CSI Implementation Bluebook Verison 1.2
CSI Implementation Bluebook Verison 1.2
for
Department of Posts
Ministry of Communications & IT, Government of India
16 Aug 2016
Version 1.0
Confidentiality Statement
This document contains information that is proprietary and confidential to Tata Consultancy
Services Limited, which shall not be disclosed outside Department of Posts, transmitted or
duplicated, used in whole or in part for any purpose other than its intended purpose. Any use or
disclosure in whole or in part of this information without express written permission of Tata
Consultancy Services is prohibited. Any other company and product names mentioned are used
for identification purposes only and may be trademarks of their respective owners.
© Copyright 2016, Tata Consultancy Services (TCS)
We, in our dealings, are self-regulated by a code of conduct as enshrined in the ‘TATA Code of
Conduct’. We request your support in helping us adhere to the code in letter and spirit. We
request that any violation or potential violation of the code by any person be promptly brought
to the notice of the Local Ethics Counsellor or the Principal Ethics Counsellors or the CEO of TCS.
All communication received in this regard will be treated and kept as confidential.
Document Details
Revision Details
Document Approvals
Revision
Revision Date Revision Description Version Author
Number
Contents
1 INTRODUCTION ....................................................................................................................................... 8
4 ANNEXURE ............................................................................................................................................ 31
List of Figures
FIGURE 1: CSI MAIL OPERATIONS SYSTEMS.................................................................................................................... 10
FIGURE 2: CSI HR SYSTEM OVERVIEW .......................................................................................................................... 11
FIGURE 3: CSI HR SYSTEM – KEY CHANGES AND BENEFITS ................................................................................................ 12
FIGURE 4 : ROLLOUT DASHBOARD – LOCAL INFRASTRUCTURE ............................................................................................ 16
FIGURE 5: USER CHAMPION NOMINATIONS – SUGGESTED REPRESENTATION ........................................................................ 17
FIGURE 6: ROLL OUT TRAINING DASHBOARD – USER CHAMPION ....................................................................................... 19
FIGURE 7: ROLL OUT TRAINING DASHBOARD – END USER................................................................................................. 19
FIGURE 8: ROLL OUT DASHBOARD – CSI CLIENT INSTALLATION .......................................................................................... 20
FIGURE 9: ROLL OUT DASHBOARD - DIGITIZATION ........................................................................................................... 23
FIGURE 10: ROLL OUT DASHBOARD - DATA MIGRATION................................................................................................... 25
FIGURE 11: ROLLOUT DASHBOARD - DCT ...................................................................................................................... 26
FIGURE 12: ROLLOUT CHECKLIST DASHBOARD ................................................................................................................ 27
List of Tables
TABLE 1: LOCAL INFRASTRUCTURE CHECKLIST FOR ROLL OUT.............................................................................................. 15
TABLE 2: USER CHAMPION TRAINING PACKAGES ............................................................................................................. 16
TABLE 3: END USER TRAINING PACKAGES ...................................................................................................................... 17
TABLE 4: DIGITIZATION CHECKLIST ................................................................................................................................ 21
TABLE 5: ROLLOUT DATA MIGRATION CHECKLIST ............................................................................................................ 24
TABLE 6: REFERENCE ROLLOUT PLAN ............................................................................................................................ 27
TABLE 7: LIST OF ANNEXURES ...................................................................................................................................... 31
1 INTRODUCTION
This document details out the CSI business Solutions implementation activities/ tasks which are pre
requisites and need to be completed for the roll out of CSI business solutions for all types of offices
(Post offices, Mail offices, Administrative offices, DAP, Training centers, store depots and so on. It
details out the roll out tasks, pre requisites, checklist and dashboards to be used for roll out tasks
execution, tracking and monitoring. This document is intended for the DoP circle/ region/ division
offices to understand the CSI roll out scope, tasks, pre requisites and monitoring mechanism.
This document is prepared based on the CSI roll out learnings from Karnataka pilot offices and will
be updated further also as required based on the learning / feedback from further CSI roll outs.
All the mentioned functions/ capabilities enable booking, transmission and delivery of mail.
The Point of Sales (POS) solution has been designated to enable Post Offices to perform all sales
operations seamlessly. The POS solution operates in ‘Online’ and ‘Offline’ mode and provides all the
post office designed banking and insurance operations at counter and at back office, and is also
integrated through options within the solution. The Point of Sale application broadly comprises of
the following components:
POS Counter - Post Office Counter components allow all the daily operations and transactional
functions. It mainly comprises of all Sales function and customer facing functions which a POS
Operator will execute at the counter. It is accessed and operated by post office counter operators at
the Post Offices and deals with citizens.
