOTAL LENGTH(M)
UNIT WEIGHT(KG/M)
TOTAL UNITE WEIGHT (KG)
φ
ar
ar

lb
e l

.b
.e

ta

8 10 12 14 16 18 20 22
no
no

to

22 286 486.2
4 52 126.88
7 91 81.9
4 16 141.6
6 12 89.508
6 6 57.348
6 6 25.812

40 80 80
39 39 39
38 38 38
31 62 62
43 43 43
17 17 17
25 25 81.25
17 17 81.6
16 16 52
17 17 49.3
14 14 54.068
21 21 53.592
26 26 100.412
26 26 127.348
14 14 62.944
24 24 61.248
26 26 116.896
24 24 117.552
TOTAL LENGTH(M) 1257.11 0 486.2 376.268 126.88
UNIT WEIGHT(KG/M) 0.39 0.61 0.88 1.2 1.56
TOTAL UNITE WEIGHT (KG) 490.27 0 427.86 451.52 197.93

4 52 189.28
19 247 222.3
4 16 140
6 12 88.908
6 6 56.748
6 6 25.212

38 114 102.6
37 37 33.3
61 122 109.8
42 42 37.8
17 17 15.3
38 38 231.496
26 26 222.3
5 5 17.51
25 25 142.05
33 33 142.593
20 20 57.02
27 27 72.9
25 25 165.025
38 38 164.198
29 29 152.25
26 26 243.334
26 26 65
33 33 231.759
42 42 277.242
41 41 287.943
35 35 99.785
4 4 39.472
4 8 213.12
4 8 64.032
4 8 55.232
4 12 307.8
4 4 18.196
4 4 22.392
4 4 22.392

36 36 25.2
49 98 68.6
14 28 19.6
13 26 18.2
31 93 65.1
17 17 11.9
21 21 14.7
21 21 14.7
4 4 21.42
4 4 22.228
4 16 89.84
36 36 32.4
37 37 33.3
38 152 136.8
21 147 102.9
7 14 90.3
7 14 44.1
10 20 62.8
7 14 32.76
10 20 49.5
9 9 18.9
25 50 50
9 9 18.9
9 18 18
22 44 44
9 18 18
11 198 89.1
TOTAL LENGTH(M) 3411.1 482.705 167.16 854.936 633.636
UNIT WEIGHT(KG/M) 0.39 0.61 0.88 1.2 1.56
TOTAL UNITE WEIGHT (KG) 1330.33 294.45 147.1 1025.92 988.47
24
ITEM NO, DESCRIPITION UNI QUANTITY Rate AMOUNT
A. SUB STRACTURE
1.EARTH WORK
1.01 Clearing and removing top soil to an average depth of 20 cm. m2 ###
1.02 Bulk excavation to reduce and level the natural ground level to a depth not exceeding 100cm m3 ###
1.03 Excavation for pit or isolated footing in ordinary soil from reduced level to 125cm m3
###
1.04 Trench Excavation for stone masonry wall to retain fill,60cm depth m3 ###
1.05 fill from 1 km hauling distance to quary site
a) Around footing pad &footing column m3
###
b) Around masonary m3 ###
c) on bulck excavation m3 ###
1.06 Cart Away m3
###
1.07 Masonary work m ###
Summery
2 Concrete Work
2.01 5cm thick lean concrete C-5, 150kg cement per meter cube of concrete under
a) under footin pad m2 ###
b) under masonary wall m2 ###
c) under Ground slab m2 ###
2.02 C25 Concrete work
Concrete quality C-25 with OPC min. cement content of 360kg /m 3 of concrete filled in to
formwork and vibrated around reinforcements, formwork and reinforcements shall be measured
separately.