POS Back Office - The back office (Post Office) component has various aspects of post office
operational control options like counter configuration and set up, counter assignment, Bagging and
dispatch, reports, post office data maintenance and post master’s dashboard. This is a back office
function for Post Office who manage these activities.
POS Central Instance - This is the central POS database system / instance at DoP data center that
governs all the central configuration, master data control and post office set up. It takes the master
data from SAP solution and transfer to POS Post office through POS Central Instance. This is
managed by CSI team.
CSI Mail operations solution will bring the following key changes and benefits to Citizens/ DoP
employees:
Multiple channels to book an article will be available to the customers, for example through
counters, online using the web portal, and through call centers.
Customers would be able to request for pickup of the articles from their premises.
Articles would be monitored centrally after their induction into the system.
Pre-printed barcodes will be tagged with the articles which will enable end-to-end tracking
of the articles.
Customers can be notified about the status of the articles through SMS.
Article pickup request from premises can be generated through call center or the web
portal.
TCS-DOP Confidential Page 10 of 31
DOP – CSI PROGRAM CSI Implementation Bluebook
CSI HR solution will bring the following key changes and benefits.
CSI F&A solution brings the following key changes and benefits:
Identification of all DoP entities as Cost center or Profit center
Each employee will be assigned to a particular cost center.
All transactions will be posted by the post offices on the SAP system.
Revenue or expense details will be available for each section in offices on the system
across the department.
Introduction of Accrual Based Accounting-Assessment of the performance and position of any
post office across the country by recognizing transactions when they occur regardless of when
the cash is actually transferred while core reporting to MOF will be available through cash basis
(CGA reporting) at each DDO level.
On line basis automatic budget checking during placement of Purchase or Service Orders.
Bottom up basis budget data accumulation process from the level of Head Post office.
Top down basis budget allocation process from Directorate to HO with re-appropriate of budget
facility.
Cost /Fund center wise cost data accumulation for Activity Based Costing.
Seamless integration with e payment application for biller payments as per CSI cash offices.
Automation of document creation - Automatic creation on the system of purchase orders, sales
orders, inventory documents, goods receipt acknowledgements, invoices, billing documents and
clearing documents as per the entries recorded and approved on the system.
Minimized Voucher Movement -Time consuming and error prone movement of vouchers
between various offices for accounting and reconciliation will be reduced considerably as all
information will be available on the centralized system for access by a DoP user. This will be
available on CSI is rolled out completely.
Capturing of transactions at the point of sale -Number of unaccounted transactions in the
Suspense Account will reduce as transactions will be captured instantly and will be
mapped/posted in SAP application with respective GL in near real time basis.
3. All offices systems (desktops and servers) are joined to CSI AD / domain and systems are
regularly kept in India post domain - Mandatory
4. CSI AV (Antivirus) is installed on all office systems (desktops and servers) along with latest AV
signature - Mandatory
5. All peripheral devices (such as Printers, Bar Code Scanners, Weighing Machines and so on) are
compatible with CSI as per specifications - Mandatory
6. CBS/PLI applications (if applicable) have been rolled out and being used for banking and
insurance business functions - Desirable
It is recommended that all the above pre-requisites completion is tracked and monitored for closure
using the following checklist and using the suggested verification guidelines.
The dashboard for the same will be created and tracked. Snapshot of the tracker is shown in the
following figure.
The suggested representation from all office types is as follows, which need to be used as guidelines
for nominations of user champions.
The template will need to be used for nomination of user champions and sharing with CSI team.
Refer the User champion’s nomination template in Annexure B.