a)
in footing pad m3 ###
b)
in footing column m3 ###
c)
in ground slab m3 ###
e)
in Grade beam m3 ###
2.03 Form Work
a) For Footing pad m2 ###
b) For Footing column m2 ###
c) For Grade beam form work m2
###
2.04 Hard Core m2 ###
20.5 Exapanesion Joint m ###
2.06 Reinforced Bar
Dia. 8mm deformed bar kg ###
Dia. 12mm deformed bar kg ###
Dia. 14mm deformed bar kg ###
Dia. 16mm deformed kg ###
summery
B .SUPER STRACTURE
1.01 C25 Concrete work
Concrete quality C-25 with OPC cement content of 360kg /m 3 of concrete filled in to formwork and
vibrated around reinforcements
a) Ground floor elivation column m3 ###
b) Frist floor elivation column m3 ###
C) stair case m3
###
D) Frist floor beam m3 ###
E) Roof beam ( Top tip beam) m3 ###
F) Frist floor slab m3
###
F) Solid floor slab m3
###
1.02 Form Work
A) For Ground floor Elivation Column m2 ###
B) For Stair Case m2 ###
C) For Frist Floor Elivation Column m2 ###
D) For Frist Floor Beam m2 ###
E) For Roof Beam m2
###
F) For Frist Floor Slab m2
###
Reinforced Bar
Dia. 8mm deformed bar Kg ###
Dia.10mm deformed bar Kg ###
Dia.12mm deformed bar Kg ###
Dia.14mm deformed bar Kg ###
Dia.16mm deformed bar Kg ###
Summery
1.03 HCB WORK
20 CM thiknes HCB for all Extenal wall m2 ###
20 cm thiknes HCB for partition wall m2 ###
15 cm thiknes HCB for partion wall m2 ###
1.04 ROOFING
A) Eculyptes truss m 102.05
B) metal sheet gutter m 15.96
C) Euclayptes rafter m 239.33
D) Euclayptes zigba 5*7 purlin m 165.6
E) corrguted iron sheet roof G-30 with thiknes 10 cm m2 95.292
F) 8mm chip wood celing m2 89.342
1.05 Metal Work
Type D1 Size:- 90 X 270cm pcs 3
Type D2 Size:- 90 X 200cm pcs 1
Type D3 Size:- 85 X 200cm pcs 2
Type D4 Size:- 70 X 200cm pcs 3
Door Glazing
Type D1 Size:- 40 X 140cm pcs 3
Type W1 Size:- 210 X 490cm pcs 1
Type W2 Size:- 390 X 251cm pcs 1
Type W3 Size:- 170 X 251cm pcs 1
Type W4 Size:- 150X 180cm pcs 1
Type W5 Size:- 101 X 150cm pcs 1
Type W6 Size:- 150 X61cm pcs 1
Type W7 Size:- 250 X200cm pcs 1
Type W8 Size:- 61 X 77cm pcs 1
Type W9 Size:- 200 X 228cm pcs 1
Type W10 Size:-290 X 200cm pcs 1
Type W11 Size:- 200 X 130cm pcs 1
Window Glazing
Type W1 Size:- 15 X 160cm PCS 9
Type W2 Size:- 85 X 240cm pcs 4
Type W3 Size:- 155 X 240cm pcs 1
Type W4 Size:- 75X 135cm pcs 2
Type W5 Size:- 130 X 90cm pcs 1
Type W6 Size:- 50 X90cm pcs 1
Type W7 Size:- 75 X195cm pcs 3
Type W8 Size:- 50 X 70cm pcs 1
Type W9 Size:- 70 X 190cm pcs 3
Type W10 Size:-90 X 195cm pcs 3
Type W11 Size:- 35 X 235cm pcs 3
Summery
1.06 Finising Work
A) plastering
1st coat, by cement and sand ratio 1:2.5 by volume ,with thiknes 5mm
2nd coat by cement, lime& sand ratio 1:1:6 by volum with thiknes 12mm
3rd coat by lime and sand ratio 1:2 by volum with thiknes 3mm
a) Plstering work for External wall both G0&G1 m2 456.38
b )Plastering work for partition wall both G0&G1 m2 256.16
c) Plastering work for column both G0&G1 m2 46.61
d) Plstering work for frist floor beam m2 32.56
e) Plastering work for Roof beam m2
62.06
f) Plastering work for slab m2
178.684
B) Painting
Net painteing for all plastered parts m2 1032.45
C) Floor finising
a) skerting 5mm thiknes and hight 100mm from floor finsh both G0 &G1 m 126.7
b) GFF ceramic tile m2 70.4
c) GFF checkened tile on parking m2 22.6
d) GF cement screed m2
92.9
e) FF P.V.C tile m2
42.5
f) FF Ceramic tile m2 37.68
g) FF Terrazo tile m2 3
h) marble finishing for stair case m2 3.01
i) FF cement screed m2 86.19
Summery
1.07 Electricall installation
Distribution board , breakers , switches, accessories etc should be complying with standards.
Distribution boards should be made of sheet metal and have separate neutral and ground
busbars/phase bars.All units in the distribution boards should should be labled to give the
reference and duty of the unit. pcs 1
Surface mounted sub main distribution board SMDB with lockable door, bus-bars rating of
20A/3ph . pcs 7
A) Socket Outlet
a) Single Outlet socket PCS 16
b) double oute let socket PCS 3
c) Heater Outlet PCS 2
d) Stove outelet PCS 1
B) Telhpon and TV out let
a) Telehpone outlet PCS 5
b) TV outlet PCS 4
c) Heater Outlet PCS 2
C) Switch
a) Single pole switch PCS 7
b) Double pole switch PCS 5
c) Single Tow way switch PCS 14
d) Double tow way switch PCS 3
e) Trible tow way switch PCS 2
D) Lithing
a) Celing maounted lighting fixture PCS 12
b) Wall mounted lighting fixture PCS 8
c) Reccssed mounted lighting fixture PCS 7
d) Double fluorescente fixture PCS 1
e) Trible tow way switch PCS 3
f) Chandeleire PCS 2
E) Electrical cable for Soket outlet and lighting line
Supply and fix copper cable of 3×2.5mm2 for Socket outlet line. m 112
conduit m 112
Supply and fix copper cable of 2×1.5mm2 for lightin line. m 174
condiut m 174
Supply and fix copper cable 3×4 mm2 for water heater & stove line m 9.55
Summery
1.08 Suantory Installation and joints
A) From riser water supplay diagram
a) φ 25 mm pvc cold water supplay pip line m 16.85
b) φ32mm pvc cold water supplay line m 7.9
c) Elbow 90 joints ɸ20mm PCS 12
d) Elbow 90 joints ɸ25mm PCS 3
e) T-joints ɸ20mm PCS 5
f) T-joints ɸ25mm PCS 2
B) From wast water diagram PCS
a) φ100mm pvc waste pipe m 21
b) φ50mm pvc waste pipe m 14.6
c) φ80mm pvc floor deraineg pipe m 0.8
d) Y-joints of ɸ100mm PCS 1
e) Y-joints of ɸ50mm PCS 8
f) Elbow 45 joints ɸ50mm PCS 1
g) Elbow 45 joints ɸ50mm PCS 1
h) Elbow 90 joints ɸ100mm PCS 3
C) Water Colest(WC)
fix water closet of wash down action,floor mounted,
closed cuopled with plastic cover. PCS 3
D) Shower Unit
a) fix shower plate of approved quality complite with PCS 1
insallation of valves size 800*800 stall typ
b) fix shower plate of approved quality PCS 1
instalation of valve bath corner
c) lavonteries vanity type PCS 3
Summery
1.09 Site Work
a) HCB Work for Mnhole m2 8.64
b) HCB Work for Septic tanck m2 5.52
c) plastering for Manhole m2
8.64
d) plastring for Septic tanck m2 5.52
Summery
PROJECResidential Building
LOCATGONDAR
OWNERTemesgen
CONSUAbriham
CONTRTENNA
No Description Unit Quantity
SUMMARY OF BOQ
A) SUB STRUCTURE
1 Excavation and earth work. Birr
2 Concrete Works Birr
3 Masonery work Birr