End Users training will consist of the following packages:
A detailed training package document for user champions and end users is available and attached as
Annexure J & K. The training package document provide the following details
Selection and Nomination of Users
Structure and content of training including Hands On Training
Schedule of training (Batch scheduling)
Venue of training
Participant Attendance
Evaluation Tests
Participant Feedback
To ensure the completion of the training of users for your respective circle/ division, the following
tasks need to be tracked and completed:
1. Identify and finalize the nominations for User Champions and share with CSI team. Verify
proportionate nominations from all Org Units (HOs, SOs, Circle/Region/Division; Mail Office;
DAP; PSD/CSD; PTC/WTC and so on) for respective business functions - Mandatory
2. Share the training room capacity and availability with CSI team - Desirable
3. Share IP range of machines in the training center for port opening for connectivity with
training server. Training center should have Sify connectivity - Mandatory
4. Finalization of batch scheduling for the User champions training - Mandatory
5. Installation / Set up of training environment / data in respective PTC/WTCs - Mandatory
6. Training of User champions as per finalized batch schedule ensuring that nominated team
members attends and complete the user training - Mandatory
7. Identify, finalize the nominations for end users training. Verify proportionate nominations
from all Org Units (HOs, SOs, Circle/Region/Division; Mail Office; DAP; PSD/CSD; PTC/WTC
and so on) as per functional roles - Mandatory
8. Finalization of batch Scheduling for the end Users training by DoP user champions except for
pilot offices where CSI team will conduct the end user training also - Mandatory
9. Training of end users as per finalized batch schedule ensuring that nominated team
members attends and complete the user training - Mandatory
All the above pre-requisites completion need to be tracked and monitored till training completion
through the following dashboard for your respective circle / division. The training attendance and
evaluation records need to be maintained and preserved. The sample training dashboard for the
Assam pilot offices is attached as reference.
Training Dashboards
POS (Point of sales) – This application need to be installed only in post offices where mail
booking (including bulk booking) is done.
SAP GUI – This application need to be installed in all the working desktops of the office in all
types of the offices.
The installation of CSI client applications need to be started about 4 to 6 weeks prior to the roll out
and completed one week before the roll out. The CSI client installation activity will be done by CSI
team. DoP system admin need to ensure the availability of the desktops and servers for client
installation as per the HW SW specifications and provide support to resolve the local system issues if
TCS-DOP Confidential Page 19 of 31
DOP – CSI PROGRAM CSI Implementation Bluebook
any. CSI team will finalize the CSI client installation schedule for the division in consultation with the
division/circle team.
Point of Sales (POS) applications will have two types of the clients and POS Database server:
POS Counter
POS Back office
POS Database server
SAP GUI client application need to be installed on all working desktops of the office.
To ensure the completion of the installation of the CSI client applications for your respective circle/
division, the following tasks need to be tracked and completed.
1. Identification of the desktops for the POS counter, POS back office and POS database server as
per hardware-software specifications in the attached template in Annexure C and share with CSI
team -Desirable
2. Ensure that all the identified systems (desktops and servers) have - Mandatory
a. Latest OS service packs
b. CSI Anti-Virus installed and updated with latest signature.
c. Systems are joined to CSI AD with Sify connectivity.
3. Finalize the tentative installation schedule with CSI team for CSI client applications - Desirable
4. Installation and Validation of POS counter, POS back office on all the identified systems in Post
offices - Mandatory
5. Installation and validation of SAP GUI client on all the systems. (Note: Windows XP is not
supported by Microsoft and not recommended, Any Windows XP need to have SAP version 7.3.)
- Mandatory
6. Local POS database server need to be remain switched ‘ON’ for 24 * 7 for data synchronization
with DC and database back up need to be ensured on daily basis - Mandatory
All the above pre-requisites completion is tracked and monitored till roll out through the following
dashboard for your respective circle / division. The sample training dashboard for the Assam pilot
offices is attached as reference.
Please read and refer to the detailed digitization handbook for the details of the above mentioned
points. The key points to be tracked and monitored prior to the digitization, during digitization and
post digitization along with verification guidelines are as follows:
Location-wise Digitization dashboard for the digitization, employee verification and upload will be
created and tracked jointly. Snapshot of the tracker for Assam is as follows:
RMFS application data is maintained at CEPT centrally. CEPT provides the complete data backup.
Franking customer master data is taken from this legacy application. This data is taken 4 weeks prior
to the roll out date as this data is not likely to change in this duration. In case any new customer or
customer status is modified during the duration, the data for the same will need to be provided
again by DoP. The Franking balance is updated through integration on the roll out date.
Customer data is being maintained centrally at CEPT in four different applications and respective
data is taken Speednet, Rnet, Parclenet, eMO applications. This data is taken 4 weeks prior to the
roll out date as this data is not likely to change in this duration. In case any new customer or
customer status is modified during the duration, the data for the same will need to be provided
again by DoP.