Total A .......... Birr

B) SUPER STRUCTURE

1 Concrete Works Birr


2 HCB work Birr
3 Roofing Birr
5 Metal Works Birr
7 Glazing Birr
8 Finishing Birr
9 Electrical installation Birr
10 Sanitary installation
Total B………
C) SITE WORK Birr

Total C.……
TOTAL SUM( A+B+C)….
Unit Rate Amount
T D S Description T D S Description
A. SUB-STRUCTURE 1.4 Trench exacvation
Excavation of ordinary soil for
1. masonry wall with working space
Excavation and earth 2 of 0.25m both side.
work 6.6 For axis A'-C
1.1
Excavation of ordinary soil L=6.6m
Site cleaning 0.95
with a depth of 20cm and
1 22 working space of 1m both 1 W=0.95m
14.5 side. D=1m
12.54 m3
W=12.5m+2m=14.5m Ditto but for axis 1-2
319 m2 2 1.7 L=1.7m
W=0.95m
1.2 Bulk excavation 0.95
1 D=1m
Excavation of ordinary soil 3.23 m3
with a depth of 30cm and
1 13.5 working space of 0.25m Ditto but for axis 1-2
11 both side. 1 2.2 L=2.2m
W=0.95m
0.03 0.95
W=10.5m+0.5m=11m 1 D=1m
3 3
4.455 m 2.09 m
1.3 Pit excavation Ditto but for axis B-C
Excavation of ordinary soil 1 3.05 L=3.05m
for footing pad with W=0.95m
working space of 0.25m 0.95
both side. 1 D=1m
3 2.8 For F1 2.898 m 3
L=2.3m+0.5m=2.8m
2.8 Ditto but for axis A"-B
2.1 W=2.3m+0.5m=2.8m 1 0.15 L=0.15m
W=0.95m
D=2.1m 0.95
49.392 m3 1 D=1m
Ditto but for F2
0.143 m3
L=2m+0.5m=2.5m
2.5 Ditto but for axis 2-3
2 2.5 W=2m+0.5m=2.5m 1.3 L=1.3m
W=0.95m
2 D=2m 1 0.95
25 m 3
1 D=1m
Ditto but for F3
L=1.6m+0.5m=2.1m 1.235 m3
2.1 Ditto but for axis 2-3
3 2.1 W=1.6m+0.5m=2.1m 1.6 L=1.6m
W=0.95m
1.9 D=1.9m 1 0.95
25.137 m3 1 D=1m
Ditto but for L-F1
1.52 m3
L=1.2m+0.5m=1.7m
1.7 0.8 Ditto but for axis 2'-3
2 1.5 W=1m+0.5m=1.5m 1 0.95 L=0.8m
W=0.95m , D=1m
1.9 D=1.9m 1
3
9.69 m 0.95 m3
T D S Description T D S Description
T D S Description T D S Description
A. SUB-STRUCTURE 2.Concrete work
2.Concrete work 1 Ditto but for masonry wall with
depth 1m.
2.1 lean Concrete 2.3 at axis
3 Use lean conrete with C-5 0.45 from 2-3

for all sub-structures 1.035 L=2.3m


2.3 lean concrete for footing 1 Ditto but for masonry wall with
depth 1m. W=0.45m
2.3 pad(F1) with depth of 5cm. 2.6 at axis
from 2-3
L = 2.3 0.45
W = 2.3 1.17 L=2.6m
15.87 1 Ditto but for masonry wall with
depth 1m. W=0.45m
2 Ditto but for F2 1.7 at axis
2.3 L=1.5m 0.45 from 2'-3

L=1.7m
2.3 W = 2.3 0.765
10.58 2 Ditto but for masonry wall with
depth 1m. W=0.5m
2 Ditto but for F3 4.05 at axis
1.5 L=1.5m 0.45 from B-C

L=4.05m
1.5 W=1.5 3.645
4.5 1 Ditto but for masonry wall with
depth 1m. W=0.45m
at axis
L=1.2 from B-C
3 1.2 4.2
L=4.2m
1.2 4.32 0.45
1 Ditto but under masonry 1.89
wall with depth 1m.
8 2 CONCERTW=0.45m
WORK
at axis from Use concrete with C-25 for all
A'-C change footing pad and foundation
0.45 column and mix ratio of1:2:3
3.6 5 For footing pad F1
L=8m wall
Ditto but for masonry
with depth 1m. L =1.8m
2 1.8
W=0.45m
at axis from A'-B
3.8 1.8 W =1.8m
0.5 0.4 6.48
3.8 2 Ditto but for footing padD=0.4
F2
1 Ditto
L=3.8but for masonry wall 1.5
with depth 1m. L =1.5m
1.1 1.5
W=0.5m
0.5 at axis from A''-B 0.4 1.8
0.55 3 W =1.5m
Ditto but for footing pad F3
1 Ditto but for masonry wall 1.2
with depth 1m. D=0.4
L =1.2m
2.7 1.2

0.5 at axis from 1-2 0.4 1.728


W =1.2m

D=0.4
1.35

T D S DE T D S DE
Ditto but for axis A''-B and 2-2'
3 Ditto but for foundation 1 2.4
column C1 0.95 W=0.95mL=2.4m
0.3
0.2 L =0.3m 2.28 m2
Ditto but for axis A-A'' and 2-2'
W 1 2.7
1.75 =0.2m L=2.7m
Ditto but for foundation 0.77 W=0.77m
0.315
column C2
6 0.2 D=1.75m 2.079
0.3 L =0.2m

1.75 0.63 W total volume of conceret work fo


=0.3m
1 0.2 0
0.3
D=1.75m
1.75
0.105 m3
Standared C-25 for ground
slab with mix ratio 1:2:3
5.4 and depth 10cm.
2
4.2
Concrete for axis A'-C
45.36 and 1-2
Ditto but for axis B-C and
2-3
1 5.4
L=5.4m
4 W=4m
21.6 m2
Ditto but for axis B-C and
3-3'
5.4
L=5.4m m3
1 1 W=1m ditto but for F3
5.4 m2 L=
Ditto but for axis A''-B and
3'-3
1 2.7
L=2.7m W=
2.4 W=2.4m D=
6.48 m2 m3
Ditto but for axis A''-B and
2'-3
1 2.4
L=2.4m Ditto but LF1
1.05 W=1.05m
1.05 W=1.05m
1.1025
m2

T D T D S D
beam with mix ratio 1:2:3 2 GB7&GB8 External
16.93 and depth of 40 cm forGB1 L= 8.6+0.15+0.15=8.9
1 10.8 L=11.3-0.1-0.3-0.1=10.8 D=0.4
0.4 D=0.4 m3
34561 dito but for GB1 external 1 GB8 internal
1 11.5 L= 11.3+0.1+0.1=11.5 L =6-0.1-0.15=5.35
0.4 m3 D=0.4 D=0.4
4.52 FOR Grade beam GB2 m3
1 internal Formwork
L= 3-0.15-0.15 =2.7 providing zigba formwork for
2.7 D =0.4 footing pad and foundation
0.4 ` column and panel for other
m3 structural part with thickness of
1.16 ditto but forGB2external 9.35 25mm by considering its overlap
1 L= 3+0.15+0.15=3.3 3 0.4 formwork for footing pad
3.3 D=0.4 3.74 formwork for F1
0.4 m3 L= 2*2.3+2*2.35=9.35
1.24 graed beam GB3andGB4 D=0.4
2 internal ditto but, for F2
L= 2.6+5.6-0.3-0.1=7.9 8.1 L=2*2+2*2.05=8.1
7.9 D=0.4 2 0.4 D=0.4
0.4 m3 3.24m2
6.32 for GB3 and GB4 external ditto but, for F3
2 L=8.3+0.1=8.4 3 L=2*1.6+2*1.65=9.9
8.4 D=0.4 9.9 d
0.4 m3 0.4 D=0.4
2
6.72 for GB5 internal 3.96 m
1 L=1.2+4.5+-0.15 =5.25 ditto but, for LF1
5.25 D=0.4 2 L=2*1.2+2*1.05=4.62
0.4 m3 4.62 D=0.4
2.1 for GB5 external 0.4
2
1 L= 5.7+0.15 =5.85 3.696 m
5.85 D=0.4 ditto but, for C1&C2
0.4 m3 10 L=2*0.3+2*2.25=1.1
2.34 GB6 external 1.1 D=1.75
2 L= 5.6 1.75
5.6 D=0.4 16.5 m2
0.4 m3 ditto but, for GB1 external
4.48 GB7 internal 1 L=11.102+(11.5+0.25)=22.6
2 L= 8.6-0.15-0.15-0.3= 8 22.6 D=0.4
8 D= 0.4 0.4
0.4 m3 9.04 m2
6.4
T D S ditto but, for GB1 internal T D S D
L=11.102*2=22.204 ditto but, for GB8
1 D=0.4 1 L= 2.4+2.4=4.8
22.2 4.8 D=0.4
0.4 m2 0.4
8.8816 ditto but, for GB2 1.92 m2
L=2.7+(2.952+0.25)=3.438
1 D=0.4 total formorkfor fondation
column footing pad&graed
3.438 beam 88.763m2
0.4 m2
1.375 ditto but, for GB3
L=2*(5.4+2.4) =15.6
1 D=0.4
15.6
0.4 m2
6.24 ditto but, for GB4
L=8.55+0.5+2.4+5.4=16.85
1 D=0.4
16.85
0.4 m2
6.74 ditto but, for FB5
L=4.225+0.775 +5.8=10.8
1 D=0.4
10.8
0.4 m2
4.32 ditto but, for FB6
L=0.775+4.45+0.95+3.98=10.2
1 D=0.4
10.2
0.4 m2
4.08 ditto but, for FB7 internal
L=(4.225+3.925+1.05)*2=18.3
1 D=0.4
18.3
0.4 m2
7.332 ditto but, for FB7 external
L=(4.225+3.925+1.05)+10.2=19.4
1 D=0.4
19.4
0.4 m2
7.76
`
m³ total volume of concrete
Standared work for foundation column
C-25 for back fill -under footing pad
ground
slab with
mix ratio for F1
1:2:3 and
depth
10cm.

Concrete
for axis
A'-C and
1-2

#VALUE!

#NAME?

0
8.8816

total formorkfor fondation column footing pad&graed beam


88.763m2

You might also like