Fixed Asset Data is maintained centrally in NIC maintained application Asset Register. The data for
the same is either provided through excel file or Database dump. This data is taken 4 weeks prior to
the roll out date as this data is not likely to change in this duration.
Payroll and Pension data from Meghdoot Payroll (Accounts, Schedule, Income tax) – This payroll
data is currently maintained at DDO level and provided accordingly. The Payroll and pensions data
for the current financial year starting 01 Mar of respective finance year till the last month prior to
the roll out data is taken 4 weeks prior to the roll out. The data for the last month will be taken post
payroll and pensions run for the month which need to be completed by 26/27 of the respective
month.
In order to extract data from these locations, scripts have been prepared and validated by CSI and
DOP. Scripts will need to be run on DOP servers. Local System administrators of respective offices
where the servers reside will help to provide the data to CSI team using the scripts. The extracted
data will be loaded in the data center servers for which ports will be opened in advance between the
DOP servers and data center. Local system administrators will be expected to provide IPs of the
servers to CSI team for port opening.
As per the experience from Karnataka pilot circles, the following points must be validated and
ensured at least 2 months prior to the roll out.
Location-wise Digitization dashboard for the Legacy data migration, upload need to be created and
tracked jointly. Snapshot of the tracker for Assam is as follows:
There are total 107 DCT templates across all the CSI business solutions (Mail operations, F&A and
HR). The detailed list of DCT is attached below in Annexure F. All the DCT templates data need to be
collected, verified for completeness as per suggested timelines and shared with CSI team for upload.
The following points need to be taken care during data collection:
1. All the DCT templates will have “Read me” that explains the key points for filling the DCT
template. Ensure that Read me is read and followed - Desirable
2. All the DCT templates will have identified mandatory fields which need to be filled and not
left blank - Mandatory
3. Verify the filled DCT template for completeness and correctness including data types and
formats - Mandatory
4. DMSL Data - Verify matching of dispatch-receipt schedule; Ensure product-wise DMSL data
(speed post, registered post and parcel and so on) separately - Mandatory
5. Ensure that loans and repayment history data is up-to-date - Mandatory
6. Ensure to share complete inventory data - including counter level inventory for HOs, Serial
numbers of all IPOs (this item took time in Karnataka roll out) - Mandatory
7. DoP team to plan for collection and sharing of time critical Dynamic cut off data with CSI
team for uploading during the cut off period / last day including identification of DoP team. -
Mandatory
The following tasks for DCT collection and verification will need to be tracked / monitored till roll out
as set up of application data is key to the successful roll out. This was also a learning in Karnataka
pilot roll out.
1. Data collection for all DCT templates as per timeline, verification for completeness prior to
sharing with CSI team.
2. DCT will be uploaded in CSI system as per mentioned timelines.
3. Support / Rectification of Data for issues/errors during the data upload.
4. Data verification in CSI system post uploading prior to the roll out (This is a critical data
verification step).
Location wise DCT dashboard for the DCT collection, upload and verification will be created and
tracked jointly. Snapshot of the tracker for Assam is as follows:
2. DoP to issue communication as required for end customer for last day before roll out -
Desirable
3. Distribution of roll out checklist (office Type wise). Roll out checklist is attached in Annexure
G and H - Mandatory
4. Each office to fill and provide updated checklist to division for tracking / monitoring -
Mandatory
5. All employees of roll out offices to change default SSO password - Mandatory
6. DoP team to avoid the transfers / deputation of the employees within division / across
division for being rolled out division during the last 2/3 weeks - Desirable
7. Deployment of onsite Support team for first week of Go Live - Mandatory
Location-wise dashboard for tracking and ensure completion of the Roll Out checklist for all the
offices will be created and tracked. Snapshot of the tracker for Assam is as follows:
# Roll Out Preparation Tasks Ownership Target Start Date Target End date
POS/SAP set-up in post offices and
administrative offices
6 POS and SAP installation in Pilot field
offices. CSI/DoP T-6weeks T-1weeks
7 Smoke testing of user access set up by DoP. DoP T-1week T- 3days
8 Validation of devices (like printers, weighing
scale, scanners and so on). DoP T-1week
Digitization, Migration and Data Set-up
9 Formation of Joint team (TCS and DoP) for
Data migration, collection and Validation
along with SPOCs. DoP / CSI T-13weeks T-12weeks
10 Service Book verification and updation by
Employees - Employee Key data. DoP T-12weeks T-4weeks
11 Validate critical data for DoP employees
- Current office, post, section data
- Transfer / new employees data. DoP/CSI T-4weeks T-3weeks
12 Migrate Employees/GDS Data to HR system CSI T-4weeks T-3weeks
13 Final verification and resolution of SB data
issues - Employee Key data. DoP T-4weeks T-2weeks
14 Freeze Cut off Dates with DoP - RMFS,
Customer data, Asset data, Payroll and
Pensions data. CSI / DoP T-6weeks
15 Providing legacy data/ database by DoP for
listed legacy applications. DoP T-6weeks T-4weeks
16 Load Legacy data CSI T-4weeks T-3weeks
17 DoP to provide the data for all the DCT T-8weeks (static)
templates. T-4weeks
(Dynamic)
T-1day (Dynamic
DoP cutoff)
18 Upload the data for pilot offices from data T-8weeks (static) T-3weeks (static)
collection templates. T-4weeks T-4weeks
(Dynamic) (Dynamic)
T-1day (Dynamic T-1day (Dynamic
CSI cutoff) cutoff)
19 DoP to resolve and validate the migrated T-3weeks (static)
data post loading. T-4weeks
(Dynamic)
T-1day (Dynamic
DoP cutoff)
20 Extract last month payroll and pension data
from Meghdoot. CSI / DoP Last EoM - 4 days
21 Update GPF balance to GASP database at
DAP, for roll out location employees. DoP T+1week
22 DMSL data verification by DoP and
confirmation to CSI for roll out offices. DoP T-8weeks T-4weeks
User Roles and Access Set-up
# Roll Out Preparation Tasks Ownership Target Start Date Target End date
23 Submission of Employee to Role mapping
template to DoP for pilot circles. CSI T-6weeks T-4weeks
24 DoP to Provide Employee to Role mapping
and Post to Post workflow mapping data for
pilot offices. DoP T-4weeks T-3weeks
25 Load DoP employee data in HR/OM as per
data provided by DOP. CSI T-3weeks T-1weeks
Integration
26 Communication to FSI and DoP for CSI go
live for FSI readiness and FSI training to
users. CSI/ DoP T-4weeks T-3weeks
27 Communication by DoP for third party
interface readiness at roll out offices. DoP T-4weeks T-3weeks
28 Evaluate if any master data need to be
configured for third party interfaces. CSI T-4weeks T-3weeks
29 Single Point of Contact (SPoC) for all CSI/DoP/F
interfaces - Communicated and Agreed with SI/Third
DoP for rollout. Party T-4weeks T-3weeks
30 CBS Sol Id / PLI offices Id mapping with CSI
facility ID and CBS and PLI user id mapping
with CSI employee id for pilot offices by
DoP. DoP T-6weeks T-3weeks
31 Confirmation from FSI for code and data FSI
migration to production for new interfaces,
if any. T-1week
32 Opening of Additional ports for new FSI
interfaces (if any). FSI/CSI T-2weeks T-1week
33 CSI to push 999 messages for pilot offices to
CEPT for legacy applications. CSI T-1day
34 CEPT to consume the 999 messages and
confirm. CEPT T-1day
General Rollout Activities and
Communication
35 Formation of Roll out support team. DoP / CSI T-2weeks T-2weeks
36 DoP to issue communication for roll out
offices for last day before roll out. DoP T-2weeks T-1weeks
37 Roll out checklist (office Type wise) to DoP
for distribution. DoP T-4weeks T-3weeks
38 DoP to fill and provide updated checklist for
all offices. DoP T-4weeks T-1weeks
39 All employees of pilot offices to change SSO
password. DoP T-4weeks T-1weeks
40 Deployment of onsite Support team for first DoP, FSI,
week of Go Live. CSI T-2days T+1week
The completion of the tasks will be monitored through the location dashboard as mentioned in
respective section. The consolidated location dashboard for Assam pilot offices is attached as sample
in the Annexure I.
For any issues related to password, users can use IM self-service portal
http://im.indiapost.gov.in/identity
CSI Applications issues can also be reported to the CSI interim helpdesk numbers 011-66076729,
011-66076730, 011-66076755, 011-66076756 from 8 AM to 8 PM. TCS helpdesk team will log the
ticket and track the ticket till closure. You can mention the ticket number for any future reference.
4 ANNEXURE
The Annexure section is listing the various documents/ checklist referred in the above sections.